CN210854680U - Building site is with removing cable frame - Google Patents

Building site is with removing cable frame Download PDF

Info

Publication number
CN210854680U
CN210854680U CN201921376976.3U CN201921376976U CN210854680U CN 210854680 U CN210854680 U CN 210854680U CN 201921376976 U CN201921376976 U CN 201921376976U CN 210854680 U CN210854680 U CN 210854680U
Authority
CN
China
Prior art keywords
backup pad
fixed
pulley
gyro wheel
cable frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921376976.3U
Other languages
Chinese (zh)
Inventor
刘迪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921376976.3U priority Critical patent/CN210854680U/en
Application granted granted Critical
Publication of CN210854680U publication Critical patent/CN210854680U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Storing, Repeated Paying-Out, And Re-Storing Of Elongated Articles (AREA)

Abstract

The utility model relates to a cable frame technical field especially relates to a building site is with removing cable frame, which comprises a supporting plate and i, the backup pad is provided with two, connects through connecting the rope between two backup pads, and installs between two backup pads and be fixed with the second spring, has all seted up the spout on the up end of backup pad, and the spout internal slip is established and is installed the pulley, and branch is installed through the pulley yoke in the top of pulley, and branch rotates and install in the pivot of receipts reel, the bottom erection fixation of backup pad has fixed pipe box, and fixed pipe box endotheca is equipped with the gyro wheel frame, and the bottom erection fixation of gyro wheel frame has the gyro wheel to make cable frame can move on the unsmooth ground of undulation, and can cushion the shock attenuation.

Description

Building site is with removing cable frame
Technical Field
The utility model relates to a cable frame technical field especially relates to a building site is with removing cable frame.
Background
Building site all is interim power consumption, need arrange transmission cable to need use a large amount of cable frame, when cable frame was carried on the factory, because pothole on the building site, the fluctuation, thereby make cable frame carry out unusual inconvenience through normal gyro wheel, and through lifting up the very manpower that consumes of transport again.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the shortcoming that exists among the prior art, and the mobile cable frame for building site who provides.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a building site is with removing cable frame, includes the backup pad, the backup pad is provided with two, connects through connecting the rope between two backup pads, and installs and be fixed with the second spring between two backup pads, has all seted up the spout on the up end of backup pad, and the spout internal slipping is established and is installed the pulley, and branch is installed through the pulley yoke in the top of pulley, and branch rotates to be installed in the pivot of receipts reel, the bottom installation of backup pad is fixed with fixed pipe box, and fixed pipe box endotheca is equipped with the gyro wheel frame, and the bottom installation of gyro wheel frame is fixed with the gyro wheel.
Preferably, one end of the supporting rod is provided with a circular ring, a bearing is installed in the circular ring, and the bearing is inserted and fixed on a rotating shaft of the winding drum.
Preferably, the two rings rotatably mounted at each end of the rotating shaft of the winding drum are staggered inside and outside.
Preferably, a first spring is arranged between the fixed pipe sleeve and the top end of the roller frame inserted into the fixed pipe sleeve.
Preferably, both sides of the groove wall of the sliding groove are provided with roller grooves, and both ends of the roller in the middle of the pulley slide in the roller grooves.
The utility model has the advantages that:
1. can cushion the shock attenuation at the removal in-process through the first spring of fixed intraductal.
2. Adjust and cushion through the connection rope and the second spring follow the ground condition at middle part through single backup pad, branch carries out the motion that accompanies through the pulley and the top ring of bottom simultaneously to make the cable frame can move on the unsmooth ground of fluctuation.
3. The utility model provides a cable frame can move on the unsmooth subaerial of fluctuation on the workplace, and can cushion the shock attenuation.
Drawings
Fig. 1 is a schematic structural view of a mobile cable rack for a construction site according to the present invention;
fig. 2 is the utility model provides a structural schematic is overlooked with backup pad of removal cable frame to building site.
In the figure: the device comprises a supporting plate 1, a winding drum 2, a supporting rod 3, a pulley 4, a first spring 5, a roller 6, a connecting rope 7, a sliding groove 8, a second spring 9 and a fixing sleeve 10.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-2, a building site is with removing cable frame, includes backup pad 1, and backup pad 1 is provided with two, connects through connecting rope 7 between two backup pads 1, and installs between two backup pads 1 and be fixed with second spring 9, has all seted up spout 8 on the up end of backup pad 1, and the smooth establishment of spout 8 is equipped with pulley 4. And the two sides of the groove wall of the sliding groove 8 are provided with roller grooves, and the two ends of the roller in the middle of the pulley 4 slide in the roller grooves.
The top of the pulley 4 is provided with a supporting rod 3 through a pulley yoke, and the supporting rod 3 is rotatably arranged on the rotating shaft of the winding drum 2. One end of the supporting rod 3 is provided with a circular ring, a bearing is installed in the circular ring, the bearing is inserted and fixed on the rotating shaft of the winding drum 2, and two circular rings rotatably installed at each end of the rotating shaft of the winding drum 2 are staggered inside and outside.
The bottom end of the supporting plate 1 is fixedly provided with a fixed pipe sleeve 10, a roller carrier is sleeved in the fixed pipe sleeve 10, a first spring 5 is arranged between the fixed pipe sleeve 10 and the top end of the roller carrier inserted into the fixed pipe sleeve 10, and the bottom end of the roller carrier is fixedly provided with a roller 6.
In this embodiment, the cable frame carries out normal rolling cable through the take-up reel 2, when the cable frame removes, the gyro wheel 6 through 1 bottom of backup pad moves in the roll, thereby can remove on the site, simultaneously can cushion the shock attenuation at the removal in-process through the first spring 5 in the adapter sleeve 10, when meetting highly uneven ground or the ground of undulation simultaneously, single backup pad 1 is adjusted and is cushioned along with the ground condition through the connection rope 7 and the second spring 9 at middle part, branch 3 carries out the motion that accompanies through pulley 4 and the top ring of bottom simultaneously, thereby make the cable frame can move on the uneven ground of undulation.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (5)

1. The utility model provides a building site is with removing cable frame, includes backup pad (1), its characterized in that, backup pad (1) is provided with two, connects through connecting rope (7) between two backup pad (1), and installs between two backup pad (1) and be fixed with second spring (9), has all seted up spout (8) on the up end of backup pad (1), and spout (8) internal slipping is established installs pulley (4), and branch (3) are installed through the pulley yoke in the top of pulley (4), and branch (3) rotate to be installed in the pivot of receipts reel (2), the bottom installation of backup pad (1) is fixed with fixed pipe box (10), and fixed pipe box (10) endotheca is equipped with the gyro wheel frame, and the bottom installation of gyro wheel frame is fixed with gyro wheel (6).
2. A mobile cable frame for construction sites according to claim 1, characterized in that one end of the supporting rod (3) is provided with a circular ring, a bearing is installed in the circular ring, and the bearing is inserted and fixed on the rotating shaft of the winding drum (2).
3. A mobile cable support for construction sites according to claim 2, characterized in that the two rings rotatably mounted on the rotating shaft of the take-up drum (2) at each end are staggered inside and outside.
4. A mobile cable carriage for construction sites according to claim 1, characterized in that a first spring (5) is installed between the fixed sleeve (10) and the top end of the roller carriage inserted into the fixed sleeve (10).
5. The mobile cable frame for the construction site according to claim 1, wherein both sides of the wall of the chute (8) are provided with roller grooves, and both ends of the roller in the middle of the pulley (4) slide in the roller grooves.
CN201921376976.3U 2019-08-23 2019-08-23 Building site is with removing cable frame Expired - Fee Related CN210854680U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921376976.3U CN210854680U (en) 2019-08-23 2019-08-23 Building site is with removing cable frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921376976.3U CN210854680U (en) 2019-08-23 2019-08-23 Building site is with removing cable frame

Publications (1)

Publication Number Publication Date
CN210854680U true CN210854680U (en) 2020-06-26

Family

ID=71305907

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921376976.3U Expired - Fee Related CN210854680U (en) 2019-08-23 2019-08-23 Building site is with removing cable frame

Country Status (1)

Country Link
CN (1) CN210854680U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111796218A (en) * 2020-09-10 2020-10-20 四川华东电气集团有限公司 Electronic transformer winding deformation tester

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111796218A (en) * 2020-09-10 2020-10-20 四川华东电气集团有限公司 Electronic transformer winding deformation tester

Similar Documents

Publication Publication Date Title
CN207192475U (en) A kind of cable coiling device that can quickly wind cable
CN210854680U (en) Building site is with removing cable frame
CN211769831U (en) Crane device for stage
CN214270075U (en) Liftable support for construction engineering construction
CN212230973U (en) Cable protection device for building electrical engineering
CN205838371U (en) A kind of Rope outlet cover structure for high pedestal jib crane
CN210882247U (en) Hydraulic engineering machinery conveyer
CN211254835U (en) Cable laying device for power engineering
CN212450364U (en) Material transfer device for building engineering
CN208897957U (en) A kind of pipe gallery small diameter pipeline transmitting device
CN209928086U (en) ODF optical fiber distribution frame
CN201660407U (en) Simple rotary hanger for tile processing
CN216052352U (en) Optical fiber cable conveying rack for 5G infrastructure construction
CN211419389U (en) Time board receiving arrangement for wall construction for architectural decoration
CN202594541U (en) Cable coiling device
CN221293859U (en) Overhauling tool transferring device for loading machinery
CN220917957U (en) Novel escape descent control device
CN219860196U (en) Pipeline overhead hoist for highway construction
CN210505014U (en) Cable coiling apparatus for communication engineering
CN111321644A (en) A safety apron is prevented rolling by water pipe for municipal administration is watered
CN210065024U (en) Hoisting device for mechanical engineering
CN219567094U (en) Cable discharging trolley
CN203269438U (en) Automatic rope arranging steel rope drawing and threading device for petroleum drilling
CN221644479U (en) Electric power supporting device for electric power installation
CN217396556U (en) Data optimization transmission equipment based on wireless network communication technology

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200626