CN210797147U - Natural permeable quarrying paving structure for sponge city - Google Patents
Natural permeable quarrying paving structure for sponge city Download PDFInfo
- Publication number
- CN210797147U CN210797147U CN201920857650.6U CN201920857650U CN210797147U CN 210797147 U CN210797147 U CN 210797147U CN 201920857650 U CN201920857650 U CN 201920857650U CN 210797147 U CN210797147 U CN 210797147U
- Authority
- CN
- China
- Prior art keywords
- laid
- permeable
- permeates water
- bituminous paving
- asphalt pavement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 37
- 239000012466 permeate Substances 0.000 claims abstract description 33
- 239000004567 concrete Substances 0.000 claims abstract description 11
- 239000010426 asphalt Substances 0.000 claims description 50
- 230000013011 mating Effects 0.000 claims description 4
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 239000004746 geotextile Substances 0.000 claims description 2
- 239000004575 stone Substances 0.000 abstract description 5
- 239000004744 fabric Substances 0.000 description 4
- 230000008595 infiltration Effects 0.000 description 2
- 238000001764 infiltration Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000008239 natural water Substances 0.000 description 2
- 238000009825 accumulation Methods 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000003344 environmental pollutant Substances 0.000 description 1
- 238000001914 filtration Methods 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011380 pervious concrete Substances 0.000 description 1
- 231100000719 pollutant Toxicity 0.000 description 1
- 238000002791 soaking Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/60—Planning or developing urban green infrastructure
Landscapes
- Road Paving Structures (AREA)
Abstract
The utility model discloses a natural stone quarrying structure that permeates water in sponge city, including the bituminous paving and the ordinary bituminous paving that permeate water, the bituminous paving that permeates water lays in the intermediate position and the both sides of road, and ordinary bituminous paving lays between two bituminous paving that permeate water, ordinary bituminous paving sets up for the slope, has laid ordinary bituminous layer under the ordinary bituminous paving, has laid the bituminous layer that permeates water under the bituminous paving that permeates water, has laid the concrete that permeates water under the bituminous layer that permeates water, has laid rubble basic unit under the concrete that permeates water, has laid the ground basic unit under the rubble basic unit, and this natural stone quarrying structure that permeates water in sponge city has increased the bearing strength of bituminous paving that permeates water, avoids the damage to the bituminous paving that permeates water through the rational distribution of bituminous paving and ordinary bituminous paving simultaneously, has improved the durable usability of the road that permeates water and paves.
Description
Technical Field
The utility model relates to a sponge city technical field specifically is a natural structure of mating formation of quarrying that permeates water in sponge city.
Background
At present, urban roads are mostly laid in a waterproof way, the waterproof road surface seriously hinders the infiltration of rainwater, so that the rainwater can be discharged through a road surface and the flood discharge capacity is very limited, and when strong rainfall weather occurs, large-range water accumulation occurs on the road surface; meanwhile, the impermeable road surface reduces the humidity of urban air, so that an urban heat island effect is formed, and the existence of the impermeable road surface also destroys a normal water ecological circulation system in the environment and seriously influences the normal growth of urban vegetation. In the rainfall process, rainwater carries a large amount of urban surface pollutants into the natural water body on the surrounding surface, secondary pollution is generated, and the pollution degree of the natural water body is increased.
Along with the country impels ecological sponge city construction vigorously, the road of permeating water to pave receives attention increasingly, and the road that permeates water accelerates rainwater infiltration and discharges, can effectively reduce the peak discharge, prevents and treats urban waterlogging, can purify the rainfall runoff simultaneously and pollute. However, the prior permeable asphalt pavement paving material has larger porosity, so that the material is loose in early stage and low in strength, is easy to sink and crack under the direct action of long-term vehicle load, and has poorer pavement durability.
Disclosure of Invention
The to-be-solved technical problem of the utility model is to overcome current defect, provide a natural stone facing structure that permeates water in sponge city, increased the bituminous paving's that permeates water bearing strength, avoid the damage to the bituminous paving that permeates water through the rational distribution of bituminous paving and ordinary bituminous paving simultaneously, can effectively solve the problem in the background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a natural stone quarrying structure that permeates water in sponge city, includes permeable asphalt pavement and ordinary asphalt pavement, permeable asphalt pavement lays in the intermediate position and the both sides of road, and ordinary asphalt pavement lays between two permeable asphalt pavement, ordinary asphalt pavement sets up for the slope, has laid ordinary asphalt layer under the ordinary asphalt pavement, has laid permeable asphalt layer under the permeable asphalt pavement, and permeable concrete has been laid to permeable asphalt layer lower extreme, and the rubble basic unit has been laid to the concrete lower extreme that permeates water, and the ground basic unit has been laid to rubble basic unit lower extreme.
As the utility model discloses a preferred technical scheme, rubble basic unit intermediate position is equipped with the drainage french drain, and the drainage end of drainage french drain is linked together with the underground drainage canal that sets up at the road both ends.
As an optimized technical scheme of the utility model, the drainage french drain sets up for inclining to both sides from the centre.
As an optimal technical scheme of the utility model, the geotechnical cloth has been laid between rubble basic unit and the ground basic unit.
Compared with the prior art, the beneficial effects of the utility model are that: this natural stone quarrying structure that permeates water in sponge city is through laying pervious concrete in proper order at the bituminous layer lower extreme that permeates water, rubble basic unit and foundation bed, the bearing strength and the steadiness of the bituminous paving that permeates water have been increased, cross laying through pervious bituminous paving and ordinary bituminous paving makes the vehicle normally travel on ordinary bituminous paving, the rainwater absorbs the rainwater along the ordinary bituminous paving that permeates water that the slope set up to the bituminous paving that flows to both sides when raining, the effectual damage of having avoided the bituminous paving that permeates water, the durable usability of the road of mating water has been improved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the pavement distribution.
In the figure: the concrete water-permeable asphalt pavement comprises a water-permeable asphalt pavement 1, a common asphalt pavement 2, a common asphalt layer 3, a water-permeable asphalt layer 4, water-permeable concrete 5, a macadam base layer 6, geotextile 7, a foundation layer 8, a drainage blind ditch 9 and a drainage channel 10.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-2, the present invention provides a technical solution: a natural permeable quarrying pavement structure for a sponge city comprises a permeable asphalt pavement 1 and a common asphalt pavement 2, wherein the permeable asphalt pavement 1 is laid at the middle position and two sides of the road, the common asphalt pavement 2 is laid between the two permeable asphalt pavements 1, the common asphalt pavement 2 is arranged in an inclined manner, a common asphalt layer 3 is laid under the common asphalt pavement 2, a permeable asphalt layer 4 is laid under the permeable asphalt pavement 1, permeable concrete 5 is laid under the permeable asphalt layer 4, a macadam base layer 6 is laid under the permeable concrete 5, a drainage blind ditch 9 is arranged at the middle position of the macadam base layer 6, the drainage end of the drainage blind ditch 9 is communicated with underground drainage channels 10 arranged at two ends of the road, the drainage blind ditch 9 can quickly drain rainwater so as to prevent rainwater from accumulating on the surface of the ground base layer 8 and soaking the ground base layer 8 for a long time, the drainage blind ditch 9 is arranged in an inclined manner from the middle to two sides, 6 lower extremes of rubble basic unit have laid basic unit 8, have laid geotechnological cloth 7 between rubble basic unit 6 and the basic unit 8, and the laying of geotechnological cloth 7 has not only increased structural stability, has reduced inhomogeneous settlement, still plays good rainwater filtering action simultaneously, and this structure is effectual has avoided the damage to the bituminous paving 1 that permeates water, has improved the durable nature of the road of mating formation that permeates water.
When in use: the asphalt pavement 1 that permeates water is laid in the centre and both sides of road, ordinary asphalt pavement 2 slope is laid between two asphalt pavement 1 that permeates water, the vehicle traveles on ordinary asphalt pavement 2, the rainwater passes through ordinary asphalt pavement 2 flow direction asphalt pavement 1 that permeates water during rainy, then flow to rubble basic unit 6 through the asphalt layer 4 that permeates water and the concrete 5 that permeates water, through setting up drainage french drain 9 in the middle of rubble basic unit 6 with rainwater drainage to underground drainage canal 10, geotechnological cloth 7 sets up and has increased structural stability between rubble basic unit 6 and basement layer 8, reduce uneven settlement.
The utility model has reasonable design, and increases the bearing strength and stability of the permeable asphalt pavement 1; the cross laying of the permeable asphalt pavement 1 and the common asphalt pavement 2 effectively avoids the damage to the permeable asphalt pavement 1, and improves the durability of the permeable pavement.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (4)
1. The utility model provides a natural structure of mating formation of quarrying that permeates water in sponge city which characterized in that: including permeable asphalt pavement (1) and ordinary asphalt pavement (2), permeable asphalt pavement (1) is laid in the intermediate position and both sides of road, and ordinary asphalt pavement (2) are laid between two permeable asphalt pavement (1), ordinary asphalt pavement (2) are the slope setting, have laid ordinary asphalt layer (3) under ordinary asphalt pavement (2), have laid permeable asphalt layer (4) under permeable asphalt pavement (1), and permeable concrete (5) have been laid to permeable asphalt layer (4) lower extreme, and rubble basic unit (6) have been laid to permeable concrete (5) lower extreme, and groundsill (8) have been laid to rubble basic unit (6) lower extreme.
2. The natural permeable quarrying paving structure for the sponge city according to claim 1, characterized in that: and a drainage blind ditch (9) is arranged in the middle of the gravel base layer (6), and the drainage end of the drainage blind ditch (9) is communicated with underground drainage channels (10) arranged at two ends of a road.
3. The natural permeable quarrying paving structure for the sponge city according to claim 2, characterized in that: the drainage blind ditch (9) is obliquely arranged from the middle to two sides.
4. The natural permeable quarrying paving structure for the sponge city according to claim 1, characterized in that: and a geotextile (7) is laid between the gravel base layer (6) and the ground base layer (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920857650.6U CN210797147U (en) | 2019-06-06 | 2019-06-06 | Natural permeable quarrying paving structure for sponge city |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920857650.6U CN210797147U (en) | 2019-06-06 | 2019-06-06 | Natural permeable quarrying paving structure for sponge city |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210797147U true CN210797147U (en) | 2020-06-19 |
Family
ID=71239283
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920857650.6U Expired - Fee Related CN210797147U (en) | 2019-06-06 | 2019-06-06 | Natural permeable quarrying paving structure for sponge city |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210797147U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113584983A (en) * | 2021-07-28 | 2021-11-02 | 张家港市吉达市政路桥工程有限公司 | Asphalt pavement structure capable of automatically collecting rainwater and construction method |
-
2019
- 2019-06-06 CN CN201920857650.6U patent/CN210797147U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113584983A (en) * | 2021-07-28 | 2021-11-02 | 张家港市吉达市政路桥工程有限公司 | Asphalt pavement structure capable of automatically collecting rainwater and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202298405U (en) | Road pavement dewatering structure system | |
CN211621076U (en) | Sponge city permeable pavement | |
CN103981785A (en) | Pervious concrete paving system with penetration and drainage guide tubes | |
CN105544342A (en) | Permeable pavement based urban road time-delay drainage structure | |
CN213571359U (en) | Natural permeable quarrying paving structure for sponge city | |
CN111535098A (en) | Rainwater drainage system for green belts and sidewalks of town roads and construction method | |
CN214033246U (en) | A road seepage prevention structure for sponge city design | |
CN210797147U (en) | Natural permeable quarrying paving structure for sponge city | |
CN105484125B (en) | A kind of step of Collection utilization rainwater | |
CN217104534U (en) | Brick structure of mating formation permeates water suitable for high ground water level region | |
CN214116117U (en) | Sponge city permeable pavement | |
CN215329163U (en) | Structure of combined sponge city system for sidewalk and green belt | |
CN213740396U (en) | Natural permeable quarrying paving structure for sponge city | |
CN211815290U (en) | Combined permeable landscape sidewalk structure for sponge city | |
CN213295953U (en) | Concrete road surface structure permeates water | |
CN212335677U (en) | Farmland operation way with drainage function | |
CN210458840U (en) | Cutting road surface infiltration drainage structures | |
CN202989722U (en) | Permeable road kerb | |
CN216378982U (en) | Full-section closed type sponge road structure | |
CN220520995U (en) | Brick structure of mating formation permeates water | |
CN221218360U (en) | Sponge urban road structure | |
CN215482028U (en) | Energy-concerving and environment-protective type city hard road structure of mating formation | |
CN113136765B (en) | Water-retaining purifying drainage sidewalk | |
CN213978431U (en) | Asphalt pavement assembled gutter top layer drainage permeates water | |
CN219174918U (en) | Surface layer permeable pavement and pavement structure of high-storage-seepage grass planting ditch |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200619 |
|
CF01 | Termination of patent right due to non-payment of annual fee |