CN210767885U - Concrete placement construction prevents discrete device - Google Patents

Concrete placement construction prevents discrete device Download PDF

Info

Publication number
CN210767885U
CN210767885U CN201921660943.1U CN201921660943U CN210767885U CN 210767885 U CN210767885 U CN 210767885U CN 201921660943 U CN201921660943 U CN 201921660943U CN 210767885 U CN210767885 U CN 210767885U
Authority
CN
China
Prior art keywords
flange
fixedly connected
conveyer pipe
concrete
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921660943.1U
Other languages
Chinese (zh)
Inventor
邢战虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921660943.1U priority Critical patent/CN210767885U/en
Application granted granted Critical
Publication of CN210767885U publication Critical patent/CN210767885U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a concrete placement construction prevents discrete device relates to construction technical field, including holding pole and conveyer pipe, the first flange of bottom surface fixedly connected with of holding pole is equipped with the support column to the below of holding pole, and the last fixed surface of support column is connected with the second flange, and four screw holes have all been seted up to the upper surface of first flange and the upper surface of second flange, and the equal threaded connection of inner wall of every screw hole has the screw rod. The utility model relates to a rational in infrastructure, it can be through the cooperation setting between second flange and the first flange, realizes being connected between holding rod and the support column, through the cartridge filter that sets up, improves the degree of consistency of concrete, and the intensity of guaranteeing concrete placement has seted up the through-hole through the locating plate, makes the conveyer pipe can follow the support column and reciprocate, can adjust the height value of conveyer pipe, when avoiding the concrete to take place the dispersion, guarantees the accuracy of pouring position.

Description

Concrete placement construction prevents discrete device
Technical Field
The utility model relates to a construction technical field specifically is a concrete placement construction prevents discrete device.
Background
The construction is a production movement for constructing various building products in a certain space and time by using various building materials and mechanical equipment according to a specific design blueprint, and comprises all production processes of basic engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and completion acceptance.
When concrete pouring is carried out on a high-rise building in the construction process of the target building, a pump truck or a pump machine needs to be utilized, the concrete is caused to be dispersed due to the fact that a certain height difference exists between a conveying pipe and a poured building, the manual pulling mode is adopted, the position of pouring cannot be accurately guaranteed, the pouring quality of the concrete is influenced, and the concrete is easily damaged to constructors.
SUMMERY OF THE UTILITY MODEL
One) technical problem to be solved
The utility model aims at providing a concrete placement construction prevents discrete device in order to compensate prior art not enough exactly.
II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: a concrete pouring construction anti-dispersion device comprises a holding rod and a conveying pipe, wherein the bottom surface of the holding rod is fixedly connected with a first flange, a support column is arranged below the holding rod, the upper surface of the support column is fixedly connected with a second flange, four threaded holes are formed in the upper surface of the first flange and the upper surface of the second flange, the inner wall of each threaded hole is in threaded connection with a screw rod, the upper surface of each screw rod is fixedly connected with a rotating plate, the outer surface of each screw rod is in threaded connection with a positioning screw, a positioning plate is arranged below the second flange, a through hole is formed in the upper surface of the positioning plate, the support column is sleeved inside the through hole, the diameter value of the support column is smaller than that of the through hole, and four spring plates are fixedly connected to the bottom surface of the positioning plate;
the fixed surface of locating plate inlays and has fixed pipe, the bottom of conveyer pipe runs through fixed pipe and extends to the outside of fixed pipe, the surface of conveyer pipe and the inner wall fixed connection of fixed pipe.
Furthermore, the bottom surface of the first flange is fixedly connected with a first rubber pad, the upper surface of the second flange is fixedly connected with a second rubber pad, and the first rubber pad is in contact with the second rubber pad.
Furthermore, the bottom surface fixedly connected with block rubber of support column, and the inside fixed of block rubber inlays and has the balancing weight.
Furthermore, the connecting lines have been seted up to the bottom of conveyer pipe, the conveyer pipe has the cartridge filter through connecting lines threaded connection, and the inside fixed mosaic of cartridge filter has the filter screen.
Furthermore, the left side surface of the positioning plate is fixedly connected with a push-pull handle, and anti-skid grains are arranged on the outer surface of the push-pull handle.
Thirdly), the beneficial effects are as follows:
compared with the prior art, the concrete pouring construction anti-dispersion device has the following beneficial effects:
the utility model discloses a cooperation setting between second flange and the first flange realizes being connected between holding rod and the support column, through the cartridge filter that sets up, improves the degree of consistency of concrete, guarantees that concrete placement's intensity has seted up the through-hole through the locating plate, makes the conveyer pipe can follow the support column and reciprocate, can adjust the height value of conveyer pipe, when avoiding the concrete to take place the discrete, guarantees the accuracy of pouring position.
Two, the utility model discloses the utilization is provided with first rubber pad and second rubber pad, and the injury that vibrations that bring when can reduce conveyer pipe transport concrete caused to workman's hand through being provided with the block rubber, vibrations that bring when can further reduce conveyer pipe transport concrete utilize simultaneously to be provided with the balancing weight, improve the stability of support column, utilize the cartridge filter of setting, avoid the concrete phenomenon of caking to appear, improve the degree of consistency of concrete.
Drawings
FIG. 1 is an overall schematic view of the anti-dispersion device for concrete pouring construction of the utility model;
FIG. 2 is an enlarged schematic view of the structure at A in FIG. 1 according to the present invention;
fig. 3 is a bottom view of the filter cartridge of the present invention.
In the figure: 1. a holding rod; 2. a delivery pipe; 3. positioning a plate; 4. a fixed tube; 5. a through hole; 6. a support pillar; 7. a rubber block; 8. a spring plate; 9. a filter cartridge; 10. a push-pull handle; 11. anti-skid lines; 12. a first flange; 13. a second flange; 14. a threaded hole; 15. a rotating plate; 16. a screw; 17. a set screw; 18. a first rubber pad; 19. a second rubber pad; 20. and (4) a filter screen.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
As shown in fig. 1-3, the utility model provides a technical solution: a concrete pouring construction anti-dispersion device comprises a holding rod 1 and a conveying pipe 2, wherein the bottom surface of the holding rod 1 is fixedly connected with a first flange 12, a supporting column 6 is arranged below the holding rod 1, the upper surface of the supporting column 6 is fixedly connected with a second flange 13, four threaded holes 14 are formed in the upper surface of the first flange 12 and the upper surface of the second flange 13, the inner wall of each threaded hole 14 is in threaded connection with a screw 16, the upper surface of each screw 16 is fixedly connected with a rotating plate 15, the outer surface of each screw 16 is in threaded connection with a positioning screw 17, a positioning plate 3 is arranged below the second flange 13, a through hole 5 is formed in the upper surface of the positioning plate 3, the supporting column 6 is sleeved inside the through hole 5, the diameter value of the supporting column 6 is smaller than that of the through hole 5, and four spring plates 8 are fixedly connected to the bottom surface;
fixed surface of locating plate 3 inlays and has fixed pipe 4, and fixed pipe 4 is run through and extends to the outside of fixed pipe 4 in the bottom of conveyer pipe 2, and the surface of conveyer pipe 2 and the inner wall fixed connection of fixed pipe 4.
Further, a first rubber pad 18 is fixedly connected to the bottom surface of the first flange 12, a second rubber pad 19 is fixedly connected to the upper surface of the second flange 13, and the first rubber pad 18 contacts with the second rubber pad 19. By arranging the first rubber pad 18 and the second rubber pad 19, the damage of vibration caused by concrete conveying of the conveying pipe 2 to hands of workers can be reduced.
Further, the bottom surface fixedly connected with block rubber 7 of support column 6, and the inside fixed of block rubber 7 is inlayed and is had the balancing weight. Through being provided with rubber block 7, can further reduce the vibrations that bring when conveyer pipe 2 carries the concrete, utilize simultaneously to be provided with the balancing weight, improve the stability of support column 6.
Further, the connecting line has been seted up to conveyer pipe 2's bottom, and conveyer pipe 2 has cartridge filter 9 through connecting line threaded connection, and the inside of cartridge filter 9 is fixed to be inlayed and is had filter screen 20. Utilize the cartridge filter 9 that sets up, avoid the concrete caking phenomenon to appear, improve the degree of consistency of concrete.
Furthermore, a push-pull handle 10 is fixedly connected to the left side surface of the positioning plate 3, and anti-skid grains 11 are formed on the outer surface of the push-pull handle 10. Through being provided with push-and-pull handle 10, can improve the convenience that locating plate 3 removed, utilize to set up anti-skidding line 11, improve the frictional force between hand and push-and-pull handle 10.
The working principle is as follows: during conveyer pipe 2 carried concrete, place support column 6 on the building mold face earlier, cooperation setting between second flange 13 and the first flange 12 that the rethread set up, realize being connected between holding pole 1 and the support column 6, through-hole 5 has been seted up to utilization locating plate 3, make conveyer pipe 2 can reciprocate along support column 6, then pulling push-and-pull handle 10, make conveyer pipe 2 remove along support column 6, adjust conveyer pipe 2's height value, when avoiding the concrete to take place the dispersion, guarantee the accuracy of pouring position, simultaneously through the cartridge filter 9 that sets up, improve the degree of consistency of concrete, guarantee the intensity of concrete placement.
It should be noted that, in this document, the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention; the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance, and furthermore, unless otherwise explicitly stated or limited, the terms "fixedly," "mounted," "connected," and "connected" are to be construed broadly, e.g., "mounted" may be fixedly connected, or detachably connected, or integrally connected; "connected" may be mechanically or electrically connected; "connected" may be directly connected or indirectly connected through an intermediate member, or may be internal or external to two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a concrete placement construction prevents discrete device, includes holding pole (1) and conveyer pipe (2), its characterized in that: the bottom surface of the holding rod (1) is fixedly connected with a first flange (12), a supporting column (6) is arranged below the holding rod (1), the upper surface of the supporting column (6) is fixedly connected with a second flange (13), the upper surface of the first flange (12) and the upper surface of the second flange (13) are respectively provided with four threaded holes (14), the inner wall of each threaded hole (14) is in threaded connection with a screw rod (16), the upper surface of each screw rod (16) is fixedly connected with a rotating plate (15), the outer surface of each screw rod (16) is in threaded connection with a positioning screw (17), a positioning plate (3) is arranged below the second flange (13), the upper surface of the positioning plate (3) is provided with a through hole (5), the supporting column (6) is sleeved inside the through hole (5), and the diameter value of the supporting column (6) is smaller than that of the through hole (5), the bottom surface of the positioning plate (3) is fixedly connected with four spring plates (8);
the fixed surface of locating plate (3) inlays and has fixed pipe (4), the bottom of conveyer pipe (2) runs through fixed pipe (4) and extends to the outside of fixed pipe (4), the surface of conveyer pipe (2) and the inner wall fixed connection of fixed pipe (4).
2. The concrete pouring construction dispersion prevention device according to claim 1, wherein: the bottom surface of the first flange (12) is fixedly connected with a first rubber pad (18), the upper surface of the second flange (13) is fixedly connected with a second rubber pad (19), and the first rubber pad (18) is in contact with the second rubber pad (19).
3. The concrete pouring construction dispersion prevention device according to claim 1, wherein: the bottom surface fixedly connected with block rubber (7) of support column (6), and the inside fixed of block rubber (7) is inlayed and is had the balancing weight.
4. The concrete pouring construction dispersion prevention device according to claim 1, wherein: connecting lines have been seted up to the bottom of conveyer pipe (2), conveyer pipe (2) have cartridge filter (9) through connecting lines threaded connection, and the inside fixed mosaic of cartridge filter (9) has filter screen (20).
5. The concrete pouring construction dispersion prevention device according to claim 1, wherein: the left side face of the positioning plate (3) is fixedly connected with a push-pull handle (10), and anti-skid grains (11) are arranged on the outer surface of the push-pull handle (10).
CN201921660943.1U 2019-10-06 2019-10-06 Concrete placement construction prevents discrete device Active CN210767885U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921660943.1U CN210767885U (en) 2019-10-06 2019-10-06 Concrete placement construction prevents discrete device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921660943.1U CN210767885U (en) 2019-10-06 2019-10-06 Concrete placement construction prevents discrete device

Publications (1)

Publication Number Publication Date
CN210767885U true CN210767885U (en) 2020-06-16

Family

ID=71060411

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921660943.1U Active CN210767885U (en) 2019-10-06 2019-10-06 Concrete placement construction prevents discrete device

Country Status (1)

Country Link
CN (1) CN210767885U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111980410A (en) * 2020-08-03 2020-11-24 常德市俊德科技发展有限公司 Concrete conveying device on building tower crane

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111980410A (en) * 2020-08-03 2020-11-24 常德市俊德科技发展有限公司 Concrete conveying device on building tower crane

Similar Documents

Publication Publication Date Title
CN206987422U (en) A kind of filling device of filling concrete base contraction-free grouting concrete
CN210767885U (en) Concrete placement construction prevents discrete device
CN102433996A (en) Method for constructing wafer board with SMC (Sheet Molding Compound) hole forming mould
CN214893613U (en) Be used for water treatment medicament production to use high accuracy weighing device
CN112978568B (en) Large-scale gallipot overhead hoist
CN205333072U (en) Portable whole hangs gravity anping building laser measuring instrument
CN210256615U (en) Tower crane counter weight making devices
CN211850905U (en) Concrete evenly shakes device for civil engineering
CN207581208U (en) A kind of dual-purpose crystal holder boom hoisting
CN209353722U (en) A kind of building 3D printing pump truck system
CN209353646U (en) A kind of construction scaffold connected fastly
CN209308414U (en) A kind of builder's road formula stair step punching block
CN219971609U (en) Hoisting device for prestressed steel cylinder concrete pipe
CN208168384U (en) A kind of adjustable steel structure assembling fixture
CN207633330U (en) Filling pile cage of reinforcement absolute altitude and verticality control device under a kind of concrete water
CN207862787U (en) A kind of pin-connected panel slideway
CN114033165B (en) Template equipment for unbonded prestressed concrete silo slip form construction
CN215289708U (en) High mound construction formwork device
CN213923819U (en) Hoisting frame convenient to assemble and used for mechanical equipment
CN218493112U (en) Steel reinforced concrete template pull rod fixing device
CN221031498U (en) Concrete placement protector
CN215331685U (en) Template supporting beam device for building engineering
CN210029796U (en) Simple small-sized hoisting device
CN218952836U (en) Rotary concrete pouring equipment
CN211588437U (en) Mold loose piece, mold and casting equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant