CN210741756U CN201921812126.3U CN201921812126U CN210741756U CN 210741756 U CN210741756 U CN 210741756U CN 201921812126 U CN201921812126 U CN 201921812126U CN 210741756 U CN210741756 U CN 210741756U
Authority
CN
China
Prior art keywords
pressure testing
operation platform
clean
pressure test
baffle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921812126.3U
Other languages
Chinese (zh)
Inventor
刘学峰
张治豪
胡立新
向文军
艾力江·阿布都热依木
崔乃军
贺俊仁
王文杰
王丽
马成龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Karamay Caifeng Industrial Co ltd
Original Assignee
Xinjiang Karamay Caifeng Industrial Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Karamay Caifeng Industrial Co ltd filed Critical Xinjiang Karamay Caifeng Industrial Co ltd
Priority to CN201921812126.3U priority Critical patent/CN210741756U/en
Application granted granted Critical
Publication of CN210741756U publication Critical patent/CN210741756U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)

Abstract

The utility model provides a clean construction equipment of oil field borehole operation is simple and easy pressure testing system relates to the clean job site technical field of oil field borehole operation, including operation platform, one side of operation platform is provided with clean special car, one side of clean special car is provided with the car locomotive, the bottom of clean special car is provided with removes the wheel, the top of clean special car is provided with special frame, top one side of operation platform is provided with the baffle, one side of baffle is provided with the film, one side that operation platform's top and be located the baffle is provided with the handling frame, one side that operation platform's top and be located the handling frame is provided with the railing. The pressure testing device solves the problems that the prior pressure testing method is adopted to carry out pressure testing inspection by pressing a large pump truck on site, the pressure testing water quantity is small, the pressure testing pressure is not very high, the pressure testing by using the pump truck is waste, and the cost is high. In field tests, a pneumatic pressure test pump is generally used for pressure testing.

Description

Simple pressure test system for cleaning construction device for oil field downhole operation
Technical Field
The utility model relates to a clean job site field of oil field borehole operation especially relates to the clean construction equipment of oil field borehole operation simple and easy pressure testing system.
Background
If the bottom hole pressure is lower than the formation pressure, the fluid in the formation can enter the shaft, and after a large amount of formation fluid enters the shaft, well kick and blowout can be caused, even the well kick and blowout is out of control, well mouth equipment damage, environmental pollution, even personnel injury can be caused, and resident safety and oil-gas well safety can be harmed. The device comprises a wellhead device, a control system, various internal blowout prevention tools and the like. All adopt clear water to test pressure. No pressure drop and no leakage are required. The high-pressure test pressure is the rated working pressure. The pressure testing and stabilizing time is 30ma according to the requirements of the Xinjiang oil field. After the inspection is qualified, the wellhead operation can be lifted.
In the past, a large pump truck is pressed on site by adopting a pressure test method to carry out pressure test inspection, the pressure test water quantity is small, the pressure test pressure is not very high, the pressure test by the pump truck is waste, and the cost is high. In field tests, pneumatic pressure test pumps have been conventionally used to perform pressure tests.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The not enough to prior art, the utility model provides a clean construction equipment of oil field borehole operation simple and easy pressure testing system possesses and realizes all can carrying out the pressure testing process at the scene at any time, improves work efficiency and reduces special car expense, increases the advantage of operation profit, and it is an extravagant to have solved with the pump truck pressure testing, the also big problem of expense.
(II) technical scheme
For realize above-mentioned realization can all carry out the pressure testing process at any time at the scene, improve work efficiency and reduce the special car expense, increase the purpose of operation profit, the utility model provides a following technical scheme: clean construction equipment simple and easy pressure testing system of oil field borehole operation, including operation platform, one side of operation platform is provided with clean special car, one side of clean special car is provided with the car locomotive, the bottom of clean special car is provided with removes the wheel, the top of clean special car is provided with special frame, operation platform's top one side is provided with the baffle, one side of baffle is provided with the film, operation platform's top and the one side that is located the baffle are provided with the handling frame, operation platform's top and the one side that is located the handling frame are provided with the railing, one side of railing is provided with the fixed plate, operation platform's top and the one side that is located the handling frame are provided with the pressure testing pump.
Preferably, the number of the moving wheels is three, the two moving wheels are rotatably connected with the bottom of the special cleaning vehicle, and the one moving wheel is rotatably connected with the bottom of the head of the vehicle.
Preferably, the number of the special frames is two, and the two special frames are fixedly installed through a fixing frame.
Preferably, the number of the baffles is two, and the two groups of baffles are respectively positioned on two sides of the film.
Preferably, one side of the operation frame is provided with an escalator, and a control mechanism is arranged in the operation frame.
Preferably, the pressure test pump is located between the operation frame and the baffle, and is located one side of the railing.
(III) advantageous effects
Compared with the prior art, the utility model provides a clean construction equipment of oil field borehole operation simple and easy pressure testing system possesses following beneficial effect:
the utility model discloses in, the pressure testing pump of adoption realizes all can carrying out the pressure testing process at the scene at any time, improves work efficiency, can reduce special car expense, increases the operation profit, and well control equipment pressure testing needs the water yield not big, so the clean construction platform of borehole operation designs a low discharge capacity high pressure micropump, carries out all kinds of pressure tests, does not need large-scale pump truck, sets for the safety that the pressure release guaranteed the pressure testing operation through the relief valve.
Drawings
FIG. 1 is a schematic view of the overall structure of the simple pressure test system of the oil field downhole operation cleaning construction device of the utility model;
fig. 2 is the utility model provides a side schematic diagram of part structure in the simple and easy pressure testing system of oil field borehole operation cleaning construction device.
Illustration of the drawings:
1. an operating platform; 2. cleaning a special vehicle; 3. a vehicle head; 4. a moving wheel; 5. a special rack; 6. a baffle plate; 7. a film; 8. an operation frame; 9. a railing; 10. a fixing plate; 11. a pressure test pump.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand and understand, the present invention is further described below with reference to the following embodiments.
Referring to fig. 1-2, clean construction equipment simple and easy pressure testing system of oil field borehole operation, including operation platform 1, one side of operation platform 1 is provided with clean special car 2, one side of clean special car 2 is provided with car locomotive 3, the bottom of clean special car 2 is provided with removes wheel 4, the top of clean special car 2 is provided with special frame 5, top one side of operation platform 1 is provided with baffle 6, one side of baffle 6 is provided with film 7, one side that the top of operation platform 1 just is located baffle 6 is provided with handling frame 8, one side that the top of operation platform 1 just is located handling frame 8 is provided with railing 9, one side of railing 9 is provided with fixed plate 10, one side that the top of operation platform 1 just is located handling frame 8 is provided with pressure testing pump 11.
Furthermore, the number of the moving wheels 4 is three, two sets of the moving wheels 4 are rotatably connected with the bottom of the special cleaning vehicle 2, and one set of the moving wheels 4 is rotatably connected with the bottom of the vehicle head 3.
Furthermore, the number of the special frames 5 is two, and the two special frames 5 are fixedly installed through a fixing frame.
Further, the number of the baffles 6 is two, and the two groups of baffles 6 are respectively positioned at two sides of the film 7.
Furthermore, an escalator is arranged on one side of the operation frame 8, and a control mechanism is arranged inside the operation frame 8.
Further, the pressure test pump 11 is located between the operation frame 8 and the baffle 6 and is located on one side of the rail 9.
The utility model discloses a theory of operation and use flow: through the pressure testing pump that sets up, realize all can carrying out the pressure testing process at the scene at any time, improve work efficiency, can reduce special car expense, increase the operation profit, well control equipment pressure testing needs the water yield little, so clean construction platform of borehole operation designs a low discharge capacity high pressure small-size pump, carries out all kinds of pressure tests, does not need large-scale pump truck, sets for the safety that the pressure release guaranteed the pressure testing operation through the relief valve.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. Oil field borehole operation cleaning construction device simple and easy pressure testing system, including operation platform (1), its characterized in that: one side of operation platform (1) is provided with clean special car (2), one side of clean special car (2) is provided with car locomotive (3), the bottom of clean special car (2) is provided with removes wheel (4), the top of clean special car (2) is provided with special frame (5), top one side of operation platform (1) is provided with baffle (6), one side of baffle (6) is provided with film (7), one side of the top of operation platform (1) and the one side that is located baffle (6) is provided with handling frame (8), one side that the top of operation platform (1) and is located handling frame (8) is provided with railing (9), one side of railing (9) is provided with fixed plate (10), one side that the top of operation platform (1) and is located handling frame (8) is provided with pressure testing pump (11).
2. The oilfield downhole operation cleaning construction device simple pressure test system according to claim 1, characterized in that: the number of the moving wheels (4) is three, the two moving wheels (4) are rotatably connected with the bottom of the special cleaning vehicle (2), and the moving wheels (4) are rotatably connected with the bottom of the vehicle head (3).
3. The oilfield downhole operation cleaning construction device simple pressure test system according to claim 1, characterized in that: the number of the special frames (5) is two, and the two special frames (5) are fixedly installed through a fixing frame.
4. The oilfield downhole operation cleaning construction device simple pressure test system according to claim 1, characterized in that: the number of the baffles (6) is two, and the two groups of baffles (6) are respectively positioned at two sides of the film (7).
5. The oilfield downhole operation cleaning construction device simple pressure test system according to claim 1, characterized in that: an escalator is arranged on one side of the operating frame (8), and a control mechanism is arranged inside the operating frame (8).
6. The oilfield downhole operation cleaning construction device simple pressure test system according to claim 1, characterized in that: the pressure test pump (11) is positioned between the operating frame (8) and the baffle (6) and positioned on one side of the railing (9).
CN201921812126.3U 2019-10-26 2019-10-26 Simple pressure test system for cleaning construction device for oil field downhole operation Active CN210741756U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921812126.3U CN210741756U (en) 2019-10-26 2019-10-26 Simple pressure test system for cleaning construction device for oil field downhole operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921812126.3U CN210741756U (en) 2019-10-26 2019-10-26 Simple pressure test system for cleaning construction device for oil field downhole operation

Publications (1)

Publication Number Publication Date
CN210741756U true CN210741756U (en) 2020-06-12

Family

ID=71007263

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921812126.3U Active CN210741756U (en) 2019-10-26 2019-10-26 Simple pressure test system for cleaning construction device for oil field downhole operation

Country Status (1)

Country Link
CN (1) CN210741756U (en)

Similar Documents

Publication Publication Date Title
CN102747989B (en) Oil well casing gas collecting device
CN206067717U (en) A kind of weighbridge with washing installation for vehicle
CN1532371A (en) Combined working platform for oil/water well
CN210741756U (en) Simple pressure test system for cleaning construction device for oil field downhole operation
CN201687416U (en) Hydraulic pressure balance workover rig
CN204627478U (en) A kind of integral type cleaning system
CN204899880U (en) Sleeve pipe gas retrieves pump and impinger thereof
CN205668922U (en) A kind of lifting working platform being applicable to machinery industry
CN208073408U (en) A kind of shaft mouth operation device
CN208057080U (en) A kind of controllable apparatus for work of no killing well
CN202755949U (en) Cylinder-type wellhead pressure device
CN208203233U (en) Environment-friendly type operation wellhead liquid collecting operating platform
CN205917642U (en) Hydraulic engineering construction is with supporting safety arrangement
CN205349315U (en) Small -size skid -mounted fracturing unit
CN204312028U (en) Underground coal mine horizontal orientation km rig water treatment facilities
CN212272075U (en) Well head hydrops device
CN207437010U (en) A kind of oil-water well downhole hydraulic rotational flow flushing device
CN205858596U (en) The power set of offshore field Operating Pressure
CN201459698U (en) Integral type well-mouth operating floor
CN220851780U (en) Ground crude oil recovery device
CN205145770U (en) Filter -pressing machine oil station box foreign matter separation device
CN204712307U (en) Nylon wiper block hydraulic pressure removal device
CN211649838U (en) Skid-mounted device and crude oil gathering and transportation equipment with same
CN217028862U (en) Double-cylinder chemical feeding device for wellhead of oil pumping unit
CN116130214B (en) Transformer convenient to outage detects

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant