CN210724009U - Colliery pit shaft installation cable anchor clamps - Google Patents
Colliery pit shaft installation cable anchor clamps Download PDFInfo
- Publication number
- CN210724009U CN210724009U CN201921539206.6U CN201921539206U CN210724009U CN 210724009 U CN210724009 U CN 210724009U CN 201921539206 U CN201921539206 U CN 201921539206U CN 210724009 U CN210724009 U CN 210724009U
- Authority
- CN
- China
- Prior art keywords
- mount
- bottom plate
- cable
- screw rod
- stationary blade
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009434 installation Methods 0.000 title claims abstract description 28
- 239000003245 coal Substances 0.000 claims description 8
- 238000003466 welding Methods 0.000 claims description 4
- 239000000463 material Substances 0.000 description 2
- 230000002035 prolonged effect Effects 0.000 description 2
- 230000001629 suppression Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010030 laminating Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Clamps And Clips (AREA)
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
The utility model discloses a colliery pit shaft installation cable clamp, comprising a base plate, the connecting block is installed to one side of bottom plate, the bottom plate rotates through the connecting block and is connected with first mount, the bottom of first mount one side is connected with the stationary blade, the intermediate position at stationary blade top is connected with first bolt, the bottom plate is close to one side of stationary blade and installs the second mount, the front of second mount is provided with the through-hole, the intermediate position department at second mount top is provided with the screw. The utility model discloses an erection joint piece, connecting block are in the same place first mount and bottom plate swing joint, when needs installation cable, only need lift up one side of first mount, place the cable in the centre of first mount after lifting up, the rethread first bolt with it fix on the stationary blade can, need not install through the mode of fixed two first bolts, saved installation time.
Description
Technical Field
The utility model relates to a field specifically is a colliery pit shaft installation cable anchor clamps.
Background
The coal mine shaft is a main inlet and outlet of a mine reaching the ground, and is a throat project for lifting and transporting coal (or gangue), conveying personnel, materials and equipment, ventilating and draining water during mine production, cables, electric wires and electrified cables in the mine are attached to a well wall and extend into the mine, and in order to avoid the phenomenon of complicated and intricate lines during well wall wiring, cable clamps are used for fixing, so that the lines are prevented from being stirred together.
General cable all is the bolt through anchor clamps both ends with the cable fixation in the centre of anchor clamps, need all fix the bolt at both ends when cable installation just can, prolonged the installation time of workman to the cable, because can install the cable of different models simultaneously during cable installation, when meetting the less cable of model, then need change and install with the corresponding anchor clamps of cable model, the installation is comparatively complicated.
Disclosure of Invention
The utility model aims to provide a: in order to solve the problem that the common cables are fixed in the middle of the clamp through bolts at two ends of the clamp, the bolts at two ends are required to be fixed well during cable installation, the installation time of a worker on the cables is prolonged, the cables of different models can be installed simultaneously during cable installation, when the cables of small models are encountered, the clamps corresponding to the cable models need to be replaced to be installed, and the installation is complex, so that the cable clamp for installing the coal mine shaft is provided.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a colliery pit shaft erection cable anchor clamps, includes the bottom plate, the connecting block is installed to one side of bottom plate, the bottom plate rotates through the connecting block and is connected with first mount, the bottom of first mount one side is connected with the stationary blade, the intermediate position at stationary blade top is connected with first bolt, the bottom plate is close to one side of stationary blade and installs the second mount, the front of second mount is provided with the through-hole, the intermediate position department at second mount top is provided with the screw, the second mount rotates through the screw and is connected with the screw rod, the top in the outside of screw rod is connected with the handle, the bottom swing joint of screw rod has the briquetting.
Preferably, the top of the bottom plate and the inner wall of the first fixing frame are both provided with gaskets, and the gaskets are made of rubber.
Preferably, the second bolt is installed at both ends of the top of the bottom plate, and the diameter of the second bolt is larger than that of the first bolt.
Preferably, a clamping block is installed at the bottom of the screw, a groove is formed in the middle of the top of the pressing block, and the screw is movably connected with the pressing block through the clamping block.
Preferably, the handle and the screw rod are connected together by welding.
Preferably, the pressing block is of an arc-shaped structure.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses an erection joint piece, the connecting block is in the same place first mount and bottom plate swing joint, when needing the installation cable, only need lift up one side of first mount, place the cable in the centre of first mount after lifting up, rethread first bolt with it fix on the stationary blade can, need not install through the mode of two fixed first bolts, the installation time has been saved, through setting up the second mount, screw rod and support briquetting through installing in the second mount, through combining use between them, can fix the less cable of model in the inside of second mount, use through combining of two kinds of modes, when cable erection, can install the cable of different models simultaneously, it is comparatively convenient.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a partial schematic view of the present invention;
fig. 3 is an enlarged schematic view of a of the present invention;
fig. 4 is a schematic view of the connection structure of the screw rod and the pressing block of the present invention.
In the figure: 1. a base plate; 2. a gasket; 3. a first fixing frame; 4. connecting blocks; 5. a fixing sheet; 6. a first bolt; 7. a second bolt; 8. a second fixing frame; 9. a screw hole; 10. a through hole; 11. a screw; 12. a handle; 13. a clamping block; 14. a pressing block; 15. and (4) a groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1:
please refer to fig. 1-4: the utility model provides a colliery pit shaft erection cable anchor clamps, comprising a base plate 1, connecting block 4 is installed to one side of bottom plate 1, bottom plate 1 rotates through connecting block 4 and is connected with first mount 3, the bottom of 3 one sides of first mount is connected with stationary blade 5, the intermediate position at 5 tops of stationary blade is connected with first bolt 6, bottom plate 1 is close to one side of stationary blade 5 and installs second mount 8, the front of second mount 8 is provided with through-hole 10, the intermediate position department at 8 tops of second mount is provided with screw 9, second mount 8 rotates through screw 9 and is connected with screw rod 11, the top in the outside of screw rod 11 is connected with handle 12, the bottom swing joint of screw rod 11 has suppression piece 14.
The utility model discloses a connecting block 4 of installation in bottom plate 1 one side, connecting block 4 is in the same place first mount 3 with bottom plate 1 swing joint, when needing to install the cable, only need lift up one side of first mount, place the cable after lifting up between first mount 3 and bottom plate 1, fix it on stationary blade 5 through first bolt 6, do not need to install through the mode of fixing two first bolts 6, installation time is saved, through setting up second mount 8, through screw rod 11 and the briquetting 14 of installing in second mount 8, press down briquetting 14 through rotating screw rod 11, the briquetting 14 after pressing down contacts with the surface of cable each other, fix it, through the combined use of both, can fix the cable that the model is less in the inside of second mount 8, through the combined use of two kinds of modes, when the cable is installed, cables of different models can be installed simultaneously, and the installation is convenient.
Example 2:
please refer to fig. 1-4: the utility model provides a colliery pit shaft erection cable anchor clamps, comprising a base plate 1, connecting block 4 is installed to one side of bottom plate 1, bottom plate 1 rotates through connecting block 4 and is connected with first mount 3, the bottom of 3 one sides of first mount is connected with stationary blade 5, the intermediate position at 5 tops of stationary blade is connected with first bolt 6, bottom plate 1 is close to one side of stationary blade 5 and installs second mount 8, the front of second mount 8 is provided with through-hole 10, the intermediate position department at 8 tops of second mount is provided with screw 9, second mount 8 rotates through screw 9 and is connected with screw rod 11, the top in the outside of screw rod 11 is connected with handle 12, the bottom swing joint of screw rod 11 has suppression piece 14.
The utility model discloses a connecting block 4 of installation in bottom plate 1 one side, connecting block 4 is in the same place first mount 3 with bottom plate 1 swing joint, when needing to install the cable, only need lift up one side of first mount, place the cable after lifting up between first mount 3 and bottom plate 1, fix it on stationary blade 5 through first bolt 6, do not need to install through the mode of fixing two first bolts 6, installation time is saved, through setting up second mount 8, through screw rod 11 and the briquetting 14 of installing in second mount 8, press down briquetting 14 through rotating screw rod 11, the briquetting 14 after pressing down contacts with the surface of cable each other, fix it, through the combined use of both, can fix the cable that the model is less in the inside of second mount 8, through the combined use of two kinds of modes, when the cable is installed, cables of different models can be installed simultaneously, and the installation is convenient.
Please refer to fig. 1, the top of the bottom plate 1 and the inner wall of the first fixing frame 3 are both provided with a gasket 2, and the gasket 2 is made of rubber, the utility model discloses a set up the gasket 2 as rubber material, rubber is difficult to appear gliding phenomenon after the atress is pressed from both sides tightly, makes the cable fixed more firm.
Please refer to fig. 1, the second bolts 7 are installed at both ends of the top of the bottom plate 1, and the diameter of the second bolts 7 is larger than the diameter of the first bolts 6, the utility model discloses a diameter of the second bolts 7 is set to be larger than the diameter of the first bolts 6, because the bottom plate 1 needs to be fixed on the inner wall of the shaft, the diameter of the second bolts 7 is enlarged, so that the bottom plate 1 is more firmly attached to the shaft wall.
Referring to fig. 4, a fixture block 13 is installed at the bottom of the screw 11, a groove 15 is disposed at the middle position of the top of the pressing block 14, and the screw 11 is movably connected with the pressing block 14 through the fixture block 13, the utility model discloses a set up the groove 15 and the fixture block 13, connect the pressing block 14 with the screw 11 in a hanging manner, when the screw 11 rotates, the pressing block 14 will not rotate along with the rotation of the screw 11.
Referring to fig. 2, the handle 12 is connected with the screw rod 11 by welding, and the handle 12 is connected with the screw rod 11 by welding, so that the phenomenon that the handle 12 is broken off due to excessive force applied by the user can be avoided.
Referring to fig. 2, the pressing block 14 is an arc structure, and since most of the outer surface of the cable is cylindrical, the contact area between the pressing block 14 and the outer surface of the cable can be increased by the arc structure of the pressing block 14.
The operating principle, at first place colliery pit shaft installation cable anchor clamps in corresponding place of use, open one side of first mount 3, can place the space between first mount 3 and bottom plate 1 with the same cable of two kinds of models after opening, use through the combination of first bolt 6 and stationary blade 5, fix it on bottom plate 1, when needs install simultaneously with the less cable of model, only need to pass it in the through-hole 10 of second mount 8 inside, through rotating screw rod 11 to handle 12, the rotatory while of screw rod 11 pushes down pressing block 14, push down to the position of laminating each other with the cable surface, and push down the cable, can fix the less cable of model in the inside of second mount 8.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Claims (6)
1. The utility model provides a colliery pit shaft erection cable anchor clamps, includes bottom plate (1), its characterized in that: connecting block (4) are installed to one side of bottom plate (1), bottom plate (1) is rotated through connecting block (4) and is connected with first mount (3), the bottom of first mount (3) one side is connected with stationary blade (5), the intermediate position at stationary blade (5) top is connected with first bolt (6), bottom plate (1) is close to one side of stationary blade (5) and installs second mount (8), the front of second mount (8) is provided with through-hole (10), the intermediate position department at second mount (8) top is provided with screw (9), second mount (8) are rotated through screw (9) and are connected with screw rod (11), the top in the outside of screw rod (11) is connected with handle (12), the bottom swing joint of screw rod (11) has briquetting (14).
2. The coal mine shaft installation cable clamp of claim 1, wherein: the top of the bottom plate (1) and the inner wall of the first fixing frame (3) are both provided with gaskets (2), and the gaskets (2) are made of rubber.
3. The coal mine shaft installation cable clamp of claim 2, wherein: and the two ends of the top of the bottom plate (1) are provided with second bolts (7), and the diameters of the second bolts (7) are larger than those of the first bolts (6).
4. The coal mine shaft installation cable clamp of claim 1, wherein: the bottom of the screw rod (11) is provided with a clamping block (13), the middle position of the top of the pressing block (14) is provided with a groove (15), and the screw rod (11) is movably connected with the pressing block (14) through the clamping block (13).
5. The coal mine shaft installation cable clamp of claim 1, wherein: the handle (12) is connected with the screw rod (11) in a welding mode.
6. The coal mine shaft installation cable clamp of claim 3, wherein: the pressing block (14) is of an arc-shaped structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921539206.6U CN210724009U (en) | 2019-09-17 | 2019-09-17 | Colliery pit shaft installation cable anchor clamps |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921539206.6U CN210724009U (en) | 2019-09-17 | 2019-09-17 | Colliery pit shaft installation cable anchor clamps |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210724009U true CN210724009U (en) | 2020-06-09 |
Family
ID=70937274
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921539206.6U Active CN210724009U (en) | 2019-09-17 | 2019-09-17 | Colliery pit shaft installation cable anchor clamps |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210724009U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113629596A (en) * | 2021-09-13 | 2021-11-09 | 广东电网有限责任公司 | Cable circular cutting device |
-
2019
- 2019-09-17 CN CN201921539206.6U patent/CN210724009U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113629596A (en) * | 2021-09-13 | 2021-11-09 | 广东电网有限责任公司 | Cable circular cutting device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210724009U (en) | Colliery pit shaft installation cable anchor clamps | |
CN206099215U (en) | Electric power transmission is cable fixing device for cable | |
CN205310207U (en) | Lift operation panel of electromechanical pipelining | |
CN211480846U (en) | Building electrical wiring device | |
CN112982821B (en) | Indoor green building wallboard | |
CN212534832U (en) | Color steel tile for mounting photovoltaic panel, color steel tile clamp and mounting tool | |
CN209766312U (en) | outdoor high-voltage isolating switch | |
CN210182948U (en) | Electric wire fixing frame convenient for fixing electric wire | |
CN209786715U (en) | Branch connects waterproof box with adjust structure | |
CN212258355U (en) | Cluster type strain clamp that fixity is good | |
CN206775068U (en) | The electric power suspension line fixture flexibly dismounted | |
CN112420321A (en) | Transformer bushing convenient to cable installation | |
CN220510699U (en) | Spool connecting device for engineering construction | |
CN215484221U (en) | Connecting device suitable for building joins externally and building main body of different sizes | |
CN220325236U (en) | Waterproof bus duct | |
CN210669381U (en) | Large-span wire collecting bridge | |
CN213599220U (en) | Hanging plate for lamp installation | |
CN216029236U (en) | Gantry type drilling and screw locking equipment | |
CN212649024U (en) | Fireproof leaky cable clamp | |
CN214116697U (en) | City utility tunnel crossing pipeline crane span structure | |
CN111129911A (en) | Portable jig for assembling electric connector | |
CN214850751U (en) | Motor wire sealing device with high air tightness and rapid installation | |
CN214314479U (en) | Water conservancy construction pipe laying thread fixing device | |
CN219086689U (en) | Explosion-proof type cable poling prosthetic devices | |
CN219145545U (en) | Sealing structure of sound equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20210723 Address after: 168 Beijing Middle Road, Jinfeng District, Yinchuan City, Ningxia Hui Autonomous Region Patentee after: China ENERGY Group Ningxia Coal Industry Co., Ltd. Address before: 751400 meihuajing coal mine, Ningdong Town, Lingwu City, Yinchuan City, Ningxia Hui Autonomous Region Patentee before: Meihuajing coal mine of Ningxia Coal Industry Co., Ltd. of state energy Group |
|
TR01 | Transfer of patent right |