CN210706350U - Steel construction assembled wallboard - Google Patents
Steel construction assembled wallboard Download PDFInfo
- Publication number
- CN210706350U CN210706350U CN201921518631.7U CN201921518631U CN210706350U CN 210706350 U CN210706350 U CN 210706350U CN 201921518631 U CN201921518631 U CN 201921518631U CN 210706350 U CN210706350 U CN 210706350U
- Authority
- CN
- China
- Prior art keywords
- plywood
- waterproof
- heat preservation
- concrete
- layer plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model discloses a steel construction assembled wallboard, including first concrete plywood, the lower fixed surface of first concrete plywood is connected with waterproof plywood, the lower fixed surface of waterproof plywood is connected with the heat preservation plywood, the lower fixed surface of heat preservation plywood is connected with the plywood that gives sound insulation, the lower fixed surface of the plywood that gives sound insulation is connected with the second concrete plywood, the equal fixedly connected with peg graft in both ends of waterproof plywood, heat preservation plywood and the plywood one side that gives sound insulation, the spliced pole has all been seted up at the both ends that peg graft one side was kept away from to waterproof plywood, heat preservation plywood and the plywood that gives sound insulation. This steel construction assembled wallboard, through the setting of spliced pole and spliced eye, personnel are when installing the wallboard, and the accessible spliced pole is pegged graft and is installed in the spliced eye of another wallboard to constructor can be quick aims at wallboard and other wall bodies of having installed, the effectual work efficiency of being under construction that has promoted.
Description
Technical Field
The utility model relates to a building material technical field specifically is a steel construction assembled wallboard.
Background
Along with the continuous rising of people's standard of living, house decoration is very general phenomenon, some shops can change the tenant at any time, consequently, different trade will decorate different styles, but if people use brick or cement, resource is more extravagant, and it is heavier, consequently, can influence the progress of construction, but some steel sheets or do the wallboard with iron sheet cystosepiment, these structural strength are not high, cause the accident easily, or when using, phenomenons such as skew take place easily, if crooked or skew can influence the pleasing to the eye of people's house decoration, the time is of a specified duration, the potential safety hazard can take place, consequently, it is the required wallboard of people's life to make a high strength steelframe structure assembly board now.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a steel construction assembled wallboard has solved the problem of proposing among the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a steel construction assembled wallboard, includes the steel mount, the first concrete plywood of lower fixed surface of steel mount is connected with, the lower fixed surface of concrete plywood is connected with waterproof plywood, the lower fixed surface of waterproof plywood is connected with the heat preservation plywood, the lower fixed surface of heat preservation plywood is connected with syllable-dividing plywood, the lower fixed surface of the plywood that gives sound insulation is connected with the second concrete plywood, the equal fixedly connected with peg graft in both ends of waterproof plywood, heat preservation plywood and syllable-dividing plywood one side, peg graft hole has all been seted up at the both ends that peg graft one side was kept away from to waterproof plywood, heat preservation plywood and syllable-dividing plywood.
Optionally, the steel fixing frame, the first concrete layer plate, the waterproof layer plate, the heat preservation layer plate, the sound insulation layer plate and the second concrete layer plate are fixedly connected through adhesives.
Optionally, the heat preservation laminate is made of a polystyrene foam board.
Optionally, the waterproof laminate is made of a high-density polyethylene non-woven waterproof breathable film.
Optionally, the front surfaces of the steel fixing frame, the first concrete layer plate, the waterproof layer plate, the heat preservation layer plate, the sound insulation layer plate and the second concrete layer plate are fixedly connected with a connecting block.
Optionally, the back surfaces of the steel fixing frame, the first concrete layer plate, the waterproof layer plate, the heat preservation layer plate, the sound insulation layer plate and the second concrete layer plate are fixedly connected with connecting grooves.
(III) advantageous effects
The utility model provides a steel construction assembled wallboard possesses following beneficial effect:
1. this steel construction assembled wallboard, through the setting of spliced pole and spliced eye, personnel are when installing the wallboard, and the accessible spliced pole is pegged graft and is installed in the spliced eye of another wallboard to constructor can be quick aims at wallboard and other wall bodies of having installed, the effectual work efficiency of being under construction that has promoted.
2. This steel construction assembled wallboard, through the setting of connecting block and connecting groove, personnel can aim at connecting groove and place to the connecting block after the connecting block when the installation wallboard on, the constructor of being convenient for aims at the wallboard fast to the spliced eye can be aimed at with the inserted bar fast to personnel, effectual promotion construction work efficiency.
Drawings
Fig. 1 is a schematic three-dimensional structure of the present invention;
fig. 2 is a schematic structural view of the side of the present invention.
In the figure: 1. a first concrete laminate; 2. a waterproof laminate; 3. a heat preservation laminate; 4. a sound insulation laminate; 5. a second concrete laminate; 6. a plug rod; 7. inserting holes; 8. connecting blocks; 9. and a connecting groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 2, the present invention provides a technical solution: a steel structure assembled wallboard comprises a first concrete layer board 1, a waterproof layer board 2 is fixedly connected to the lower surface of the first concrete layer board 1, personnel can decorate an outer wall through the first concrete layer board 1 after the wallboard is installed through the arrangement of the first concrete layer board 1, so that the appearance of the outer wall is changed uniformly, a heat preservation layer board 3 is fixedly connected to the lower surface of the waterproof layer board 2, a sound insulation layer board 4 is fixedly connected to the lower surface of the heat preservation layer board 3, a second concrete layer board 5 is fixedly connected to the lower surface of the sound insulation layer board 4, personnel can decorate the interior on the surface of the second concrete layer board 5 through the arrangement of the second concrete layer board 5, inserting rods 6 are fixedly connected to two ends of one side of the waterproof layer board 2, the heat preservation layer board 3 and the sound insulation layer board 4, inserting holes 7 are formed in two ends of the heat preservation layer board 3 and the sound insulation layer board 4 far away from the inserting rods 6, through the arrangement of the inserting rod 6 and the inserting hole 7, when a worker installs a wall plate, the worker can insert the wall plate into the inserting hole 7 of another wall plate through the inserting rod 6 to install the wall plate, so that the constructor can quickly align the wall plate with other installed wall bodies, the construction work efficiency is effectively improved, the first concrete layer plate 1, the waterproof layer plate 2, the heat-preservation layer plate 3, the sound-insulation layer plate 4 and the second concrete layer plate 5 are fixedly connected by using a binder, the heat-preservation layer plate 3 is made of a polystyrene foam plate, the waterproof layer plate 2 is made of a high-density polyethylene non-woven waterproof and breathable film, the front surfaces of the first concrete layer plate 1, the waterproof layer plate 2, the heat-preservation layer plate 3, the sound-insulation layer plate 4 and the second concrete layer plate 5 are fixedly connected with a connecting block 8, and the back surfaces of the first concrete layer plate 1, the waterproof layer plate 2, the heat-preservation layer plate 3, the sound-insulation layer, through connecting block 8 and connecting groove 9's setting, personnel can place to connecting block 8 after connecting groove 9 aims at the connecting block when the installation wallboard on, the constructor of being convenient for aims at the wallboard fast to personnel can aim at plug-in connection hole 7, effectual promotion construction work efficiency with plug-in connection pole 6 fast.
To sum up, this steel construction assembled wallboard, during the use, through the setting of peg graft 6 and spliced eye 7, personnel are when installing the wallboard, install in the spliced eye 7 of another wallboard is pegged graft to accessible peg graft 6, thereby constructor can be quick aim at the wallboard with other wall bodies of having installed, the effectual work efficiency of construction that has promoted, setting through connecting block 8 and connecting groove 9, personnel can aim at connecting groove 9 when installing the wallboard and place to connecting block 8 after the connecting block on, the constructor of being convenient for aims at the wallboard fast, thereby personnel can aim at spliced eye 7 with peg graft 6 fast, effectual promotion work efficiency of construction.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.
Claims (6)
1. The utility model provides a steel construction assembled wallboard, includes first concrete plywood (1), its characterized in that: the lower fixed surface of first concrete plywood (1) is connected with waterproof plywood (2), the lower fixed surface of waterproof plywood (2) is connected with heat preservation plywood (3), the lower fixed surface of heat preservation plywood (3) is connected with syllable-dividing plywood (4), the lower fixed surface of syllable-dividing plywood (4) is connected with second concrete plywood (5), the equal fixedly connected with peg graft pole (6) in both ends of waterproof plywood (2), heat preservation plywood (3) and syllable-dividing plywood (4) one side, peg hole (7) have all been seted up at the both ends that peg pole (6) one side was kept away from in waterproof plywood (2), heat preservation plywood (3) and syllable-dividing plywood (4).
2. The steel structure assembled wallboard of claim 1, wherein: and the first concrete layer plate (1), the waterproof layer plate (2), the heat preservation layer plate (3), the sound insulation layer plate (4) and the second concrete layer plate (5) are fixedly connected by using a bonding agent.
3. The steel structure assembled wallboard of claim 1, wherein: the heat preservation laminated plate (3) is made of a polystyrene foam plate.
4. The steel structure assembled wallboard of claim 1, wherein: the waterproof laminate (2) is made of a high-density polyethylene non-woven waterproof breathable film.
5. The steel structure assembled wallboard of claim 1, wherein: the front faces of the first concrete layer plate (1), the waterproof layer plate (2), the heat preservation layer plate (3), the sound insulation layer plate (4) and the second concrete layer plate (5) are fixedly connected with connecting blocks (8).
6. The steel structure assembled wallboard of claim 1, wherein: the back fixedly connected with connecting groove (9) of first concrete plywood (1), waterproof plywood (2), heat preservation plywood (3), syllable-dividing plywood (4) and second concrete plywood (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921518631.7U CN210706350U (en) | 2019-09-12 | 2019-09-12 | Steel construction assembled wallboard |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921518631.7U CN210706350U (en) | 2019-09-12 | 2019-09-12 | Steel construction assembled wallboard |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210706350U true CN210706350U (en) | 2020-06-09 |
Family
ID=70960929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921518631.7U Active CN210706350U (en) | 2019-09-12 | 2019-09-12 | Steel construction assembled wallboard |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210706350U (en) |
-
2019
- 2019-09-12 CN CN201921518631.7U patent/CN210706350U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20140124291A1 (en) | Gypsum-panel acoustical monolithic ceiling | |
DK2971391T3 (en) | Gypsum panel for monolithic acoustic ceilings | |
CN210706350U (en) | Steel construction assembled wallboard | |
CN100398763C (en) | External wall insulating decorative board and its manufacturing method | |
CN209837455U (en) | Building decoration integration surrounding wall board, partition plate and building carrier plate | |
CN207905234U (en) | A kind of assembled heat insulation Acoustic barrier plate | |
CN210395921U (en) | Assembled dry-process fine-assembling system | |
CN203939178U (en) | A kind of multi-functional environment-protection panel | |
CN201895441U (en) | Novel decorative board | |
CN216446397U (en) | Spliced decorative plate for building engineering decoration | |
CN205329983U (en) | A fire prevention type rock wool partition plate for building | |
CN204386122U (en) | A kind of light-weight building ceiling corner line | |
CN204282590U (en) | Foam concrete curtain wall | |
CN213539474U (en) | Light composite concrete plate | |
CN214531289U (en) | Building construction firewall structure | |
CN213115273U (en) | Graphene composite wood board | |
CN213979716U (en) | Calcium silicate board | |
CN211341505U (en) | Elevator layer shows beautifies plate structure | |
CN216142311U (en) | Hanging plate wall | |
CN214834297U (en) | Dado coupling mechanism | |
CN203296291U (en) | Background wall veneer | |
CN100398764C (en) | Fixing device of heat insulating decorative board | |
CN216142310U (en) | Integrated indoor environmental protection integration fitment subassembly | |
CN209779866U (en) | decoration-free environment-friendly building structural member | |
CN212317361U (en) | Artistic carved board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||