CN210685427U - Concrete pouring tool for complex node of building structure - Google Patents

Concrete pouring tool for complex node of building structure Download PDF

Info

Publication number
CN210685427U
CN210685427U CN201921590199.2U CN201921590199U CN210685427U CN 210685427 U CN210685427 U CN 210685427U CN 201921590199 U CN201921590199 U CN 201921590199U CN 210685427 U CN210685427 U CN 210685427U
Authority
CN
China
Prior art keywords
concrete
storage cavity
building
building structure
drainage device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921590199.2U
Other languages
Chinese (zh)
Inventor
吴必深
李永辉
王昆
杨槐
钟乙册
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201921590199.2U priority Critical patent/CN210685427U/en
Application granted granted Critical
Publication of CN210685427U publication Critical patent/CN210685427U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a concrete pouring tool for complex nodes of building structures, which relates to the concrete pouring field of building nodes, and comprises a pump pipe for conveying concrete, wherein the outlet of the pump pipe is connected with a drainage device for draining the concrete, the drainage device is arranged on a movable assembly to form a structure that the movable assembly drives the drainage device to move and pour the building nodes, the drainage device comprises a feed inlet, a storage cavity and a guide pipe, the pump pipe is formed by pouring the concrete from the feed inlet into the storage cavity and further pours the building nodes through the guide pipe, a stirring assembly for stirring the concrete is further arranged in the storage cavity, the concrete pouring work of workers can be conveniently carried out, and the compactness of pouring the building nodes can be increased by uniformly pouring the building nodes, the construction quality is improved.

Description

Concrete pouring tool for complex node of building structure
Technical Field
The utility model relates to a complicated node concrete placement instrument of building structure.
Background
The concrete is required to be poured after the formwork is erected in the building construction process, in the prior art, the pump pipes are used for conveying the concrete and pouring the concrete into the formwork by workers, the pump pipes containing the concrete are heavy, when the formwork is poured, a plurality of workers are required to lift and move along the formwork for pouring, the moving speed of the pump pipes cannot be controlled in the pouring process, the concrete has certain fluidity, but the fluidity is not strong, so that the uniformity of concrete pouring in the formwork cannot be guaranteed in the traditional method for pouring the building formwork, the compactness of concrete pouring at certain positions in the formwork is insufficient, the pouring efficiency of the workers is reduced, and the construction quality is influenced.
Some more complicated node positions that relate to in the construction, because of the reinforcing bar of laying is too intensive, if the not closely knit problem of pouring appears more easily in the unable assurance of concrete pouring's homogeneity, make building shock resistance reduce, produce the influence to the appearance quality of concrete simultaneously.
SUMMERY OF THE UTILITY MODEL
The utility model provides a can realize concrete evenly pour a complicated node concrete placement instrument of building structure, the closely knit degree that increases building node and pour is evenly pour through building node simultaneously in the work of workman concrete placement of being convenient for, improves construction quality.
The technical scheme of the utility model is realized like this: the utility model provides a complicated node concrete placement instrument of building structure, is including the pump line that is used for concrete feeding, the exit linkage of pump line has the drainage device that is used for carrying out the drainage to the concrete, drainage device locates on the removal subassembly, forms the removal subassembly drives drainage device removes and carries out the structure of pouring to the building node, drainage device includes feed inlet, storage chamber and honeycomb duct, forms the pump line with the concrete by the feed inlet is emptyd into the storage intracavity and further pour the structure of building node through the honeycomb duct, the storage intracavity further is equipped with the stirring subassembly that is used for carrying out the stirring to the concrete.
The technical effect of the scheme is as follows: the removal subassembly of pump line connection carries out the drainage to the concrete, make the concrete pour the in-process to the template with a comparatively even speed, it drives the pump line removal through leaving over the device to replace the manual work to remove the subassembly simultaneously, can realize controlling the displacement rate of pump line through the control to control removal subassembly, be convenient for guarantee the homogeneity that concrete placement in-process was pour, the concrete is discharged by the honeycomb duct after the stirring of stirring assembly in the storage intracavity, the homogeneity in the concrete gets into the template by the honeycomb duct has further been increased, the pouring speed to the concrete is cushioned, cause the impact to the good reinforcing bar of building node ligature when preventing that the concrete from toppling over, the quality of concrete placement has been increased to a certain extent.
On the basis of the scheme, the stirring assembly is further improved as follows, the stirring assembly comprises a stirring blade, a rotating shaft and a motor, the output end of the motor is connected with the rotating shaft to form a structure that the motor drives the stirring blade to rotate through the rotating shaft.
The technical effect of the scheme is as follows: the motor stirs the concrete through pivot electric mixing blade at the storage cavity internal rotation, guarantees the concrete and has promoted the quality of pouring of concrete by the intraductal exhaust homogeneity of water conservancy diversion behind the storage cavity.
On the basis of the scheme, the drainage device is further improved as follows, the moving assembly comprises a supporting base and a roller, and the supporting base is arranged below the drainage device.
On the basis of the scheme, the material storage cavity is further improved as follows, and the material storage cavity is fixed on the supporting base through a fixing support.
On the basis of the scheme, the structure is further improved as follows, the fixing supports are of an L-shaped structure, the number of the fixing supports is multiple, the fixing supports are evenly arranged on the side portions of the material storage cavity, and the fixing supports are respectively connected with the supporting base and the material storage cavity through bolts.
The technical effect of the scheme is as follows: the storage cavity passes through the fixed bolster to be fixed on supporting the base, and wherein the fixed bolster has increased the fixed stability of storage cavity on the fixed bolster.
On the basis of the scheme, the structure is further improved as follows, the feed inlet is of a circular truncated cone-shaped structure, and the lower end of the storage cavity is communicated with the inside of the storage cavity through the flow guide pipe.
On the basis of the scheme, the structure is further improved as follows, and the guide pipe is obliquely arranged at the lower end of the storage cavity.
On the basis of the scheme, the diameter of the lower end of the material storage cavity is gradually contracted from top to bottom to form a conical structure.
The technical effect of the scheme is as follows: the feed inlet concrete of being convenient for gets into the storage intracavity by the opening of pump line, and the honeycomb duct slope sets up and can cushions the concrete of pouring the in-process, and the velocity of flow of control concrete makes the concrete evenly carry out in the template, and the toper structure of storage chamber lower extreme is convenient for the concrete and flows into the honeycomb duct, reduces the gathering of concrete in the storage intracavity simultaneously.
On the basis of the scheme, the feed inlet is further improved as follows, and the upper side of the feed inlet is connected with a fixed flange through a fixed frame.
On the basis of the scheme, the outlet of the pump pipe is connected with the fixed flange through a bolt.
The technical effect of the scheme is as follows: the opening of pump line passes through mounting flange and is connected with fixed frame, has further increased the fixed stability in feed inlet upper end of pump line.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without inventive exercise.
Fig. 1 is a cross-sectional view of the front view of the present invention in the vertical direction;
FIG. 2 is a schematic view of a connection structure between a stirring assembly and a material storage chamber of the present invention;
FIG. 3 is a schematic view of the connection structure between the fixing flange and the discharge hole of the present invention;
wherein: 1-pump pipe, 21-feed inlet, 22-storage cavity, 221-fixed support, 23-guide pipe, 24-stirring component, 241-stirring blade, 242-rotating shaft, 243-motor, 31-supporting base, 32-roller, 4-fixed frame and 42-fixed flange.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention. It should be noted that in the description of the present invention, the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicating the directions or positional relationships are based on the directions or positional relationships shown in the drawings, which are only for convenience of description, and do not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," "third," and "fourth" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
Furthermore, it should be noted that, in the description of the present invention, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
The utility model relates to a concrete placement tool's of complicated node of building structure concrete placement's embodiment:
as shown in fig. 1-3, including pump line 1 that is used for the concrete to carry, the exit linkage of pump line 1 has the drainage device that is used for carrying out the drainage to the concrete, and pump line 1 carries the concrete after the stirring to drainage device, and on drainage device located the removal subassembly, the removal subassembly drove the drainage device and removes, further is equipped with the stirring subassembly 24 that is used for carrying out the stirring to the concrete in the drainage device.
The drainage device comprises a feed inlet 2, a storage cavity 22 and a guide pipe 23, wherein the feed inlet 2 is of a round table structure, the lower end of the feed inlet 2 is communicated with the inside of the storage cavity 22, the storage cavity 22 is of a cylindrical structure, the lower end of the storage cavity 22 is of a conical structure, the central position of the lower end of the storage cavity 22 is communicated with the guide pipe 23, the guide pipe 23 is of a cylindrical structure, the guide pipe 23 is communicated with the inside of the storage cavity 22 through the joint of the guide pipe 23 and the storage cavity 22, a certain included angle is formed between the axis of the guide pipe 23 and the axis of the storage cavity 22, the guide pipe 23 is obliquely arranged relative to the storage cavity 22, a stirring assembly 24 for stirring concrete is arranged in the storage cavity 22, the upper part of the guide pipe 23 is connected with an outlet of the pump pipe 1 through a fixing frame 4, wherein the fixing frame 4 is a rectangular frame, four corners of the fixing frame, the fixing flange 42 is fixed at the center of the fixing frame 4, the fixing flange 42 is connected to four corners of the fixing frame 4 by connecting rods, and the fixing flange 42 is connected to the outlet of the pump pipe 1 by bolts.
Stirring subassembly 24 includes stirring vane 241, pivot 242 and motor 243, the output and the pivot 242 of motor 243 are connected, stirring vane 241 sets up relatively fixed connection structure with pivot 242, motor 243 drives stirring vane 241 through pivot 242 after being connected with the power and stirs the concrete that gets into in storage cavity 22 at storage cavity 22 internal rotation, the homogeneity that the concrete mixes has further been guaranteed, certain cushioning effect is played to the concrete that falls into in the storage cavity simultaneously.
The moving assembly includes a supporting base 31 and a roller 32, the roller 32 is installed at the lower end of the supporting base 31, the supporting base 31 can be pushed to move by the roller 32, the storage cavity 22 in the drainage device is arranged on the moving component by the fixed bracket 221, wherein fixed bolster 221 is "L" font structure, the vertical part of fixed bolster 221 is the arc surface structure with storage cavity 22 outer wall looks adaptation, the vertical part of fixed bolster 221 is connected through the outer wall of bolt with storage cavity 22, the horizontal part of fixed bolster 221 passes through the bolt and fixes with the upper end that supports base 31, fixed bolster 221 has a plurality ofly, evenly fix the outside at storage cavity 22 between each is fixed, the fixed stability between drainage device and the removal subassembly has been increased, the removal subassembly drives the pump line and the removal of drainage subassembly, remove the subassembly through promoting and remove the change that the subassembly removed and can realize the concrete placement position.
The utility model discloses a concrete using-way as follows:
the mixed concrete is conveyed through the pump pipe 1, the outlet of the pump pipe 1 is fixed above the feed inlet 2, the concrete enters the feed inlet 2 from the outlet of the pump pipe 1, the feed inlet 2 is of a round table structure, the concrete can conveniently enter the feed inlet 2, the concrete further enters the storage cavity 22 through the feed inlet 2, the concrete entering the storage cavity 22 is further stirred by the stirring component 24 arranged in the storage cavity 22, the concrete entering the storage cavity 22 can not be directly led out through the guide pipe 23, the concrete is further mixed under the stirring action of the stirring blades 241, the impact force of the concrete falling into the storage cavity 22 is buffered, the concrete is poured to a building node through the guide pipe 23 after being stirred, the guide pipe 23 is obliquely arranged with the storage cavity 22, and the uniformity of the concrete discharged from the guide pipe 23 after passing through the storage cavity 22 is further ensured, meanwhile, the pouring speed of the concrete is buffered to a certain extent, so that the condition that the templates and the reinforcing steel bars are deformed due to the fact that several kinds of poured concrete impact the reinforcing steel bars bound by the building nodes is prevented, the pouring quality of the concrete is improved, the material storage cavity 22 is fixed on the supporting base 31 through the fixing support 221, the roller 32 arranged below the supporting base 31 further drives the supporting base 31 to move, when the building nodes are poured, the supporting base 31 is pushed to move on the pouring platform, the position of the guide pipe 23 and the relative position of the templates are changed to realize the change of the pouring position of the templates, compared with the traditional mode that the pump pipe 1 is manually supported to pour the templates, the operation is facilitated, the uniformity of the concrete pouring is also improved, and the uniformity and the compactness of the pouring of the building templates, particularly building nodes with complicated preset reinforcing steel bar structures are improved, the concrete pouring quality of the building node is improved.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. The utility model provides a complicated node concrete placement instrument of building structure, a serial communication port, including the pump line that is used for concrete feeding, the exit linkage of pump line has the drainage device that is used for carrying out the drainage to the concrete, drainage device locates on the removal subassembly, forms the removal subassembly drives drainage device removes and carries out the structure of pouring to the building node, drainage device includes feed inlet, storage cavity and honeycomb duct, forms the pump line with the concrete by the feed inlet is emptyd into the storage cavity further carries out the structure of pouring to the building node through the honeycomb duct, the storage cavity is interior further to be equipped with the stirring subassembly that is used for carrying out the stirring to the concrete.
2. The concrete pouring tool for the complex node of the building structure is characterized in that the stirring assembly comprises a stirring blade, a rotating shaft and a motor, wherein the output end of the motor is connected with the rotating shaft, so that a structure that the motor drives the stirring blade to rotate through the rotating shaft is formed.
3. The building structure complex node concrete pouring tool of claim 1, wherein the moving assembly comprises a support base and rollers, the support base is arranged below the drainage device.
4. The concrete pouring tool for the complex node of the building structure as recited in claim 3, wherein the storage cavity is fixed on the supporting base by a fixing bracket.
5. The building structure complex node concrete pouring tool according to claim 4, wherein the fixing support is of an L-shaped structure, the number of the fixing supports is multiple, each fixing support is uniformly arranged on the side of the storage cavity, and the fixing supports are respectively connected with the supporting base and the storage cavity through bolts.
6. The building structure complex node concrete pouring tool as claimed in claim 1, wherein the feed inlet is of a truncated cone structure, and the flow guide pipe is communicated with the interior of the storage cavity at the lower end of the storage cavity.
7. The concrete pouring tool for the complex node of the building structure as recited in claim 6, wherein the draft tube is obliquely arranged at the lower end of the storage cavity.
8. The concrete pouring tool for the complex node of the building structure as claimed in claim 6, wherein the diameter of the lower end of the storage cavity gradually shrinks from top to bottom to form a conical structure.
9. The concrete pouring tool for the complex node of the building structure is characterized in that a fixing flange is connected to the upper side of the feeding hole through a fixing frame.
10. The concrete pouring tool for the complex node of the building structure is characterized in that the outlet of the pump pipe is connected with the fixing flange through a bolt.
CN201921590199.2U 2019-09-24 2019-09-24 Concrete pouring tool for complex node of building structure Expired - Fee Related CN210685427U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921590199.2U CN210685427U (en) 2019-09-24 2019-09-24 Concrete pouring tool for complex node of building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921590199.2U CN210685427U (en) 2019-09-24 2019-09-24 Concrete pouring tool for complex node of building structure

Publications (1)

Publication Number Publication Date
CN210685427U true CN210685427U (en) 2020-06-05

Family

ID=70893084

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921590199.2U Expired - Fee Related CN210685427U (en) 2019-09-24 2019-09-24 Concrete pouring tool for complex node of building structure

Country Status (1)

Country Link
CN (1) CN210685427U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113202311A (en) * 2021-04-28 2021-08-03 上海建工二建集团有限公司 Concrete pumping self-stirring device and mounting method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113202311A (en) * 2021-04-28 2021-08-03 上海建工二建集团有限公司 Concrete pumping self-stirring device and mounting method thereof

Similar Documents

Publication Publication Date Title
CN212498312U (en) Prevent stifled concrete mixer of using
CN210685427U (en) Concrete pouring tool for complex node of building structure
CN218643887U (en) Civil engineering watering device
CN220146379U (en) Stirring equipment for melting materials
CN112372797A (en) Pouring device for producing concrete bricks
CN209207752U (en) A kind of thermal insulation mortar mixing plant
CN214026190U (en) A auxiliary device for prefabricated pit shaft concrete placement
CN213198183U (en) High-uniformity compact concrete pouring structure
CN210500825U (en) Concrete mixing device
CN213107478U (en) Aerated concrete block pouring device
CN212146981U (en) Cement stirring device
CN214644774U (en) Concrete mixing device with anti-blocking structure for building
CN220725778U (en) High security pouring device
CN210210882U (en) Be applied to cement mixer of town road construction
CN213868803U (en) Plastering device for building construction
CN215319544U (en) Diversion trench for concrete mixing plant
CN220373556U (en) Anti-blocking concrete mixer
CN215790675U (en) Soft material arranging and distributing device
CN211597751U (en) Adjustable concrete pouring device and concrete pouring equipment
CN213674765U (en) Improved pouring mixer
CN212355102U (en) Discharging mechanism of dry-mixed mortar bulk mobile silo
CN217353605U (en) Building is built with pouring machine
CN219359780U (en) Pouring device for processing concrete aerated bricks
CN215150383U (en) Pouring equipment for manufacturing concrete square pile
CN210361907U (en) High and large formwork construction equipment for constructional engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200605

CF01 Termination of patent right due to non-payment of annual fee