CN210684429U - A kind of long-span tied arch bridge approach bridge jacking system - Google Patents
A kind of long-span tied arch bridge approach bridge jacking system Download PDFInfo
- Publication number
- CN210684429U CN210684429U CN201921276039.0U CN201921276039U CN210684429U CN 210684429 U CN210684429 U CN 210684429U CN 201921276039 U CN201921276039 U CN 201921276039U CN 210684429 U CN210684429 U CN 210684429U
- Authority
- CN
- China
- Prior art keywords
- bridge
- column
- vertical
- jacking
- pier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本实用新型属于桥梁顶升施工技术领域,尤其是涉及一种大跨径系杆拱桥引桥顶升系统。The utility model belongs to the technical field of bridge jacking construction, in particular to a jacking system for an approach bridge of a large-span tie-rod arch bridge.
背景技术Background technique
桥梁顶升施工(也称为桥梁顶升技术)是指采用整体液压同步升高方案,也就是利用原有灌注桩承重,不破坏原桥面铺装层、栏杆扶手、人行道、梁板间的连接等,先用液压顶升装置整体顶住桥梁上部结构,然后截断各墩、台帽梁下的立柱,再操作液压顶升装置,使该桥整体升高到设计高度,最后接长立柱钢筋立模浇灌二期砼。桥梁上部结构指的是桥梁支座以上(无铰拱起拱线或框架主梁底线以上)跨越桥孔部分的总称。近年来,随着经济发展的需要以及桥梁顶升技术的提高,越来越多桥梁顶升技术被应用于桥梁改造工程中。桥梁顶升技术是通过液压顶升系统将桥面顶高至期望标高的一项技术,桥梁顶升技术在国内桥梁改造和支座更换中应用较广,而且桥梁液压同步顶升也有一定的研究和工程应用,实践证明,在桥梁顶升平移改造中完全可以达到安全运营、节约投资、造型美观等方面的要求。Bridge jacking construction (also known as bridge jacking technology) refers to the use of the overall hydraulic synchronous lifting scheme, that is, the use of the original cast-in-place piles to bear the load without damaging the original bridge deck pavement, railings, sidewalks, beams and slabs. For connection, etc., first use the hydraulic jacking device to stand up the upper structure of the bridge as a whole, then cut off the columns under each pier and the cap beam, and then operate the hydraulic jacking device to raise the bridge as a whole to the design height, and finally connect the column steel bars. The second-stage concrete is poured by vertical formwork. The superstructure of the bridge refers to the general term for the part that spans the bridge hole above the bridge support (the arch line of the unhinged arch or the bottom line of the main girder of the frame). In recent years, with the needs of economic development and the improvement of bridge jacking technology, more and more bridge jacking technologies have been used in bridge reconstruction projects. Bridge jacking technology is a technology that lifts the bridge deck to the desired elevation through a hydraulic jacking system. Bridge jacking technology is widely used in domestic bridge reconstruction and bearing replacement, and bridge hydraulic synchronous jacking has also been studied to some extent. And engineering application, practice has proved that the requirements of safe operation, saving investment, and beautiful appearance can be fully met in bridge jacking and translation transformation.
但目前国内尚没有针对桥梁顶升平移改造的设计、施工与检测规范,这使得桥梁顶升、平移改造的技术先进性能的应用受到一定程度的限制,而且现有的顶升工程大多为简支结构和连续梁。对跨运河航道的大跨径钢管砼系杆拱桥的大吨位整体同步顶升的技术应用国内尚无先例。However, there is currently no design, construction and testing specification for bridge jacking and translation transformation in China, which limits the application of the technologically advanced performance of bridge jacking and translation transformation to a certain extent, and most of the existing jacking projects are simply supported. Structural and continuous beams. There is no domestic precedent for the application of the technology for the overall synchronous jacking of the large tonnage of the large-span concrete-filled steel tube tied arch bridge across the canal channel.
大跨桥梁也称为大跨度桥梁或大跨径桥梁,大跨度桥梁是指多孔跨径总长≥100米或单孔跨径≥40米的桥梁。桥梁跨径也称桥梁跨度,一般指桥梁的总跨径,总跨径是指多孔桥梁中各孔净跨径的总和。其中多孔跨径总长是指桥梁的总长度,即桥梁主梁的总长度。对跨运河航道的大跨径钢管砼系杆拱桥进行顶升施工时,施工难度非常大且存在的安全隐患多。如位于宁杭高速公路溧阳段与芜申线运河交叉处的南河特大桥,南北走向,该桥于2003年建成通车且其作为高速公路的一部分,修建时间较短,使用状况良好。但现阶段根据航道整治规划的要求,南河特大桥现状通航尺度不满足整治后的三级航道通航净空尺度要求。桥位段高速公路处在8500m半径的圆曲线上,高速公路设计速度120km/h,双向六车道。北引桥纵坡为1.570%上坡,南引桥纵坡为1.570%下坡,桥梁处竖曲线半径20000m,路桥分界填土高度约6.5m,桥跨布置为10×25m组合箱梁+130m钢管混凝土系杆拱+4×25m组合箱梁+(2×20+18+14)现浇连续箱梁+4×25m组合箱梁,组合箱梁为先简支后连续结构。桥梁总长659.44m,横向双幅布置,桥面全宽=15.75m(单幅宽度)+4.5m(中分带)+15.75m(单幅宽度)=36m,单幅桥横向布置为:0.5m(护栏)+15.25m(机动车道)+1m(护栏)=16.75m,因而桥梁设计等级高、主桥跨度大且引桥跨数多。桥位处水面宽60m,通行净高5m。主墩(即主桥桥墩)的墩身为矩形截面,外侧墩柱截面尺寸3.6×2.4m,内侧墩柱截面尺寸3.6×4.6m,均采用钻孔灌注桩群桩基础,桩径为φ1.8m,桩底进入强风化岩,承台高度为3m;引桥采用柱式桥墩,钻孔灌注桩基础,桥墩直径为φ1.3m,桩径为φ1.5m;桥台为肋板式桥台,钻孔灌注桩基础且桩径为φ1.2m。南河特大桥的拱肋采用哑铃型钢管混凝土结构,横梁和系梁均为预应力混凝土结构。引桥桥墩中还包括两个独柱墩,独柱墩采用直径为φ1.8m的独墩柱,群桩基础且桩径为φ1.2m。南河特大桥的主桥为长度为130m的钢管混凝土系杆拱桥(也称为钢管砼系杆拱桥),引桥为预应力组合箱梁和现浇混凝土箱梁结构,因而引桥为混凝土箱梁。南河特大桥的通航净宽为60m,满足三级航道净宽;但净高为5m,不满足三级航道要求,需调整为7m。因此需要抬高老桥,对老桥进行顶升改造,改造桥梁提升高度为2.161m。由于桥梁整体顶升抬高,为了降低桥台填土高度并与周边协调,两侧引桥需相应延长,本次北引桥增加4孔跨径为25米的组合箱梁,南引桥增加6孔跨径为25米的组合箱梁,由于增加桥跨,桥台需改造为桥墩。Long-span bridges are also called long-span bridges or large-span bridges. Long-span bridges refer to bridges with a total length of multi-hole spans ≥ 100 meters or a single-hole span ≥ 40 meters. Bridge span, also known as bridge span, generally refers to the total span of the bridge, and the total span refers to the sum of the net spans of each hole in the porous bridge. The total length of the porous span refers to the total length of the bridge, that is, the total length of the main beam of the bridge. When the large-span concrete-filled steel tube tied arch bridge across the canal channel is jacked up, the construction is very difficult and there are many potential safety hazards. For example, the Nanhe Bridge, located at the intersection of the Liyang section of the Nanjing-Hangzhou Expressway and the Wushen Line Canal, runs north-south. The bridge was completed and opened to traffic in 2003 and is part of the expressway. It has been constructed for a short time and is in good condition. However, at this stage, according to the requirements of the waterway regulation plan, the current navigable scale of the Nanhe Extra Large Bridge does not meet the requirements of the navigable clearance scale of the third-level waterway after the regulation. The expressway in the bridge section is on a circular curve with a radius of 8500m, the design speed of the expressway is 120km/h, and there are six lanes in both directions. The longitudinal slope of the north approach bridge is 1.570% upslope, the south approach bridge is 1.570% downslope, the vertical curve radius at the bridge is 20000m, the filling height of the road and bridge boundary is about 6.5m, and the bridge span is arranged as 10×25m composite box girder + 130m steel tube concrete Tie-rod arch+4×25m composite box girder+(2×20+18+14) cast-in-situ continuous box girder+4×25m composite box girder, composite box girder is simply supported first and then continuous structure. The total length of the bridge is 659.44m, and the horizontal double width is arranged. The full width of the bridge deck = 15.75m (single width) + 4.5m (middle section) + 15.75m (single width) = 36m, and the horizontal layout of the single bridge is: 0.5m ( guardrail) + 15.25m (motor vehicle lane) + 1m (guardrail) = 16.75m, so the bridge design level is high, the main bridge span is large and the number of approach bridge spans is large. The width of the water surface at the bridge is 60m, and the clear height is 5m. The pier body of the main pier (that is, the main bridge pier) has a rectangular section, the section size of the outer pier column is 3.6 × 2.4 m, and the section size of the inner pier column is 3.6 × 4.6 m. 8m, the pile bottom enters strongly weathered rock, and the height of the cap is 3m; the approach bridge adopts column pier, bored pile foundation, the diameter of the pier is φ1.3m, and the diameter of the pile is φ1.5m; the bridge abutment is a ribbed abutment, drilled Hole cast-in-place pile foundation and the pile diameter is φ1.2m. The arch rib of the Nanhe Bridge adopts a dumbbell-shaped concrete-filled steel tubular structure, and the beams and the tie beams are all prestressed concrete structures. The approach bridge pier also includes two single-column piers. The single-column pier adopts a single pier column with a diameter of φ1.8m, and the group pile foundation and the pile diameter is φ1.2m. The main bridge of the Nanhe Bridge is a 130m long CFST tied arch bridge (also known as a CFST tied arch bridge), and the approach bridge is a prestressed composite box girder and cast-in-place concrete box girder structure, so the approach bridge is a concrete box girder. The navigable net width of the Nanhe Extra Large Bridge is 60m, which meets the clear width of the third-level channel; but the clear height is 5m, which does not meet the requirements of the third-level channel, and needs to be adjusted to 7m. Therefore, the old bridge needs to be raised, and the old bridge needs to be lifted and reconstructed. The lifting height of the reconstructed bridge is 2.161m. Due to the overall lifting of the bridge, in order to reduce the height of the abutment fill and coordinate with the surrounding area, the approach bridges on both sides need to be extended accordingly. This time, the north approach bridge will add 4 holes of composite box girder with a span of 25 meters, and the south approach bridge will have 6 holes span. The combined box girder with a diameter of 25 meters needs to be transformed into a bridge pier due to the increase of the bridge span.
经过慎重的安全、技术方面的比选,对南河特大桥进行顶升施工时,对南河特大桥的主桥和两个引桥分别进行顶升。对引桥进行顶升时,存在以下施工难题:第一、引桥跨数多且顶升重量大,风险点分散,整体顶升施工过程不易控制;第二、顶升过程中,桥梁上部结构处于悬浮状态,存在极大的安全隐患,必须采取有效措施化解以上风险,确保桥梁和施工人员的安全;第三、顶升高度较高,顶升高度达2.16m,临时垫块和顶升循环多,对支撑结构的整体稳定性提出了更高的要求,必须确保纵横支撑体系的牢固、可靠、不失稳。After careful comparison of safety and technology, the main bridge and the two approach bridges of the Nanhe Bridge were jacked up respectively during the jacking construction of the Nanhe Bridge. When jacking the approach bridge, there are the following construction problems: First, the approach bridge has a large number of spans and heavy lifting weight, the risk points are scattered, and the overall jacking construction process is not easy to control; second, during the jacking process, the upper structure of the bridge is in suspension There is a great potential safety hazard, and effective measures must be taken to resolve the above risks to ensure the safety of the bridge and construction personnel; third, the jacking height is high, the jacking height is 2.16m, and there are many temporary pads and jacking cycles. Higher requirements are placed on the overall stability of the support structure, and the vertical and horizontal support systems must be firm, reliable, and not destabilized.
由上述内容可知,对跨运河航道的大跨径钢管砼系杆拱桥进行顶升施工时,工艺复杂、难度大、安全风险高,并且顶升高度为2m以上,施工工期短,任务重,目前尚无成功经验借鉴,可供借鉴的技术资料较少。From the above content, it can be seen that the construction of the large-span concrete-steel-steel tie-rod arch bridge across the canal channel is complex, difficult, and has high safety risks, and the jacking height is more than 2m, the construction period is short, and the task is heavy. There is no successful experience for reference, and there are few technical materials for reference.
实用新型内容Utility model content
本实用新型所要解决的技术问题在于针对上述现有技术中的不足,提供一种大跨径系杆拱桥引桥顶升系统,其结构设计合理、施工简便且使用效果好,采用左右两个对称布设的引桥主梁顶升装置对待顶升引桥主梁进行竖向顶升,引桥主梁顶升装置中采用竖向顶升装置与辅助支撑结构相配合进行顶升,辅助支撑结构对待顶升引桥主梁进行平稳支撑的同时对待顶升引桥主梁进行主动顶升,竖向顶升装置与辅助支撑结构中的千斤顶均倒置布设,每次完成顶升后在千斤顶下方支垫临时支撑件时无需移动千斤顶,省工省时,并能确保千斤顶位置不动;同时所采用的临时支撑结构不仅支撑强度大,承重效果好,并且支撑稳定性好,结构稳定、可靠,确保引桥主梁顶升过程平稳、可靠。The technical problem to be solved by the present invention is to provide a large-span tied arch bridge approach bridge jacking system in view of the above-mentioned deficiencies in the prior art, which has reasonable structural design, simple construction and good use effect. The main beam jacking device of the approach bridge is used to vertically lift the main beam of the approach bridge to be jacked up. The vertical jacking device is used in the main beam jacking device of the approach bridge to cooperate with the auxiliary support structure to support the main beam of the approach bridge to be lifted smoothly. At the same time, the main beam of the approach bridge is to be actively jacked. The vertical jacking device and the jack in the auxiliary support structure are arranged upside down. After each jacking is completed, there is no need to move the jack when a temporary support is placed under the jack, saving labor. It saves time and can ensure that the position of the jack is not fixed; at the same time, the temporary support structure adopted not only has high supporting strength, good load-bearing effect, but also has good supporting stability, stable and reliable structure, and ensures the stable and reliable lifting process of the main beam of the approach bridge.
为解决上述技术问题,本实用新型采用的技术方案是:一种大跨径系杆拱桥引桥顶升系统,其特征在于:包括左右两个对称布设且对待顶升引桥主梁进行竖向顶升的引桥主梁顶升装置,所述待顶升引桥主梁为大跨径系杆拱桥的引桥主梁;所述待顶升引桥主梁呈水平布设且其包括左右两幅对称布设的纵向主梁,两幅所述纵向主梁均沿纵桥向布设;每个所述引桥主梁顶升装置均支撑于一幅所述纵向主梁的正下方,每个所述引桥主梁顶升装置均包括一个桥台侧液压顶升装置和一个桥墩侧液压顶升装置,所述桥台侧液压顶升装置和桥墩侧液压顶升装置的结构相同且二者均为引桥梁端顶升装置;In order to solve the above-mentioned technical problems, the technical scheme adopted by the present utility model is: a large-span tied arch bridge approach bridge jacking system, which is characterized in that it includes two symmetrical layouts on the left and right and vertical jacking of the main beam of the approach bridge to be jacked up. The main beam of the approach bridge to be lifted is the main beam of the approach bridge of the large-span tie-rod arch bridge; the main beam of the approach bridge to be lifted is horizontally arranged and includes two symmetrically arranged longitudinal main beams on the left and right, The two longitudinal main beams are arranged along the longitudinal bridge direction; each of the approach bridge main beam jacking devices is supported directly below one of the longitudinal main beams, and each approach bridge main beam jacking device includes an abutment side hydraulic jack Lifting device and a bridge pier side hydraulic jacking device, the abutment side hydraulic jacking device and the bridge pier side hydraulic jacking device have the same structure and both are approach bridge end jacking devices;
所述待顶升引桥主梁支撑于引桥下部结构上,所述引桥下部结构包括左右两个对称布设的引桥下部支撑结构,每幅所述纵向主梁均支撑于一个所述引桥下部支撑结构上;每个所述引桥下部支撑结构均包括一个桥台和一个竖向桥墩上;所述纵向主梁的一端为支撑于桥台上的待接续端,所述纵向主梁的另一端为支撑于所述竖向桥墩上的连接端;The main beam of the approach bridge to be lifted is supported on the lower structure of the approach bridge, and the lower structure of the approach bridge includes two symmetrically arranged lower support structures of the approach bridge, and each of the longitudinal main beams is supported on one of the lower support structures of the approach bridge Each of the lower support structures of the approach bridge includes an abutment and a vertical pier; one end of the longitudinal main girder is the end to be connected to be supported on the abutment, and the other end of the longitudinal main girder is supported on the abutment. the connecting end on the vertical pier;
每个所述桥台上均设置有一个对纵向主梁进行竖向顶升的桥台侧液压顶升装置,每个所述竖向桥墩上均设置有一个对纵向主梁进行竖向顶升的桥墩侧液压顶升装置;每个所述桥台侧液压顶升装置均支撑于一个所述纵向主梁的所述待接续端下方,每个所述桥墩侧液压顶升装置均支撑于一个所述纵向主梁的所述连接端下方;Each of the bridge abutments is provided with an abutment-side hydraulic jacking device for vertically lifting the longitudinal main beam, and each vertical bridge pier is provided with a vertical lifting device for the vertical main beam The bridge pier side hydraulic jacking device; each abutment side hydraulic jacking device is supported under the to-be-connected end of one of the longitudinal main beams, and each bridge pier side hydraulic jacking device is supported on a below the connecting end of the longitudinal main beam;
每个所述桥台侧液压顶升装置均支撑于一个所述桥台的桥台基础上,每个所述桥墩侧液压顶升装置均支撑于一个所述竖向桥墩的桥墩基础上或均支撑于一个水平混凝土基础上,所述水平混凝土基础位于所述桥墩基础一侧且其与所述桥墩基础浇筑为一体;所述桥台基础和所述桥墩基础均为呈水平布设的钢筋混凝土基础;所述桥台基础、所述桥墩基础和所述水平混凝土基础均为反力基础;Each of the abutment-side hydraulic jacking devices is supported on an abutment foundation of the abutment, and each of the bridge pier-side hydraulic jacking devices is supported on a bridge pier foundation of the vertical pier or both Supported on a horizontal concrete foundation, the horizontal concrete foundation is located on one side of the bridge pier foundation and is cast into one with the bridge pier foundation; the bridge abutment foundation and the bridge pier foundation are both reinforced concrete foundations arranged horizontally ; The abutment foundation, the bridge pier foundation and the horizontal concrete foundation are all reaction force foundations;
每个所述引桥梁端顶升装置均包括一道支撑于纵向主梁底部的横向分配梁、多个沿横桥向由左至右布设的竖向顶升装置和多个沿横桥向由左至右布设的辅助支撑结构,所述竖向顶升装置和辅助支撑结构均呈竖直向布设且二者的数量均相同,所述竖向顶升装置和辅助支撑结构均支撑于横向分配梁的正下方,所述横向分配梁沿横桥向布设且其与所支撑纵向主梁的底面呈平行布设;每个所述引桥梁端顶升装置中多个竖向顶升装置和多个所述辅助支撑结构均布设于待顶升引桥主梁的同一个横断面上,每个所述引桥梁端顶升装置中所述竖向顶升装置和辅助支撑结构呈交错布设;Each of the approach bridge end jacking devices includes a horizontal distribution beam supported at the bottom of the longitudinal main girder, a plurality of vertical jacking devices arranged from left to right along the transverse bridge direction, and a plurality of vertical jacking devices arranged from left to right along the transverse bridge direction To the auxiliary support structure arranged to the right, the vertical jacking device and the auxiliary support structure are arranged vertically and the number of the two are the same, and both the vertical jacking device and the auxiliary support structure are supported on the horizontal distribution beam Just below the horizontal distribution beam, the horizontal distribution beam is arranged along the transverse bridge direction and is arranged in parallel with the bottom surface of the supported longitudinal main beam; in each of the approach bridge end jacking devices, a plurality of vertical jacking devices and a plurality of The auxiliary support structures are all arranged on the same cross section of the main girder of the approach bridge to be jacked up, and the vertical jacking device and the auxiliary support structure in each of the approach bridge end jacking devices are arranged in a staggered manner;
所述竖向顶升装置包括竖向千斤顶和布设于竖向千斤顶正下方的竖向支顶机构,所述辅助支撑结构包括随动千斤顶和布设于随动千斤顶正下方的竖向支撑结构,所述竖向支顶机构和所述竖向支撑结构均为临时支撑结构;所述竖向千斤顶和随动千斤顶均为呈竖直向布设的倒置千斤顶,所述倒置千斤顶为底座朝上且刚性顶举件朝下的液压千斤顶;每个所述倒置千斤顶的底座均水平固定在位于其正上方的横向分配梁底部,每个所述倒置千斤顶的刚性顶举件均支顶在位于其正下方的所述临时支撑结构上;每个所述临时支撑结构均支撑于位于其下方的所述反力基础上,每个所述临时支撑结构均由多个从下至上布设的临时支撑件拼接而成,多个所述临时支撑件的结构均相同且其均为呈水平布设的钢管支撑结构;The vertical jacking device includes a vertical jack and a vertical jacking mechanism arranged directly below the vertical jack, and the auxiliary support structure includes a follow-up jack and a vertical support structure arranged directly below the follow-up jack, so The vertical jacking mechanism and the vertical support structure are both temporary support structures; the vertical jacks and the follower jacks are both vertically arranged upside-down jacks, and the upside-down jack is a rigid jack with a base facing upwards. The hydraulic jack with the lifting piece facing down; the base of each said inverted jack is fixed horizontally at the bottom of the horizontal distribution beam directly above it, and the rigid jacking piece of each said inverted jack is supported on the bottom of the horizontal distribution beam directly below it. on the temporary support structure; each temporary support structure is supported on the reaction force foundation located below it, and each temporary support structure is formed by splicing a plurality of temporary supports arranged from bottom to top , the structures of a plurality of the temporary supports are the same and they are all steel pipe support structures arranged horizontally;
所述钢管支撑结构为圆柱形,所述临时支撑结构中所有钢管支撑结构的直径均相同且其均呈同轴布设;每个所述钢管支撑结构均包括竖向支撑钢管、一个同轴固定于竖向支撑钢管上部的上连接环和一个同轴固定于竖向支撑钢管底部的下连接环,所述上连接环和下连接环均为水平圆环形钢板且二者均固定在竖向支撑钢管的外侧壁上,所述上连接环和下连接环的结构和尺寸均相同;所述上连接环的上表面与竖向支撑钢管的上表面相平齐,下连接环的底面与竖向支撑钢管的底面相平齐;所述上连接环和下连接环上均开有多个沿圆周方向均匀布设的螺栓安装孔;The steel pipe support structure is cylindrical, and all the steel pipe support structures in the temporary support structure have the same diameter and are arranged coaxially; each of the steel pipe support structures includes a vertical support steel pipe, a The upper connecting ring on the upper part of the vertical support steel pipe and a lower connecting ring fixed on the bottom of the vertical support steel pipe coaxially, the upper connecting ring and the lower connecting ring are both horizontal circular steel plates and both are fixed on the vertical support On the outer side wall of the steel pipe, the structure and size of the upper connecting ring and the lower connecting ring are the same; the upper surface of the upper connecting ring is flush with the upper surface of the vertical support steel pipe, and the bottom surface of the lower connecting ring is the same as the vertical The bottom surfaces of the supporting steel pipes are flush with each other; the upper connecting ring and the lower connecting ring are provided with a plurality of bolt mounting holes evenly arranged along the circumferential direction;
所述临时支撑结构中上下相邻两个所述钢管支撑结构组成一个钢管支撑组合,所述钢管支撑组合中位于上方的钢管支撑结构为上钢管支撑结构,所述钢管支撑组合中位于下方的钢管支撑结构为下钢管支撑结构,所述钢管支撑组合中所述上钢管支撑结构的下连接环与所述下钢管支撑结构的上连接环通过多个连接螺栓紧固连接为一体,通过多个所述连接螺栓紧固连接为一体的下连接环与上连接环组成一个加固环;所述连接螺栓呈竖直向布设,每个所述连接螺栓均安装于所述加固环中上下连通的两个所述螺栓安装孔内。In the temporary support structure, the upper and lower adjacent steel pipe support structures form a steel pipe support combination. The support structure is a lower steel pipe support structure. In the steel pipe support combination, the lower connection ring of the upper steel pipe support structure and the upper connection ring of the lower steel pipe support structure are fastened and connected together through a plurality of connecting bolts. The lower connecting ring and the upper connecting ring, which are integrally fastened and connected by the connecting bolts, form a reinforcing ring; the connecting bolts are arranged vertically, and each connecting bolt is installed on two upper and lower connecting rings in the reinforcing ring. in the bolt mounting hole.
上述一种大跨径系杆拱桥引桥顶升系统,其特征是:每个所述引桥主梁顶升装置还包括多个对所述倒置千斤顶的位置进行调整的千斤顶纠偏机构;每个所述引桥主梁顶升装置中所述千斤顶纠偏机构的数量与该引桥主梁顶升装置中所包括倒置千斤顶的数量相同,所述引桥主梁顶升装置中每个所述倒置千斤顶上均安装有一个千斤顶纠偏机构;The above-mentioned jacking system for an approach bridge of a large-span tied arch bridge is characterized in that: each of the approach bridge main girder jacking devices further includes a plurality of jack correction mechanisms for adjusting the position of the inverted jack; The number of the jack correction mechanisms in the beam jacking device is the same as the number of inverted jacks included in the approach bridge main beam jacking device, and a jack deflection correction mechanism is installed on each of the inverted jacks in the approach bridge main beam jacking device;
所述千斤顶纠偏机构包括对所调整倒置千斤顶的位置进行水平调整的水平纠偏机构,所述水平纠偏机构包括多个水平调整件、一个供所调整倒置千斤顶的底座安装的下固定板和一个位于下固定板上方的上固定板,多个所述水平调整件的结构均相同且其沿圆周方向布设于所调整倒置千斤顶的四周外侧;所调整倒置千斤顶的底座水平固定在下固定板底部,所述下固定板固定于所调整倒置千斤顶的底座上方,所述下固定板为平直钢板且其与所调整倒置千斤顶的底座呈平行布设;所述上固定板为平直钢板;The jack correction mechanism includes a horizontal correction mechanism for horizontally adjusting the position of the adjusted upside-down jack, and the horizontal correction mechanism includes a plurality of horizontal adjustment pieces, a lower fixing plate for the base of the adjusted upside-down jack to be installed, and a lower fixed plate. On the upper fixing plate above the fixing plate, a plurality of the horizontal adjustment pieces have the same structure and are arranged on the outer periphery of the adjusted inverted jack in the circumferential direction; the base of the adjusted inverted jack is horizontally fixed on the bottom of the lower fixed plate, and the lower The fixing plate is fixed above the base of the adjusted upside-down jack, the lower fixing plate is a flat steel plate and is arranged in parallel with the base of the adjusted upside-down jack; the upper fixing plate is a flat steel plate;
每个所述水平调整件均包括一个呈竖直向布设的螺栓杆、一个同轴安装于螺栓杆上的限位螺母和一个同轴安装在螺栓杆顶部的上滑移件,所述螺栓杆为平直杆,所述限位螺母位于上滑移件下方,所述限位螺母与螺栓杆之间以螺纹方式进行连接;Each of the horizontal adjustment pieces includes a bolt rod arranged in a vertical direction, a limit nut coaxially mounted on the bolt rod, and an upper sliding piece coaxially mounted on the top of the bolt rod. It is a straight rod, the limit nut is located under the upper sliding member, and the limit nut and the bolt rod are connected by a thread;
所述上固定板上开有多个供上滑移件横向滑移的横向滑移槽和多个供螺栓杆进行横向移动的横向插孔,所述横向滑移槽为平直槽且其与上固定板呈平行布设,所述上滑移件与上固定板呈平行布设;所述横向滑移槽的数量与上滑移件的数量相同,多个所述横向滑移槽均呈平行布设且其均沿所施工桥梁的横桥向进行布设,多个所述横向滑移槽的结构和尺寸均相同;所述横向插孔的数量与横向滑移槽的数量相同,多个所述横向插孔均为长条形孔且其结构和尺寸均相同,多个所述横向插孔均与横向滑移槽呈平行布设;所述横向插孔的长度与横向滑移槽的长度相同,所述横向插孔的宽度大于横向滑移槽的宽度;每个所述横向插孔均位于一个所述横向滑移槽的正下方,每个所述横向插孔均与位于其正上方的横向滑移槽连通;The upper fixing plate is provided with a plurality of lateral sliding grooves for the lateral sliding of the upper sliding member and a plurality of lateral insertion holes for the bolt rods to move laterally, and the lateral sliding grooves are straight grooves and are connected with each other. The upper fixing plate is arranged in parallel, the upper sliding piece and the upper fixing plate are arranged in parallel; the number of the lateral sliding grooves is the same as that of the upper sliding piece, and the plurality of lateral sliding grooves are arranged in parallel And they are all arranged along the transverse bridge direction of the bridge under construction, and the structures and dimensions of the plurality of said transverse sliding grooves are the same; the number of said transverse insertion holes is the same as that of The jacks are all elongated holes with the same structure and size, and a plurality of the horizontal jacks are arranged in parallel with the horizontal sliding groove; the length of the horizontal jacks is the same as that of the horizontal sliding groove, so The width of the lateral insertion holes is greater than the width of the lateral sliding grooves; each of the lateral insertion holes is located directly below one of the lateral sliding grooves, and each of the lateral insertion holes is connected to the lateral sliding slot directly above it. transfer groove connection;
所述下固定板上开有多个供螺栓杆进行纵向移动的纵向插孔,多个所述纵向插孔均为长条形孔且其结构和尺寸均相同,多个所述纵向插孔均呈平行布设且其均与横向插孔呈垂直布设;所述纵向插孔的数量与横向插孔的数量相同,每个所述纵向插孔均位于一个所述横向插孔下方,每个所述纵向插孔均与位于其下方的横向插孔组成一个十字形调整孔;每个所述十字形调整孔中纵向插孔与横向插孔相交叉的区域为供一个所述螺栓杆安装的螺栓安装孔,每个所述螺栓杆均安装于一个所述螺栓安装孔内;The lower fixing plate is provided with a plurality of longitudinal insertion holes for the bolt rod to move longitudinally, and the plurality of longitudinal insertion holes are all elongated holes and have the same structure and size. are arranged in parallel and are arranged perpendicular to the horizontal jacks; the number of the vertical jacks is the same as the number of horizontal jacks, each of the vertical jacks is located under one of the horizontal jacks, and each of the vertical jacks The longitudinal sockets and the transverse sockets below it form a cross-shaped adjustment hole; the area where the longitudinal sockets and the transverse sockets intersect in each of the cross-shaped adjustment holes is a bolt installation for one of the bolt rods to be installed. holes, each of the bolt rods is installed in one of the bolt installation holes;
所述千斤顶纠偏机构中上固定板和下固定板组成水平调整平台,每个所述上滑移件均布设于一个所述横向滑移槽内,每个所述限位螺母均支撑于下固定板底部,每个所述螺栓杆均通过上滑移件和限位螺母紧固固定在所述水平调整平台上;所述下固定板通过多个所述水平调整件与上固定板紧固连接。The upper fixed plate and the lower fixed plate in the jack correction mechanism constitute a horizontal adjustment platform, each of the upper sliding parts is arranged in one of the lateral sliding grooves, and each of the limit nuts is supported on the lower fixed plate. At the bottom of the plate, each of the bolt rods is fastened and fixed on the horizontal adjustment platform through the upper sliding piece and the limit nut; the lower fixed plate is fastened to the upper fixed plate through a plurality of the horizontal adjustment pieces. .
上述一种大跨径系杆拱桥引桥顶升系统,其特征是:所述千斤顶纠偏机构还包括在竖直面上对所调整倒置千斤顶的位置进行调整的竖向纠偏机构,所述竖向纠偏机构包括支垫于上固定板与下固定板之间的楔形钢板,所述竖向纠偏机构紧固夹装于上固定板与下固定板之间。The above-mentioned lifting system for the approach bridge of a large-span tie-rod arch bridge is characterized in that: the jack rectification mechanism further comprises a vertical deviation rectification mechanism for adjusting the position of the adjusted upside-down jack on a vertical plane, and the vertical deviation rectification mechanism The mechanism includes a wedge-shaped steel plate supported between the upper fixing plate and the lower fixing plate, and the vertical deviation correction mechanism is fastened and clamped between the upper fixing plate and the lower fixing plate.
上述一种大跨径系杆拱桥引桥顶升系统,其特征是:所述临时支撑结构中位于底部的钢管支撑结构为底部钢管支撑结构,所述底部钢管支撑结构的下连接环为底部支撑环,所述底部支撑环通过多个下锚栓固定在所述反力基础上,所述下锚栓呈竖直向布设;所述底部支撑环上的所述螺栓安装孔为底部安装孔,每个所述下锚栓均安装于一个所述底部安装孔内。The above-mentioned large-span tie-rod arch bridge approach bridge jacking system is characterized in that: the steel pipe support structure at the bottom of the temporary support structure is the bottom steel pipe support structure, and the lower connecting ring of the bottom steel pipe support structure is the bottom support ring , the bottom support ring is fixed on the reaction force foundation through a plurality of lower anchor bolts, and the lower anchor bolts are arranged vertically; the bolt installation holes on the bottom support ring are bottom installation holes, each Each of the lower anchor bolts is installed in one of the bottom installation holes.
上述一种大跨径系杆拱桥引桥顶升系统,其特征是:所述引桥下部支撑结构还包括多个均位于桥台与所述竖向桥墩之间的柱式桥墩,多个所述柱式桥墩沿纵桥向由前至后布设,多个所述柱式桥墩均呈竖直向布设且其均支撑于一幅所述纵向主梁的正下方;The above-mentioned lifting system for an approach bridge of a large-span tied arch bridge is characterized in that: the lower support structure of the approach bridge further comprises a plurality of column-type bridge piers located between the bridge abutment and the vertical bridge pier, a plurality of the columns The column-type bridge piers are arranged from front to rear along the longitudinal bridge direction, and a plurality of the column-type bridge piers are arranged in the vertical direction and are supported directly below one of the longitudinal main beams;
多个所述柱式桥墩的结构均相同,每个所述柱式桥墩均包括左右两个对称布设的竖向墩柱和一个支撑于两个所述竖向墩柱上方的上部盖梁,所述竖向墩柱为钢筋混凝土柱,所述上部盖梁为沿横桥向布设的混凝土盖梁,两个所述竖向墩柱通过上部盖梁紧固连接为一体;The structures of a plurality of the column-type piers are the same, and each of the column-type piers includes two symmetrically arranged vertical piers on the left and right and an upper cover beam supported above the two vertical piers. The vertical pier columns are reinforced concrete columns, the upper cover beams are concrete cover beams arranged along the transverse bridge direction, and the two vertical pier columns are fastened and connected as a whole through the upper cover beams;
所述引桥主梁顶升装置还包括多个柱式桥墩液压顶升装置,所述柱式桥墩液压顶升装置的数量与所述引桥下部支撑结构中柱式桥墩的数量相同,每个所述柱式桥墩上均设置有一个所述柱式桥墩液压顶升装置;The main girder jacking device of the approach bridge also includes a plurality of column-type bridge pier hydraulic jacking devices, and the number of the column-type bridge pier hydraulic jacking devices is the same as the number of the column-type bridge piers in the lower support structure of the approach bridge. The bridge piers are all provided with a hydraulic jacking device of the column-type bridge piers;
每个所述引桥主梁顶升装置中桥台侧液压顶升装置、桥墩侧液压顶升装置和多个所述柱式桥墩液压顶升装置均布设于同一竖直面上,多个所述柱式桥墩液压顶升装置的结构均相同,每个所述柱式桥墩液压顶升装置均位于一幅所述纵向主梁的正下方;In each of the approach bridge main girder jacking devices, the abutment-side hydraulic jacking device, the bridge pier-side hydraulic jacking device, and the plurality of column-type bridge pier hydraulic jacking devices are all arranged on the same vertical surface, and a plurality of the column-type hydraulic jacking devices are arranged on the same vertical surface. The structures of the bridge pier hydraulic jacking devices are all the same, and each of the column-type bridge pier hydraulic jacking devices is located directly below one of the longitudinal main beams;
每个所述柱式桥墩上均设置有一个下抱柱梁和一个上抱柱梁,所述上抱柱梁位于下抱柱梁的正上方;所述下抱柱梁和上抱柱梁均为水平抱柱梁,所述水平抱柱梁为固定于两个所述竖向墩柱上的钢筋混凝土梁,所述水平抱柱梁为矩形且其套装于两个所述竖向墩柱上;每个所述柱式桥墩液压顶升装置均支撑于一个所述下抱柱梁和位于该下抱柱梁正上方的上抱柱梁之间,所述下抱柱梁为所述反力基础;Each of the column-type piers is provided with a lower column beam and an upper column beam, and the upper column beam is located directly above the lower column beam; the lower column beam and the upper column beam are both It is a horizontal pillar-holding beam, and the horizontal pillar-holding beam is a reinforced concrete beam fixed on two described vertical piers. Each described column type bridge pier hydraulic jacking device is all supported between a described lower column-holding beam and the upper column-holding beam located just above the lower column-holding beam, and the lower column-holding beam is the reaction force Base;
每个所述柱式桥墩液压顶升装置均包括支撑于下抱柱梁与上抱柱梁之间的竖向液压顶升机构,所述竖向液压顶升机构包括竖向顶升装置和辅助支撑结构;所述柱式桥墩液压顶升装置中每个所述倒置千斤顶的底座均水平固定在上抱柱梁底部,每个所述倒置千斤顶的刚性顶举件均支顶在位于其正下方的所述临时支撑结构上;所述柱式桥墩液压顶升装置中每个所述临时支撑结构均支撑于下抱柱梁上。Each of the column-type bridge pier hydraulic jacking devices includes a vertical hydraulic jacking mechanism supported between the lower pillar-holding beam and the upper pillar-holding beam, and the vertical hydraulic jacking mechanism includes a vertical jacking device and an auxiliary Supporting structure; the base of each inverted jack in the hydraulic jacking device of the column type bridge pier is horizontally fixed on the bottom of the upper pillar beam, and the rigid jacking member of each inverted jack is supported directly below it Each temporary support structure in the column-type bridge pier hydraulic jacking device is supported on the lower column beam.
上述一种大跨径系杆拱桥引桥顶升系统,其特征是:每个所述柱式桥墩液压顶升装置中所述竖向液压顶升机构的数量为两组,两组所述竖向液压顶升机构对称支撑于下抱柱梁的左右两侧上方;每组所述竖向液压顶升机构均包括两个对称布设于一个所述竖向墩柱前后两侧的所述竖向液压顶升机构;The above-mentioned jacking system for an approach bridge of a large-span tied arch bridge is characterized in that: the number of the vertical hydraulic jacking mechanisms in the hydraulic jacking device of each column-type pier is two groups, and the two groups of the vertical hydraulic jacking mechanism The hydraulic jacking mechanism is symmetrically supported on the left and right sides of the lower pillar beam; each group of the vertical hydraulic jacking mechanism includes two vertical hydraulic jacks symmetrically arranged on the front and rear sides of one of the vertical piers jacking mechanism;
每个所述竖向液压顶升机构均包括两个竖向顶升装置和一个支撑于两个所述竖向顶升装置之间的辅助支撑结构,每个所述竖向液压顶升机构中两个所述竖向顶升装置对称布设于辅助支撑结构的左右两侧且三者均布设于待顶升引桥主梁的同一个横断面上。Each of the vertical hydraulic jacking mechanisms includes two vertical jacking devices and an auxiliary support structure supported between the two vertical jacking devices, and each of the vertical hydraulic jacking mechanisms The two vertical jacking devices are symmetrically arranged on the left and right sides of the auxiliary support structure, and the three are arranged on the same cross section of the main beam of the approach bridge to be jacked.
上述一种大跨径系杆拱桥引桥顶升系统,其特征是:每个所述柱式桥墩上均设置有一个顶升限位装置;The above-mentioned jacking system for an approach bridge of a large-span tied arch bridge is characterized in that: each of the column-type piers is provided with a jacking-up limiting device;
所述下抱柱梁的长度与上抱柱梁的长度相同,所述下抱柱梁的宽度大于上抱柱梁的宽度;The length of the lower column-supporting beam is the same as the length of the upper column-supporting beam, and the width of the lower column-supporting beam is greater than the width of the upper column-supporting beam;
每个所述顶升限位装置包括两个对称于下抱柱梁左右两端上方的顶升限位机构,每个所述顶升限位机构均包括两个对称于下抱柱梁前后两端的顶升限位柱;所述顶升限位柱为竖向立柱,所述竖向立柱为由多个平直杆件拼接而成的钢立柱;所述顶升限位装置中顶升限位柱的数量为四个,四个所述顶升限位柱分别固定在下抱柱梁的四个顶角上;Each of the lifting limiting devices includes two lifting limiting mechanisms symmetrically positioned above the left and right ends of the lower pillar-holding beam. The lifting limit column at the end; the lifting limit column is a vertical column, and the vertical column is a steel column spliced by a plurality of straight rods; the lifting limit device in the lifting limit device The number of position columns is four, and the four lifting limit columns are respectively fixed on the four top corners of the lower column beam;
所述上抱柱梁卡装于所述顶升限位机构中的两个所述顶升限位柱之间。The upper pillar-holding beam is clamped between the two jacking-limiting columns in the jacking-limiting mechanism.
上述一种大跨径系杆拱桥引桥顶升系统,其特征是:所述引桥下部支撑结构还包括多个均位于桥台与所述竖向桥墩之间的独柱墩,多个所述独柱墩沿纵桥向由前至后布设,多个所述独柱墩均呈竖直向布设且其均支撑于一幅所述纵向主梁的正下方;The above-mentioned lifting system for an approach bridge of a large-span tied arch bridge is characterized in that: the lower support structure of the approach bridge further comprises a plurality of single-column piers located between the bridge abutment and the vertical bridge pier, and a plurality of the single-column piers are located between the abutment and the vertical bridge pier. The column piers are arranged from front to back along the longitudinal bridge direction, and a plurality of the single-column piers are arranged vertically and are supported directly below one of the longitudinal main beams;
所述引桥主梁顶升装置还包括多个独柱墩液压顶升装置,所述独柱墩液压顶升装置的数量与所述引桥下部支撑结构中独柱墩的数量相同,每个所述独柱墩上均设置有一个所述独柱墩液压顶升装置;The main girder jacking device of the approach bridge also includes a plurality of hydraulic jacking devices for single-column piers, and the number of the hydraulic jacking devices for single-column piers is the same as the number of single-column piers in the lower support structure of the approach bridge. A single-column pier hydraulic jacking device is arranged on each pier;
每个所述引桥下部支撑结构中所有柱式桥墩分为前后两组,每组所述柱式桥墩均包括多个沿纵桥向由前至后布设的柱式桥墩;每个所述引桥下部支撑结构中多个所述独柱墩均位于两组所述柱式桥墩之间,每个所述引桥下部支撑结构中多个所述独柱墩与两组所述柱式桥墩均布设于同一个竖直面上;All column piers in the lower support structure of each approach bridge are divided into two groups, front and rear, each group of column piers includes a plurality of column piers arranged from front to rear along the longitudinal bridge direction; the lower part of each approach bridge A plurality of the single-column piers in the support structure are located between the two groups of the column-type piers, and the plurality of the single-column piers and the two groups of the column-type piers in each of the lower support structures of the approach bridge are arranged in the same place. a vertical plane;
每个所述独柱墩均包括一个竖向墩柱,所述竖向墩柱位于一幅所述纵向主梁的正下方;Each of the single-column piers includes a vertical pier, and the vertical pier is located directly below one of the longitudinal main beams;
每个所述独柱墩上均设置有一个墩体抱柱梁,所述墩体抱柱梁为固定于竖向墩柱上且呈水平布设的钢筋混凝土梁,所述墩体抱柱梁为方形且其套装于竖向墩柱上;每个所述独柱墩液压顶升装置均支撑于一个所述墩体抱柱梁上,所述墩体抱柱梁为所述反力基础;Each of the single-column piers is provided with a pier-column-carrying beam, the pier-column-carrying beam is a reinforced concrete beam fixed on the vertical pier column and arranged horizontally, and the pier-column-carrying beam is It is square and is sleeved on the vertical pier column; each of the single-column pier hydraulic jacking devices is supported on one of the pier body-supporting column beams, and the pier body-supporting column beam is the reaction foundation;
每个所述独柱墩液压顶升装置均包括多组沿纵桥向布设由前至后布设在同一竖直面上的墩体顶升机构,多组所述墩体顶升机构的结构均相同且其均位于一幅所述纵向主梁的正下方;每组所述墩体顶升机构均包括两个对称布设于竖向墩柱左右两侧的竖向顶升装置和两个对称布设于竖向墩柱左右两侧的辅助支撑结构,每组所述墩体顶升机构中两个所述辅助支撑结构均位于两个所述竖向顶升装置之间,每组所述墩体顶升机构中两个所述辅助支撑结构和两个所述竖向顶升装置均位于待顶升引桥主梁的同一个横断面上;Each of the single-column pier hydraulic jacking devices includes a plurality of groups of pier body jacking mechanisms arranged along the longitudinal bridge direction from front to back on the same vertical plane, and the structures of the plurality of groups of pier body jacking mechanisms are all The same and they are all located directly below the longitudinal main beam; each group of the pier body jacking mechanism includes two symmetrically arranged vertical piers on the left and right sides of the vertical jacking device and two symmetrically arranged The auxiliary support structures on the left and right sides of the vertical pier column, the two auxiliary support structures in each group of the pier body jacking mechanisms are located between the two vertical jacking devices, each group of the pier body In the jacking mechanism, the two auxiliary support structures and the two vertical jacking devices are located on the same cross section of the main beam of the approach bridge to be jacked;
所述独柱墩液压顶升装置中每个所述倒置千斤顶的底座均水平支顶在待顶升引桥主梁底部,每个所述倒置千斤顶的刚性顶举件均支顶在位于其正下方的所述临时支撑结构上;所述独柱墩液压顶升装置中每个所述临时支撑结构均支撑于墩体抱柱梁上。The base of each inverted jack in the single-column pier hydraulic jacking device is horizontally supported at the bottom of the main girder of the approach bridge to be lifted, and the rigid jacking member of each inverted jack is supported directly below it. on the temporary support structure; each temporary support structure in the single-column pier hydraulic jacking device is supported on the column-carrying beam of the pier body.
本实用新型与现有技术相比具有以下优点:Compared with the prior art, the utility model has the following advantages:
1、结构简单、设计合理且投入施工成本较低。1. The structure is simple, the design is reasonable and the construction cost is low.
2、竖向顶升装置与辅助支撑结构中所采用的千斤顶均倒置且固定于待顶升桥梁上部结构底部,每次完成顶升后在千斤顶下方支垫临时支撑件时无需移动千斤顶,省工省时,并能确保千斤顶位置不动。并且,也能避免频繁对千斤顶进行拆装时所产生的施工误差,并能有效降低施工难度,减少施工工期。2. The jacks used in the vertical jacking device and the auxiliary support structure are all inverted and fixed at the bottom of the upper structure of the bridge to be jacked up. After each jacking is completed, there is no need to move the jack when a temporary support is placed under the jack, saving labor Save time and keep the jacks in place. In addition, construction errors caused when the jack is frequently disassembled and assembled can be avoided, and the construction difficulty and construction period can be effectively reduced.
3、所采用的临时支撑件结构简单、设计合理且投入成本较低,并且临时支撑件提前在加工厂进行加工,加工简便且加工质量易于保证。3. The temporary support used is simple in structure, reasonable in design and low in investment cost, and the temporary support is processed in the processing plant in advance, which is easy to process and easy to guarantee the processing quality.
4、所采用的临时支撑件支撑强度大、承重效果好,并且由于多个临时支撑件均为圆柱形且其外径均相同,因而现场垫装简便,无需进行对位安装,只需同轴固定为一体即可。4. The temporary support used has high supporting strength and good load-bearing effect, and because multiple temporary supports are cylindrical and have the same outer diameter, the on-site pad installation is simple, no need for alignment installation, only coaxial It can be fixed as one.
5、竖向顶升装置与辅助支撑结构中由多个临时支撑件组成的临时支撑结构稳定、可靠,使用效果好且实用价值高,多个临时支撑件紧固连接为一体,能有效确保临时支撑结构的整体性和牢靠性,不仅能有效提高支撑强度,满足桥梁上部结构顶升后的承重需求,能有效解决顶升过程中进行千斤顶托换时因顶升后的桥梁上部结构重量巨大存在的千斤顶托换风险高、稳固支撑难度大等承重问题;同时该临时支撑结构紧固固定在反力基础上,能有效确保顶升效果。5. The temporary support structure composed of multiple temporary supports in the vertical jacking device and the auxiliary support structure is stable and reliable, with good use effect and high practical value. The multiple temporary supports are fastened and connected as a whole, which can effectively ensure temporary support. The integrity and reliability of the support structure can not only effectively improve the support strength, meet the load-bearing requirements of the bridge superstructure after jacking, but also effectively solve the problem of the huge weight of the bridge superstructure after jacking when the jack is underpinned during the jacking process. The high risk of underpinning the jack, and the difficulty of stable support, and other load-bearing problems; at the same time, the temporary support structure is fastened and fixed on the basis of the reaction force, which can effectively ensure the lifting effect.
6、竖向顶升装置与辅助支撑结构中所采用的传力顶托结构简单、设计合理且使用效果好,实际顶升过程中,传力顶托与竖向千斤顶能相应进行旋转,从而能对竖向千斤顶与水平面之间的夹角进行微调,使竖向千斤顶始终处于竖直向状态,从而能充分保证竖向千斤顶在竖直方向上的受力,能有效纠正竖向千斤顶在顶升过程中产生的微弱倾斜力,增加了桥梁整体顶升过程中的安全系数。6. The force-transmitting jack used in the vertical jacking device and the auxiliary support structure is simple in structure, reasonable in design and good in use. During the actual jacking process, the force-transmitting jack and the vertical jack can rotate accordingly, so that the Fine-tune the angle between the vertical jack and the horizontal plane, so that the vertical jack is always in the vertical state, which can fully ensure the vertical force of the vertical jack in the vertical direction, and can effectively correct the vertical jack in the jacking. The weak tilting force generated in the process increases the safety factor during the overall jacking process of the bridge.
7、所采用的竖向顶升装置结构简单、设计合理且使用效果好,将竖向千斤顶倒置并固定于待顶升桥梁上部结构底部,每次完成顶升后在千斤顶下方支垫临时支撑件时无需移动千斤顶,省工省时,并能确保千斤顶位置不动;同时采用多个紧固连接为一体的临时支撑件组成临时支撑结构,不仅支撑强度大,承重效果好,并且支撑稳定性好,结构稳定、可靠。并且,临时支撑结构拆除简便,实际拆除时无需对临时支撑件进行逐一拆除,将临时支撑结构整体拆除即可,能有效节约施工工期。7. The vertical jacking device used is simple in structure, reasonable in design and good in use. The vertical jack is inverted and fixed at the bottom of the upper structure of the bridge to be jacked up. After each jacking is completed, a temporary support is placed under the jack. There is no need to move the jack, saving labor and time, and can ensure that the position of the jack does not move; at the same time, a temporary support structure is formed by using a plurality of temporary supports that are fastened and connected as a whole, which not only has high support strength, good load-bearing effect, and good support stability , The structure is stable and reliable. Moreover, the dismantling of the temporary support structure is simple and convenient, and the temporary support members do not need to be dismantled one by one during the actual dismantling, and the temporary support structure can be dismantled as a whole, which can effectively save the construction period.
8、所采用的辅助支撑结构使用效果好且使用价值高,采用随动千斤顶对待顶升桥梁上部结构进行主动顶升,防止向辅助支撑结构进行荷载转移时存在的支撑间隙引起的待顶升桥梁上部结构受力不均的问题发生,顶升过程安全、可靠,并且能避免待顶升桥梁上部结构发生横向侧移。同时,临时支撑结构拆除简便,实际拆除时无需对临时支撑件进行逐一拆除,将临时支撑结构整体拆除即可,能有效节约施工工期。8. The auxiliary support structure used has good use effect and high use value. The follow-up jack is used to actively lift the upper structure of the bridge to be lifted to prevent the bridge to be lifted caused by the support gap existing when the load is transferred to the auxiliary support structure. The problem of uneven force on the superstructure occurs, the lifting process is safe and reliable, and the lateral side shift of the superstructure of the bridge to be lifted can be avoided. At the same time, the dismantling of the temporary support structure is simple and convenient, and it is not necessary to dismantle the temporary supports one by one during the actual dismantling, and the temporary support structure can be dismantled as a whole, which can effectively save the construction period.
9、引桥主梁梁段布设的引桥梁端顶升装置设计合理,安装布设简便且使用效果好,将所有竖向顶升装置与辅助支撑结构沿横桥向布设在引桥主梁的同一横断面上,能确保顶升过程中纵向主梁各部位受力均匀,同时能满足纵向主梁的平稳顶升需求。引桥梁端顶升装置的反力基础为桥台基础或桥墩基础,支撑稳固、可靠,并且竖向顶升装置与辅助支撑结构安装简便。9. The approach bridge end jacking device arranged in the main girder section of the approach bridge has a reasonable design, easy installation and good use effect, all vertical jacking devices and auxiliary support structures are arranged in the same cross section of the approach bridge main girder along the transverse bridge direction It can ensure that all parts of the longitudinal main girder are uniformly stressed during the jacking process, and at the same time can meet the stable lifting requirements of the longitudinal main girder. The reaction force foundation of the jacking device at the end of the approach bridge is the abutment foundation or the bridge pier foundation, the support is stable and reliable, and the vertical jacking device and the auxiliary support structure are easy to install.
10、每个柱式支墩上均设置一个柱式支墩液压顶升装置,确保引桥主梁每个下部支撑结构上均布设一个液压顶升装置,以便对引桥主梁进行平稳、安全顶升。柱式支墩液压顶升装置中竖向液压顶升机构中竖向顶升装置与辅助支撑结构的布设位置合理,两个竖向顶升装置与一个辅助支撑结构组成一个竖向液压顶升机构,两个竖向顶升装置对称布设于辅助支撑结构两侧,竖向液压顶升机构不仅占地空间小,拆装简便,并且两个竖向顶升装置同步顶升能满足所处支顶位置的平稳、可靠支顶需求,而位于两个竖向顶升装置之间的辅助支撑结构能满足辅助支撑需求并能进行主动顶升,确保千斤顶托换过程安全、可靠。并且,将竖向液压顶升机构支撑于竖向墩柱上设置的下抱柱梁与上抱柱梁之间,能有效解决上部无盖梁的桥墩上布设液压顶升装置的难题,并且能满足桥梁上部结构的顶升需求。同时,竖向液压顶升机构的数量以及各竖向液压顶升机构的布设位置均能进行简便调整,同时多个竖向液压顶升机构同步动作能确保顶升过程简便、快速进行,并能确保顶升施工质量,节约施工工期。10. A column-type buttress hydraulic jacking device is installed on each column-type buttress to ensure that a hydraulic jacking device is arranged on each lower support structure of the approach bridge main girder, so that the approach bridge main beam can be lifted smoothly and safely . In the vertical hydraulic jacking mechanism of the column-type buttress hydraulic jacking mechanism, the arrangement position of the vertical jacking device and the auxiliary support structure is reasonable. Two vertical jacking devices and an auxiliary support structure form a vertical hydraulic jacking mechanism. , The two vertical jacking devices are symmetrically arranged on both sides of the auxiliary support structure. The vertical hydraulic jacking mechanism not only occupies a small space, but is easy to disassemble and assemble, and the simultaneous jacking of the two vertical jacking devices can meet the needs of the supporting roof. The position is stable and reliable, and the auxiliary support structure located between the two vertical jacking devices can meet the auxiliary support requirements and can perform active jacking, ensuring the safety and reliability of the jack underpinning process. In addition, the vertical hydraulic jacking mechanism is supported between the lower column beam and the upper column beam set on the vertical pier column, which can effectively solve the problem of arranging the hydraulic jacking device on the pier without the upper cover beam, and can Meet the lifting needs of the bridge superstructure. At the same time, the number of vertical hydraulic jacking mechanisms and the arrangement position of each vertical hydraulic jacking mechanism can be easily adjusted. At the same time, the synchronous action of multiple vertical hydraulic jacking mechanisms can ensure that the lifting process is simple and fast. Ensure the construction quality of jacking and save the construction period.
11、独柱墩上设置独柱墩液压顶升装置,设计合理,安装布设简便且使用效果好,仅需在独柱墩上设置一个墩体抱柱梁对竖向顶升装置与辅助支撑结构进行平稳支撑即可。11. The single-column pier is equipped with a single-column pier hydraulic jacking device. The design is reasonable, the installation and layout are simple, and the use effect is good. It is only necessary to set a pier-column beam on the single-column pier for the vertical jacking device and auxiliary support structure. Just hold it steady.
12、系统整体设计合理、施工简便且使用效果好,采用左右两个对称布设的引桥主梁顶升装置对待顶升引桥主梁进行竖向顶升,引桥主梁顶升装置中采用竖向顶升装置与辅助支撑结构相配合进行顶升,辅助支撑结构对待顶升引桥主梁进行平稳支撑的同时对待顶升引桥主梁进行主动顶升,竖向顶升装置与辅助支撑结构中的千斤顶均倒置布设,每次完成顶升后在千斤顶下方支垫临时支撑件时无需移动千斤顶,省工省时,并能确保千斤顶位置不动;同时所采用的临时支撑结构不仅支撑强度大,承重效果好,并且支撑稳定性好,结构稳定、可靠,确保引桥主梁顶升过程平稳、可靠。12. The overall design of the system is reasonable, the construction is simple, and the use effect is good. Two symmetrically arranged main beam jacking devices on the left and right are used for vertical jacking of the main beam of the approach bridge to be lifted. The supporting structure is matched to carry out jacking. The auxiliary supporting structure supports the main beam of the approach bridge to be lifted smoothly and actively lifts the main beam of the approach bridge to be lifted. The vertical jacking device and the jacks in the auxiliary support structure are arranged upside down. After the first lifting is completed, there is no need to move the jack when the temporary support is placed under the jack, which saves labor and time, and can ensure that the position of the jack does not move. Good performance, stable and reliable structure, to ensure the smooth and reliable lifting process of the main beam of the approach bridge.
13、施工方法简单、设计合理且施工过程易于控制、施工效果好,能对大跨度引桥进行整体顶升,并且顶升过程安全、可靠。13. The construction method is simple, the design is reasonable, the construction process is easy to control, the construction effect is good, and the large-span approach bridge can be lifted as a whole, and the lifting process is safe and reliable.
下面通过附图和实施例,对本实用新型的技术方案做进一步的详细描述。The technical solutions of the present utility model will be described in further detail below through the accompanying drawings and embodiments.
附图说明Description of drawings
图1为本实用新型待顶升引桥主梁顶升到位后的施工状态示意图。Figure 1 is a schematic diagram of the construction state of the utility model after the main beam of the approach bridge to be lifted is lifted into place.
图2为本实用新型桥台侧液压顶升装置的平面布设位置示意图。Fig. 2 is a schematic diagram of the plane layout position of the hydraulic jacking device on the abutment side of the utility model.
图3为本实用新型桥台侧液压顶升装置的立面结构示意图。FIG. 3 is a schematic view of the vertical structure of the hydraulic jacking device on the abutment side of the utility model.
图4为本实用新型桥墩侧液压顶升装置的平面布设位置示意图。FIG. 4 is a schematic diagram of the plane layout position of the hydraulic jacking device on the pier side of the utility model.
图5为本实用新型桥墩侧液压顶升装置的立面结构示意图。FIG. 5 is a schematic view of the elevation structure of the hydraulic jacking device on the pier side of the utility model.
图6为本实用新型柱式桥墩液压顶升装置的横桥向顶升状态示意图。FIG. 6 is a schematic diagram of the horizontal bridge jacking state of the hydraulic jacking device for column-type bridge piers of the present invention.
图7为本实用新型柱式桥墩液压顶升装置的纵桥向顶升状态示意图。FIG. 7 is a schematic view of the vertical bridge jacking state of the hydraulic jacking device for column-type bridge piers of the present invention.
图8为本实用新型下抱柱梁上竖向液压顶升机构的平面位置示意图。FIG. 8 is a schematic diagram of the plane position of the vertical hydraulic jacking mechanism on the lower pillar-holding beam of the present invention.
图9为本实用新型柱式桥墩液压顶升装置顶升到位后的横桥向顶升状态示意图。FIG. 9 is a schematic diagram of the horizontal bridge jacking state after the hydraulic jacking device of the column type bridge pier of the present invention is jacked into place.
图10为本实用新型竖向顶升装置的结构示意图。FIG. 10 is a schematic structural diagram of the vertical jacking device of the present invention.
图11为本实用新型辅助支撑结构的结构示意图。FIG. 11 is a schematic structural diagram of the auxiliary support structure of the present invention.
图12为本实用新型独柱墩液压顶升装置的平面布设位置示意图。Figure 12 is a schematic diagram of the plane layout position of the hydraulic jacking device for a single-column pier of the present invention.
图13为本实用新型独柱墩液压顶升装置的立面结构示意图。Figure 13 is a schematic diagram of the vertical structure of the hydraulic jacking device for a single-column pier of the present invention.
图14为本实用新型上抱柱梁底部竖向千斤顶所安装千斤顶纠偏装置的使用状态参考图。Fig. 14 is a reference diagram of the use state of the jack rectifying device installed on the vertical jack at the bottom of the upper column beam of the present invention.
图15为本实用新型上固定板的结构示意图。FIG. 15 is a schematic structural diagram of the upper fixing plate of the present invention.
图16为本实用新型下固定板的结构示意图。FIG. 16 is a schematic structural diagram of the lower fixing plate of the present invention.
图17为本实用新型水平纠偏机构的上部结构示意图。17 is a schematic diagram of the upper structure of the horizontal deviation correction mechanism of the present invention.
图18为本实用新型水平纠偏机构的底部结构示意图。18 is a schematic diagram of the bottom structure of the horizontal deviation correction mechanism of the present invention.
图19为采用本实用新型进行引桥顶升时的施工方法流程框图。Fig. 19 is a flow chart of the construction method when the utility model is used to lift the approach bridge.
图20为本实用新型柱式桥墩上连接墩柱施工完成后的结构示意图。附图标记说明:FIG. 20 is a schematic structural diagram of the connecting pier and column on the column-type bridge pier of the present invention after the construction is completed. Explanation of reference numbers:
1—待顶升引桥主梁; 1-1—纵向主梁; 2—竖向千斤顶;1—The main beam of the approach bridge to be jacked; 1-1—The longitudinal main beam; 2—The vertical jack;
3—钢管支撑结构; 3-1—竖向支撑钢管; 3-2—上连接环;3—steel pipe support structure; 3-1—vertical support steel pipe; 3-2—upper connecting ring;
3-3—下连接环; 4—连接螺栓; 6—传力顶托;3-3—lower connecting ring; 4—connecting bolts; 6—force transmission jacking;
6-1—下支撑座; 6-11—连接座; 6-12—上固定环;6-1—lower support seat; 6-11—connection seat; 6-12—upper fixing ring;
6-2—上铰接座; 6-3—上铰接头; 7—竖向支顶座;6-2—upper hinged seat; 6-3—upper hinged head; 7—vertical support head seat;
10—下锚栓; 11—竖向顶升装置;10—lower anchor bolt; 11—vertical jacking device;
12—辅助支撑结构; 13—竖向墩柱; 14—下抱柱梁;12—Auxiliary support structure; 13—Vertical pier column; 14—Lower column beam;
15—上抱柱梁; 16—随动千斤顶; 17—顶升限位柱;15—upper column beam; 16—following jack; 17—lifting limit post;
18—桥台; 18-1—肋板; 18-2—台顶盖梁;18—the bridge abutment; 18-1—the rib plate; 18-2—the abutment roof beam;
18-3—钢混桥台基础; 18-4—桥台新增基础; 18-5—新增肋板;18-3—steel-concrete abutment foundation; 18-4—new foundation for abutment; 18-5—new rib;
18-6—新增盖梁; 19—桥台侧液压顶升装置;18-6—Added cover beam; 19—Abutment side hydraulic jacking device;
20—桥墩侧液压顶升装置; 21—水平混凝土基础;20—hydraulic jacking device on the pier side; 21—horizontal concrete foundation;
22—横向分配梁; 23—柱式桥墩; 24—上部盖梁;22—transverse distribution beam; 23—column pier; 24—upper cover beam;
25—柱式桥墩液压顶升装置; 26—竖向钻孔桩;25—Hydraulic jacking device for column pier; 26—Vertical bored pile;
27—独柱墩; 27-1—竖向墩柱; 27-2—钢混基础;27—single-column pier; 27-1—vertical pier; 27-2—steel concrete foundation;
28—独柱墩液压顶升装置;28—Hydraulic jacking device for single-column pier;
29—墩体抱柱梁; 30—新建主梁; 31—竖向支撑墩;29—column-bearing beam of pier body; 30—new main beam; 31—vertical support pier;
32—水平调整件; 32-1—螺栓杆; 32-2—限位螺母;32—level adjustment piece; 32-1—bolt rod; 32-2—limit nut;
32-3—上滑移件; 33—上固定板; 33-1—横向滑移槽;32-3—upper sliding piece; 33—upper fixing plate; 33-1—transverse sliding groove;
33-2—横向插孔; 34—下固定板; 34-1—纵向插孔;33-2—horizontal jack; 34—lower fixing plate; 34-1—vertical jack;
35—楔形钢板; 36—条形基础; 37—竖向支墩;35—wedge-shaped steel plate; 36—strip foundation; 37—vertical buttress;
37-1—竖向支撑墩柱; 37-2—墩顶盖梁; 37-3—钢混桥墩基础;37-1—vertical support pier column; 37-2—pier roof beam; 37-3—steel concrete pier foundation;
38—横向支撑梁; 39—连接墩柱。38—transverse support beam; 39—connecting pier column.
具体实施方式Detailed ways
如图1所示,本实用新型包括左右两个对称布设且对待顶升引桥主梁1进行竖向顶升的引桥主梁顶升装置;所述待顶升引桥主梁1为大跨径系杆拱桥的引桥主梁;所述待顶升引桥主梁1呈水平布设且其包括左右两幅对称布设的纵向主梁1-1,两幅所述纵向主梁1-1均沿纵桥向布设;每个所述引桥主梁顶升装置均支撑于一幅所述纵向主梁1-1的正下方,每个所述引桥主梁顶升装置均包括一个桥台侧液压顶升装置19和一个与桥台侧液压顶升装置19呈对称布设的桥墩侧液压顶升装置20,所述桥台侧液压顶升装置19和桥墩侧液压顶升装置20的结构相同且二者均为引桥梁端顶升装置;As shown in Figure 1, the present utility model includes two symmetrically arranged left and right approach bridge main beam jacking devices for vertical jacking of the approach bridge
所述待顶升引桥主梁1支撑于引桥下部结构上,所述引桥下部结构包括左右两个对称布设的引桥下部支撑结构,每幅所述纵向主梁1-1均支撑于一个所述引桥下部支撑结构上;每个所述引桥下部支撑结构均包括一个桥台18和一个竖向桥墩上;所述纵向主梁1-1的一端为支撑于桥台18上的待接续端,所述纵向主梁1-1的另一端为支撑于所述竖向桥墩上的连接端;The
每个所述桥台18上均设置有一个对纵向主梁1-1进行竖向顶升的桥台侧液压顶升装置19,每个所述竖向桥墩上均设置有一个对纵向主梁1-1进行竖向顶升的桥墩侧液压顶升装置20;每个所述桥台侧液压顶升装置19均支撑于一个所述纵向主梁1-1的所述待接续端下方,每个所述桥墩侧液压顶升装置20均支撑于一个所述纵向主梁1-1的所述连接端下方;Each of the
如图2、图3所示,每个所述桥台侧液压顶升装置19均支撑于一个所述桥台18的桥台基础上,每个所述桥墩侧液压顶升装置20均支撑于一个所述竖向桥墩的桥墩基础上或均支撑于一个水平混凝土基础21上,所述水平混凝土基础21位于所述桥墩基础一侧且其与所述桥墩基础浇筑为一体;所述桥台基础和所述桥墩基础均为呈水平布设的钢筋混凝土基础;所述桥台基础、所述桥墩基础和所述水平混凝土基础21均为反力基础;As shown in FIGS. 2 and 3 , each abutment-side hydraulic jacking device 19 is supported on an abutment foundation of the
如图4、图5所示,每个所述引桥梁端顶升装置均包括一道支撑于纵向主梁1-1底部的横向分配梁22、多个沿横桥向由左至右布设的竖向顶升装置11和多个沿横桥向由左至右布设的辅助支撑结构12,所述竖向顶升装置11和辅助支撑结构12均呈竖直向布设且二者的数量均相同,所述竖向顶升装置11和辅助支撑结构12均支撑于横向分配梁22的正下方,所述横向分配梁22沿横桥向布设且其与所支撑纵向主梁1-1的底面呈平行布设;每个所述引桥梁端顶升装置中多个竖向顶升装置11和多个所述辅助支撑结构12均布设于待顶升引桥主梁1的同一个横断面上,每个所述引桥梁端顶升装置中所述竖向顶升装置11和辅助支撑结构12呈交错布设;As shown in Figures 4 and 5, each of the approach bridge end jacking devices includes a
如图10和图11所示,所述竖向顶升装置11包括竖向千斤顶2和布设于竖向千斤顶2正下方的竖向支顶机构,所述辅助支撑结构12包括随动千斤顶16和布设于随动千斤顶16正下方的竖向支撑结构,所述竖向支顶机构和所述竖向支撑结构均为临时支撑结构;所述竖向千斤顶2和随动千斤顶16均为呈竖直向布设的倒置千斤顶,所述倒置千斤顶为底座朝上且刚性顶举件朝下的液压千斤顶;每个所述倒置千斤顶的底座均水平固定在位于其正上方的横向分配梁22底部,每个所述倒置千斤顶的刚性顶举件均支顶在位于其正下方的所述临时支撑结构上;每个所述临时支撑结构均支撑于位于其下方的所述反力基础上,每个所述临时支撑结构均由多个从下至上布设的临时支撑件拼接而成,多个所述临时支撑件的结构均相同且其均为呈水平布设的钢管支撑结构3;As shown in FIGS. 10 and 11 , the vertical jacking
所述钢管支撑结构3为圆柱形,所述临时支撑结构中所有钢管支撑结构3的直径均相同且其均呈同轴布设;每个所述钢管支撑结构3均包括竖向支撑钢管3-1、一个同轴固定于竖向支撑钢管3-1上部的上连接环3-2和一个同轴固定于竖向支撑钢管3-1底部的下连接环3-3,所述上连接环3-2和下连接环3-3均为水平圆环形钢板且二者均固定在竖向支撑钢管3-1的外侧壁上,所述上连接环3-2和下连接环3-3的结构和尺寸均相同;所述上连接环3-2的上表面与竖向支撑钢管3-1的上表面相平齐,下连接环3-3的底面与竖向支撑钢管3-1的底面相平齐;所述上连接环3-2和下连接环3-3上均开有多个沿圆周方向均匀布设的螺栓安装孔;The steel
所述临时支撑结构中上下相邻两个所述钢管支撑结构3组成一个钢管支撑组合,所述钢管支撑组合中位于上方的钢管支撑结构3为上钢管支撑结构,所述钢管支撑组合中位于下方的钢管支撑结构3为下钢管支撑结构,所述钢管支撑组合中所述上钢管支撑结构的下连接环3-3与所述下钢管支撑结构的上连接环3-2通过多个连接螺栓4紧固连接为一体,通过多个所述连接螺栓4紧固连接为一体的下连接环3-3与上连接环3-2组成一个加固环;所述连接螺栓4呈竖直向布设,每个所述连接螺栓4均安装于所述加固环中上下连通的两个所述螺栓安装孔内。In the temporary support structure, the upper and lower adjacent steel
本实施例中,所述待顶升引桥主梁1的顶升高度大于2m。所述待顶升引桥主梁1为南河特大桥的引桥主梁。In this embodiment, the jacking height of the
本实施例中,所述竖向支撑钢管3-1的直径为Φ609mm或Φ500mm;当竖向支撑钢管3-1的直径为Φ609mm时,竖向支撑钢管3-1的壁厚为16mm,下连接环3-3与上连接环3-2的外径为Φ750mm;当竖向支撑钢管3-1的直径为Φ500mm时,竖向支撑钢管3-1的壁厚为12mm,下连接环3-3与上连接环3-2的外径为Φ600mm。In this embodiment, the diameter of the vertical support steel pipe 3-1 is Φ609mm or Φ500mm; when the diameter of the vertical support steel pipe 3-1 is Φ609mm, the wall thickness of the vertical support steel pipe 3-1 is 16mm, and the lower connection The outer diameter of the ring 3-3 and the upper connecting ring 3-2 is Φ750mm; when the diameter of the vertical support steel pipe 3-1 is Φ500mm, the wall thickness of the vertical support steel pipe 3-1 is 12mm, and the lower connecting ring 3-3 The outer diameter of the upper connecting ring 3-2 is Φ600mm.
实际进行顶升时,当待顶升引桥主梁1的顶升高度在2m内时,所述临时支撑结构中所采用竖向支撑钢管3-1的直径为Φ500mm;当待顶升引桥主梁1的顶升高度超过2m时,所述临时支撑结构中所采用竖向支撑钢管3-1的直径为Φ609mm。During the actual jacking, when the jacking height of the
所述钢管支撑结构3的厚度为10cm、20cm、50cm、100cm或200cm,实际进行顶升时,可根据具体需要更换相应厚度的钢管支撑结构3。The thickness of the steel
实际施工时,所述桥台侧液压顶升装置19和桥墩侧液压顶升装置20均通过一道横向分配梁22对待顶升引桥主梁1进行直接顶升,这样无需对待顶升引桥主梁1的结构做任何改变,以钢筋混凝土基础作为反力平台,在待顶升引桥主梁1梁底安装的横向分配梁22作为顶升受力点,施工简便,且顶升过程平稳、可靠。所述横向分配梁22直接承担上部梁体的重量,并将力转移给所述倒置千斤顶。During the actual construction, the hydraulic jacking device 19 on the abutment side and the hydraulic jacking
本实施例中,如图2所示,所述桥台18包括所述桥台基础、三个沿横桥向由左至右布设于所述桥台基础上的肋板18-1和水平支撑于三个所述肋板18-1上的台顶盖梁18-2,所述肋板18-1和台顶盖梁18-2均为钢筋混凝土结构,三个所述肋板18-1均呈竖直向布设且其均沿纵桥向布设。所述桥台基础为钢混桥台基础18-3且为钻孔桩基础,所述钻孔桩基础包括水平承台和多根支撑于所述水平承台下方的竖向钻孔灌注桩,所述水平承台和所述竖向钻孔灌注桩均为钢筋混凝土结构。所述桥台侧液压顶升装置19支撑于所述桥台基础中的水平承台上。In this embodiment, as shown in FIG. 2 , the
为方便支撑且固定牢靠,所述桥台基础上设置有供桥台侧液压顶升装置19支撑的条形基础36,所述条形基础36沿横桥向布设且其位于所支撑桥台侧液压顶升装置19中的横向分配梁22正下方,所述条形基础36为呈水平布设的立方体基础且其支撑于所述桥台基础中的水平承台上。本实施例中,所述条形基础36通过三个所述肋板18-1分隔为四个布设于同一竖直面上的基础节段。In order to facilitate the support and be firmly fixed, the abutment foundation is provided with a
如图2所示,本实施例中,每个所述竖向桥墩均包括一个墩顶盖梁37-2、多个对墩顶盖梁37-2进行支撑的竖向支撑墩柱37-1和两个供竖向支撑墩柱37-1支撑的所述桥墩基础,两个所述桥墩基础布设于待顶升引桥主梁1的同一个横断面上;每个所述桥墩基础上均布设有竖向支撑墩柱37-1,所述钢混桥墩基础37-3为所述钻孔桩基础。所述竖向支撑墩柱37-1和墩顶盖梁37-2均为钢筋混凝土结构。As shown in FIG. 2 , in this embodiment, each of the vertical piers includes a pier top cover beam 37-2 and a plurality of vertical support pier columns 37-1 supporting the pier top cover beam 37-2 and the two said bridge pier foundations supported by the vertical support pier columns 37-1, the two said bridge pier foundations are arranged on the same cross section of the
所述引桥下部结构中两个所述竖向桥墩组成过渡段桥墩,两个所述竖向桥墩的墩顶盖梁37-2浇筑为一体且二者形成水平盖梁37。本实施例中,所述过渡段桥墩中包括四个所述桥墩基础,并且四个所述桥墩基础中位于中部的两个所述桥墩基础浇筑为一体。In the lower structure of the approach bridge, the two vertical piers form a transition section pier, and the pier top cover beams 37 - 2 of the two vertical bridge piers are cast as a whole, and the two form a
由于钢混桥墩基础37-3的埋深较深,并且钢混桥墩基础37-3长期被谁浸泡,在钢混桥墩基础37-3上支撑桥墩侧液压顶升装置20时,不仅施工难度,并且存在的安全隐患较多,同时将钢混桥墩基础37-3开挖后对周侧环境的影响较大。因而,本实施例中,所述支撑桥墩侧液压顶升装置20支撑于水平混凝土基础21上,所述水平混凝土基础21与钢混桥墩基础37-3紧固连接为一体,一方面能确保支撑桥墩侧液压顶升装置20的支撑稳固性,另一方面对钢混桥墩基础37-3形成加固。Due to the deep burial depth of the steel-concrete pier foundation 37-3 and the long-term soaking of the steel-concrete pier foundation 37-3, when supporting the pier-side hydraulic jacking
实际施工时,在所述竖向桥墩的两个所述钢混桥墩基础37-3上均施工一个水平混凝土基础21。为支撑平稳、可靠,并且为满足支撑桥墩侧液压顶升装置20的支撑需求,在两个所述水平混凝土基础21上施工一道沿横桥向布设的横向支撑梁38,所述横向支撑梁38为呈水平布设的钢筋混凝土梁且其与两个所述水平混凝土基础21浇筑为一体,所述横向支撑梁38位于所支撑桥墩侧液压顶升装置20中的横向分配梁22正下方。During actual construction, a horizontal
本实施例中,每个所述引桥梁端顶升装置中均包括5个所述竖向顶升装置11和5个所述辅助支撑结构12,因而能满足对待顶升引桥主梁1两端进行稳固顶升的需求。并且,所述竖向顶升装置11和辅助支撑结构12中所述倒置千斤顶均为最大承重为200吨的液压千斤顶。In this embodiment, each of the approach bridge end jacking devices includes 5 vertical jacking
实际施工时,可根据具体需要,对每个所述引桥梁端顶升装置中所包括竖向顶升装置11和辅助支撑结构12的数量和布设位置分别进行相应调整。During actual construction, the number and arrangement positions of the vertical jacking
本实施例中,所述纵向主梁1-1为现浇混凝土梁或组合箱梁。In this embodiment, the longitudinal main beam 1-1 is a cast-in-place concrete beam or a composite box beam.
本实施例中,所述临时支撑结构中位于底部的钢管支撑结构3为底部钢管支撑结构,所述底部钢管支撑结构的下连接环3-3为底部支撑环,所述底部支撑环通过多个下锚栓10固定在所述反力基础上,所述下锚栓10呈竖直向布设;所述底部支撑环上的所述螺栓安装孔为底部安装孔,每个所述下锚栓10均安装于一个所述底部安装孔内。因而,通过多个所述下锚栓10能简便、快速将所述临时支撑结构紧固固定在所述反力基础上,确保顶升过程中所述临时支撑结构的稳固性。In this embodiment, the steel
为确保所述临时支撑结构能水平、平稳安装在所述反力基础上,所述底部钢管支撑结构与反力基础之间设置有一层下找平层,所述下找平层的上表面为水平面且其上表面与所述底部钢管支撑结构紧贴;所述下找平层为砂浆找平层或混凝土找平层。In order to ensure that the temporary support structure can be installed horizontally and smoothly on the reaction force foundation, a lower leveling layer is arranged between the bottom steel pipe support structure and the reaction force foundation, and the upper surface of the lower leveling layer is a horizontal plane and Its upper surface is in close contact with the bottom steel pipe support structure; the lower leveling layer is a mortar leveling layer or a concrete leveling layer.
本实施例中,如图10和图11所示,所述临时支撑结构中位于最上方的钢管支撑结构3为顶部钢管支撑结构,所述临时支撑结构还包括布设于所述顶部钢管支撑结构上的传力顶托6,所述传力顶托6呈水平布设且其位于所述顶部钢管支撑结构的正上方;In this embodiment, as shown in FIG. 10 and FIG. 11 , the steel
所述倒置千斤顶的刚性顶举件与位于其下方的传力顶托6之间通过球铰进行连接。The rigid jacking member of the inverted jack is connected with the force-transmitting
本实施例中,所述传力顶托6与位于上方的所述倒置千斤顶呈同轴布设。In this embodiment, the
实际使用时,通过传力顶托6向下进行均匀传力。In actual use, uniform force is transmitted downward through the
本实施例中,所述刚性顶举件的正下方设置有竖向支顶座7,所述竖向支顶座7固定于所述刚性顶举件上且其位于所述临时支撑结构的正上方;In this embodiment, a
所述传力顶托6包括下支撑座6-1和布设于下支撑座6-1上的上铰接座6-2,所述上铰接座6-2位于下支撑座6-1的正上方;所述上铰接座6-2包括座体和一个布设于所述座体正上方的上铰接头6-3,所述下支撑座6-1位于所述顶部钢管支撑结构的正上方,所述上铰接头6-3和所述座体均位于下支撑座6-1的正上方;The
所述上铰接头6-3位于竖向支顶座7的正下方且二者组成所述球铰。The upper hinge joint 6-3 is located just below the
并且,所述上铰接头6-3布设于竖向支顶座7底部且其位于竖向支顶座7的正下方,所述上铰接头6-3的上表面与竖向支顶座7的底面相贴;所述竖向支顶座7与上铰接座6-2组成所述球铰。In addition, the upper hinge joint 6-3 is arranged at the bottom of the
本实施例中,如图10所示,所述竖向顶升装置11中所述上铰接头6-3的上表面为凸球面,所述竖向支顶座7的底面为凹球面。实际使用时,所述竖向顶升装置11中所述上铰接头6-3的上表面也可以为凹球面,此时竖向支顶座7的底面为凸球面,只需传力顶托6与竖向千斤顶2之间能形成铰接即可。如图11所示,所述辅助支撑结构12中所述上铰接头6-3的上表面为凹球面,所述竖向支顶座7的底面为凸球面。实际使用时,所述辅助支撑结构12中所述上铰接头6-3的上表面也可以为凸球面,此时竖向支顶座7的底面为凹球面,只需传力顶托6与竖向千斤顶2之间能形成铰接即可。In this embodiment, as shown in FIG. 10 , the upper surface of the upper hinge joint 6 - 3 in the vertical jacking
由上述内容可知,所述竖向顶升装置11和辅助支撑结构12中传力顶托6与所述倒置千斤顶之间以铰接方式进行连接。实际使用时,所述传力顶托6与所述倒置千斤顶的接触面(即上铰接头6-3的上表面与竖向支顶座7的底面)之间能自由活动。实际顶升过程中,所述传力顶托6与所述倒置千斤顶能相应进行旋转,从而能对述倒置千斤顶与水平面之间的夹角进行微调,使述倒置千斤顶始终处于竖直向状态,从而能充分保证述倒置千斤顶在竖直方向上的受力,能有效纠正述倒置千斤顶在顶升过程中产生的微弱倾斜力,增加了桥梁整体顶升过程中的安全系数。As can be seen from the above content, the vertical jacking
本实施例中,所述下支撑座6-1固定在所述顶部钢管支撑结构上,所述顶部钢管支撑结构的上连接环3-2为下固定环,所述下支撑座6-1通过多个固定螺栓18固定在所述下固定环上;所述下固定环上的所述螺栓安装孔为固定孔,所述固定螺栓18呈竖直向布设,每个所述固定螺栓18均安装于一个固定孔内。In this embodiment, the lower support seat 6-1 is fixed on the top steel pipe support structure, the upper connecting ring 3-2 of the top steel pipe support structure is a lower fixing ring, and the lower support seat 6-1 passes through A plurality of fixing
实际安装时,通过固定螺栓18能将传力顶托6简便、快速且紧固固定在所述临时支撑结构上,使传力顶托6与所述临时支撑结构紧固连接为一体,确保顶升过程中传力顶托6与所述临时支撑结构连接稳固、可靠。During the actual installation, the
本实施例中,所述上铰接头6-3的底面为水平面,所述座体为圆柱形且其呈水平布设;In this embodiment, the bottom surface of the upper hinge joint 6-3 is a horizontal plane, and the seat body is cylindrical and arranged horizontally;
所述下支撑座6-1由连接座6-11和固定于连接座6-11底部外侧的上固定环6-12组成,所述连接座6-11为圆锥台形且上部直径与所述座体的直径相同,所述连接座6-11的底部直径与上固定环6-12的内径相同;所述上固定环6-12呈水平布设且其与连接座6-11和上铰接座6-2均呈同轴布设,所述上固定环6-12上沿圆周方向均匀开设有多个供固定螺栓18安装的安装孔。The lower support seat 6-1 is composed of a connecting seat 6-11 and an upper fixing ring 6-12 fixed on the outer side of the bottom of the connecting seat 6-11. The diameter of the body is the same, the bottom diameter of the connecting seat 6-11 is the same as the inner diameter of the upper fixing ring 6-12; -2 are all arranged coaxially, and a plurality of mounting holes for mounting the fixing
实际加工时,所述竖向支顶座7、下支撑座6-1和上铰接座6-2均为钢支撑座,所述竖向支顶座7为圆柱形,所述传力顶托6中下支撑座6-1和上铰接座6-2加工制作为一体。In actual processing, the
本实施例中,所述上连接环3-2、下连接环3-3和上固定环6-12均为水平连接环,所述临时支撑结构中所有水平连接环的结构和尺寸均相同,所述临时支撑结构中所有竖向支撑钢管3-1的横截面尺寸均相同;所述竖向支撑钢管3-1的外径大于所述刚性顶举件的直径。In this embodiment, the upper connecting ring 3-2, the lower connecting ring 3-3 and the upper fixing ring 6-12 are all horizontal connecting rings, and all the horizontal connecting rings in the temporary support structure have the same structure and size, All vertical support steel pipes 3-1 in the temporary support structure have the same cross-sectional size; the outer diameter of the vertical support steel pipes 3-1 is larger than the diameter of the rigid jacking member.
为了提高竖向支撑钢管3-1的支撑强度,所述竖向支撑钢管3-1的外径均大于所述刚性顶举件的直径,通过传力顶托6能简便、快速将所述倒置千斤顶的作用下向下均匀传递至所述临时支撑结构上。In order to improve the support strength of the vertical supporting steel pipe 3-1, the outer diameter of the vertical supporting steel pipe 3-1 is larger than the diameter of the rigid jacking member, and the force-transmitting jacking 6 can easily and quickly reverse the Under the action of the jack, it is evenly transmitted downward to the temporary support structure.
如图1所示,所述引桥下部支撑结构还包括多个均位于桥台18与所述竖向桥墩之间的柱式桥墩23,多个所述柱式桥墩23沿纵桥向由前至后布设,多个所述柱式桥墩23均呈竖直向布设且其均支撑于一幅所述纵向主梁1-1的正下方;As shown in FIG. 1 , the lower support structure of the approach bridge further includes a plurality of
多个所述柱式桥墩23的结构均相同,每个所述柱式桥墩23均包括左右两个对称布设的竖向墩柱13和一个支撑于两个所述竖向墩柱13上方的上部盖梁24,所述竖向墩柱13为钢筋混凝土柱,所述上部盖梁24为沿横桥向布设的混凝土盖梁,两个所述竖向墩柱13通过上部盖梁24紧固连接为一体;The structures of the plurality of
所述引桥主梁顶升装置还包括多个柱式桥墩液压顶升装置25,所述柱式桥墩液压顶升装置25的数量与所述引桥下部支撑结构中柱式桥墩23的数量相同,每个所述柱式桥墩23上均设置有一个所述柱式桥墩液压顶升装置25;The main girder jacking device of the approach bridge also includes a plurality of column-type pier hydraulic jacking
结合图6、图7、图8和图9,每个所述引桥主梁顶升装置中桥台侧液压顶升装置19、桥墩侧液压顶升装置20和多个所述柱式桥墩液压顶升装置25均布设于同一竖直面上,多个所述柱式桥墩液压顶升装置25的结构均相同,每个所述柱式桥墩液压顶升装置25均位于一幅所述纵向主梁1-1的正下方;6 , 7 , 8 and 9 , in each of the main girder jacking devices of the approach bridge, the hydraulic jacking device 19 on the abutment side, the hydraulic jacking
每个所述柱式桥墩23上均设置有一个下抱柱梁14和一个上抱柱梁15,所述上抱柱梁15位于下抱柱梁14的正上方;所述下抱柱梁14和上抱柱梁15均为水平抱柱梁,所述水平抱柱梁为固定于两个所述竖向墩柱13上的钢筋混凝土梁,所述水平抱柱梁为矩形且其套装于两个所述竖向墩柱13上;每个所述柱式桥墩液压顶升装置25均支撑于一个所述下抱柱梁14和位于该下抱柱梁14正上方的上抱柱梁15之间,所述下抱柱梁14为所述反力基础;Each of the
每个所述柱式桥墩液压顶升装置25均包括支撑于下抱柱梁14与上抱柱梁15之间的竖向液压顶升机构,所述竖向液压顶升机构包括竖向顶升装置11和辅助支撑结构12;所述柱式桥墩液压顶升装置25中每个所述倒置千斤顶的底座均水平固定在上抱柱梁15底部,每个所述倒置千斤顶的刚性顶举件均支顶在位于其正下方的所述临时支撑结构上;所述柱式桥墩液压顶升装置25中每个所述临时支撑结构均支撑于下抱柱梁14上。Each of the column-type bridge pier hydraulic jacking
本实施例中,所述柱式桥墩23中每个所述竖向墩柱13均支撑于一个竖向钻孔桩26正上方。In this embodiment, each of the
由上述内容可知,每个所述柱式桥墩23中均未设置系梁。It can be seen from the above content that each of the column-
为确保顶升过程平稳、顺利进行,本实施例中,如图8所示,每个所述柱式桥墩液压顶升装置25均包括两组所述竖向液压顶升机构,两组所述竖向液压顶升机构对称支撑于下抱柱梁14的左右两侧上方;每组所述竖向液压顶升机构均包括两个对称布设于一个所述竖向墩柱13前后两侧的所述竖向液压顶升机构。因而,每个所述柱式桥墩液压顶升装置25中所述竖向液压顶升机构的数量为两组。In order to ensure the smooth and smooth lifting process, in this embodiment, as shown in FIG. 8 , each of the column-type bridge pier hydraulic jacking
每个所述竖向液压顶升机构均包括两个竖向顶升装置11和一个支撑于两个所述竖向顶升装置11之间的辅助支撑结构12,每个所述竖向液压顶升机构中两个所述竖向顶升装置11对称布设于辅助支撑结构12的左右两侧且三者均布设于所述主梁的同一个横断面上。Each of the vertical hydraulic jacking mechanisms includes two vertical jacking
实际施工时,可根据具体需要,对每个所述柱式桥墩液压顶升装置25中所包括竖向液压顶升机构的数量和各竖向液压顶升机构的布设位置以及每个所述竖向液压顶升机构中竖向顶升装置11和辅助支撑结构12的数量和布设位置分别进行相应调整。During actual construction, according to specific needs, the number of vertical hydraulic jacking mechanisms included in each of the column-type pier hydraulic jacking
本实施例中,每个所述竖向墩柱13与位于其前后两侧的两个所述辅助支撑结构12均布设于同一个竖直面上。In this embodiment, each of the
如图9所示,每个所述柱式桥墩23上均设置有一个顶升限位装置;As shown in FIG. 9 , each of the
所述下抱柱梁14的长度与上抱柱梁15的长度相同,所述下抱柱梁14的宽度大于上抱柱梁15的宽度;The length of the
每个所述顶升限位装置包括两个对称于下抱柱梁14左右两端上方的顶升限位机构,每个所述顶升限位机构均包括两个对称于下抱柱梁14前后两端的顶升限位柱17;所述顶升限位柱17为竖向立柱,所述竖向立柱为由多个平直杆件拼接而成的钢立柱;所述顶升限位装置中顶升限位柱17的数量为四个,四个所述顶升限位柱17分别固定在下抱柱梁14的四个顶角上;所述顶升限位柱17的高度大于待顶升引桥主梁1的顶升高度;Each of the lifting limiting devices includes two lifting limiting mechanisms that are symmetrical to the upper left and right ends of the lower pillar-holding
所述上抱柱梁15卡装于所述顶升限位机构中的两个所述顶升限位柱17之间。The
所述下抱柱梁14的宽度指的是下抱柱梁14的横桥向宽度,所述上抱柱梁15的宽度指的是上抱柱梁15的横桥向宽度。The width of the
本实施例中,所述钢立柱为立方体柱且其包括四根呈竖直向布设的竖向支撑钢管,相邻两根所述竖向支撑钢管通过多根由下至上布设于同一竖直面上的连接钢管紧固连接为一体。In this embodiment, the steel column is a cubic column and includes four vertical support steel pipes arranged vertically, and two adjacent vertical support steel pipes are arranged on the same vertical plane from bottom to top through a plurality of them. The connecting steel pipes are tightly connected as a whole.
所述顶升限位装置中的四个所述顶升限位柱17的机构均相同,每个所述顶升限位柱17底部均通过多个预埋螺栓22固定于下抱柱梁14上,每个所述顶升限位柱17上部均伸至上抱柱梁15的底面上方,确保顶升施工过程安全、可靠。The mechanisms of the four
四个所述顶升限位柱17均为在下抱柱梁14上焊接成型的限位柱,焊接方便且施工简便,只需通过多个预埋螺栓22固定于下抱柱梁14上即可,改变了传统采用钢筋混凝土限位结构时存在的施工时间长、施工过程复杂的难题,减少了在下抱柱梁14和上抱柱梁15上进行植筋、支模板和浇筑混凝土的施工工序,并且减少了钢筋混凝土限位柱养护等强的时间,成功缩短了施工工期,同时顶升施工结束后对顶升限位柱17进行整体拆除即可,拆除方便,减少了传统钢筋混凝土限位结构凿除的工序。The four
本实施例中,每个所述引桥下部支撑结构中所包括柱式桥墩23的数量为9个,因而每个所述引桥主梁顶升装置均包括9个所述柱式桥墩液压顶升装置25。In this embodiment, the number of
实际使用时,根据柱式桥墩23的数量对柱式桥墩液压顶升装置25的数量进行确定。In actual use, the number of the column-type pier hydraulic jacking
由于竖向墩柱13上没有供竖向顶升装置11和辅助支撑结构12底部支撑的承台,并且竖向墩柱13上部设置有上部盖梁24,但上部盖梁24的梁体较窄且不能均匀传递顶升作用力,因而在竖向墩柱13上设置下抱柱梁14和上抱柱梁15,并将竖向顶升装置11和辅助支撑结构12均置于竖向顶升装置11和辅助支撑结构12之间,将下抱柱梁14作为反力基础,且通过向上顶升上抱柱梁15对待顶升引桥主梁1进行同步顶升。Since the
顶升施工之前,先在竖向墩柱13上施工下抱柱梁14和上抱柱梁15,待下抱柱梁14和上抱柱梁15均施工完成后,对两组所述竖向液压顶升机构进行安装,并使所述竖向液压顶升机构均位于下抱柱梁14和上抱柱梁15之间;两个所述竖向墩柱13中位于下抱柱梁14和上抱柱梁15之间的墩柱节段为待切割节段,待两组所述竖向液压顶升机构均安装完成后,对两个所述待切割节段进行水平切割,具体是在两个所述待切割节段的中部进行水平切割,使每个所述竖向墩柱13均分割成下部墩柱和位于所述下部墩柱正上方的上部墩柱;待两个所述竖向墩柱13均切割完成后,采用柱式桥墩液压顶升装置25对上抱柱梁15、上部盖梁24和待顶升引桥主梁1进行同步顶升,直至将待顶升引桥主梁1顶升到位,详见图9。Before the jacking construction, the
如图1所示,所述引桥下部支撑结构还包括多个均位于桥台18与所述竖向桥墩之间的独柱墩27,多个所述独柱墩27沿纵桥向由前至后布设,多个所述独柱墩27均呈竖直向布设且其均支撑于一幅所述纵向主梁1-1的正下方;As shown in FIG. 1 , the lower support structure of the approach bridge further includes a plurality of single-
所述引桥主梁顶升装置还包括多个独柱墩液压顶升装置28,所述独柱墩液压顶升装置28的数量与所述引桥下部支撑结构中独柱墩27的数量相同,每个所述独柱墩27上均设置有一个所述独柱墩液压顶升装置28;The main girder jacking device of the approach bridge also includes a plurality of single-column pier hydraulic jacking
如图12、图13所示,每个所述引桥下部支撑结构中所有柱式桥墩23分为前后两组,每组所述柱式桥墩23均包括多个沿纵桥向由前至后布设的柱式桥墩23;每个所述引桥下部支撑结构中多个所述独柱墩27均位于两组所述柱式桥墩23之间,每个所述引桥下部支撑结构中多个所述独柱墩27与两组所述柱式桥墩23均布设于同一个竖直面上;As shown in Fig. 12 and Fig. 13 , all the
每个所述独柱墩27均包括一个竖向墩柱27-1,所述竖向墩柱27-1位于一幅所述纵向主梁1-1的正下方;Each of the single-
每个所述独柱墩27上均设置有一个墩体抱柱梁29,所述墩体抱柱梁29为固定于竖向墩柱27-1上且呈水平布设的钢筋混凝土梁,所述墩体抱柱梁29为方形且其套装于竖向墩柱27-1上;每个所述独柱墩液压顶升装置28均支撑于一个所述墩体抱柱梁29上,所述墩体抱柱梁29为所述反力基础;Each of the single-
每个所述独柱墩液压顶升装置28均包括多组沿纵桥向布设由前至后布设在同一竖直面上的墩体顶升机构,多组所述墩体顶升机构的结构均相同且其均位于一幅所述纵向主梁1-1的正下方;每组所述墩体顶升机构均包括两个对称布设于竖向墩柱27-1左右两侧的竖向顶升装置11和两个对称布设于竖向墩柱27-1左右两侧的辅助支撑结构12,每组所述墩体顶升机构中两个所述辅助支撑结构12均位于两个所述竖向顶升装置11之间,每组所述墩体顶升机构中两个所述辅助支撑结构12和两个所述竖向顶升装置11均位于待顶升引桥主梁1的同一个横断面上;Each of the single-column pier hydraulic jacking
所述独柱墩液压顶升装置28中每个所述倒置千斤顶的底座均水平支顶在待顶升引桥主梁1底部,每个所述倒置千斤顶的刚性顶举件均支顶在位于其正下方的所述临时支撑结构上;所述独柱墩液压顶升装置28中每个所述临时支撑结构均支撑于墩体抱柱梁29上。The base of each inverted jack in the single-column pier hydraulic jacking
本实施例中,每个所述独柱墩液压顶升装置28均包括两组所述墩体顶升机构,两组所述墩体顶升机构对称布设于竖向墩柱27-1的前后两侧。In this embodiment, each of the single-column pier hydraulic jacking
所述竖向墩柱27-1支撑于一个钻孔桩基础上,所述竖向墩柱27-1所支撑的钻孔桩基础为钢混基础27-2。The vertical pier 27-1 is supported on a bored pile foundation, and the bored pile foundation supported by the vertical pier 27-1 is a steel-concrete foundation 27-2.
本实施例中,每个所述引桥下部支撑结构中所包括独柱墩27的数量为两个,因而每个所述引桥主梁顶升装置均包括两个所述独柱墩液压顶升装置28。In this embodiment, the number of single-
实际使用时,根据独柱墩27的数量对独柱墩液压顶升装置28的数量进行确定。In actual use, the number of single-column pier hydraulic jacking
本实施例中,每个所述引桥主梁顶升装置还包括多个对所述倒置千斤顶的位置进行调整的千斤顶纠偏机构;每个所述引桥主梁顶升装置中所述千斤顶纠偏机构的数量与该引桥主梁顶升装置中所包括倒置千斤顶的数量相同,所述引桥主梁顶升装置中每个所述倒置千斤顶上均安装有一个千斤顶纠偏机构;In this embodiment, each of the main beam jacking devices of the approach bridge further includes a plurality of jack rectification mechanisms for adjusting the position of the inverted jack; The number of inverted jacks included in the main girder jacking device is the same, and a jack rectifying mechanism is installed on each of the inverted jacks in the approach bridge main girder jacking device;
如图14所示,所述千斤顶纠偏机构包括对所调整倒置千斤顶的位置进行水平调整的水平纠偏机构;结合图15、图16、图17及图18,所述水平纠偏机构包括多个水平调整件32、一个供所调整倒置千斤顶的底座安装的下固定板34和一个位于下固定板34上方的上固定板33,多个所述水平调整件32的结构均相同且其沿圆周方向布设于所调整倒置千斤顶的四周外侧;所调整倒置千斤顶的底座水平固定在下固定板34底部,所述下固定板34固定于所调整倒置千斤顶的底座上方,所述下固定板34为平直钢板且其与所调整倒置千斤顶的底座呈平行布设;所述上固定板33为平直钢板;As shown in Figure 14, the jack correction mechanism includes a horizontal correction mechanism for horizontally adjusting the position of the adjusted upside-down jack; with reference to Figure 15, Figure 16, Figure 17 and Figure 18, the horizontal correction mechanism includes a plurality of
每个所述水平调整件32均包括一个呈竖直向布设的螺栓杆32-1、一个同轴安装于螺栓杆32-1上的限位螺母32-2和一个同轴安装在螺栓杆32-1顶部的上滑移件32-3,所述螺栓杆32-1为平直杆,所述限位螺母32-2位于上滑移件32-3下方,所述限位螺母32-2与螺栓杆32-1之间以螺纹方式进行连接;Each of the
如图15所示,所述上固定板33上开有多个供上滑移件32-3横向滑移的横向滑移槽33-1和多个供螺栓杆32-1进行横向移动的横向插孔33-2,所述横向滑移槽33-1为平直槽且其与上固定板33呈平行布设,所述上滑移件32-3与上固定板33呈平行布设;所述横向滑移槽33-1的数量与上滑移件32-3的数量相同,多个所述横向滑移槽33-1均呈平行布设且其均沿所施工桥梁的横桥向进行布设,多个所述横向滑移槽33-1的结构和尺寸均相同;所述横向插孔33-2的数量与横向滑移槽33-1的数量相同,多个所述横向插孔33-2均为长条形孔且其结构和尺寸均相同,多个所述横向插孔33-2均与横向滑移槽33-1呈平行布设;所述横向插孔33-2的长度与横向滑移槽33-1的长度相同,所述横向插孔33-2的宽度大于横向滑移槽33-1的宽度;每个所述横向插孔33-2均位于一个所述横向滑移槽33-1的正下方,每个所述横向插孔33-2均与位于其正上方的横向滑移槽33-1连通;As shown in FIG. 15 , the
如图16所示,所述下固定板34上开有多个供螺栓杆32-1进行纵向移动的纵向插孔34-1,多个所述纵向插孔34-1均为长条形孔且其结构和尺寸均相同,多个所述纵向插孔34-1均呈平行布设且其均与横向插孔33-2呈垂直布设;所述纵向插孔34-1的数量与横向插孔33-2的数量相同,每个所述纵向插孔34-1均位于一个所述横向插孔33-2下方,每个所述纵向插孔34-1均与位于其下方的横向插孔33-2组成一个十字形调整孔;每个所述十字形调整孔中纵向插孔34-1与横向插孔33-2相交叉的区域为供一个所述螺栓杆32-1安装的螺栓安装孔,每个所述螺栓杆32-1均安装于一个所述螺栓安装孔内;As shown in FIG. 16 , the
所述千斤顶纠偏机构中上固定板33和下固定板34组成水平调整平台,每个所述上滑移件32-3均布设于一个所述横向滑移槽33-1内,每个所述限位螺母32-2均支撑于下固定板34底部,每个所述螺栓杆32-1均通过上滑移件32-3和限位螺母32-2紧固固定在所述水平调整平台上;所述下固定板34通过多个所述水平调整件32与上固定板33紧固连接。The upper fixed
因而,在每个所述倒置千斤顶上均设置一个所述千斤顶纠偏机构。Therefore, each of the upside-down jacks is provided with one of the jack rectifying mechanisms.
实际施工时,所述上滑移件32-3与螺栓杆32-1之间以焊接方式固定连接或以螺纹连接方式固定连接。During actual construction, the upper sliding member 32-3 and the bolt rod 32-1 are fixedly connected by welding or by screwing.
本实施例中,所述上滑移件32-3为安装在螺栓杆32-1上的螺母或螺帽。并且,所述上滑移件32-3的顶面不高于上固定板33的顶面。每个所述上滑移件32-3均卡装于一个所述横向滑移槽33-1内。In this embodiment, the upper sliding member 32-3 is a nut or a nut mounted on the bolt rod 32-1. Moreover, the top surface of the upper sliding member 32 - 3 is not higher than the top surface of the
所述上滑移件32-3也可以为其它类型的滑移块,只需能在横向滑移槽33-1内进行平移且固定在螺栓杆32-1顶部接口。The upper sliding member 32-3 can also be other types of sliding blocks, as long as it can translate in the lateral sliding groove 33-1 and be fixed on the top interface of the bolt rod 32-1.
为加工简便,所述上固定板33和下固定板34均为矩形钢板。For the convenience of processing, the
本实施例中,所述上固定板33和下固定板34均为长方形钢板且二者呈垂直布设。In this embodiment, the
实际使用时,所述上固定板33和下固定板34也可以采用其它类型的平直钢板,如正方形钢板、圆形钢板等。In actual use, the
本实施例中,所述水平调整件32的数量为四个,四个所述水平调整件32分别布设于一个矩形的四个顶点上。In this embodiment, the number of the
实际加工时,可根据具体需要,对水平调整件32的数量以及各水平调整件32的布设位置分别进行相应调整。During actual processing, the number of the leveling
本实施例中,所述千斤顶纠偏机构还包括在竖直面上对所调整倒置千斤顶的位置进行调整的竖向纠偏机构,所述竖向纠偏机构包括支垫于上固定板33与下固定板34之间的楔形钢板35,所述竖向纠偏机构紧固夹装于上固定板33与下固定板34之间。并且,所述竖向纠偏机构位于多个水平调整件32之间。In this embodiment, the jack rectifying mechanism further includes a vertical rectifying mechanism for adjusting the position of the adjusted upside-down jack on the vertical plane. The wedge-shaped
所述楔形钢板36的数量为一个或多个,多个所述楔形钢板36由下至上垫装于上固定板33与下固定板34之间。实际使用时,可根据具体需要,对所述竖向纠偏机构中楔形钢板36的数量进行相应调整。The number of the wedge-shaped
由上述内容可知,所述引桥梁端顶升装置中每个倒置千斤顶上均设置有一个所述千斤顶纠偏机构,所述引桥梁端顶升装置中所述上固定板33固定于横向分配梁22上,并且上固定板33通过多个紧固件固定于横向分配梁22底部,所述紧固件呈竖直向布设且为紧固螺栓等。It can be seen from the above content that each of the inverted jacks in the approach bridge end jacking device is provided with a jack rectifying mechanism, and the
本实施例中,所述横向分配梁22由两道布设于同一水平面上的工字钢拼接而成,两道所述工字钢均沿横桥向布设。所述横向分配梁22呈水平布设,因而能确保固定于其上的上固定板33呈水平布设。In this embodiment, the
实际施工时,也可以将所述引桥梁端顶升装置中的上固定板33直接焊接固定于横向分配梁22上。In actual construction, the
并且,所述柱式桥墩液压顶升装置25中每个倒置千斤顶上均设置有一个所述千斤顶纠偏机构,所述柱式桥墩液压顶升装置25中所述上固定板33固定于上抱柱梁15底部。通过上固定板33将所述倒置千斤顶固定于上抱柱梁15底部,能确保顶升过程中所述倒置千斤顶位置不动,以保证顶升过程顺利进行。因而,所述倒置千斤顶实际安装简便且拆装方便,上固定板33与所述倒置千斤顶之间连接可靠,上固定板33与所述倒置千斤顶紧固连接为一体。In addition, each upside-down jack in the column-type bridge pier hydraulic jacking
为确保上抱柱梁15底部的上固定板33能水平、平稳安装,进一步确保所述倒置千斤顶呈竖直向布设,所述上固定板33通过多个上锚固件紧固固定于上抱柱梁15底部;所述上固定板33与上抱柱梁15底部之间设置有一层上找平层,所述上找平层的底面为水平面且其底面与上固定板33紧贴;所述上找平层为砂浆找平层或混凝土找平层,多个所述上锚固件均固定于上找平层内;所述上锚固件为锚栓;实际固定时,所述上固定板33通过多个竖向锚固件紧固固定于上抱柱梁15底部。In order to ensure that the
本实施例中,所述竖向锚固件为锚栓。实际施工时,所述竖向锚固件也可以采用其它类型的锚固件,如固定于上抱柱梁15底部的植筋等。In this embodiment, the vertical anchor is an anchor. In actual construction, the vertical anchors may also use other types of anchors, such as planting bars fixed at the bottom of the
相应地,所述独柱墩液压顶升装置28中每个倒置千斤顶上均设置有一个所述千斤顶纠偏机构,所述独柱墩液压顶升装置28中所述上固定板33固定于待顶升引桥主梁1(即纵向主梁1-1)底部。Correspondingly, each of the upside-down jacks in the single-column pier hydraulic jacking
为确保纵向主梁1-1底部的上固定板33能水平、平稳安装,进一步确保所述倒置千斤顶呈竖直向布设,所述上固定板33通过多个锚栓紧固固定于纵向主梁1-1底部;所述上固定板33与纵向主梁1-1底部之间设置有一层上找平层,所述上找平层的底面为水平面且其底面与上固定板33紧贴;所述上找平层为砂浆找平层或混凝土找平层,多个所述锚栓均固定于上找平层内。In order to ensure that the
因而,所述千斤顶纠偏机构中所述上固定板33实际安装简便且拆装方便,并且通过所述上找平层进行找平后,能进一步确保上固定板33呈水平布设。所述下固定板34与所述倒置千斤顶之间连接可靠,下固定板34与所述倒置千斤顶紧固连接为一体,通过调整下固定板34的位置便简便、快速且有效对所述倒置千斤顶的位置进行相应调整。Therefore, the actual installation and disassembly of the
实际使用过程中,所述上固定板33的位置固定不动。通过所述水平纠偏机构对所述倒置千斤顶的位置进行横向水平调整时,沿横桥向水平推动下固定板34或所述倒置千斤顶,使下固定板34与所述倒置千斤顶同步进行横桥向移动;所述下固定板34与所述倒置千斤顶横桥向移动过程中,每个所述水平调整件32均沿所处横向插孔33-2进行平移;并且,通过所述水平纠偏机构对所述倒置千斤顶的位置进行纵向水平调整时,沿纵桥向水平推动下固定板34或所述倒置千斤顶,使下固定板34与所述倒置千斤顶同步进行纵桥向移动;所述下固定板34与所述倒置千斤顶纵桥向移动过程中,多个所述水平调整件32均固定不动。因而,通过所述水平纠偏机构能简便、快速对所述倒置千斤顶的位置进行简便、快速调整,并且能在纵桥向和横桥向上对所述倒置千斤顶的位置分别进行调整,能有效确保将所述倒置千斤顶的水平位置调整到位。During actual use, the position of the
在竖直方向上对所述倒置千斤顶的位置进行调整时,通过所述竖向纠偏机构进行调整,具体是通过在上固定板33与下固定板34之间垫装楔形钢板36的方法对所述倒置千斤顶的位置进行调整,因而实际操作简便,实现方便。When adjusting the position of the inverted jack in the vertical direction, the vertical deviation correction mechanism is used to adjust, specifically, the wedge-shaped
本实施例中,两个所述引桥主梁顶升装置中的所有竖向顶升装置11组成液压顶升装置,两个所述引桥主梁顶升装置中的所有辅助支撑结构12组成随动支撑装置。实际进行顶升时,所述液压顶升装置中的所有竖向千斤顶2同步动作,所述随动支撑装置中的所有随动千斤顶16同步动作。并且,所述液压顶升装置和所述随动支撑装置交替动作,完成待顶升引桥主梁1的顶升施工过程。并且,所述液压顶升装置和所述随动支撑装置交替动作指的是:对所述液压顶升装置和所述随动支撑装置中的钢管支撑结构3进行交替更换,实际操作非常简便,并且更换过程安全、可靠。In this embodiment, all vertical jacking
对所述反力基础进行确定时,一般以桥梁下部结构中的承台作为顶升反力基础,当未设置承台时一般依附于桥梁下部结构的承台或施工抱柱梁作为顶升反力基础;当桥梁下部结构上设置有盖梁时,可利用盖梁作为顶升受力点,当盖梁宽度范围内不足以安装液压千斤顶时,采用抱柱梁作为顶升受力点;当桥梁下部结构未设置盖梁时,则以桥梁上部结构的主梁作为受力点。When determining the reaction force foundation, the platform in the substructure of the bridge is generally used as the lifting reaction force foundation. When the platform is not set, the platform or the construction column beam attached to the substructure of the bridge is generally used as the lifting reaction force. Force foundation; when there is a cover beam on the lower structure of the bridge, the cover beam can be used as the jacking force point. When the width of the cover beam is not enough to install hydraulic jacks, the column-holding beam is used as the jacking force point; when When the lower structure of the bridge is not provided with a cover beam, the main beam of the upper structure of the bridge is used as the stress point.
如图19所示,采用本实用新型对大跨径系杆拱桥引桥进行顶升施工时,包括以下步骤:As shown in Figure 19, when the utility model is used to carry out the jacking construction of the approach bridge of the large-span tied arch bridge, the following steps are included:
步骤一、顶升装置安装:对两个所述引桥主梁顶升装置分别进行安装,并将两个所述引桥主梁顶升装置对称布设于待顶升引桥主梁1的左右两幅纵向主梁1-1下方;
步骤二、顶升:采用步骤一中两个所述引桥主梁顶升装置对待顶升引桥主梁1的左右两幅纵向主梁1-1同步进行竖向顶升,直至将左右两幅纵向主梁1-1均顶升到位;
步骤三、引桥下部结构接高:对位于左右两幅纵向主梁1-1下方的所述引桥下部支撑结构分别进行接高,并使步骤二中顶升到位的每幅所述纵向主梁1-1均支撑于一个接高后的所述引桥下部支撑结构上;
步骤四、顶升装置拆除:对步骤一中两个所述引桥主梁顶升装置分别进行拆除,完成待顶升引桥主梁1的顶升过程。
本实施例中,步骤一中对两个所述引桥主梁顶升装置进行安装时,两个所述引桥主梁顶升装置的安装方法相同。两个所述引桥主梁顶升装置对称布设,能确保顶升引桥主梁1顶升过程中受力均匀,支撑平稳。In this embodiment, when the two approach bridge main girder jacking devices are installed in
对任一个所述引桥主梁顶升装置进行安装时,对该引桥主梁顶升装置中的桥台侧液压顶升装置19、支撑桥墩侧液压顶升装置20、所有柱式桥墩液压顶升装置25和所有独柱墩液压顶升装置28分别进行安装,并将桥台侧液压顶升装置19安装在桥台18上,将支撑桥墩侧液压顶升装置20安装的所述竖向桥墩,在每个所述柱式桥墩23上均安装一个柱式桥墩液压顶升装置25,同时每个独柱墩27上均安装一个独柱墩液压顶升装置28,确保待顶升引桥主梁1的每个支撑墩上均安装有一个液压顶升装置,以便对待顶升引桥主梁1进行平稳顶升。When any one of the approach bridge main girder jacking devices is installed, the bridge abutment side hydraulic jacking device 19, the supporting bridge pier side hydraulic jacking
步骤二中进行顶升之前,先在每个所述柱式桥墩23上均施工上抱柱梁15和下抱柱梁14,并且在每个所述独柱墩27上施工墩体抱柱梁29,同时对水平混凝土基础21、条形基础36和横向支撑梁38分别进行施工。Before lifting in
所述上抱柱梁15、下抱柱梁14和墩体抱柱梁29均为钢筋混凝土抱柱梁,钢筋混凝土抱柱梁的布设位置灵活,可有效降低支撑高度,钢筋混凝土抱柱梁依靠新旧混凝土结构之间的摩擦力承担顶升荷载,因而在新老混凝土接触面范围内需对老混凝土结构表面进行凿毛处理,凿毛深度不小于6mm,以增大摩擦系数。The upper column-supporting
本实施例中,在柱式桥墩23上施工上抱柱梁15和下抱柱梁14时,在所述上抱柱梁15和下抱柱梁14所处位置处的柱式桥墩23的外侧壁分别进行凿毛处理,以便上抱柱梁15和下抱柱梁14与柱式桥墩23紧固连接为一体。In the present embodiment, when the
相应地,在独柱墩27上施工墩体抱柱梁29时,在墩体抱柱梁29所处位置处的独柱墩27的外侧壁进行凿毛处理,以便墩体抱柱梁29与独柱墩27紧固连接为一体。Correspondingly, when the pier body-supporting
本实施例中,所述大跨径系杆拱桥包括拱桥主桥和两个分别布设于所述拱桥主桥前后两侧的拱桥引桥,所述拱桥主桥与两个所述拱桥引桥布设于同一竖直面上;In this embodiment, the large-span tie-rod arch bridge includes a main arch bridge and two approach bridges respectively arranged on the front and rear sides of the main arch bridge, and the main arch bridge and the two approach bridges are arranged in the same vertical plane;
每个所述拱桥引桥均包括一个所述引桥主梁和一个支撑于所述引桥主梁下方的所述引桥下部结构;Each of the approach bridges includes a main beam of the approach bridge and a lower structure of the approach bridge supported below the main beam of the approach bridge;
所述拱桥主桥包括左右两幅对称布设的拱桥上部结构,两幅所述拱桥上部结构均沿纵桥向布设,每幅所述拱桥上部结构的前后两端均支撑于一个所述竖向桥墩上;每幅所述拱桥上部结构均包括两个呈对称布设的拱桥组合结构和多个沿纵桥向由前至后连接于两个所述拱桥组合结构之间的横梁,多个所述横梁均呈水平布设且其均沿横桥向布设,多个所述横梁均位于同一水平面上;每个所述拱桥组合结构均为钢管砼系杆拱且其包括一个呈水平布设的纵桥向主梁和一个架设于所述纵桥向主梁正上方且呈竖直向布设的拱肋,所述拱肋为钢管混凝土拱肋;所述纵桥向主梁和所述横梁均为钢筋混凝土梁,每幅所述拱桥上部结构中两个所述纵桥向主梁均通过多个所述横梁紧固连接为一体并形成一幅主桥主梁;The main bridge of the arch bridge includes two symmetrically arranged left and right arch bridge superstructures, both of which are arranged along the longitudinal bridge direction, and the front and rear ends of each of the arch bridge superstructures are supported on one of the vertical piers. Each of the arch bridge superstructures includes two symmetrically arranged arch bridge composite structures and a plurality of cross beams connected between the two arch bridge composite structures from front to back along the longitudinal bridge direction, and a plurality of the cross beams All of them are arranged horizontally and along the transverse bridge direction, and a plurality of the beams are located on the same horizontal plane; each of the arch bridge composite structures is a steel tube concrete tied arch and includes a horizontally arranged longitudinal bridge main bridge. beam and an arch rib erected directly above the longitudinal bridge girder and arranged vertically, the arch rib is a steel tube concrete arch rib; the longitudinal bridge girder and the cross beam are reinforced concrete beams , the two longitudinal bridge main beams in the upper structure of each arch bridge are fastened and connected together by a plurality of the transverse beams to form a main bridge main beam;
两幅所述主桥主梁分别为左侧主桥主梁和位于所述左侧主桥主梁右侧的右侧主桥主梁,每个所述引桥主梁中两幅所述纵向主梁1-1分别为左侧纵向主梁和位于所述左侧纵向主梁右侧的右侧纵向主梁,The two main beams of the main bridge are the left main bridge main beam and the right main bridge main beam located on the right side of the left main bridge main beam, and each of the approach bridge main beams has two longitudinal main beams. The beams 1-1 are respectively the left longitudinal main beam and the right longitudinal main beam located on the right side of the left longitudinal main beam,
所述左侧主桥主梁与位于其前后两侧的所述左侧纵向主梁均布设于同一竖直面上,所述右侧主桥主梁与位于其前后两侧的所述右侧纵向主梁均布设于同一竖直面上,所述左侧主桥主梁与位于其前后两侧的所述左侧纵向主梁之间以及所述右侧主桥主梁与位于其前后两侧的所述右侧纵向主梁之间均通过横向伸缩缝进行连接,所述横向伸缩缝呈水平布设;The left main bridge main girder and the left longitudinal main girder located on the front and rear sides thereof are all arranged on the same vertical plane, and the right main bridge main girder and the right side main beam located on the front and rear sides thereof are arranged on the same vertical plane. The longitudinal main beams are all arranged on the same vertical plane, between the left main bridge main beam and the left longitudinal main beam located on the front and rear sides of the left main bridge, and the right main bridge main beam and the front and rear two main beams. The right longitudinal main beams on the side are connected by transverse expansion joints, and the transverse expansion joints are arranged horizontally;
步骤二中进行顶升之前,将待顶升引桥主梁1中两幅所述纵向主梁1-1的待接续端与所述主桥主梁之间的横向伸缩缝均断开,使待顶升引桥主梁1中两幅所述纵向主梁1-1与所述主桥主梁均分离,同时将待顶升引桥主梁1中两幅所述纵向主梁1-1与其下方的桥台18和所述竖向桥墩均分离;Before the jacking in
所述待顶升引桥主梁1中每幅所述纵向主梁1-1的待接续端一侧均设置有一个新建主梁30,所述新建主梁30为混凝土梁或组合梁且其沿纵桥向布设;每个所述新建主梁30均与一幅所述纵向主梁1-1的待接续端连接,每个所述新建主梁30与其所连接的纵向主梁1-1布设于同一竖直面上,每个所述新建主梁30下方均设置有多个竖向支撑墩31,多个所述竖向支撑墩31沿纵桥向由前至后布设,所述竖向支撑墩31为钢筋混凝土桥墩;One side of the to-be-connected end of each of the longitudinal main beams 1-1 in the
步骤三中引桥下部结构接高后,将顶升到位的每幅所述纵向主梁1-1均与一个所述新建主梁30紧固连接为一体。In
本实施例中,步骤二中进行顶升时,先进行试顶升;经试顶升检测各倒置千斤顶均工作正常后,再进行正式顶升。In this embodiment, when the jacking is performed in
本实施例中,步骤二中进行顶升之前,将桥台18、所述竖向桥墩、柱式桥墩23和独柱墩27上对纵向主梁1-1进行支撑的桥梁支座均拆除。In this embodiment, before lifting in
并且,步骤二中进行顶升之前,还需对待顶升引桥主梁1下方的所有柱式桥墩23分别进行切割。并且,对各柱式桥墩23进行切割时,在柱式桥墩液压顶升装置25中各倒置千斤顶均处于保压状态下进行切割。In addition, before the jacking is performed in
步骤三中进行引桥下部结构时,对桥台18、所述竖向桥墩、柱式桥墩23和独柱墩27分别进行接高。In
其中,对桥台18进行接高时,对台顶盖梁18-2进行接高。在台顶盖梁18-2上施工台顶接高盖梁,所述台顶接高盖梁为钢筋混凝土盖梁且其与台顶盖梁18-2浇筑为一体,所述台顶接高盖梁内的钢筋笼与台顶盖梁18-2内的钢筋笼紧固连接为一体。待所述台顶接高盖梁施工完成后,在所述台顶接高盖梁上施工对顶升到位的待顶升引桥主梁1进行支撑的桥梁支座。Wherein, when the
对台顶盖梁18-2进行接高时,包括以下步骤:When connecting the ceiling beam 18-2 of the platform, the following steps are included:
步骤A1、对台顶盖梁18-2上部的混凝土进行凿除,并露出台顶盖梁18-2上部内侧的钢筋笼;Step A1, chisel off the concrete on the upper part of the table top cover beam 18-2, and expose the reinforcement cage inside the upper part of the table top cover beam 18-2;
步骤A2、对所述台顶接高盖梁内的钢筋笼进行绑扎,并将所绑扎钢筋笼与台顶盖梁18-2内的钢筋笼紧固连接为一体;Step A2, binding the reinforcement cages in the platform top-connected high cover beams, and fasten the binding reinforcement cages with the reinforcement cages in the platform top cover beams 18-2 as a whole;
步骤A3、在台顶盖梁18-2上部外侧支立模板,并利用所支立的模板对所述台顶接高盖梁进行混凝土浇筑,获得施工成型的所述台顶接高盖梁。In step A3, a formwork is erected on the outer side of the upper part of the platform top cover beam 18-2, and the platform top-connected high-cap beam is poured with concrete using the erected template to obtain the construction-formed platform-top connected high-cap beam.
本实施例中,步骤二中进行顶升之前,还需对桥台18上的挡墙进行拆除。In this embodiment, before lifting in
本实施例中,对新建主梁30进行施工之前,还需对桥台18进行改造,具体是在桥台18中钢混桥台基础18-3靠近新建主梁30的一侧施工桥台新增基础18-4,所述桥台新增基础18-4为钻孔桩基础且其为钢筋混凝土基础,所述桥台新增基础18-4中的水平承台与钢混桥台基础18-3的水平承台浇筑为一体;同时,在桥台18中每个所述肋板18-1靠近新建主梁30的一侧均施工新增肋板18-5,并使新增肋板18-5与肋板18-1浇筑为一体,所述新增肋板18-5为钢筋混凝土结构;并且,在台顶盖梁18-2靠近新建主梁30的一侧施工新增盖梁18-6,所述新增盖梁18-6为钢筋混凝土盖梁且其与台顶盖梁18-2浇筑为一体,这样便将桥台18改造为桥墩,并且所述新建主梁30的一端支撑于该桥墩上。In this embodiment, before the construction of the newly-built
对所述竖向桥墩进行接高时,对水平盖梁37进行接高。对水平盖梁37进行接高时,在水平盖梁37上施工墩顶接高盖梁,所述墩顶接高盖梁为钢筋混凝土盖梁且其与水平盖梁37浇筑为一体,所述墩顶接高盖梁内的钢筋笼与水平盖梁37内的钢筋笼紧固连接为一体。When the vertical bridge pier is heightened, the
待所述墩顶接高盖梁施工完成后,在所述墩顶接高盖梁上施工对顶升到位的待顶升引桥主梁1进行支撑的桥梁支座。After the construction of the pier top-connecting the high-cap beam is completed, the bridge bearing supporting the
对水平盖梁37进行接高时,包括以下步骤:When the
步骤B1、对水平盖梁37上部的混凝土进行凿除,并露出水平盖梁37上部内侧的钢筋笼;Step B1, chisel off the concrete on the upper part of the
步骤B2、对所述墩顶接高盖梁内的钢筋笼进行绑扎,并将所绑扎钢筋笼与水平盖梁37内的钢筋笼紧固连接为一体;Step B2, binding the reinforcement cages in the high cover beams on the top of the pier, and tightening the binding reinforcement cages with the reinforcement cages in the horizontal cover beams 37 as a whole;
步骤B3、在水平盖梁37上部外侧支立模板,并利用所支立的模板对所述墩顶接高盖梁进行混凝土浇筑,获得施工成型的所述墩顶接高盖梁。Step B3, erect a formwork on the upper outer side of the
如图20所示,对柱式桥墩23进行接高时,在柱式桥墩23中每个所述竖向墩柱13的所述下部墩柱和所述上部墩柱之间均施工连接墩柱39,所述连接墩柱39为钢筋混凝土柱且其与所连接的所述下部墩柱和所述上部墩柱均布设于同一个竖直线上。每个所述竖向墩柱13中所述下部墩柱和所述上部墩柱的竖向受力钢筋之间均通过连接墩柱39内的竖向受力钢筋紧固连接为一体。As shown in FIG. 20 , when the
在柱式桥墩23中任一个所述竖向墩柱13的所述下部墩柱和所述上部墩柱之间施工连接墩柱39时,包括以下步骤:When constructing the connecting
步骤C1、对所述上部墩柱下部的混凝土进行凿除,使所述上部墩柱内侧下部的竖向受力钢筋露出,且所述竖向受力钢筋露出高度为22cm~28cm;同时,对对所述下部墩柱上部的混凝土进行凿除,使所述下部墩柱内侧上部的竖向受力钢筋露出,且所述竖向受力钢筋露出高度为22cm~28cm;Step C1, chisel off the concrete at the lower part of the upper pier column, so as to expose the vertical stress steel bar on the inner and lower part of the upper pier column, and the exposed height of the vertical stress steel bar is 22cm-28cm; The concrete on the upper part of the lower pier column is chiseled, so that the vertical stress steel bar on the inner upper part of the lower pier column is exposed, and the exposed height of the vertical stress steel bar is 22cm-28cm;
步骤C2、在下抱柱梁14上对连接墩柱39内的钢筋笼进行绑扎,并采用挤压套筒将连接墩柱39内的钢筋笼中各竖向受力钢筋分别与所述下部墩柱和所述上部墩柱内的竖向受力钢筋紧固连接;Step C2, bind the reinforcement cages in the connecting
步骤C3、在下抱柱梁14上支立用于施工连接墩柱39的模板,并利用所支立模板对连接墩柱39进行混凝土浇筑。In step C3, a formwork for constructing the connecting
为使连接墩柱39与所述下部墩柱和所述上部墩柱均浇筑为一体,步骤C3中进行混凝土浇筑之前,还需对所述下部墩柱和所述上部墩柱与连接墩柱39的混凝土接触面分别进行凿毛处理,以利于新老砼的连接。In order to make the connecting
步骤C2和步骤C3中均利用下抱柱梁14进行施工,施工简便,能有效节约施工成本,并节约施工工期。In both steps C2 and C3, the lower pillar beams 14 are used for construction, which is convenient for construction, and can effectively save construction costs and construction period.
所述柱式桥墩23中每个所述竖向墩柱13的所述下部墩柱和所述上部墩柱之间通过连接墩柱39进行连接后,获得接高后墩柱;所述接高后墩柱施工完成后,还需在所述接高后墩柱外侧施工外包钢筋混凝土层,所述外包钢筋混凝土层的横截面为圆环形且其同轴套装在所述接高后墩柱外侧,通过所述外包钢筋混凝土层对所述接高后墩柱中的连接墩柱39以及连接墩柱39与所述下部墩柱和所述上部墩柱之间的连接处进行加固。After the lower pier and the upper pier of each of the
待柱式桥墩23中两个所述竖向墩柱13的所述下部墩柱和所述上部墩柱之间均通过连接墩柱39进行连接后,对上抱柱梁15进行拆除。所述外包钢筋混凝土层的上表面高于上抱柱梁15的上表面。After the lower piers and the upper piers of the two
本实施例中,对所述外包钢筋混凝土层进行施工时,利用下抱柱梁14进行施工。对所述外包钢筋混凝土层进行施工时,在下抱柱梁14上支立用于施工所述外包钢筋混凝土层的模板,并利用所支立的模板对所述外包钢筋混凝土层进行施工。并且,所述外包钢筋混凝土层内的钢筋笼通过植筋与下抱柱梁14紧固连接为一体,因而通过下抱柱梁14为所述外包钢筋混凝土层提供了极大便利,同时也便于支模。由于下抱柱梁14本身是临时结构,在拆除之前先进行立柱外包部分施工,很好的利用了现场资源。In this embodiment, when the outer reinforced concrete layer is constructed, the lower column-supporting
待所述外包钢筋混凝土层施工完成后,完成柱式桥墩23的接高过程,无需对下抱柱梁14进行拆除。所述下抱柱梁14回填即可,不仅施工简便,并且更有利于桥梁整体结构的稳定。After the construction of the outer reinforced concrete layer is completed, the height connection process of the
对独柱墩27进行接高时,在独柱墩27上施工一个接高墩柱,所述接高墩柱为钢筋混凝土墩柱且其位于独柱墩27的正上方。When the single-
对独柱墩27进行接高时,包括以下步骤:When the single-
步骤D1、对独柱墩27上部的混凝土进行凿除,使独柱墩27内侧上部的竖向受力钢筋露出,且所述竖向受力钢筋露出高度为22cm~28cm;In step D1, the concrete on the upper part of the single-
步骤D2、在独柱墩27上对所述接高墩柱内的钢筋笼进行绑扎,并采用挤压套筒将所述接高墩柱内的钢筋笼中各竖向受力钢筋分别与独柱墩27内的竖向受力钢筋紧固连接;Step D2, on the single-
步骤D3、在独柱墩27上支立用于施工所述接高墩柱的模板,并利用所支立模板对所述接高墩柱进行混凝土浇筑。In step D3, a formwork for constructing the high-connecting pier column is supported on the single-
待所述接高墩柱施工完成后,在所述接高墩柱上施工对顶升到位的待顶升引桥主梁1进行支撑的桥梁支座。After the construction of the high-connecting pier column is completed, a bridge bearing for supporting the
以上所述,仅是本实用新型的较佳实施例,并非对本实用新型作任何限制,凡是根据本实用新型技术实质对以上实施例所作的任何简单修改、变更以及等效结构变化,均仍属于本实用新型技术方案的保护范围内。The above are only preferred embodiments of the present utility model, and do not limit the present utility model. Any simple modifications, changes and equivalent structural changes made to the above embodiments according to the technical essence of the present utility model still belong to the scope of the present utility model. within the protection scope of the technical solution of the present invention.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201921276039.0U CN210684429U (en) | 2019-08-08 | 2019-08-08 | A kind of long-span tied arch bridge approach bridge jacking system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201921276039.0U CN210684429U (en) | 2019-08-08 | 2019-08-08 | A kind of long-span tied arch bridge approach bridge jacking system |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN210684429U true CN210684429U (en) | 2020-06-05 |
Family
ID=70896511
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201921276039.0U Active CN210684429U (en) | 2019-08-08 | 2019-08-08 | A kind of long-span tied arch bridge approach bridge jacking system |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN210684429U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110424246A (en) * | 2019-08-08 | 2019-11-08 | 中铁二十局集团第一工程有限公司 | A long-span tied arch bridge approach jacking system and jacking construction method |
| CN114197339A (en) * | 2022-01-27 | 2022-03-18 | 贵州省交通规划勘察设计研究院股份有限公司 | Supporting structure capable of supporting bridge structure above bridge pier |
| CN114541269A (en) * | 2022-03-05 | 2022-05-27 | 南通市港闸市政工程有限公司 | Bridge jacking device and synchronous slope adjusting jacking method for continuous multi-span curved beam bridge |
-
2019
- 2019-08-08 CN CN201921276039.0U patent/CN210684429U/en active Active
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110424246A (en) * | 2019-08-08 | 2019-11-08 | 中铁二十局集团第一工程有限公司 | A long-span tied arch bridge approach jacking system and jacking construction method |
| CN114197339A (en) * | 2022-01-27 | 2022-03-18 | 贵州省交通规划勘察设计研究院股份有限公司 | Supporting structure capable of supporting bridge structure above bridge pier |
| CN114541269A (en) * | 2022-03-05 | 2022-05-27 | 南通市港闸市政工程有限公司 | Bridge jacking device and synchronous slope adjusting jacking method for continuous multi-span curved beam bridge |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104452597B (en) | Pier prestressed cap beam with extra length Construction Supporting System in water | |
| CN211947993U (en) | Support for large-span cast-in-situ bridge construction | |
| CN215329323U (en) | Light combined pier hoisted in small tonnage | |
| CN210684429U (en) | A kind of long-span tied arch bridge approach bridge jacking system | |
| CN110424246A (en) | A long-span tied arch bridge approach jacking system and jacking construction method | |
| CN107761542A (en) | One kind arch oblique pull combined system bridge and its construction method | |
| CN110593115A (en) | Cast-in-place box girder support system and its construction method | |
| CN110184903A (en) | A kind of prefabricated tubing string assembly bridge pier of truss-like | |
| CN112095495A (en) | Bridge underpinning support structure and construction method | |
| CN210684430U (en) | Main bridge jacking system of large-span tied arch bridge | |
| CN108265618A (en) | A kind of reverse increasing layer construction method in overpass pier base underground | |
| CN102392417B (en) | Dual-cantilever bearing support structure for large steel pipe and installation method | |
| CN110700122A (en) | A antidumping reinforced structure for rectangle single-column mound bridge | |
| CN211772934U (en) | Zero number block support system of bridge | |
| CN110424243A (en) | A main bridge jacking system and jacking construction method of a long-span tied arch bridge | |
| CN209816632U (en) | Arch foot structure for special-shaped space arch bridge | |
| CN110424245B (en) | Large-span tied arch bridge reconstruction method based on bridge hydraulic jacking system | |
| CN211228134U (en) | Large cantilever prestress bent cap support device | |
| CN116084293B (en) | Triangular steel arch formwork system and construction method for cast-in-place concrete main arch ring | |
| CN107558606A (en) | A kind of prefabricated construction construction method | |
| CN215164738U (en) | Tied-rod arch type fast-splicing support | |
| CN213571600U (en) | Bridge underpins bearing structure | |
| CN112281684B (en) | Continuous beam zero number block combined support mounting construction method and support | |
| CN104532758A (en) | A Construction Support for No. 0 Block of Prestressed Concrete Cantilevered Continuous Beam | |
| CN110424244B (en) | Large-span steel pipe concrete tied arch bridge jacking construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP03 | Change of name, title or address |
Address after: 215151 No. 10, Datong Road, high tech Zone, Suzhou, Jiangsu Patentee after: China Railway Construction Urban Construction Transportation Development Co.,Ltd. Country or region after: China Address before: Engineering technology management center of the first Engineering Co., Ltd. of China Railway 20th bureau group, No.10 Datong Road, high tech Zone, Suzhou City, Jiangsu Province Patentee before: NO.1 ENGINEERING CORPORATION LIMITED OF CR20G Country or region before: China |
|
| CP03 | Change of name, title or address |