CN210661644U - Pipe jacking hat brim device - Google Patents

Pipe jacking hat brim device Download PDF

Info

Publication number
CN210661644U
CN210661644U CN201921438004.2U CN201921438004U CN210661644U CN 210661644 U CN210661644 U CN 210661644U CN 201921438004 U CN201921438004 U CN 201921438004U CN 210661644 U CN210661644 U CN 210661644U
Authority
CN
China
Prior art keywords
baffle
pipeline
pipe
soil
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921438004.2U
Other languages
Chinese (zh)
Inventor
崔永
顷博
汤海涛
崔彩香
李倩倩
李燕云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Water Conservancy Machinery Equipment Manufacturing Installation Co ltd
Sinohydro Corp Engineering Bureau 15 Co Ltd
Original Assignee
Shaanxi Water Conservancy Machinery Equipment Manufacturing Installation Co ltd
Sinohydro Corp Engineering Bureau 15 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Water Conservancy Machinery Equipment Manufacturing Installation Co ltd, Sinohydro Corp Engineering Bureau 15 Co Ltd filed Critical Shaanxi Water Conservancy Machinery Equipment Manufacturing Installation Co ltd
Priority to CN201921438004.2U priority Critical patent/CN210661644U/en
Application granted granted Critical
Publication of CN210661644U publication Critical patent/CN210661644U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a pipe jacking brim of a hat device is provided with the sleeve outside the pipeline, and telescopic one end is provided with the baffle, and the baffle downside is provided with the mount, and the baffle outward flange is provided with the protective layer. The utility model discloses a be provided with the sleeve outside the pipeline, be provided with the baffle on the sleeve, in the baffle can prevent that the outer soil of pipeline from gushing into the pipeline, protection operation personnel and equipment, the baffle also plays the supporting role to the soil body on pipeline upper strata simultaneously, and the protection concrete pipe can not produce local destruction at the whole atress of pipe jacking in-process. The baffle downside is provided with the mount, and the baffle outward flange is provided with the protective layer, and the protective layer can ensure that the pipeline can not produce local distortion because of the atress inequality at the in-process baffle of advancing, reduces the resistance that the pipeline pushed up into the soil body. The utility model discloses can play certain supporting role to upper soil, the guarantee pipeline is gone on safely when the operation is advanced in the top, does not influence the operation personnel construction simultaneously, makes things convenient for the operation personnel to come in and go out.

Description

Pipe jacking hat brim device
Technical Field
The utility model belongs to the technical field of tunnel and underground works construction, concretely relates to push pipe brim of a hat device.
Background
The pipe jacking construction is a common non-excavation construction method in water conservancy and hydropower construction, namely under the condition of not excavating the earth surface, the friction force between a pipeline and surrounding soil is overcome by means of jacking equipment in a working pit, the pipeline is jacked into the soil according to a designed gradient and the earthwork is transported away, after one section of pipe is jacked into the soil layer, the lower second section of pipe is jacked continuously, the principle is that a tool pipe or a heading machine is pushed into a receiving pit from the working pit through the soil layer by means of the thrust of a main jacking oil cylinder, the space between the pipelines, the relay and the like, and the pipeline is buried between the two pits after following the tool pipe or the heading machine. The pipe jacking operation can be carried out by manual excavation jacking and muddy water balance excavation jacking for different soil materials. In the manual jacking operation construction, an operator is required to enter a jacking pipe to carry out the work of digging, clearing and the like, and due to the instability of gravel soil, the phenomenon of collapse and the like easily occurs, or the phenomenon of digging material to flow into the area with abundant underground water occurs, so that the guarantee of the safety of the operator is the extremely important work in the jacking pipe operation. At present, in the only pipe jacking operation construction method, a grid is applied to a pipe opening to protect operating personnel in the pipe jacking, but the measure can cause great influence on the construction and increase the project construction cost. In order to meet the requirement of safe jacking operation under the condition of gravel geology and save project cost, the pipe jacking brim device is developed by combining the actual condition of a project site.
Disclosure of Invention
The utility model aims to solve the technical problem that overcome above-mentioned prior art's shortcoming, provide an economic safety, guarantee operation personnel's safety, reduced the push pipe brim of a hat device of cost when push pipe advances.
The technical scheme for solving the technical problems is as follows: the pipeline is provided with a sleeve outside, one end of the sleeve is provided with a baffle, the lower side of the baffle is provided with a fixing frame, and the outer edge of the baffle is provided with a protective layer.
The utility model discloses a terminal surface of baffle is the arc plate of downwarping, and the centre of a circle is located the below of arc plate, and the central angle of arc plate is 135 ~ 225 °, and the radius of arc plate is 2 with the diameter ratio of pipeline: 5-3: 5.
The utility model discloses a be provided with the sleeve outside the pipeline, be provided with the baffle on the sleeve, in the baffle can prevent that the outer soil of pipeline from gushing into the pipeline, protection operation personnel and equipment, the baffle also plays the supporting role to the soil body on pipeline upper strata simultaneously, and protection concrete pipe can not produce local destruction at the whole atress of pipe jacking in-process. The baffle downside is provided with the mount, and the baffle outward flange is provided with the protective layer, and the protective layer can ensure that the pipeline can not produce local distortion because of the atress inequality at the in-process baffle of advancing, reduces the resistance that the pipeline pushed up into the soil body. The utility model discloses can play certain supporting role to upper soil, the guarantee pipeline is gone on safely when the operation is advanced in the top, does not influence the operation personnel construction simultaneously, makes things convenient for the operation personnel to come in and go out. The utility model has the advantages of simple structure, low cost and wide application range, and is suitable for various soil working faces.
Drawings
Fig. 1 is a schematic structural diagram of an embodiment of the present invention.
Fig. 2 is an expanded view of fig. 1.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Example 1
Taking the advancing direction of the pipeline 1 as an example, as shown in fig. 1-2, the pipe-jacking visor device of the embodiment is formed by connecting a sleeve 2, a baffle 3, a fixing frame 4 and a protective layer 5.
The pipe jacking device comprises a pipe 1, a sleeve 2, a baffle 3, a downward-bent arc plate, a circle center and a baffle 3, wherein the sleeve 2 is arranged outside the pipe 1, the protective pipe 1 is integrally stressed in the pipe jacking construction process and cannot be locally damaged, the front end of the sleeve 2 is provided with the baffle 3, the front end surface of the baffle 3 is the arc plate which is bent downwards, the circle center is located below the arc plate, the central angle of the arc plate is 180 degrees, the diameter ratio of the radius of the arc plate to the pipe 1 is 2.5:5, the baffle 3 can prevent soil outside the pipe 1 from flowing into the pipe 1 to protect operating personnel and equipment, meanwhile, the baffle 3 also plays a supporting role in supporting soil on the upper layer of the pipe 1, and plays a role in guiding a sample plate for. Fixing frame 4 is installed to 3 downside of baffle, and fixing frame 4 is the square steel, and the intensity, the rigidity of baffle 3 in the jacking in-process can be strengthened to the square steel, guarantees wholeness, stability and the security of this embodiment. The outward flange welding of baffle 3 has protective layer 5, and protective layer 5 can ensure that pipeline 1 can not produce local distortion because of the atress inequality at the in-process baffle 3 that advances, reduces the resistance that pipeline 1 pushed into the soil body. This embodiment is advanced along with pipeline 1 together when pipeline 1 advances in the top, does not need frequent installation to dismantle, can play certain supporting role to pipeline 2's upper soil, and the guarantee this device is gone on at the operation safety that advances in the top, does not influence the operation personnel construction simultaneously, makes things convenient for the operation personnel to come in and go out.
Example 2
Install sleeve 2 outside pipeline 1, baffle 3 is installed to 2 one ends of sleeve, and the preceding terminal surface of baffle 3 is the circular arc board of downwarping, and the centre of a circle is located the below of circular arc board, and the central angle of circular arc board is 135 °, and the radius of circular arc board is 2 with the diameter ratio of pipeline 1: 5. the fixing frame 4 is installed on the lower side of the baffle 3, and the protective layer 5 is welded on the outer edge of the baffle 3.
Other components and the coupling relationship of the components are the same as those in embodiment 1.
Example 3
The pipeline comprises a pipeline 1, a sleeve 2 is arranged outside the pipeline 1, a baffle 3 is arranged at one end of the sleeve 2, the front end face of the baffle 3 is a downward-bent arc plate, the center of a circle is located below the arc plate, the central angle of the arc plate is 225 degrees, and the ratio of the radius of the arc plate to the diameter of the pipeline 1 is 3: 5. The fixing frame 4 is installed on the lower side of the baffle 3, and the protective layer 5 is welded on the outer edge of the baffle 3.
Other components and the coupling relationship of the components are the same as those in embodiment 1.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the scope of the present invention.

Claims (2)

1. The utility model provides a push pipe brim of a hat device which characterized in that: the pipeline protection device is characterized in that a sleeve (2) is arranged outside the pipeline (1), a baffle (3) is arranged at one end of the sleeve (2), a fixing frame (4) is arranged on the lower side of the baffle (3), and a protection layer (5) is arranged on the outer edge of the baffle (3).
2. The push pipe visor device of claim 1, wherein: one end face of the baffle (3) is an arc plate bent downwards, the circle center is positioned below the arc plate, the central angle of the arc plate is 135 degrees to 225 degrees, and the diameter ratio of the radius of the arc plate to the pipeline (1) is 2: 5-3: 5.
CN201921438004.2U 2019-08-30 2019-08-30 Pipe jacking hat brim device Active CN210661644U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921438004.2U CN210661644U (en) 2019-08-30 2019-08-30 Pipe jacking hat brim device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921438004.2U CN210661644U (en) 2019-08-30 2019-08-30 Pipe jacking hat brim device

Publications (1)

Publication Number Publication Date
CN210661644U true CN210661644U (en) 2020-06-02

Family

ID=70811449

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921438004.2U Active CN210661644U (en) 2019-08-30 2019-08-30 Pipe jacking hat brim device

Country Status (1)

Country Link
CN (1) CN210661644U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111458085A (en) * 2020-06-22 2020-07-28 胜利油田新大管业科技发展有限责任公司 Air tightness testing machine and air tightness testing method suitable for epoxy glass reinforced plastic pipeline
CN112942468A (en) * 2021-02-06 2021-06-11 北京市市政二建设工程有限责任公司 Top-entering construction method for open trench digging pipeline

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111458085A (en) * 2020-06-22 2020-07-28 胜利油田新大管业科技发展有限责任公司 Air tightness testing machine and air tightness testing method suitable for epoxy glass reinforced plastic pipeline
CN111458085B (en) * 2020-06-22 2020-09-08 胜利油田新大管业科技发展有限责任公司 Air tightness testing machine and air tightness testing method suitable for epoxy glass reinforced plastic pipeline
CN112942468A (en) * 2021-02-06 2021-06-11 北京市市政二建设工程有限责任公司 Top-entering construction method for open trench digging pipeline
CN112942468B (en) * 2021-02-06 2022-04-19 北京市市政二建设工程有限责任公司 Top-entering construction method for open trench digging pipeline

Similar Documents

Publication Publication Date Title
CN106761785B (en) A kind of subway tunnel shield originates construction technology
CN101457853B (en) Non-digging tube-pulling construction method
CN103469817B (en) Existing subway station main structure broadening construction method
CN210661644U (en) Pipe jacking hat brim device
CN103821544A (en) Tunnel and underground engineering high-pressure high-flow-rate sudden surging water control method
CN103485790A (en) Shallow tunneling method for pipe-proof-supporting structure combined system
CN210564534U (en) Rectangular pipe jacking oblique crossing construction structure
CN104131821B (en) A kind of shield tunnel plug-in conduit grooving structure and fixing means thereof
CN110924978A (en) Construction method for preventing instability of shield tunnel under high-sensitivity stratum condition
CN110541966B (en) Auxiliary equipment for jacking pipe joint in narrow space and application method thereof
CN201424658Y (en) Water leakage detection of underground continuous wall groove seams and block repair device
CN202627165U (en) Device for repairing completely collapsed and large-deformation pipes without excavating whole pipes
CN112627840A (en) Leading guiding mechanism of pipe jacking engineering
CN201581902U (en) Sand layer pipe jacking shield machine
CN205206847U (en) Shield constructs business turn over hole portal annular and freezes sealed sealing device
CN109058583B (en) Tool pipe for hand-digging type pipe jacking construction
CN204609814U (en) A kind of deep thick alluvium bored shaft broken grouting orifice tube is anti-goes out device
CN112267889B (en) Construction method for penetrating through filling material of molten cavity
CN107060812A (en) A kind of constructing tunnel excavating device and method
CN213329041U (en) Utility tunnel deep basal pit supports steel column spare with supporting construction
Zhang et al. Construction applicability of mechanical methods for connecting aisle in the bohai mudstone stratum with high water pressure
CN104344086A (en) Pipeline buttress device and use method
CN215949485U (en) Temporary door sealing structure for pipe jacking construction
CN114483163A (en) Gas extraction method
CN204152529U (en) A kind of anchor cable rack tunnel cut-off equipment for mine dynamic water sealing

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant