CN210636770U - Special moving platform integrating high-altitude falling protection and construction operation - Google Patents

Special moving platform integrating high-altitude falling protection and construction operation Download PDF

Info

Publication number
CN210636770U
CN210636770U CN201920433268.2U CN201920433268U CN210636770U CN 210636770 U CN210636770 U CN 210636770U CN 201920433268 U CN201920433268 U CN 201920433268U CN 210636770 U CN210636770 U CN 210636770U
Authority
CN
China
Prior art keywords
truss
construction
platform
protection
construction operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920433268.2U
Other languages
Chinese (zh)
Inventor
苏毅
苟国强
孙乾
李坤
邵奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Shitong Chongqing Heavy Industry Co ltd
Cccc Worldcom Heavy Industries Beijing Co ltd
CCCC First Highway Engineering Co Ltd
Original Assignee
Cccc Shitong Chongqing Heavy Industry Co ltd
Cccc Worldcom Heavy Industries Beijing Co ltd
CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Shitong Chongqing Heavy Industry Co ltd, Cccc Worldcom Heavy Industries Beijing Co ltd, CCCC First Highway Engineering Co Ltd filed Critical Cccc Shitong Chongqing Heavy Industry Co ltd
Priority to CN201920433268.2U priority Critical patent/CN210636770U/en
Application granted granted Critical
Publication of CN210636770U publication Critical patent/CN210636770U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a special moving platform of high altitude protection and construction operation integration that falls, connect external member, truss, landing leg post, gyro wheel chunk, landing leg post tie rod including the railing. The utility model discloses the platform relates to the architectural equipment field, and this platform is particularly useful for station, the long linear building structure's of corridor formula decoration construction. Can also be used as a building safety passage to prevent falling from high altitude. The height can be adjusted within a certain range; the span and the width of the platform can meet the construction requirements by adjusting the structural size and the material model of the truss according to specific projects; can be disassembled for reuse. The construction method is convenient and fast to construct, meets the protection requirement of high-altitude operation within a certain range, saves construction cost and can accelerate construction progress.

Description

Special moving platform integrating high-altitude falling protection and construction operation
Technical Field
The utility model relates to a construction equipment technical field especially relates to a high altitude is fallen and is protected and special moving platform of construction operation integration, specifically is the special moving platform of construction that the protection is fallen and is decorated construction operation as an organic whole for the building high altitude.
Background
The building decoration is a kind of treatment process to protect the main structure of the building, improve the physical performance and use function of the building and beautify the building, and the interior and exterior surfaces and spaces of the building are treated with decoration materials or ornaments. Especially, the interior and exterior decoration of large public buildings is more sophisticated and exquisite in structure, vision and spirit along with the development of the times economy and is rich in times inspiration. The large public buildings are generally places where people move intensively, and in order to build a light and wide space, steel structure design and application are more and more, especially, the installation of a large-span steel structure roof structural member and the installation operation of a top plate generally need high-altitude operation, workers need to position, connect and fix the structural member at high altitude and sometimes need to weld; meanwhile, when working aloft, the lower part of the relative position needs to be provided with an anti-falling measure. Because the operating points are many, the operating frame body platform is erected, the safety net is pulled, the safety channel is arranged, the spatial arrangement is complicated, and the space arrangement is not flexible enough. Causing the worker to work very inconveniently.
SUMMERY OF THE UTILITY MODEL
The not enough to current construction technology measure, the utility model provides a construction installation decorates construction specialty operation platform has solved in the current construction support body operation platform and has set up not enough nimble removal, unable regulation size, height, and the railing is connected not convenient enough and prevent that the high altitude safety measure that falls uses inflexible flexible problem.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a special moving platform of high altitude protection and construction operation integration that falls, includes that railing connects external member 1, truss 2, landing leg post 3 and boots board gyro wheel 4.
The handrail connecting sleeve 1 is used for connecting the truss 2 and a handrail, and the handrail connecting sleeve 1 is clamped at the upper chord position of the truss 2 in a sleeving manner; the bottom end of the truss 2 is connected with a supporting leg column 3, and the bottom end of the supporting leg column 3 is connected with a shoe plate roller 4.
The truss 2 is formed by connecting truss sections in a combined mode, the handrail is arranged on the outer side of the truss 2 and used for enclosing the truss 2, and the handrail and the truss 2 form a construction protection platform.
The leg posts 3 are connected by an adjusting tie bar 5; the adjusting tie rod 5 consists of an inclined rod and cross rods, the inclined rod is connected with the leg posts 3 and the truss 2, and each cross rod is arranged between the inclined rods; the height of the leg post 3 is adjusted by the inclined rod, and the leg post is fixed and supported by the cross rod.
Between railing connection external member 1 and truss 2, between truss 2 and landing leg post 3, be connected between landing leg post 3 and the boots board gyro wheel 4 and all pass through bolted connection.
Compared with the prior art, the utility model discloses the special moving platform of construction that protection and decoration construction operation as an organic whole fall in building high altitude, simple structure can be high altitude construction protection canopy, also can do the construction operation support body, can assemble according to concrete engineering characteristics scene is nimble, can recycle, and the cost is practiced thrift again in convenient construction. The method has the following specific beneficial effects:
1. the utility model discloses moving platform the truss is standard festival connection combination, highly can be through changing different cross-sections, and once adjustment is done to the web member of height, and the standard truss altitude mixture control condition is: the width of the required frame body with particularly large span can be adjusted within a certain range by replacing the chord web member.
2. The supporting legs are connected by the blocks and the truss through bolts, and field assembly is facilitated.
3. The utility model discloses whether the gyro wheel can set up the track according to concrete engineering under the moving platform, and the difference is selected, also can use the high fine setting of doing to the support body.
4. The utility model discloses it is simple and convenient to install protection railing on the moving platform, and the railing is connected with the external member silk braid that the chord member set up on the truss, and the external member is overlapped on the chord member with standard component form, and the position can be transferred, and convenient ann tears open, reuse.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the side view of the structure and an enlarged schematic view of the connection of the shoe roller block of the present invention;
fig. 3 is a schematic view of the roller structure of the present invention.
In the figure: 1. railing connecting external member, 2, truss, 3, landing leg post, 4, boots board gyro wheel, 5, adjusting tie rod.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. The described embodiments are only some, but not all embodiments of the invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The utility model provides a special moving platform of high altitude protection and construction operation integration that falls, includes that railing connects external member 1, truss 2, landing leg post 3 and boots board gyro wheel 4.
The handrail connecting sleeve 1 is used for connecting the truss 2 and a handrail, and the handrail connecting sleeve 1 is clamped at the upper chord position of the truss 2 in a sleeving manner; the bottom end of the truss 2 is connected with a supporting leg column 3, and the bottom end of the supporting leg column 3 is connected with a shoe plate roller 4.
The truss 2 is formed by connecting truss sections in a combined mode, the handrail is arranged on the outer side of the truss 2 and used for enclosing the truss 2, and the handrail and the truss 2 form a construction protection platform.
The leg posts 3 are connected by an adjusting tie bar 5; the adjusting tie rod 5 consists of an inclined rod and cross rods, the inclined rod is connected with the leg posts 3 and the truss 2, and each cross rod is arranged between the inclined rods; the height of the leg post 3 is adjusted by the inclined rod, and the leg post is fixed and supported by the cross rod.
Between railing connection external member 1 and truss 2, between truss 2 and landing leg post 3, be connected between landing leg post 3 and the boots board gyro wheel 4 and all pass through bolted connection.
Referring to fig. 1-3, a construction-dedicated mobile platform integrating building high-altitude falling protection and decoration construction operation is provided. The truss is formed by assembling standard sections, the supporting leg columns are blocks, all components are connected through bolts, and when construction is needed, the supporting leg columns are assembled on site and connected with the truss through bolts. The roller is a shoe plate block connected with the support leg column through bolts.
The utility model discloses simple structure, platform height, span, width all can be through the replacement of corresponding standard component and adjust. The platform equipment is simple, and the construction is removed conveniently, can effectively solve ordinary scaffold frame, protection canopy and set up the problem of removing not nimble. Can be repeatedly recycled, and particularly can greatly save the cost in the construction of gallery type linear building structures and large-span public buildings.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. The utility model provides a special moving platform of protection and construction operation integration falls in high altitude which characterized in that: comprises a handrail connecting suite (1), a truss (2), a leg post (3) and a boot board roller (4);
the handrail connecting external member (1) is used for connecting the truss (2) and the handrail, and the handrail connecting external member (1) is clamped at the upper chord position of the truss (2); the bottom end of the truss (2) is connected with a supporting leg column (3), and the bottom end of the supporting leg column (3) is connected with a shoe plate roller (4).
2. The special integrated high-altitude falling protection and construction operation mobile platform as claimed in claim 1, wherein: truss (2) are formed by truss festival built-up connection, and the railing sets up in the outside of truss (2) and encloses truss (2), and railing and truss (2) constitute construction protection platform.
3. The special integrated high-altitude falling protection and construction operation mobile platform as claimed in claim 1, wherein: the supporting leg columns (3) are connected by an adjusting tie rod (5); the adjusting tie rod (5) consists of inclined rods and cross rods, the inclined rods are connected with the supporting leg columns (3) and the truss (2), and each cross rod is arranged between the inclined rods; the height of the leg support (3) is adjusted through the inclined rod, and the leg support is fixed and supported through the cross rod.
4. The special integrated high-altitude falling protection and construction operation mobile platform as claimed in claim 1, wherein: between railing connection external member (1) and truss (2), between truss (2) and landing leg post (3), be connected between landing leg post (3) and boots board gyro wheel (4) and all pass through bolted connection.
CN201920433268.2U 2019-04-02 2019-04-02 Special moving platform integrating high-altitude falling protection and construction operation Active CN210636770U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920433268.2U CN210636770U (en) 2019-04-02 2019-04-02 Special moving platform integrating high-altitude falling protection and construction operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920433268.2U CN210636770U (en) 2019-04-02 2019-04-02 Special moving platform integrating high-altitude falling protection and construction operation

Publications (1)

Publication Number Publication Date
CN210636770U true CN210636770U (en) 2020-05-29

Family

ID=70794226

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920433268.2U Active CN210636770U (en) 2019-04-02 2019-04-02 Special moving platform integrating high-altitude falling protection and construction operation

Country Status (1)

Country Link
CN (1) CN210636770U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109930806A (en) * 2019-04-02 2019-06-25 中交一公局集团有限公司 A kind of falling from high altitude protection special mobile platform integrated with constructing operation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109930806A (en) * 2019-04-02 2019-06-25 中交一公局集团有限公司 A kind of falling from high altitude protection special mobile platform integrated with constructing operation

Similar Documents

Publication Publication Date Title
CN112482577B (en) Large-span space chord supporting wheel spoke type truss structure system and construction method
CN107268969B (en) A kind of scaffold structure for high altitude operation
US10731327B2 (en) Structure and method of making the same
CN109057365A (en) A kind of Node In Large-span Pipe Truss roof truss air translation installation method
CN210636770U (en) Special moving platform integrating high-altitude falling protection and construction operation
CN109930806A (en) A kind of falling from high altitude protection special mobile platform integrated with constructing operation
CN110616885A (en) Movable overhanging working frame
CN109812021B (en) Installation method of large-span welding ball net rack
CN206053270U (en) The detachable mobile turnover safe operation platform that a kind of rack is installed
CN210828394U (en) High-rise building demolishs device
CN204299072U (en) The two badly bleeding stair of a kind of two circular hollow steel column supporting
CN205312979U (en) Building structure hydraulic pressure elevating gear strides greatly
CN208235916U (en) A kind of in-situ beam casting job platform
CN207484936U (en) A kind of nacelle device of Landscape Lighting installation
CN213297069U (en) Scaffold for architectural decoration
CN207044363U (en) A kind of new precast beam protection and operating platform
CN211622532U (en) A interim construction structures for factory building furred ceiling
CN215291317U (en) Truss car platform convenient to equipment and economy
CN215978631U (en) Stand system of view pavilion for municipal garden
CN219387066U (en) Anti-tilting scaffold
CN219710914U (en) Telescopic mobile platform
CN107060204A (en) A kind of construction stability ring beam of slip
CN210829037U (en) Ladder stand
CN212984576U (en) Scaffold convenient to dismouting
CN220014009U (en) Movable scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant