CN210622344U - Installation device for building large-scale building equipment based on modular steel structure - Google Patents

Installation device for building large-scale building equipment based on modular steel structure Download PDF

Info

Publication number
CN210622344U
CN210622344U CN201921275947.8U CN201921275947U CN210622344U CN 210622344 U CN210622344 U CN 210622344U CN 201921275947 U CN201921275947 U CN 201921275947U CN 210622344 U CN210622344 U CN 210622344U
Authority
CN
China
Prior art keywords
column
clamping
groove
base
bearing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921275947.8U
Other languages
Chinese (zh)
Inventor
姜海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Donghai Construction Group Co ltd
Original Assignee
Shenzhen Donghai Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Donghai Construction Group Co ltd filed Critical Shenzhen Donghai Construction Group Co ltd
Priority to CN201921275947.8U priority Critical patent/CN210622344U/en
Application granted granted Critical
Publication of CN210622344U publication Critical patent/CN210622344U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an installation device for building large-scale building equipment based on modular steel construction, which comprises a base, depressed center A, depressed center B, the card hole, the card post, the screens recess, bearing A, bearing B, column spinner A, column spinner B, reference column and draw-in groove, base one side upper surface sets up depressed center A, base opposite side lower surface sets up and depressed center B with depressed center A matched with, set up the card hole on the depressed center A, fixed setting and the card post of calorie hole matched with on the depressed center B, the upper surface middle part of base sets up the screens recess, the screens recess contains an inboard, another inboard and the groove opening in groove, the fixed bearing A that sets up of a inslot survey of screens recess. The utility model discloses reducing high altitude construction in needs, when ground formation modularization steel construction in advance, realizing that single workman carries out the modularization equipment to the steel construction on ground in the place that needs installation large building equipment, reduce to manpower resource consumption, raise the efficiency.

Description

Installation device for building large-scale building equipment based on modular steel structure
Technical Field
The utility model relates to an installation device of large-scale building equipment is built to steel construction based on modularization.
Background
When the parts are conveyed to a construction site of large-scale building equipment, the modularized steel structure needs to be assembled so as to form a modularized structure on the ground in advance for integral combination and installation, so that the aerial work during integral combination and installation is reduced, and most work can be completed on the ground. However, in the prior art, when the worker assembles the modular mechanism on the ground, due to the absence of a suitable installation device for auxiliary installation, the combination of a module steel structure can be realized by the cooperation of a plurality of works, which wastes human resources and has low efficiency and poor use effect.
In order to solve the technical problems, a new technical scheme is especially provided.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an installation device based on large-scale building equipment is built to modular steel construction to solve the problem that provides among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a mounting device for building large-scale building equipment based on modularized steel structure comprises a base, a sunken table A, a sunken table B, a clamping hole, a clamping column, a clamping groove, a bearing A, a bearing B, a rotating column A, a rotating column B, a positioning column and a clamping groove, wherein the sunken table A is arranged on the upper surface of one side of the base, the sunken table B matched with the sunken table A is arranged on the lower surface of the other side of the base, the clamping hole is arranged on the sunken table A, the clamping column matched with the clamping hole is fixedly arranged on the sunken table B, the clamping groove is arranged in the middle of the upper surface of the base and comprises a groove one inner side, a groove other inner side and a groove opening, the bearing A is fixedly arranged in the groove one inner side of the clamping groove, the bearing B is fixedly arranged in the groove other groove inner side of the clamping groove, one end of the rotating column A is rotatably connected with the base through the bearing A, the other end of the rotating column A is fixedly connected with one end, the other end fixed connection reference column of column B's one end, the lateral surface of reference column sets up the draw-in groove that quantity is 2 at least, the shape and the size that quantity is 2 draw-in grooves at least are different respectively.
Preferably, the clamping column and the base are of an integrated structure.
Preferably, the fixing device is fixedly arranged by means of welding connection, clamping connection and/or bolt connection.
Preferably, the axis of the rotating column A, the axis of the rotating column B and the axis of the positioning column are on the same straight line.
Preferably, the center line of the bearing A and the center line of the bearing B are respectively parallel to the horizontal line.
Preferably, the fixed connection is not fixedly connected by means of a welded connection, a snap connection and/or a screw connection.
Preferably, each corner of the base and the positioning column is respectively provided with a circular arc transition.
Preferably, the center line of the clamping hole and the axis line of the clamping column are respectively parallel to the plumb line.
Compared with the prior art, the beneficial effects of the utility model are that: when high-altitude operation needs to be reduced and a modular steel structure is formed on the ground in advance, modular assembly of the steel structure on the ground by a single worker in a field needing large-scale building equipment is achieved, manpower resource consumption is reduced, and efficiency is improved.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a sectional view a-a of fig. 1.
Fig. 3 is a schematic view of the structure of 2 mounting devices of fig. 1 in combination.
Fig. 4 is a schematic structural diagram of the water tank of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention. The utility model discloses only use to the scene that is applied to the background art and mentions very much, probably produce other new problems from this because space restriction and utility model people are limited to the first research and development efforts of a technique, are difficult to accomplish once research and development and just form a perfect technical scheme, consequently all can adopt current mode to understand and solve.
Referring to the attached drawings of the specification, the utility model provides a technical scheme: a mounting device for building large-scale building equipment based on a modularized steel structure comprises a base 1, a sunken table A2, a sunken table B3, a clamping hole 4, a clamping column 5, a clamping groove 6, a bearing A7, a bearing B8, a rotary column A9, a rotary column B10, a positioning column 11 and a clamping groove 12, wherein the sunken table A2 is arranged on the upper surface of one side of the base 1, a sunken table B3 matched with the sunken table A2 is arranged on the lower surface of the other side of the base 1, a clamping hole 4 is arranged on the sunken table A2, a clamping column 5 matched with the clamping hole 4 is fixedly arranged on the sunken table B3, a clamping groove 6 is arranged in the middle of the upper surface of the base 1, the clamping groove 6 comprises a groove one inner side 13, a groove other inner side 14 and a groove opening 15, a bearing A7 is fixedly arranged on the groove one inner side of the clamping groove 6, a bearing B8 is fixedly arranged on the groove other side of the clamping groove 6, one end of the rotary column A9 is rotatably connected with the base 1 through a bearing A7, and a, one end of a rotating column B10 is rotatably connected with the base 1 through a bearing B8, the other end of the rotating column B10 is fixedly connected with one end of a positioning column 11, the outer side surface of the positioning column 11 is provided with at least 2 clamping grooves 12, and the at least 2 clamping grooves 12 are different in shape and size; the utility model discloses reducing high altitude construction in needs, when ground formation modularization steel construction in advance, realizing that single workman carries out the modularization equipment to the steel construction on ground in the place that needs installation large building equipment, reduce to manpower resource consumption, raise the efficiency.
Preferably, the clamp column 5 is of an integral structure with the base 1, and it should be noted that the base 1 should have a certain gravity, generally 5 kg-12 kg; in the expanded embodiment of the present invention, in order to reduce the problems of high cost and inconvenient carrying caused by this gravity, the structure of the water tank 16 can be adopted, that is, the water tank 16 is fixedly arranged on the lower surface of the base 1, the water tank 16 comprises a water containing cavity 17, the water tank 16 is provided with a water inlet 18 communicated with the water containing cavity 17 and a water outlet 19 which are respectively provided with a sealing plug 20 for plugging the water inlet 18 and the water outlet 19, by adopting the structure, the water tank 16 has no water in the water containing cavity 17 during transportation, and can be filled with water during use, the gravity is increased by water, and after use, water can be discharged, and in this way, the gravity required by the base 1 is ensured, and simultaneously, the cost of following the base and the problem of inconvenient carrying are lovely; however, in this way, the person skilled in the art must keep the water tank 16 and the base 1 rigid to avoid damage, and the present invention does not mention the reaching part, which can be understood as the prior art or solved in the prior art.
Preferably, the fastening is arranged fixedly by means of a welded connection, a snap connection and/or a screw connection.
Preferably, the axis of the rotating column A9, the axis of the rotating column B10 and the axis of the positioning column 11 are on the same straight line.
Preferably, the centerline of bearing a7 and the centerline of bearing B8 are each parallel to the horizontal.
Preferably, the fixed connection is not fixedly connected by means of a welded connection, a snap connection and/or a screw connection.
Preferably, each corner of the base 1 and the positioning column 11 is provided with a circular arc transition.
Preferably, the center line of the chucking hole 4 and the axis line of the chucking post 5 are parallel to the vertical line, respectively.
The utility model discloses in the time of using, the utility model discloses installation device can transport the place that needs installed large-scale architectural equipment in advance by the enterprise to respectively place 2-4 in advance in every workman's worker position, work when carrying out the steel construction equipment, because the utility model discloses, 1 one side upper surface of base sets up sunken platform A2, and 1 opposite side lower surface of base sets up sunken platform B3 with sunken platform A2 matched with, sets up card hole 4 on sunken platform A2, and sunken platform B3 is last to be fixed set up with card hole 4 matched with card post 5, realizes wherein 2, wherein 3 or 4 the utility model discloses an installation device can be based on work oneself needs through card hole 4 and card post 5 combination use each other, also can use respectively alone, during the concrete use, because the upper surface middle part of base 1 sets up screens recess 6, screens recess 6 contains an inboard 13 in groove, The other inner side 14 of the groove and the groove opening 15, a bearing A7 is fixedly arranged on the inner side of one groove of the clamping groove 6, a bearing B8 is fixedly arranged on the inner side of the other groove of the clamping groove 6, one end of a rotating column A9 is rotatably connected with the base 1 through a bearing A7, the other end of the rotating column A9 is fixedly connected with one end of a positioning column 11, one end of a rotating column B10 is rotatably connected with the base 1 through a bearing B8, the other end of the rotating column B10 is fixedly connected with one end of the positioning column 11, the outer side surface of the positioning column 11 is provided with at least 2 clamping grooves 12, the shapes and the sizes of the at least 2 clamping grooves 12 are respectively different, on one hand, a worker can adjust the clamping grooves to different positions through the rotating positioning column 11 which is convenient for the bearing A7 and the bearing B8 to use, and the mode of using the clamping grooves 12 which can be matched with, the user can be with this steel construction component's one end through groove opening 15 in probing into screens recess 6, and then probe into and carry out the screens in this steel construction matched with draw-in groove 12, and on the same hand, the same mode card of the other end accessible of this steel construction is gone into another the utility model discloses an installation device carries on spacingly, and the locate mode this moment is except that the both ends screens, also utilizes the gravity of this steel construction itself to fix a position, reaches the result of use of carrying out the location installation of standing vertically to the steel construction to single staff, simultaneously, because the shape of draw-in groove 12 and the size diversification that differs respectively to and this shape and size can set up in advance according to several types of the steel construction that the enterprise needs to install, reach and be adapted to on a large scale and the effect that more scenes used.
The design to be explained is: the control circuit involved in the present design is a conventional technique for controlling the operation of each component and the corresponding control program. The utility model discloses model and/or size between each part only need mutual adaptation, can realize the utility model discloses a principle can, other not mentioned parts can all regard as prior art to understand. On the basis of the scheme of the utility model, the ordinary technical personnel in the field can make up some deficiencies on the details through logical analysis and/or reasoning, make the technical scheme of the utility model perfect and optimize more. The technical solutions described in the present application are limited to the technical problems to be solved in the background art, and other portions can be implemented in other patent applications by other persons skilled in the art, and the other portions can be implemented in other patent applications, so as to achieve the optimal application effect.
In the description of the present invention, it is to be understood that the terms "coaxial", "bottom", "one end", "top", "middle", "other end", "upper", "one side", "top", "inner", "front", "center", "both ends", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
Based on the fact that there is no product, only one advantage and no disadvantage, the present invention is only used for specific environments, such as the scenes mentioned in the background, if some users consider the factors of price, inconvenient carrying and the like, the users do not recommend to buy the product, the product is only used for the scenes which need to be mentioned in the background art, and can accept and ignore the customers who use other negative factors, and in view of the fact that no one technology is developed at a time, the technical solutions of the present application are clearly described and fully disclosed only by describing technical solutions adopted for the problems mentioned in the background, other problems which arise therefrom are not within the scope of the claims of the present application and can be perfected again by a person skilled in the art in order to be able to create relatively more sophisticated solutions, all in a way known per se in the art.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "disposed," "connected," "fixed," "screwed" and the like are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate medium, and may be connected through the inside of two elements or in an interaction relationship between two elements, unless otherwise specifically defined, and the specific meaning of the above terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides a large-scale building equipment's installation device is built to steel construction based on modularization which characterized in that: comprises a base, a sunken platform A, a sunken platform B, a clamping hole, a clamping column, a clamping groove, a bearing A, a bearing B, a rotary column A, a rotary column B, a positioning column and a clamping groove, wherein the upper surface of one side of the base is provided with the sunken platform A, the lower surface of the other side of the base is provided with the sunken platform B matched with the sunken platform A, the sunken platform A is provided with the clamping hole, the sunken platform B is fixedly provided with the clamping column matched with the clamping hole, the middle part of the upper surface of the base is provided with the clamping groove, the clamping groove comprises a groove one inner side, a groove other inner side and a groove opening, the bearing A is fixedly arranged in the groove one inner side of the clamping groove, the bearing B is fixedly arranged in the groove other inner side of the clamping groove, one end of the rotary column A is rotatably connected with the base through the bearing A, the other end of the rotary column A is fixedly connected with one end of the positioning column, one end of the, the lateral surface of reference column sets up the quantity and is 2 draw-in grooves at least, the shape and the size that the quantity is 2 draw-in grooves at least are different respectively.
2. The installation apparatus for constructing large construction equipment based on modular steel structures according to claim 1, wherein: the clamping column and the base are of an integrated structure.
3. The installation apparatus for constructing large construction equipment based on modular steel structures according to claim 1, wherein: the fixing device is fixedly arranged in a welding connection mode, a clamping connection mode and/or a bolt connection mode.
4. The installation apparatus for constructing large construction equipment based on modular steel structures according to claim 1, wherein: the axial lead of the rotating column A, the axial lead of the rotating column B and the axial lead of the positioning column are on the same straight line.
5. The installation apparatus for constructing large construction equipment based on modular steel structures according to claim 1, wherein: the central line of the bearing A and the central line of the bearing B are respectively parallel to a horizontal line.
6. The installation apparatus for constructing large construction equipment based on modular steel structures according to claim 1, wherein: the fixed connection is not fixedly connected in a welding connection mode, a clamping connection mode and/or a bolt connection mode.
7. The installation apparatus for constructing large construction equipment based on modular steel structures according to claim 1, wherein: and arc transition is respectively arranged at each corner of the base and the positioning column.
8. The installation apparatus for constructing large construction equipment based on modular steel structures according to claim 1, wherein: the central line of the clamping hole and the axial line of the clamping column are respectively parallel to the plumb line.
CN201921275947.8U 2019-08-03 2019-08-03 Installation device for building large-scale building equipment based on modular steel structure Active CN210622344U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921275947.8U CN210622344U (en) 2019-08-03 2019-08-03 Installation device for building large-scale building equipment based on modular steel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921275947.8U CN210622344U (en) 2019-08-03 2019-08-03 Installation device for building large-scale building equipment based on modular steel structure

Publications (1)

Publication Number Publication Date
CN210622344U true CN210622344U (en) 2020-05-26

Family

ID=70753104

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921275947.8U Active CN210622344U (en) 2019-08-03 2019-08-03 Installation device for building large-scale building equipment based on modular steel structure

Country Status (1)

Country Link
CN (1) CN210622344U (en)

Similar Documents

Publication Publication Date Title
CN206321678U (en) Electric energy meter connector
CN210622344U (en) Installation device for building large-scale building equipment based on modular steel structure
CN209788961U (en) Novel administrative management multifunctional workbench
CN106593282A (en) Folding face plate and combination type ladder platform
CN211080690U (en) Energy-conserving curtain of architectural decoration
CN208581328U (en) A kind of communication equipment distributing frame
CN215252458U (en) Warning device for engineering construction management
CN212029045U (en) Data display device
CN211115425U (en) Prefabricated door frame assembly of cement of easy installation
CN211183773U (en) Mobile phone charging support matched with wall socket for use
CN211286731U (en) Integrated house wallboard installation supporting component
CN210807154U (en) Photovoltaic board adjusting device of photovoltaic power generation
CN207456444U (en) A kind of digitized photography auxiliary device of architectural mapping accurate positioning
CN207624892U (en) A kind of GPS antenna mounting structure for outdoor cabinet
CN205377766U (en) Foldable photovoltaic module
CN206224327U (en) A kind of pluggable hard disc structure
CN205480116U (en) Hand -held device and handheld cloud platform thereof
CN217719621U (en) Monocrystalline silicon piece beneficial to combined installation
CN212726103U (en) Portable weak current computer lab debugging bracket
CN216487029U (en) Multi-functional environment art sign
CN210072713U (en) Construction supervision is with device of registering
CN215265321U (en) Cement electric pole convenient to change anticollision warning subsides
CN211811208U (en) CD61 antibody detection kit
CN219666414U (en) Positioning device for photovoltaic panel installation
CN212078933U (en) Combined partition plate device in building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant