CN210599100U CN201920941491.8U CN201920941491U CN210599100U CN 210599100 U CN210599100 U CN 210599100U CN 201920941491 U CN201920941491 U CN 201920941491U CN 210599100 U CN210599100 U CN 210599100U
Authority
CN
China
Prior art keywords
ditch
well body
manhole
cylindrical
central
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920941491.8U
Other languages
Chinese (zh)
Inventor
肖明清
焦齐柱
杨剑
郑强
刘斌
廖辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201920941491.8U priority Critical patent/CN210599100U/en
Application granted granted Critical
Publication of CN210599100U publication Critical patent/CN210599100U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model belongs to the technical field of tunnel engineering, specifically provide a there is tiny fragments of stone, coal, etc. tunnel center ditch manhole, including the cylindrical work well body and well lid, the work well body is formed by the concatenation of polylith arc steel sheet, when needs overhaul the center ditch, tak away an apron on taking place the center ditch of the district section of jam, then splice polylith arc steel sheet and enclose to close on the center ditch lateral wall and form the work well body, then backfill, the work well body alright keep apart center ditch and external, the staff alright enter into the center ditch from the work well body and overhaul the construction this moment, it can to cover the well lid again after the completion to overhaul. The manhole is of a cylindrical splicing structure, so that on one hand, the problem of unsmooth drainage caused by blockage of drainage of a central cover plate ditch is solved, and the safety of a tunnel structure is ensured; on the other hand, the cylindrical well body is evenly stressed and dispersed, and each arc-shaped steel plate for splicing is light in weight and convenient to install and transport.

Description

There is tiny fragments of stone, coal, etc. tunnel center ditch manhole
Technical Field
The utility model belongs to the technical field of tunnel engineering, concretely relates to there is tiny fragments of stone, coal, etc. tunnel center ditch manhole.
Background
The existing tunnel is mostly provided with a bilateral ditch and a central cover plate ditch, drainage holes are arranged at the wall feet at two sides for drainage, wherein the central cover plate ditch bears the main drainage function, and the bilateral ditch assists in drainage. The two side ditches are located on the side of the side wall of the tunnel, and the central cover plate ditch is located below the ballast bed between two lines. And a phi 50 annular drainage blind pipe (a perforated corrugated pipe) is arranged behind the two linings, the two ends of the annular blind ditch and the two ends of the longitudinal blind ditch are directly communicated with the tunnel side ditch, and the middle part of each section of the longitudinal blind ditch is provided with a phi 50PVC drainage hole connected to the tunnel side ditch. And a phi 50PVC drainage hole is arranged in the middle of each section of longitudinal blind ditch and connected to the side ditch of the tunnel. Underground water behind the lining is collected through the annular blind pipes and the longitudinal blind pipes and then discharged into the side ditches, is collected and precipitated through the side ditches, is introduced into the central cover plate ditch through PVC transverse water guide pipes at intervals of 30 m phi 100, and is discharged out of the hole through the central cover plate ditch.
As the line in the tunnel is a ballast track bed, in order to meet the related requirements of the maintenance rules of the ballast track line of the high-speed railway, stone ballasts need to be filled between two lines to meet the slope-releasing regulations of the track bed, and 0.7m of stone ballasts cover the upper part of the central trench cover plate. Because of central apron ditch does not set up the inspection shaft, its inspection is overhauld and is carried out in combination with the maintenance of ballast bed, when a large amount of surface waters seeped down after the heavy rainfall of local surface, can be because construction such as stone tiny fragments of stone, coal, etc. is left over the thing and is blockked up, leads to the water cross-section of actual center ditch to be less than the design cross-section, causes central ditch drainage not smooth seriously to be obstructed, and the water level rises water and overflows the ballast bed, causes track structure circuit height to appear and changes, will cause major traffic accident.
Disclosure of Invention
The utility model aims at overcoming the difficult problem of having tiny fragments of stone, coal, etc. tunnel center ditch to overhaul among the prior art.
Therefore, the utility model provides a there is tiny fragments of stone, coal, etc. tunnel center ditch manhole, including the cylindrical work well body and well lid, the cylindrical work well body includes polylith arc steel sheet, and each is adjacent arc steel sheet lateral wall head and the tail butt closes and forms the cylindrical work well body, the top of the cylindrical work well body with the connection can be dismantled to the well lid, the bottom and the center ditch lateral wall fixed connection of the cylindrical work well body.
Preferably, two adjacent arc-shaped steel plates are connected through two connecting plates and two connecting bolts, the two connecting plates are respectively positioned on the inner side and the outer side of the arc-shaped steel plate, and through holes for the connecting bolts to penetrate through are formed in the arc-shaped steel plates.
Preferably, a steel rib plate is pre-embedded in the well cover, and a steel bar used for being clamped at the top end of the cylindrical working well body is arranged on the steel rib plate.
Preferably, the manhole cover is provided with a handle.
Preferably, the well lid is formed by splicing a plurality of precast slabs, and each precast slab is provided with a handle.
Preferably, the well cover is provided with air holes, and the well body is communicated with the outside through the air holes.
Preferably, the bottom end of the cylindrical working well body abuts against the top end of the side wall of the central ditch, and the cylindrical working well body is connected with the top end of the side wall of the central ditch through angle steel.
Preferably, one side of the angle steel is connected with the side wall of the cylindrical working well body through a bolt, and the other side of the angle steel is connected with the top end of the side wall of the central ditch through a chemical anchor bolt.
Preferably, a central ditch cover plate is sealed on the side wall of the central ditch, and the bottom end of the cylindrical working well body abuts against the top surface of the central ditch cover plate.
The utility model has the advantages that: the utility model provides a there is tiny fragments of stone, coal, etc. tunnel center ditch manhole, including the cylindrical work well body and well lid, the work well body is formed by the concatenation of polylith arc steel sheet, when needs overhaul the center ditch, tak away an apron on the center ditch of the district section that takes place to block up, then splice polylith arc steel sheet and enclose to close on the center ditch lateral wall and form the work well body, then backfill, the work well body alright keep apart center ditch and external, the staff alright enter into the center ditch from the work well body and overhaul the construction this moment, it can the well lid to cover again after the completion to overhaul. The manhole is of a cylindrical splicing structure, so that on one hand, the problem of unsmooth drainage caused by blockage of drainage of a central cover plate ditch is solved, and the safety of a tunnel structure is ensured; on the other hand, the cylindrical well body is evenly stressed and dispersed, and each arc-shaped steel plate for splicing is light in weight and convenient to install and transport.
The present invention will be described in further detail with reference to the accompanying drawings.
Drawings
Fig. 1 is a schematic plan view of a trench manhole in the center of a ballast tunnel;
fig. 2 is a sectional view of the utility model discloses there is a ballast tunnel center ditch manhole A-A to.
Description of reference numerals: the well comprises a cylindrical working well body 1, a connecting plate 2, a connecting bolt 3, angle steel 4, a chemical anchor bolt 5, a central ditch 6, a well cover 7, a steel rib plate 8, a central ditch side wall 9, a central ditch cover plate 10 and air holes 11.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "center", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on those shown in the drawings, and are merely for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, are not to be construed as limiting the present invention.
The terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature; in the description of the present invention, "a plurality" means two or more unless otherwise specified.
The utility model provides a there is tiny fragments of stone, coal, etc. tunnel center ditch manhole, including the cylindrical work well body and well lid, the cylindrical work well body includes polylith arc steel sheet, and each is adjacent arc steel sheet lateral wall head and the tail butt closes and forms the cylindrical work well body, the top of the cylindrical work well body with the connection can be dismantled to the well lid, the bottom and the center ditch lateral wall fixed connection of the cylindrical work well body.
It can be seen that, as shown in fig. 1 and 2, the central ditch 6 for draining the ballast tunnel is located in the middle of the ballast tunnel, the central ditch 6 extends longitudinally along the track direction, the central ditch cover plate 10 is sealed on the side wall 9 of the central ditch, the central ditch cover plate 10 is relatively short in length and convenient to install, so that a plurality of central ditch cover plates 10 are continuously covered on the central ditch 6 to cover the whole central ditch, wherein the central ditch cover plate 10 is installed on the step of the side wall of the central ditch, so that the central ditch cover plate 10 is as high as the top end of the side wall of the central ditch, and is convenient to backfill and seal. When central ditch 6 takes place to block up or other circumstances need overhaul central ditch 6, according to the approximate position of jam, take out a central ditch apron 10, carry the polylith arc steel sheet that prepares in advance to central ditch lateral wall top, generally be six arc steel sheets and can enclose into a complete cylindricality, connect between the arc steel sheet lateral wall, the bottom supports with central ditch lateral wall top and lean on, polylith arc steel sheet end to end each other just can form a cylindrical work well body 1 like this, the diameter of this cylindrical work well body 1 is greater than the length of central ditch apron 10, and make the bottom of this cylindrical work well body 1 just with two central ditch apron 10 in front and back, guarantee that cylindrical work well body 1 covers the opening area who takes away and leave behind a central ditch apron 10 comprehensively. Finally, the cylindrical well body 1 is connected with the top end of the side wall of the central ditch.
The utility model has the advantages that: the utility model provides a there is tiny fragments of stone, coal, etc. tunnel center ditch manhole, including the cylindrical work well body and well lid, the work well body is formed by the concatenation of polylith arc steel sheet, when needs overhaul the center ditch, tak away an apron on the center ditch of the district section that takes place to block up, then splice polylith arc steel sheet and enclose to close on the center ditch lateral wall and form the work well body, then backfill, the work well body alright keep apart center ditch and external, the staff alright enter into the center ditch from the work well body and overhaul the construction this moment, it can the well lid to cover again after the completion to overhaul. The manhole is of a cylindrical splicing structure, so that on one hand, the problem of unsmooth drainage caused by blockage of drainage of a central cover plate ditch is solved, and the safety of a tunnel structure is ensured; on the other hand, the cylindrical well body is evenly stressed and dispersed, and each arc-shaped steel plate for splicing is light in weight and convenient to install and transport.
According to the preferable scheme, two adjacent arc-shaped steel plates are connected through two connecting plates and two connecting bolts, the two connecting plates are respectively positioned on the inner side and the outer side of each arc-shaped steel plate, and through holes for the connecting bolts to penetrate through are formed in the arc-shaped steel plates. Therefore, as shown in fig. 1, the corresponding position on the side wall of each arc-shaped steel plate is provided with a hole for connection and installation, the side walls of two adjacent arc-shaped steel plates are abutted to each other during installation, the holes of the two adjacent arc-shaped steel plates are aligned to the two connecting plates 2, then the connecting bolts 3 are passed through the connecting bolts 3, the bolts 3 sequentially pass through the inner side connecting blocks, the arc-shaped steel plates and the outer side connecting blocks, and then the nuts are screwed up to connect and fix the two arc-shaped steel plates. Wherein, the connecting block is the rectangle plane piece, also can correspond according to the radian of arc steel sheet and set up the radian, and the connecting block is steel.
According to the preferable scheme, a steel rib plate is pre-embedded in the well cover, and a steel bar used for being clamped at the top end of the cylindrical working well body is arranged on the steel rib plate. Therefore, as shown in fig. 1 and 2, the tops of the six arc-shaped steel plates are connected in a clamped mode through the steel bars on the steel bar plate 8, specifically, the steel bar plate 8 is welded in the well lid 7, the steel bar plate 8 extends outwards to form two steel bars, when the well lid 7 is fastened, the two steel bars are just clamped on the arc-shaped steel plates, and the clamping force can be set according to the distance between the two steel bars and the thickness of the arc-shaped steel plates through pre-design.
According to the preferred scheme, a lifting handle is arranged on the well lid. Therefore, the well lid 7 can be conveniently and quickly lifted and installed in the disassembly mode through the lifting handle.
According to the preferred scheme, the well cover is formed by splicing a plurality of prefabricated plates, and each prefabricated plate is provided with a handle. Therefore, the well lid 7 is modularized, the multiple precast slabs can be concrete slabs or precast steel plates, each precast slab is independent, each precast slab can be independently operated through the lifting handle during disassembly and assembly, the well lid 7 is partitioned to achieve light-weight installation, and construction difficulty is reduced.
According to the preferable scheme, the well cover is provided with air holes, and the well body is communicated with the outside through the air holes. Therefore, when the well lid 7 is disassembled, the cylindrical working well body 1 and the central ditch are in a sealing state, so that the well lid 7 is difficult to install or take out due to air pressure change, the balance of the air pressure inside and outside the cylindrical working well body 1 can be ensured due to the air holes 11, and the well lid 7 is convenient to disassemble and assemble.
According to the preferable scheme, the bottom end of the cylindrical working well body abuts against the top end of the side wall of the central ditch, and the cylindrical working well body is connected with the top end of the side wall of the central ditch through angle steel. Therefore, as shown in fig. 1 and 2, the central gutter side wall 9 and the bottom end of the cylindrical working well body 1 are connected through four symmetrically distributed angle steels 4, and during installation, drill holes are distributed at corresponding positions on the central gutter side wall 9 and the arc-shaped steel plate, and then the angle steels 4 are installed.
According to the preferable scheme, one side of the angle steel is connected with the side wall of the cylindrical working well body through a bolt, and the other side of the angle steel is connected with the top end of the side wall of the central ditch through a chemical anchor bolt. As shown in fig. 2, the chemical anchor bolt 5 is fast to install and quickly cured, thereby accelerating the construction process.
Preferably, the bottom end of the cylindrical working well body is abutted against the top surface of the central ditch cover plate. Therefore, as shown in fig. 1, before the cylindrical working well body 1 is installed, a central ditch cover plate 10 is taken out, and when the bottom end of the cylindrical working well body 1 is pressed on the central ditch side wall 9 and the front and rear central ditch cover plates 10, the cylindrical working well body 1 is ensured to completely cover the opening of the central ditch 6, so that outside gravel is prevented from entering the central ditch 6.
The utility model also provides a ballast tunnel center ditch maintenance method, take off center ditch apron, support the arc steel sheet on the center ditch lateral wall top, enclose the end-to-end connection of arc steel sheet lateral wall and close and form the working well body;
connecting the bottom end of the working well body with the side wall of the central ditch through angle steel;
and clamping the well cover with the top end of the working well body.
Therefore, the spliced cylindrical working well 1 is arranged above the central ditch 6, the cylindrical working well 1 consists of six steel plates and a well cover 7, the steel plates are connected together through a connecting bolt 3 by a connecting plate 2, the bottom of the steel plate above the side wall of the central ditch is fixed on the side wall through a chemical anchor bolt 5 by an angle steel 4, the well cover 7 extends out of a steel bar for cheering through an embedded steel rib plate 8 and is fixed together with the steel plates, the scheme can effectively solve the problem that the central cover plate ditch of the ballast tunnel of the existing high-speed railway is blocked and cleaned in time, the problem that the central ditch is not smooth in drainage due to blocking is fundamentally solved, and the safety of the tunnel structure is ensured.
The above illustration is merely an illustration of the present invention, and does not limit the scope of the present invention, and all designs identical or similar to the present invention are within the scope of the present invention.

Claims (9)

1. The utility model provides a there is tiny fragments of stone, coal, etc. tunnel center ditch manhole which characterized in that: including cylindrical work well body and well lid, cylindrical work well body includes polylith arc steel sheet, and each is adjacent arc steel sheet lateral wall head and the tail butt closes and forms cylindrical work well body, cylindrical work well body's top with the connection can be dismantled to the well lid, cylindrical work well body's bottom and central ditch lateral wall fixed connection.
2. The ballast tunnel center ditch manhole of claim 1, which is characterized in that: two adjacent arc-shaped steel plates are connected through two connecting plates and two connecting bolts, the two connecting plates are respectively positioned on the inner side and the outer side of each arc-shaped steel plate, and through holes for the connecting bolts to penetrate through are formed in the arc-shaped steel plates.
3. The ballast tunnel center ditch manhole of claim 1, which is characterized in that: the well cover is characterized in that a steel rib plate is pre-embedded in the well cover, and a steel bar used for being clamped at the top end of the cylindrical working well body is arranged on the steel rib plate.
4. The ballast tunnel center ditch manhole of claim 1, which is characterized in that: the well lid is provided with a handle.
5. The ballast tunnel center ditch manhole of claim 1, which is characterized in that: the well lid is formed by the concatenation of polylith prefabricated plate, all is equipped with the handle on each prefabricated plate.
6. The ballast tunnel center ditch manhole of claim 1, 4 or 5, wherein: the manhole cover is provided with air holes, and the manhole body is communicated with the outside through the air holes.
7. The ballast tunnel center ditch manhole of claim 1, which is characterized in that: the bottom end of the cylindrical working well body is abutted against the top end of the side wall of the central ditch, and the cylindrical working well body is connected with the top end of the side wall of the central ditch through angle steel.
8. The ballast tunnel center ditch manhole of claim 7, which is characterized in that: one side of the angle steel is connected with the side wall of the cylindrical working well body through a bolt, and the other side of the angle steel is connected with the top end of the side wall of the central ditch through a chemical anchor bolt.
9. The ballast tunnel center ditch manhole of claim 1, which is characterized in that: the central ditch cover plate is sealed on the side wall of the central ditch, and the bottom end of the cylindrical working well body is abutted against the top surface of the central ditch cover plate.
CN201920941491.8U 2019-06-21 2019-06-21 There is tiny fragments of stone, coal, etc. tunnel center ditch manhole Active CN210599100U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920941491.8U CN210599100U (en) 2019-06-21 2019-06-21 There is tiny fragments of stone, coal, etc. tunnel center ditch manhole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920941491.8U CN210599100U (en) 2019-06-21 2019-06-21 There is tiny fragments of stone, coal, etc. tunnel center ditch manhole

Publications (1)

Publication Number Publication Date
CN210599100U true CN210599100U (en) 2020-05-22

Family

ID=70692551

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920941491.8U Active CN210599100U (en) 2019-06-21 2019-06-21 There is tiny fragments of stone, coal, etc. tunnel center ditch manhole

Country Status (1)

Country Link
CN (1) CN210599100U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110195613A (en) * 2019-06-21 2019-09-03 中铁第四勘察设计院集团有限公司 One kind having tiny fragments of stone, coal, etc. tunnel Central drain inspection-pit and repair method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110195613A (en) * 2019-06-21 2019-09-03 中铁第四勘察设计院集团有限公司 One kind having tiny fragments of stone, coal, etc. tunnel Central drain inspection-pit and repair method
CN110195613B (en) * 2019-06-21 2024-08-30 中铁第四勘察设计院集团有限公司 Repairing well and repairing method for central ditch of ballasted tunnel

Similar Documents

Publication Publication Date Title
CN109611150B (en) Waterproof drainage structure and waterproof drainage method for tunnel
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN104947714A (en) End sealing door structure for immersed tube tunnel
CN210599100U (en) There is tiny fragments of stone, coal, etc. tunnel center ditch manhole
CN114673169A (en) Multi-layer large-span deep foundation pit cover-excavation forward-backward combined construction method for urban core area
CN111878115A (en) Cavity assembly type tunnel inverted arch and construction method
CN211621598U (en) A foundation ditch structure for hole passes steel pipe installation
CN210529748U (en) Subway station prefabricated rail top air duct and prefabricated middle plate connection node structure
CN210118138U (en) Reinforcing structure for large-span tunnel to pass existing railway downwards
CN210068239U (en) There is tiny fragments of stone, coal, etc. tunnel center ditch maintenance system
CN216043765U (en) Plateau railway tunnel assists gallery assembled wind channel formula ventilation structure
CN110195613B (en) Repairing well and repairing method for central ditch of ballasted tunnel
CN108343069A (en) Precast concrete braced wall
CN113174995B (en) Construction method of TRD composite type enclosure comprehensive pipe gallery close to river channel
CN214118206U (en) Submarine subway tunnel in hard rock stratum
CN212614740U (en) Hole internal reinforcement structure of existing shield tunnel is striden on closely
CN212983870U (en) Circular working pit supporting member
CN113897945A (en) Ground-connecting wall combined connecting structure and construction method
CN110080820B (en) Ballasted tunnel center ditch overhauling system and method
CN217128303U (en) Reverse lining wall template system for soft geological round foundation pit
CN211174216U (en) There is tiny fragments of stone, coal, etc. track tunnel center ditch to overhaul work well
CN220620140U (en) Barrier construction structure is cleared away to major diameter deep buries reinforced concrete sewage pipeline
CN117845664B (en) Integral vibration reduction structure of shield tunnel and construction method
CN218563142U (en) Construction system for removing concrete plugging wall of ultra-deep foundation pit
CN220246597U (en) Temporary bridge crossing device for maintaining tunnel transverse ditch

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant