Prior art keywords
pipe
guiding device
joint
guide pipe
mud guiding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921222582.2U
Other languages
Chinese (zh)
Inventor
邓成宏
吴治勐
吴国清
闫名成
李路哲
李伟
彭斌
耿维
肖代文
金鑫
齐子康
张旭涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 8 Engineering Group Co Ltd
Kunming Railway Construction Co of China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Kunming Railway Construction Co of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd, Kunming Railway Construction Co of China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Priority to CN201921222582.2U priority Critical patent/CN210597292U/en
Application granted granted Critical
Publication of CN210597292U publication Critical patent/CN210597292U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a bored concrete pile construction is with protecting mud guiding device between a section of thick bamboo locates two and protects between a section of thick bamboo, its characterized in that: the flexible guide pipe comprises two joint pipes and one section of flexible guide pipe, wherein one end of each joint pipe is connected with two protective cylinders, two ends of each guide pipe are respectively sleeved on the other ends of the two joint pipes, a support piece is arranged below each guide pipe, two ends of each support piece are respectively and fixedly connected to the two protective cylinders, or two ends of each support piece are respectively hung on the two joint pipes. The utility model discloses in, use through bellows and the steel pipe joint cooperation with flexibility to set up support piece in order to support the bellows, can effectively prevent the leakage of mud, easy dismounting moreover, the recovery of the spare part of being convenient for is recycled.

Description

Mud guiding device between a section of thick bamboo is protected with construction of drilling bored concrete pile
Technical Field
The utility model relates to a bored concrete pile technical field on water especially relates to a bored concrete pile construction is with protecting mud guiding device between a section of thick bamboo.
Background
Cast-in-situ bored piles are a type of pile defined by classification according to the method of forming the pile. When the cast-in-situ bored pile is formed, slurry needs to be added into the hole in the hole forming process to protect the hole wall in order to conveniently carry drilling slag and prevent the hole wall from collapsing. The slurry is generally composed of water, clay and chemical treatment agent, and has good physical and chemical stability, proper viscosity and small sand content. The mud flowing out of the hole in the hole forming process contains drilling slag which can not meet the wall protection requirement, and can be sent into the hole again through a mud pump for use after being properly treated, and the good wall protection effect of the mud is ensured through continuous circulation treatment of the mud. In the prior engineering, in order to solve the problems of slurry storage and circulation, a long steel casing is generally used to be driven into a riverbed and also used as a slurry pond, and a connecting pipe is arranged between the casings to circulate the slurry. The conventional methods for connecting the casing pipes comprise two methods:
the first is a rigid connecting pipe, namely a section of steel pipe is welded between two steel casing pipes to be used as a slurry guide pipe. However, in the pile drilling operation, due to the disturbance of a drilling machine, the welding line is easy to tear, slurry leakage is caused, and the environment is polluted; and this kind of way requires highly to the machining precision of connecting pipe, is difficult for maintaining in the use, and later stage demolishs also troublesome.
The second type is a flexible connecting pipe, namely a section of corrugated pipe is directly connected between two steel casing pipes to be used as a slurry guide pipe. However, the method for directly connecting the corrugated pipe with the steel casing has many problems, because the corrugated pipe and the steel casing cannot be directly welded, and only the joint gap can be plugged and blocked by matching geotextile with foam rubber and the like, the connection mode is unstable, the strength of the corrugated pipe is low, the corrugated pipe is easy to deform, and the situations of slurry leakage of the joint and deformation and falling of the corrugated pipe are easy to occur in the use process.
SUMMERY OF THE UTILITY MODEL
The utility model provides a problem to the aforesaid exists provides a bored concrete pile construction is with protecting mud guiding device between a section of thick bamboo, uses through bellows and the steel pipe joint cooperation with flexibility to set up support piece in order to support the bellows, can effectively prevent the leakage of mud, easy dismounting, the recovery of the spare part of being convenient for is recycled moreover.
The utility model adopts the technical scheme as follows:
the utility model provides a drilling bored concrete pile construction is with protecting mud guiding device between section of thick bamboo, locates between two protect a, including two joint pipes and one section flexible honeycomb duct, the one end of two joint pipes is connected with two protect a respectively, and the honeycomb duct both ends cup joint respectively on two joint pipe other ends, and the honeycomb duct below is equipped with support piece, and support piece's both ends rigid coupling respectively protects on two, perhaps support piece's both ends are hung respectively on two joint pipes.
Furthermore, the guide pipe and the joint pipe are sealed by adopting elastic fillers, and the guide pipe and the joint pipe are hooped at the sealing position by a hoop or an iron wire;
furthermore, the filler is one or a combination of a plurality of geotextiles, foam rubber and rubber gaskets.
Furthermore, the honeycomb duct is a flexible non-telescopic pipe, the length of the honeycomb duct is slightly larger than the distance between the two connector pipes, and the honeycomb duct is placed on the support in a bending mode.
Furthermore, the honeycomb duct is a flexible telescopic pipe, and the length of the honeycomb duct can be slightly larger than, smaller than or equal to the distance between the two joint pipes.
Further, the joint pipe and the protective cylinder are arranged perpendicular to each other.
Further, one end of the joint pipe close to the protective cylinder is slightly inclined downwards.
Furthermore, the support piece is a smooth curved plate piece, and the middle of the support piece is concave downwards and is used for placing the flow guide pipe.
Furthermore, the supporting piece is a plane plate piece, and baffles are arranged on two sides of the supporting piece and used for placing the flow guide pipe.
Furthermore, the protective cylinder is a steel protective cylinder, the flow guide pipe is a plastic corrugated pipe, the joint pipe is a short steel pipe, and the supporting piece is a channel steel.
To sum up, owing to adopted above-mentioned technical scheme, the beneficial effects of the utility model are that:
(1) when having avoided pure rigid connection, the influence of rig disturbance to the welding seam to avoid the welding seam to tear, reduce the outer phenomenon of leaking of mud, compare in the steel pipe connection simultaneously, more material saving.
(2) The problems that when the slurry guide pipe is connected in a pure flexible mode, a gap between the slurry guide pipe and the steel casing is difficult to plug, and the guide pipe is easy to deform are solved.
(3) The method has the advantages of simple actual operation, integration of the advantages of rigid connection and flexible connection, long service life, less maintenance work and effective improvement of the working efficiency.
Drawings
The invention will now be described, by way of example, with reference to the accompanying drawings, in which:
fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is an enlarged sample view at A in FIG. 1;
fig. 3 is a cross-sectional view at B-B in fig. 1.
Description of reference numerals:
1-protective cylinder, 2-joint pipe, 3-guide pipe, 4-filler, 5-support piece and 6-iron wire.
Detailed Description
All of the features disclosed in this specification, or all of the steps in any method or process so disclosed, may be combined in any combination, except combinations of features and/or steps that are mutually exclusive.
Any feature disclosed in this specification may be replaced by alternative features serving equivalent or similar purposes, unless expressly stated otherwise. That is, unless expressly stated otherwise, each feature is only an example of a generic series of equivalent or similar features.
Referring to fig. 1-3, in this embodiment, a slurry guiding device between pile casings for cast-in-situ bored pile construction is disposed between two steel pile casings 1, and includes two steel joint pipes 2 and a section of flexible flow guide pipe 3, one end of each of the two joint pipes 2 is connected to each of the two pile casings 1, the joint pipes 2 are perpendicular to the pile casings 1, two ends of the flow guide pipe 3 are respectively sleeved on the other ends of the two joint pipes 2, a support member 5 is disposed below the flow guide pipe 3, and two ends of the support member 5 are respectively and fixedly connected to the two pile casings 1.
The mounting means of adapter tube 2 on protecting a section of thick bamboo 1 is, and the corresponding position carries out the trompil on two protect a section of thick bamboos 1, and the trompil diameter slightly is lighter than adapter tube 2 diameter, cuts the arc with two adapter tube 2's one end respectively, and the radian is the same with protecting a 1 outer wall radian, welds two adapter tube 2 correspondences on two protect a 1, and during welding adapter tube 2, control welding quality prevents that the crack from producing.
The guide pipe 3 and the joint pipe 2 are sealed by adopting an elastic filler 4, the guide pipe and the joint pipe are hooped tightly at the sealing position by an iron wire 6, and the iron wire 6 can be replaced by tools such as a hoop and the like; the filler 4 is one or a combination of several of geotextile, foam rubber and rubber gasket, and in the embodiment, the geotextile and the foam rubber are preferably used in combination to ensure the sealing effect and prevent mud from leaking outwards.
The draft tube 3 is a flexible telescopic tube, and is preferably a plastic corrugated tube in this embodiment, when the distance between the casing tubes 1 changes slightly due to the vibration of the drilling machine, the draft tube 3 can be stretched accordingly, so that the length of the draft tube 3 can be equal to, slightly longer than or slightly shorter than the distance between the two joint tubes 2.
The support piece 5 can be a smooth curved plate piece with a concave middle part, can also be a flat plate piece with baffles on two sides and is used for placing the guide pipe 3, and can also be of other types of structures, so that the support function of the guide pipe 3 can be realized; in this embodiment, the support 5 is preferably a channel steel, and two ends of the channel steel are respectively welded to the outer walls of the two casing barrels 1.
Example 2:
the present embodiment is different from embodiment 1 in that:
in the embodiment, the guide pipe 3 is a flexible non-telescopic pipe, the length of the guide pipe is slightly larger than the distance between the two joint pipes 2, the guide pipe is placed on the support part 5 in a bending way, and when the distance between the pile casings is slightly changed due to the vibration of the drilling machine, the guide pipe is stretched or bent along with the guide pipe.
Example 3:
the present embodiment is different from embodiment 1 in that:
in the embodiment, one end of the joint pipe 2 close to the protective sleeve 1 is slightly inclined downwards, the inclination angle is 5-15 degrees, and stagnation of slurry in the flow guide device can be prevented.
Example 4:
the present embodiment is different from embodiment 1 in that:
in the present embodiment, the brace 5 is also preferably a channel, but both ends of the channel are hung on the two joint pipes 2. The adoption is hung the mode and is connected, and the welded mode can avoid leading to the condition that the welding seam ftractures, the channel-section steel drops because of the rig vibration, can make the channel-section steel provide more stable, reliable support.
The present invention is not limited to the foregoing embodiments. The invention extends to any novel feature or any novel combination of features disclosed in this specification, and to any novel method or process steps or any novel combination of features disclosed.

Claims (10)

1. The utility model provides a construction of drilling bored concrete pile is with protecting mud guiding device between a section of thick bamboo, locates two and protects between a section of thick bamboo its characterized in that: the flexible guide pipe comprises two joint pipes and one section of flexible guide pipe, wherein one end of each joint pipe is connected with two protective cylinders, two ends of each guide pipe are respectively sleeved on the other ends of the two joint pipes, a support piece is arranged below each guide pipe, two ends of each support piece are respectively and fixedly connected to the two protective cylinders, or two ends of each support piece are respectively hung on the two joint pipes.
2. The mud guiding device between the pile casings for cast-in-situ bored pile construction according to claim 1, characterized in that: the honeycomb duct and the joint pipe are sealed by elastic fillers, and the honeycomb duct and the joint pipe are hooped tightly at the sealing position by a hoop or an iron wire.
3. The mud guiding device between the pile casings for cast-in-situ bored pile construction according to claim 2, wherein: the filler is one or a combination of a plurality of geotextiles, foam rubber and rubber gaskets.
4. The mud guiding device between the pile casings for cast-in-situ bored pile construction according to claim 1 or 2, characterized in that: the honeycomb duct is a flexible non-telescopic pipe, the length of the honeycomb duct is slightly larger than the distance between the two joint pipes, and the honeycomb duct is placed on the support in a bending mode.
5. The mud guiding device between the pile casings for cast-in-situ bored pile construction according to claim 1 or 2, characterized in that: the honeycomb duct is a flexible telescopic pipe.
6. The mud guiding device between the pile casings for cast-in-situ bored pile construction according to claim 1 or 2, characterized in that: the joint pipe and the protective cylinder are arranged perpendicular to each other.
7. The mud guiding device between the pile casings for cast-in-situ bored pile construction according to claim 1 or 2, characterized in that: one end of the joint pipe close to the protective cylinder is slightly inclined downwards.
8. The mud guiding device between the pile casings for cast-in-situ bored pile construction according to claim 1 or 2, characterized in that: the support piece is a smooth curved plate piece, and the middle of the support piece is concave downwards and is used for placing the flow guide pipe.
9. The mud guiding device between the pile casings for cast-in-situ bored pile construction according to claim 1 or 2, characterized in that: the support piece is a plane plate piece, and baffles are arranged on two sides of the support piece and used for placing the flow guide pipe.
10. The mud guiding device between the pile casings for cast-in-situ bored pile construction according to claim 1 or 2, characterized in that: the protective cylinder is a steel protective cylinder, the flow guide pipe is a plastic corrugated pipe, the joint pipe is a short steel pipe, and the supporting piece is a channel steel.
CN201921222582.2U 2019-08-01 2019-08-01 Mud guiding device between a section of thick bamboo is protected with construction of drilling bored concrete pile Active CN210597292U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921222582.2U CN210597292U (en) 2019-08-01 2019-08-01 Mud guiding device between a section of thick bamboo is protected with construction of drilling bored concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921222582.2U CN210597292U (en) 2019-08-01 2019-08-01 Mud guiding device between a section of thick bamboo is protected with construction of drilling bored concrete pile

Publications (1)

Publication Number Publication Date
CN210597292U true CN210597292U (en) 2020-05-22

Family

ID=70696504

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921222582.2U Active CN210597292U (en) 2019-08-01 2019-08-01 Mud guiding device between a section of thick bamboo is protected with construction of drilling bored concrete pile

Country Status (1)

Country Link
CN (1) CN210597292U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851478A (en) * 2020-07-13 2020-10-30 深圳市工勘岩土集团有限公司 Pile-forming construction method for light corrugated steel pile casing isolation non-filling karst cave filling pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851478A (en) * 2020-07-13 2020-10-30 深圳市工勘岩土集团有限公司 Pile-forming construction method for light corrugated steel pile casing isolation non-filling karst cave filling pile

Similar Documents

Publication Publication Date Title
CN210597292U (en) Mud guiding device between a section of thick bamboo is protected with construction of drilling bored concrete pile
CN107420640A (en) Attachment means between jacking construction end-protecting device and jacking construction steel pipe
CN110374640A (en) Pipe jacking tunnel head stops husky antipriming into hole
CN219159776U (en) High-impact-resistance reinforced pipe
CN200974984Y (en) Self-floating type PE pipeline for dredge
CN218598214U (en) Pipe jacking slurry grouting device
CN217355817U (en) Automatic expansion device for slurry pipe between pipe jacking construction relays
CN1274060A (en) Expansion shaped insertion-type steel tubes for both flexible and rigid joining and its manufacture technology
CN216157667U (en) Pipe piece fixing pile for supporting mud pipe piece grouting process for shield
CN204879188U (en) External pressure rubber connector
CN212107092U (en) Novel valve structure convenient for replacing sealing ring
CN212297990U (en) Anti-leakage metal hose with micro-pressure corrosion prevention and end part armoring functions
CN212564894U (en) Mine pipeline expansion device
CN206770822U (en) Attachment structure for pipeline
CN218441049U (en) Flexible anti-seepage circulating water pipe sleeve device and sleeve mounting structure
CN207673293U (en) A kind of oil-gas mining casing
CN205781534U (en) A kind of quickly spigot-and-socket HDPE reality wall drain pipe
CN219866883U (en) Anti-blocking agent application device for petroleum exploitation
CN205424280U (en) Can prevent feed pipe construction structures that flexible cast iron pipe leaked
CN1260460A (en) Expanding formed spigot-and-socket flexible joint steel pipe and its making method
CN217556930U (en) Slurry flow guiding device and flow guiding system for construction of water cast-in-place pile
CN220037864U (en) Impact-resistant PE water supply pipe
CN105148786B (en) A kind of installation method of hydraulic-driven slurry agitator
CN220134906U (en) Sewage discharge pipeline
CN215806768U (en) Sewage pipeline anti-leakage connecting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant