CN210564567U - Two lining platform trucks of tunnel gradual change cross-section can be under construction - Google Patents

Two lining platform trucks of tunnel gradual change cross-section can be under construction Download PDF

Info

Publication number
CN210564567U
CN210564567U CN201921586696.5U CN201921586696U CN210564567U CN 210564567 U CN210564567 U CN 210564567U CN 201921586696 U CN201921586696 U CN 201921586696U CN 210564567 U CN210564567 U CN 210564567U
Authority
CN
China
Prior art keywords
arc
tunnel
guide rail
lining
rail seat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921586696.5U
Other languages
Chinese (zh)
Inventor
刘纪飞
衣忠强
高成龙
李仁强
舒承兴
阎树东
周文军
张天翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd of China Railway No 9 Group Co Ltd
Original Assignee
Sixth Engineering Co Ltd of China Railway No 9 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd of China Railway No 9 Group Co Ltd filed Critical Sixth Engineering Co Ltd of China Railway No 9 Group Co Ltd
Priority to CN201921586696.5U priority Critical patent/CN210564567U/en
Application granted granted Critical
Publication of CN210564567U publication Critical patent/CN210564567U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a two lining trolleys capable of constructing a tunnel with a gradually-changed section, which comprises a first two lining trolley and a second two lining trolley, wherein the second lining trolley is arranged inside the first two lining trolley, the first two lining trolley comprises a first arc arch die, a first pin shaft, a first guide rail seat and a second guide rail seat, the two lining trolleys capable of constructing the tunnel with the gradually-changed section are improved on the basis of the original two lining trolleys, the existing cylindrical two lining trolleys are changed into a combined structure of the first two lining trolley and the second two lining trolley, the first two lining trolley can construct the tunnel mouth into a horn shape with the gradually-changed section, the second two lining trolley can construct the interior of the tunnel, and the second lining trolley can move inside the first two lining trolley, so that the construction is more convenient and the tunnel mouth does not need to be constructed independently, the tunnel construction efficiency is improved.

Description

Two lining platform trucks of tunnel gradual change cross-section can be under construction
Technical Field
The utility model relates to a two lining platform trucks, in particular to can be under construction two lining platform trucks in tunnel gradual change cross-section belongs to tunnel construction technical field.
Background
When a train enters the tunnel at a high speed, the air in the tunnel is extruded due to the impact of the high speed on the air in the tunnel, so that high pressure waves are easily generated and transmitted to the downstream in the tunnel at the sonic speed, and the air in the tunnel is extruded to generate a flow velocity, thereby forming a piston effect in the tunnel. When the high-pressure wave is transmitted to the downstream exit of the tunnel and rushes out of the tunnel entrance, the high-pressure wave is converted into a micro-pressure wave due to the suddenly wide space outside the tunnel, and the micro-pressure wave may generate an unpleasant micro-pressure wave noise. In order to reduce the high pressure wave generated when the train enters the tunnel and reduce the micro pressure wave noise at the downstream tunnel entrance, the tunnel entrance is designed into a tapered shape, such as a trumpet shape, which is helpful to reduce the micro pressure wave noise. The existing two-lining trolley is generally of a similar straight cylindrical structure, and because a gradual change section cannot be manufactured during tunnel construction, the gradual change section of a tunnel can be completed only by secondary construction, and the tunnel construction efficiency is reduced.
SUMMERY OF THE UTILITY MODEL
The utility model provides a can be under construction two lining platform trucks in tunnel gradual change cross-section, effectively solved the problem that exists among the prior art.
In order to solve the technical problem, the utility model provides a following technical scheme:
the utility model relates to a can be under construction two lining platform trucks in tunnel gradual change cross-section, including first two lining platform trucks and second two lining platform trucks, second two lining platform trucks set up the inside at first two lining platform trucks, first two lining platform trucks include that first arc encircles touches, first round pin axle, first guide rail seat and second guide rail seat, first arc encircles touches and is provided with six, and six first arc encircles touches and articulates through first round pin axle between two liang, the below that first arc encircles is provided with first guide rail seat, the top of first guide rail seat is provided with second guide rail seat, first arc encircles touches with first guide rail seat sliding connection, just second guide rail seat sliding connection is at the top of first guide rail seat.
As a preferred technical scheme of the utility model, the second liner trolley comprises a second arc arch die, a second pin shaft, angle modulation hydraulic rods, a top beam, supporting tables, jacking hydraulic rods and supporting rods, wherein six second arc arch dies are arranged, and the six second arc arch dies are hinged by the second pin shaft between two pairs, two ends of the top beam are respectively and fixedly connected with the inner walls of the two second arc arch dies at the top end, two angle modulation hydraulic rods are respectively arranged at two sides of the top beam, two ends of four angle modulation hydraulic rods are respectively hinged with the inner walls of the adjacent second arc arch dies, the supporting tables are arranged below the top beam, two ends at the top of the supporting tables are respectively provided with the jacking hydraulic rods, two ends of the jacking hydraulic rods are respectively and fixedly connected with the top beam and the supporting tables, two ends at the bottom of the supporting tables are both fixedly connected with the supporting rods, the support rod is matched with the second guide rail seat.
As an optimized technical scheme of the utility model, six the radius size that the arc surface was touched to first arc arch is the same.
As an optimized technical scheme of the utility model, six the radius size that the circular arc face was touched to the second arc arch is the same.
As a preferred technical scheme of the utility model, first arc encircles the radius of touching interior cambered surface and the radius size that the outer cambered surface was touched to the second arc arch is the same.
As a preferred technical scheme of the utility model, six the second arc encircles and touches the position that corresponds first round pin axle on the lateral wall of excircle side and has seted up a plurality of shaft groove, shaft groove and first round pin axle phase-match set up, just the concrete quantity in shaft groove is five.
The utility model discloses the beneficial effect who reaches is: the utility model relates to a can construct two lining platform trucks of tunnel gradual change cross section through improving on the basis at original two lining platform trucks, change into the structure by first two lining platform trucks and second two lining platform trucks combination formula with current cylindric two lining platform trucks, first two lining platform trucks can be to the horn shape of tunnel portal construction for gradual change cross section, second two lining platform trucks can be under construction in the tunnel, and second two lining platform trucks can be at the inside removal of first two lining platform trucks, make the construction more convenient, need not to be under construction alone to the tunnel portal, tunnel efficiency of construction has been improved.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic structural diagram of the present invention;
FIG. 2 is a side view of the present invention in use;
FIG. 3 is a schematic structural view of a first and second liner trolley according to the present invention;
fig. 4 is a schematic structural view of a second liner carriage of the present invention.
In the figure: 1. a first and a second liner trolleys; 11. a first arcuate arch form; 12. a first pin shaft; 13. a first guide rail seat; 14. a second rail seat; 2. a second liner trolley; 21. a second arc arch model; 22. a second pin shaft; 23. an angle adjusting hydraulic rod; 24. a shaft groove; 25. a top beam; 26. a support table; 27. jacking a hydraulic rod; 28. a support rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example (b): as shown in fig. 1-4, the utility model relates to a can be under construction tunnel gradual change cross-section two lining platform trucks, including first two lining platform trucks 1 and second two lining platform trucks 2, second two lining platform trucks 2 set up in first two lining platform trucks 1's inside, first two lining platform trucks 1 include that first arc encircles touches 11, first round pin axle 12, first guide rail seat 13 and second guide rail seat 14, first arc encircles and touches 11 and is provided with six, and six first arcs encircle and touch 11 two liang between articulate through first round pin axle 12, first arc encircles and touches 11 below and is provided with first guide rail seat 13, the top of first guide rail seat 13 is provided with second guide rail seat 14, 11 and first guide rail seat 13 sliding connection are touched to first arc, and second guide rail seat 14 sliding connection is at the top of first guide rail seat 13.
The second liner trolley 2 comprises six second arc-shaped arch moulds 21, a second pin shaft 22, angle-adjusting hydraulic rods 23, top beams 25, a support platform 26, a jacking hydraulic rod 27 and a support rod 28, and six second arcs encircle touch 21 and articulate through second round pin axle 22 between two liang, the both ends of back timber 25 respectively with two second arcs of top arch touch 21's inner wall fixed connection, the both sides of back timber 25 all are provided with two angle modulation hydraulic stem 23, the both ends of four angle modulation hydraulic stem 23 respectively with adjacent second arc encircle touch 21's inner wall articulated, the below of back timber 25 is provided with a supporting bench 26, the both ends at supporting bench 26 top all are provided with jacking hydraulic stem 27, jacking hydraulic stem 27's both ends respectively with back timber 25 and supporting bench 26 fixed connection, the equal fixedly connected with bracing piece 28 in both ends of supporting bench 26 bottom, bracing piece 28 and the setting of second guide rail seat 14 phase-match.
Six first arc arches touch 11 arc surfaces's radius size the same, six second arc arches touch 21 arc surfaces's radius size the same, be applicable to the construction of second lining in the tunnel, the radius that 11 inner arc surfaces were touched to first arc arch is the same with the radius that 21 outer arc surfaces were touched to the second arc arch, first second lining platform truck 1 can be placed in the inside of second lining platform truck 2, six second arc arches touch the position that corresponds first round pin axle 12 on the lateral wall of 21 excircle side and seted up a plurality of shaft groove 24, shaft groove 24 and first round pin axle 12 phase-match set up, and the specific quantity of shaft groove 24 is five, five shaft groove 24 just in time with six first arc arches touch first round pin axle 12 phase-match settings between 11, make second lining platform truck 2 can be in the inside removal of first second lining platform truck 1.
Specifically, the appearance shape structure of first two lining platform trucks 1 and second two lining platform trucks 2 is as shown in description figure 2, first two lining platform trucks 1 are horn-shaped structures, and the diameter that first two lining platform trucks 1 are close to second two lining platform trucks 2 one end diminishes gradually, when using, be under construction first two lining platform trucks 1 to the tunnel portal, when under construction, first arc arch on first two lining platform trucks 1 touches 11 and supports the tunnel portal, can be the horn-shaped with the tunnel portal construction, satisfy the gradual change cross section requirement of tunnel portal construction, second two lining platform trucks 2 can be in the inside removal of first two lining platform trucks 1, make can be under construction simultaneously in tunnel portal and the tunnel, make the construction more convenient, need not to carry out the construction alone to the tunnel portal, the work efficiency of tunnel construction has been improved.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. A two-lining trolley capable of constructing a tunnel with a gradually-changed section is characterized by comprising a first two-lining trolley (1) and a second two-lining trolley (2), the second liner trolley (2) is arranged inside the first liner trolley (1), the first and second lining trolleys (1) comprise a first arc arch die (11), a first pin shaft (12), a first guide rail seat (13) and a second guide rail seat (14), six first arc arch dies (11) are arranged, and every two of the six first arc-shaped arch moulds (11) are hinged through first pin shafts (12), a first guide rail seat (13) is arranged below the first arc arch mould (11), a second guide rail seat (14) is arranged above the first guide rail seat (13), the first arc arch die (11) is connected with the first guide rail seat (13) in a sliding way, and the second guide rail seat (14) is connected to the top of the first guide rail seat (13) in a sliding manner.
2. The second lining trolley capable of constructing the gradually-changed cross section of the tunnel according to claim 1, wherein the second lining trolley (2) comprises six second arc-shaped arch dies (21), second pin shafts (22), angle-adjusting hydraulic rods (23), top beams (25), support tables (26), jacking hydraulic rods (27) and support rods (28), the number of the second arc-shaped arch dies (21) is six, every two of the six second arc-shaped arch dies (21) are hinged through the second pin shafts (22), two ends of each top beam (25) are respectively and fixedly connected with inner walls of the two second arc-shaped arch dies (21) at the uppermost end, two angle-adjusting hydraulic rods (23) are respectively arranged on two sides of each top beam (25), two ends of the four angle-adjusting hydraulic rods (23) are respectively hinged with inner walls of the adjacent second arc-shaped arches (21), and the support tables (26) are arranged below the top beams (25), both ends at brace table (26) top all are provided with jacking hydraulic stem (27), the both ends of jacking hydraulic stem (27) respectively with back timber (25) and brace table (26) fixed connection, the equal fixedly connected with bracing piece (28) in both ends of brace table (26) bottom, bracing piece (28) and second guide rail seat (14) phase-match set up.
3. A two-lining trolley capable of constructing a tunnel with a gradually-changed section as claimed in claim 1, wherein the radii of the circular arc surfaces of the six first arc-shaped arches (11) are the same.
4. A two-lining trolley capable of constructing a tunnel with a gradually-changed section as claimed in claim 2, wherein the radii of the circular arc surfaces of the six second arc-shaped arches (21) are the same.
5. A secondary lining trolley capable of constructing a tunnel with a gradually-changed section as claimed in claim 2, wherein the radius of the inner arc surface of the first arc-shaped arch die (11) is the same as the radius of the outer arc surface of the second arc-shaped arch die (21).
6. The two-lining trolley capable of constructing the tunnel gradually-changing section according to claim 2, wherein a plurality of shaft grooves (24) are formed in the positions, corresponding to the first pin shafts (12), on the side walls of the outer circle sides of the six second arc-shaped arches (21), the shaft grooves (24) are arranged in a matched manner with the first pin shafts (12), and the specific number of the shaft grooves (24) is five.
CN201921586696.5U 2019-09-23 2019-09-23 Two lining platform trucks of tunnel gradual change cross-section can be under construction Active CN210564567U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921586696.5U CN210564567U (en) 2019-09-23 2019-09-23 Two lining platform trucks of tunnel gradual change cross-section can be under construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921586696.5U CN210564567U (en) 2019-09-23 2019-09-23 Two lining platform trucks of tunnel gradual change cross-section can be under construction

Publications (1)

Publication Number Publication Date
CN210564567U true CN210564567U (en) 2020-05-19

Family

ID=70642550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921586696.5U Active CN210564567U (en) 2019-09-23 2019-09-23 Two lining platform trucks of tunnel gradual change cross-section can be under construction

Country Status (1)

Country Link
CN (1) CN210564567U (en)

Similar Documents

Publication Publication Date Title
CN210564567U (en) Two lining platform trucks of tunnel gradual change cross-section can be under construction
CN102673586A (en) Side top structure of vehicle body of high-speed railway vehicle
CN207223394U (en) A kind of High-strength light-weight beam structure
CN206329348U (en) A kind of minitunnel lining trolley
CN202544967U (en) Inner pipe component of vehicle silencer and vehicle silencer
CN206397065U (en) A kind of computing device of cigarette air channel reinforcing rib
CN204201916U (en) A kind of power-plant flue gas discharge flue
CN206966377U (en) A kind of curved equipment of steel pipe connecting
CN217056436U (en) Large-flow reversing valve structure
CN204817591U (en) Pole steel ring butt joint former
CN108019036A (en) External corner aluminum alloy pattern plate system
CN203611461U (en) Retractable steel mold for manufacturing large fiber reinforced plastic chimneys
CN202781376U (en) Square cement flue molding equipment
CN202555644U (en) Mold frame suitable for thick wall steel pipe bended arc
CN110202040A (en) Steel pipe socket molding machine
CN202001022U (en) Movable lining arch center formwork
CN206997429U (en) A kind of how winding pipe forming apparatus
CN206645443U (en) A kind of end carriage transfer track-type facilities of single-beam crane
CN206435651U (en) A kind of numerical controlled bending of pipe mould
CN102733609B (en) A kind of jib, boom system and engineering machinery
CN205327166U (en) Frame Y type crossbeam
CN204163739U (en) A kind of hydraulic lining trolley
CN210830832U (en) Sound absorption composite construction tuber pipe of modularization installation
CN203389948U (en) Circular pipe blank material poking device with material shielding and buffer material catching mechanism
CN213175635U (en) Sliding type round vertical shaft mold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant