CN210556970U - Cement bin with diversion arch-proof structure - Google Patents
Cement bin with diversion arch-proof structure Download PDFInfo
- Publication number
- CN210556970U CN210556970U CN201921320041.3U CN201921320041U CN210556970U CN 210556970 U CN210556970 U CN 210556970U CN 201921320041 U CN201921320041 U CN 201921320041U CN 210556970 U CN210556970 U CN 210556970U
- Authority
- CN
- China
- Prior art keywords
- bin
- cement
- bin body
- platform
- bearing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The utility model relates to a cement manufacture equipment field discloses a cement bin with arch structure is prevented in water conservancy diversion. The utility model has the advantages of it is following and effect: the bearing bin body is installed on the rack, the platform is arranged on the upper portion of the bearing bin body, and the erection bin body is arranged on the platform, a discharge port is formed in the bottom of the bearing bin body, a feeding port is formed in the top of the erection bin body, and a guide rod is spirally arranged on the erection bin body. The whole cement bin is divided into a bearing bin body and an erection bin body, the erection bin body is spirally provided with the guide rods, cement falling from the top of the bin firstly impacts the guide rods, and the guide rods in multiple layers can effectively relieve the impact of the cement so as to reduce the impact on the wall of the bin; and meanwhile, the guide rods which are spirally arranged can disperse cement more uniformly so as to reduce the formation of an arch and reduce the operation cost of the cement bin.
Description
Technical Field
The utility model relates to a cement manufacture equipment field, in particular to cement bin with arch structure is prevented in water conservancy diversion.
Background
The cement bin is generally used in bulk cement storage of a concrete mixing plant or cement production, the cement bin is a closed tank for storing bulk materials, is suitable for storing various bulk materials such as grain cement, fly ash and cement powder, and is provided with a material level system which can display the position and the quantity of the materials, and the hole breaking device can relieve firmness caused by long-term material deposition: at present, with the continuous development of science and technology and the progress of times, the living standard of people is continuously improved, so that the requirements of people on a cement bin are higher and higher, cement lumps in the cement bin form an arch to cause that the cement is difficult to output, and the operation cost of the cement bin can be effectively reduced by reducing the formation of the arch structurally; on the other hand, the abrasion of cement is a key factor for limiting the service life of the cement bin, and it is necessary to reduce the impact of cement on the bin wall.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a cement bin with structure is prevented encircleing in water conservancy diversion has the formation that reduces to encircle and alleviates the effect of cement to the wearing and tearing of bulkhead.
The above technical purpose of the present invention can be achieved by the following technical solutions: the automatic feeding device comprises a rack, a bearing bin body arranged on the rack, a platform arranged on the upper portion of the bearing bin body and an erection bin body arranged on the platform, wherein a discharge hole is formed in the bottom of the bearing bin body, and a feeding hole is formed in the top of the erection bin body.
Through adopting above-mentioned technical scheme, divide into two parts with the cement bin, be located the lower part and bear the bearing storehouse body of cement, the upper portion erects buffer structure's the storehouse body of erectting, separates the different parts of the storehouse body like this, reforms transform separately, can control cost.
The utility model discloses a further set up to: erect and to have a plurality of mounting holes for the heliciform on the storehouse body, be provided with the water conservancy diversion pole in the mounting hole, through threaded connection between water conservancy diversion pole and the mounting hole, it has the pan feeding mouth and prevents the railing to fall to erect storehouse body top division.
By adopting the technical scheme, the spiral guide rod array can be formed by arranging the spiral mounting holes, cement dust falling from the upper part can collide on the guide rods firstly, and on one hand, the guide rods play a role in buffering and reduce the impact of the cement dust; on the other hand, the cement falling position is more uniform than that of a cement bin without a guide rod, the effect of forming peaks due to cement accumulation is relieved, and the formation of cement arches is reduced; and the diversion rod is spirally connected with the erection cabin body, so that workers can directly replace the diversion rod seriously abraded, and the service life of the cement cabin is correspondingly prolonged.
The utility model discloses a further set up to: the guide rod comprises a rod body, a handle is arranged at one end of the rod body, and a sealing baffle lining is arranged at the joint of the handle and the rod body.
Through adopting above-mentioned technical scheme for the workman can directly change the guide rod of wearing and tearing on the platform, and the sealed lining of keeping off can avoid the cement dust to reveal, can take off the guide rod simultaneously when some trouble, observes the inside condition through the mounting hole.
The utility model discloses a further set up to: the material of guide rod is steel or hard pottery.
By adopting the technical scheme, the selected material is a wear-resistant material under the condition of low cost, so that too many impurities are prevented from being mixed in the powder.
The utility model discloses a further set up to: the platform is provided with a safety rail, an ascending ladder I and an ascending ladder II, one end of the ascending ladder is arranged on the platform, and the other end of the ascending ladder is arranged on the ground; one end of the ascending ladder is arranged on the platform, and the other end of the ascending ladder is arranged at the top of the erection cabin body.
By adopting the technical scheme, a worker can climb the platform through the ascending ladder to install and replace the guide rod; meanwhile, maintenance work can be carried out by climbing the top of the bin through the ascending ladder II.
The utility model discloses a further set up to: the bearing bin body is provided with a plurality of transverse reinforcing ribs and longitudinal reinforcing ribs.
By adopting the technical scheme, the pressure resistance of the bearing bin body can be enhanced, and the collapse danger is reduced.
The utility model has the advantages that: the whole cement bin is divided into a bearing bin body and an erection bin body, the erection bin body is spirally provided with the guide rods, cement falling from the top of the bin firstly impacts the guide rods, and the guide rods in multiple layers can effectively relieve the impact of the cement so as to reduce the impact on the wall of the bin; and meanwhile, the guide rods which are spirally arranged can disperse cement more uniformly so as to reduce the formation of an arch and reduce the operation cost of the cement bin.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without creative efforts.
Fig. 1 is a schematic perspective view of the present invention.
Fig. 2 is a plan view of the present invention.
3 fig. 33 3 is 3 a 3 sectional 3 view 3 of 3 the 3 plane 3 a 3- 3 a 3 of 3 the 3 present 3 invention 3. 3
In the figure, 1, a frame; 2. a bearing bin body; 21. transverse reinforcing ribs; 22. longitudinal reinforcing ribs; 3. a platform; 31. a safety rail; 32. a first ascending ladder; 33. a second ascending ladder; 4. erecting a bin body; 41. mounting holes; 42. a guide rod; 421. a rod body; 422. a handle; 423. a sealing barrier liner; 43. a feeding port; 44. prevent falling railing.
Detailed Description
The technical solution of the present invention will be clearly and completely described below with reference to the specific embodiments.
In this embodiment, as shown in fig. 1, the cement silo is divided into a frame 1, a bearing silo body 2 erected on the frame 1, a platform 3 arranged on the bearing silo body 2, and an erection silo body 4 arranged on the platform 3. A plurality of mounting holes 41 are formed in the outer wall of the erection cabin body 4, the mounting holes 41 are spirally arranged, the guide rods 42 are mounted on the erection cabin body 4 through the mounting holes 41, the guide rods 42 are in threaded connection with the mounting holes 41, so that a spirally arranged guide rod 42 array is formed in the erection cabin body 4, cement coming from a feeding port 43 firstly impacts the guide rods 42 and then falls into the bearing cabin body 2 after being impacted for a plurality of times, and thus the abrasion of the cement to the cabin wall is greatly reduced; meanwhile, the diversion rod 42 can change the impact direction of the cement, so that the cement is not distributed in a pointed shape any more and falls down more uniformly, the formation of an arch structure can be reduced, and the running cost of the cement bin is reduced; the top of the erection cabin 4 is also provided with a feeding port 43 and a falling prevention railing 44 for inputting cement powder and preventing workers from falling.
In this embodiment, as shown in fig. 1-3, the platform 3 is provided with a first ascending ladder 32, a second ascending ladder 33 and a mounting rail, the first ascending ladder 32 is erected between the bottom surface and the platform 3, and the second ascending ladder 33 is erected between the platform 3 and the top of the cabin; the guide rod 42 includes a handle 422, a rod 421 and a sealing gasket 423. The worker can carry the guide pole 42 to the platform 3 from the first ascending ladder 32, and then replace the damaged guide pole 42, so that the service life of the cement bin is prolonged.
In this embodiment, as shown in fig. 1, a transverse reinforcing rib 21 and a longitudinal reinforcing rib 22 are disposed outside the bearing bin body 2 to reinforce the bearing bin body 2, and a discharge hole is further disposed at the bottom of the bearing bin body 2 to output cement powder.
It is obvious that the described embodiments are only some of the embodiments of the present invention, and not all of them. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
Claims (6)
1. The utility model provides a cement bin with structure is prevented encircleing in water conservancy diversion which characterized in that: the automatic feeding device comprises a rack (1), a bearing bin body (2) arranged on the rack (1), a platform (3) arranged on the upper portion of the bearing bin body (2), and a set-up bin body (4) arranged on the platform (3), wherein a discharge hole is formed in the bottom of the bearing bin body (2), and a feeding hole (43) is formed in the top of the set-up bin body (4).
2. The cement bin with the diversion arch-proof structure according to claim 1, wherein: erect and be the heliciform on the storehouse body (4) and open and to have a plurality of mounting holes (41), be provided with water conservancy diversion pole (42) in mounting hole (41), through threaded connection between water conservancy diversion pole (42) and mounting hole (41), it has pan feeding mouth (43) and prevents railing (44) to fall to open at the top of erecting the storehouse body (4).
3. The cement bin with the diversion arch-proof structure as claimed in claim 2, wherein: the guide rod (42) comprises a rod body (421), a handle (422) is arranged at one end of the rod body (421), and a sealing blocking lining (423) is arranged at the joint of the handle (422) and the rod body (421).
4. The cement bin with the diversion arch-proof structure as claimed in claim 3, wherein: the material of the guide rod (42) is steel or hard ceramic.
5. The cement bin with the diversion arch-proof structure according to claim 1, wherein: a safety rail (31), a first ascending ladder (32) and a second ascending ladder (33) are arranged on the platform (3), one end of the first ascending ladder (32) is arranged on the platform (3), and the other end of the first ascending ladder is arranged on the ground; one end of the second ascending ladder (33) is arranged on the platform (3), and the other end is arranged at the top of the erection cabin body (4).
6. The cement bin with the diversion arch-proof structure according to claim 1, wherein: the bearing bin body (2) is provided with a plurality of transverse reinforcing ribs (21) and longitudinal reinforcing ribs (22).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921320041.3U CN210556970U (en) | 2019-08-14 | 2019-08-14 | Cement bin with diversion arch-proof structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921320041.3U CN210556970U (en) | 2019-08-14 | 2019-08-14 | Cement bin with diversion arch-proof structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210556970U true CN210556970U (en) | 2020-05-19 |
Family
ID=70630071
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921320041.3U Active CN210556970U (en) | 2019-08-14 | 2019-08-14 | Cement bin with diversion arch-proof structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210556970U (en) |
-
2019
- 2019-08-14 CN CN201921320041.3U patent/CN210556970U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA1067476A (en) | Embedded housing for ore crusher | |
CN206013914U (en) | A kind of circular storage yard | |
CN210556970U (en) | Cement bin with diversion arch-proof structure | |
CN210564652U (en) | Underground mine filling buffer | |
CN101735943A (en) | Gas generation and storage integrated biomass pool | |
CN206352413U (en) | A kind of new multiple spot multi-pipeline granular material storage steel plate storehouse | |
CN205818097U (en) | A kind of continuous concrete revetment brick produces machine | |
EP2282959B1 (en) | An apparatus for storing rolling material in a pile and reclaiming from the pile | |
CN204979824U (en) | Special storage device of wet mixture mortar | |
CN208201877U (en) | The constructing device of the underwater back cover of large-area deep foundation pit is carried out using small hopper | |
CN103274130B (en) | Large floor formula fluidization storehouse | |
CN107476590A (en) | A kind of guard rail being used in turn | |
CN218840534U (en) | Ore bin structure | |
CN206691730U (en) | A kind of square steel construction storing group storehouse and storing list storehouse | |
CN207420069U (en) | A kind of guard rail being used in turn | |
CN206860195U (en) | A kind of bottom arch filling overcoat of baseboard of coal mine roadway | |
CN206645330U (en) | A kind of dual depositing dust formula environment-friendly type water hopper dredger | |
CN211056241U (en) | Fly ash storage device | |
CN214614029U (en) | Novel high-pressure jet grouting pile | |
CN105040701B (en) | A kind of lattice steel sheet-pile cofferdam water jet cloth bucket device | |
CN217050741U (en) | Assembled high-order feed bin structure | |
CN109663441A (en) | A kind of concrete mixing station cementing tank dust-extraction unit and method | |
CN210762325U (en) | Anti-segregation dry-mixed mortar storage bin | |
CN208868702U (en) | A kind of anti-overflow cementing tank of brick-making raw material | |
CN214636091U (en) | Lime liquid configuration system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |