CN210535271U - Engineering progress display device that civil engineering used - Google Patents

Engineering progress display device that civil engineering used Download PDF

Info

Publication number
CN210535271U
CN210535271U CN201922110317.1U CN201922110317U CN210535271U CN 210535271 U CN210535271 U CN 210535271U CN 201922110317 U CN201922110317 U CN 201922110317U CN 210535271 U CN210535271 U CN 210535271U
Authority
CN
China
Prior art keywords
progress
civil engineering
magnetic attraction
magnetic suction
magnetic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922110317.1U
Other languages
Chinese (zh)
Inventor
张启珲
张萌萌
兰永钢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northeast Forestry University
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201922110317.1U priority Critical patent/CN210535271U/en
Application granted granted Critical
Publication of CN210535271U publication Critical patent/CN210535271U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to an engineering progress display device that civil engineering used, including supporting base and progress show fence, its characterized in that: the supporting base comprises a base and two supporting rods connected with the progress display fence, and wheel bodies are arranged at four end corners of the bottom surface of the base; the schedule display bar is characterized in that a date plate is arranged on the left side of the front face of the schedule display bar, three magnetic suction parts which are longitudinally arranged are embedded in the schedule display bar, magnetic suction plates are magnetically sucked in the magnetic suction parts, and transparent insert bags are arranged right above the magnetic suction plates; the magnetic attraction plates comprise white boards and matched magnetic attraction parts which are arranged on the back surfaces of the white boards and magnetically attract the magnetic attraction parts, and the magnetic attraction plates are magnetically attracted on the magnetic attraction parts through the matched magnetic attraction parts; the utility model discloses a display device conveniently removes and supports stably, can show civil engineering progress is simple, convenient to use, and easy operation conveniently knows civil engineering's engineering progress.

Description

Engineering progress display device that civil engineering used
Technical Field
The utility model relates to a civil engineering field, in particular to engineering progress display device that civil engineering used.
Background
Civil engineering is a general term for scientific technology for building various land engineering facilities, and refers to both applied materials, equipment, technical activities such as surveying, designing, constructing, maintaining and repairing, and the like, and objects of engineering construction. I.e. various engineering facilities such as houses, roads, railways, pipelines, tunnels, bridges, canals, dams, ports, power stations, airports, ocean platforms, water supply and drainage and protection projects, which are built on or under the ground, on land and directly or indirectly serve human life, production, military affairs and scientific research. The civil engineering refers to engineering entities for surveying, planning, designing, constructing, installing and maintaining various technical works and the like of newly-built, reconstructed or expanded buildings, structures, related supporting facilities and the like of various projects except house buildings. In the civil engineering, it is necessary to record the progress of the engineering to effectively ensure the completion of the civil engineering according to the schedule, so that a display device capable of recording the progress of the engineering is required to be used, so that the progress of the engineering can be known at any time, and the work can be carried out according to the schedule.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a solve prior art's problem, provide an engineering progress display device that civil engineering used.
The utility model discloses a concrete technical scheme as follows: the utility model provides an engineering progress display device that civil engineering used, is including supporting base and progress show fence, its characterized in that: the supporting base comprises a base and two supporting rods connected with the progress display fence, and wheel bodies are arranged at four end corners of the bottom surface of the base;
the schedule display bar is characterized in that a date plate is arranged on the left side of the front face of the schedule display bar, three magnetic suction parts which are longitudinally arranged are embedded in the schedule display bar, magnetic suction plates are magnetically sucked in the magnetic suction parts, and transparent insert bags are arranged right above the magnetic suction plates; the magnetic attraction plates comprise white boards and matched magnetic attraction parts which are arranged on the back surfaces of the white boards and magnetically attract the magnetic attraction parts, and the magnetic attraction plates are magnetically attracted on the magnetic attraction parts through the matched magnetic attraction parts;
at least three lighting components arranged opposite to the magnetic suction plate are arranged on the top surface of the progress display bar.
As the preferred scheme, be equipped with on the base and insert the chamber, inserted the counter weight plate that the front was equipped with the handle in inserting the chamber.
Preferably, the magnetic suction part is embedded with a magnetic suction sheet.
Preferably, the magnetic suction piece is embedded in the magnetic suction part.
Preferably, the number of the lighting components is at least three, the lighting components comprise a fixed pipe and a gooseneck pipe integrated with the fixed pipe, a lamp part is mounted on the gooseneck pipe, and a lamp holder with a lamp bead is mounted on the lamp part.
As preferred scheme, the lamp pearl is installed in the front of lamp stand.
Preferably, the lamp beads with the lamp beads in the at least three lighting components are connected sequentially through the lead, and the switch and the plug are installed at one end of the lead.
The technical effects of the utility model:
the supporting base is stably supported by inserting the bearing plate into the base in the supporting base, the wheel body arranged on the bottom surface of the base is convenient to move, the progress display fence is stably supported by the two supporting rods arranged on the supporting base, and the date plate arranged on the progress display fence is arranged relative to the magnetic suction plate magnetically sucked on the magnetic suction part, so that the civil engineering progress can be recorded simply on the magnetic suction plate and can be illuminated by the illuminating part;
the device conveniently removes and supports stably, can simply demonstrate civil engineering progress, convenient to use, and easy operation can know civil engineering's engineering progress.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a diagram illustrating a structure of a progress display bar;
FIG. 3 is a schematic view of a magnetic plate structure;
FIG. 4 is a schematic view of an illumination assembly;
fig. 5 is a schematic diagram of the electrical connections of the lighting components.
In the figure: support base 1, base 11, insert chamber 12, counterweight plate 13, handle 131, bracing piece 14, wheel body 15, progress show fence 2, date board 21, magnetism portion of inhaling 22, magnetism piece 23, magnetism board 3 of inhaling connects magnetism portion 31, magnetism connects magnetism piece 32 of inhaling, blank 33, lighting parts 5, fixed pipe 51, gooseneck 52, lamp portion 54, lamp stand 55, lamp pearl 56, switch 57, plug 58.
Detailed Description
The present invention will be further explained with reference to the accompanying drawings.
Example one
As shown in fig. 1 to 5, the engineering progress display device for civil engineering of the present embodiment includes a supporting base 1 and a progress display fence 2, where the supporting base 1 includes a base 11 and two supporting rods 14 connected to the progress display fence 2 for stably supporting the progress display fence, and four end corners of the bottom surface of the base 11 are respectively provided with a wheel body 15; for movement of the device.
The schedule display board 2 is characterized in that a date board 21 is arranged on the left side of the front face of the schedule display board 2, dates of 30 days of a month are recorded on the date board from top to bottom, at least three magnetic attraction parts 22 embedded with longitudinal magnetic sheets 23 are arranged in the schedule display board 2, the magnetic attraction parts 22 are magnetically attracted with magnetic attraction boards 3, the magnetic attraction boards in the embodiment are as shown in fig. 3, each magnetic attraction board 3 comprises a white board 33 and a matching magnetic attraction part 31 which is arranged on the back face of the white board 33 and is magnetically attracted with the magnetic attraction parts 22, a matching magnetic attraction sheet 32 is embedded in the matching magnetic attraction part 31, the magnetic attraction boards 3 are magnetically attracted on the magnetic attraction parts 22 through the matching magnetic attraction parts 33 and are used for displaying the schedule of a Mark pen writing project relative to the dates every month, and transparent inserting bags 23 are arranged right above the at least; the transparent insert pocket is used for inserting the month label, three transparent insert pockets are arranged in the embodiment and represent three month engineering progress, and in actual use, the transparent insert pocket can be arranged for a plurality of months according to the engineering quantity of civil engineering.
At least three illuminating components 5 which are arranged relative to the magnetic suction plates 3 are arranged on the top surface of the progress display fence 2 and used for respectively displaying the at least three magnetic suction plates so as to be convenient for clear illumination.
The base 11 is provided with an inserting cavity 12, and a weight plate 13 with a handle 131 at the front is inserted into the inserting cavity 12. So that the base remains stable.
The lighting components 5 are at least three, each of which comprises a fixed tube 51 and a gooseneck 52 integrated with the fixed tube 51, a lamp part 54 is arranged on the gooseneck 52, and a lamp holder 55 with a lamp bead 56 is arranged on the lamp part 54. Be equipped with the through-hole that passes the wire in gooseneck one side, through the gooseneck bending, make things convenient for the illumination of lamp portion, can make things convenient for marketing teaching to the illumination of progress show fence.
The lamp bead 54 is arranged on the front surface of the lamp holder 55. The illumination is convenient.
The lamp holder 56 with the lamp beads 55 in the at least three lighting components 5 are connected sequentially through the conducting wires, one ends of the conducting wires are provided with the switch 57 and the plug 58, the plug is externally connected with a power supply, and the lamp beads are lightened by pressing the switch.
Example two
Based on the technical scheme, the utility model discloses in use, promote this display device to civil engineering construction site, insert the bearing plate in the plug-in cavity that the base was equipped with, make its support stable, owing to be equipped with two bracing pieces on the base, it supports progress show fence, at the inside at least three magnetism portion of inhaling that has inlayed of progress show fence, a board is inhaled to the magnetism, because magnetism inhales the board back and glues inherent magnetic stripe, it is consequently can write civil engineering's progress on the blank for the blank setting, through insert month label in transparent plug-in bag, so that make clear and definite progress condition to monthly civil engineering, and assist in the contrast of date board, can the nimble illumination of bending forward through lighting components, it is clear to corresponding magnetism and inhale the board illumination, high durability and convenient use.
It should be noted that the above-mentioned preferred embodiments are only for illustrating the technical concepts and features of the present invention, and the purpose thereof is to enable those skilled in the art to understand the contents of the present invention and to implement the present invention accordingly, and the protection scope of the present invention cannot be limited thereby. All equivalent changes and modifications made according to the spirit of the present invention should be covered by the protection scope of the present invention.

Claims (7)

1. The utility model provides an engineering progress display device that civil engineering used, is including supporting base and progress show fence, its characterized in that: the supporting base comprises a base and two supporting rods connected with the progress display fence, and wheel bodies are arranged at four end corners of the bottom surface of the base; the schedule display bar is characterized in that a date plate is arranged on the left side of the front face of the schedule display bar, three magnetic suction parts which are longitudinally arranged are embedded in the schedule display bar in a bent mode, magnetic suction plates are magnetically sucked in the magnetic suction parts, and transparent inserting bags are arranged right above the magnetic suction plates; the magnetic attraction plate comprises a white board and a matched magnetic attraction part which is arranged on the back of the white board and is magnetically attracted with the magnetic attraction part, and the magnetic attraction plate is magnetically attracted on the magnetic attraction part through the matched magnetic attraction part; at least three lighting components arranged opposite to the magnetic suction plate are arranged on the top surface of the progress display bar.
2. A construction progress exhibiting apparatus for civil engineering works as set forth in claim 1, wherein: the base is provided with an inserting cavity, and a counterweight plate with a handle arranged on the front side is inserted into the inserting cavity.
3. A construction progress exhibiting apparatus for civil engineering works as set forth in claim 1, wherein: the magnetic suction part is internally embedded with a magnetic suction sheet.
4. A construction progress exhibiting apparatus for civil engineering works as set forth in claim 1, wherein: the inside of the matching magnetic suction part is embedded with a matching magnetic suction sheet.
5. A construction progress exhibiting apparatus for civil engineering works as set forth in claim 1, wherein: the lighting components are at least three, and the lighting components comprise a fixed pipe and a gooseneck pipe integrated with the fixed pipe, wherein a lamp part is arranged on the gooseneck pipe, and a lamp holder with a lamp bead is arranged on the lamp part.
6. A construction progress exhibiting apparatus for civil engineering works as set forth in claim 5, wherein: the lamp bead is installed in the front of lamp stand.
7. A construction progress exhibiting apparatus for civil engineering works as set forth in claim 6, wherein: the lamp beads with the lamp beads in the at least three lighting components are connected sequentially through the wires, and the head and the plug are installed at one end of each wire.
CN201922110317.1U 2019-11-30 2019-11-30 Engineering progress display device that civil engineering used Expired - Fee Related CN210535271U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922110317.1U CN210535271U (en) 2019-11-30 2019-11-30 Engineering progress display device that civil engineering used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922110317.1U CN210535271U (en) 2019-11-30 2019-11-30 Engineering progress display device that civil engineering used

Publications (1)

Publication Number Publication Date
CN210535271U true CN210535271U (en) 2020-05-15

Family

ID=70609108

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922110317.1U Expired - Fee Related CN210535271U (en) 2019-11-30 2019-11-30 Engineering progress display device that civil engineering used

Country Status (1)

Country Link
CN (1) CN210535271U (en)

Similar Documents

Publication Publication Date Title
Chase et al. E Groups and the rise of complexity in the southeastern Maya Lowlands
CN210535271U (en) Engineering progress display device that civil engineering used
Fokkens The Maaskant project: Continuity and change of a regional research project1
CN108010464A (en) For surveying and drawing the alarming device in operation
Doyle A vision of ‘deep time’: the ‘Geological Illustrations’ of Crystal Palace Park, London
CN219642497U (en) Engineering progress display device
CN215244009U (en) Combined mathematics teaching board
CN210896002U (en) Staff teaching aid
CN2731615Y (en) Magnetic teaching acid for middle and primary school
Jones et al. The Severan Buildings at Lepcis Magna
CN217084141U (en) Illumination analogue means for architectural design
CN213720595U (en) Civil engineering management budget drawing device
CN205861050U (en) Light structures on levelling rod
Downum The Observer: Julian Hayden at Pueblo Grande
Sinopoli Human representation in the South Indian Iron Age: examples from Kadebakele, South India
CN214372083U (en) Measuring device for civil engineering
CN209859475U (en) Chinese three-dimensional map
CN201633384U (en) Novel writing instrument
CN2785874Y (en) Magnetic dust-eliminating blackboard
Baker et al. A balancing act
Los Baños Los Baños
CN206649288U (en) The memorandum of particular surroundings can be applied to
Loprieno-Gnirs Life Histories of Theban Tombs: Transdisciplinary Investigations of a Cluster of Rock-cut Tombs at Sheikh ‘Abd al-Qurna
CN204367675U (en) A kind of mathematical education blackboard
CN107804093A (en) A kind of drawing ruler suitable for mathematical education

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200717

Address after: 150040 Northeast Forestry University, Harbin Road, Xiangfang District, Heilongjiang, 26

Patentee after: NORTHEAST FORESTRY University

Address before: 150001 No. 26 Hexing Road, Xiangfang District, Heilongjiang, Harbin

Patentee before: Zhang Qihui

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200515

Termination date: 20201130

CF01 Termination of patent right due to non-payment of annual fee