CN210491476U - Novel 5G system installation equipment - Google Patents

Novel 5G system installation equipment Download PDF

Info

Publication number
CN210491476U
CN210491476U CN201921523820.3U CN201921523820U CN210491476U CN 210491476 U CN210491476 U CN 210491476U CN 201921523820 U CN201921523820 U CN 201921523820U CN 210491476 U CN210491476 U CN 210491476U
Authority
CN
China
Prior art keywords
baffle
install bin
novel
system installation
filter screen
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921523820.3U
Other languages
Chinese (zh)
Inventor
谷昕澜
宋艳
谷寒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Lanhuang Industry Co Ltd
Original Assignee
Shanghai Lanhuang Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Lanhuang Industry Co Ltd filed Critical Shanghai Lanhuang Industry Co Ltd
Priority to CN201921523820.3U priority Critical patent/CN210491476U/en
Application granted granted Critical
Publication of CN210491476U publication Critical patent/CN210491476U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a novel 5G system installation equipment, includes the install bin, the top fixed mounting of install bin has rain-proof cover, and the inside from the top down of install bin activity respectively is provided with second baffle and first baffle, the connecting hole has been seted up to the upper surface of second baffle and first baffle, the top fixed mounting that the inner wall of install bin is close to second baffle and first baffle has the winding displacement subassembly, and the front surface of install bin is provided with spacing subassembly, the bottom fixed mounting of install bin has the heat recovery subassembly. The utility model discloses a winding displacement subassembly can carry out reasonable distribution to the wire rod that 5G network hardware equipment used, makes things convenient for the time that the managers combed the wire rod, its work efficiency of effectual improvement, and one side of spacing buckle is provided with first fixed plate, second fixed plate and spring, through the effect of spring, can carry out spacing protection's effect in to 5G network hardware equipment, prevents that the collision from causing the damage to it.

Description

Novel 5G system installation equipment
Technical Field
The utility model relates to an erection equipment specifically is a novel 5G system installation equipment.
Background
The 5G is a fifth generation mobile communication technology and also an extension behind the 4G, the 5G network is used as a fifth generation mobile communication network, the peak value theoretical transmission speed can reach dozens of GB per second, which is hundreds of times faster than the transmission speed of the 4G network, the 5G network is mainly used for enabling a terminal user to be in a networking state all the time, equipment supported by the 5G network is far more than a smart phone, the 5G network is in a test stage at present, large-scale experimental networking is formed, and 5G network construction is started on the basis.
However, when the 5G network hardware equipment is used and installed, the number of wires used is large, confusion is easily caused, large heat can be generated in the use process of the 5G network hardware equipment, and the heat is dissipated in the air and cannot be recovered, so that waste is caused. Accordingly, a person skilled in the art provides a new 5G system installation apparatus to solve the problems set forth in the above background art.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a novel 5G system installation equipment to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a novel 5G system installation equipment, includes the install bin, the top fixed mounting of install bin has rain-proof cover, and the inside from the top down of install bin activity respectively is provided with second baffle and first baffle, the connecting hole has been seted up to the upper surface of second baffle and first baffle, the top fixed mounting that the inner wall of install bin is close to second baffle and first baffle has the winding displacement subassembly, and the front surface of install bin is provided with spacing subassembly, the bottom fixed mounting of install bin has the heat recovery subassembly.
As a further aspect of the present invention: the winding displacement subassembly includes first fixed plate, protective layer, second fixed plate and spring, the both ends of spring are the embedding respectively and are installed in the inside of first fixed plate and second fixed plate, one side of first fixed plate is connected with spacing buckle, the opening part fixed mounting of spacing buckle has the protective layer.
As a further aspect of the present invention: the limiting buckle is arranged in a semicircular shape, and the protective layer is made of sponge materials.
As a further aspect of the present invention: the limiting assembly comprises a movable sleeve, a movable plate, a through hole and a bolt, the movable plate is movably mounted outside the movable sleeve, the through hole is formed in the front surface of the movable plate, and the bolt is fixedly mounted inside the through hole.
As a further aspect of the present invention: the movable plate is arranged in a rectangular shape.
As a further aspect of the present invention: the heat recovery subassembly includes connecting box, first filter screen, second filter screen, fan, communicating pipe and collection box, the inside from the top down of connecting box is provided with first filter screen and second filter screen respectively, and the bottom fixed mounting of connecting box has the fan, one side through connection of connecting box has communicating pipe, the other end of communicating pipe runs through the inside of collection box.
As a further aspect of the present invention: the first filter screen is a filter screen made of HPEA materials, and the second filter screen is a filter screen made of activated carbon materials.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a winding displacement subassembly can carry out reasonable distribution to the wire rod that 5G network hardware equipment used, makes things convenient for the time that the managers combed the wire rod, its work efficiency of effectual improvement, and one side of spacing buckle is provided with first fixed plate, second fixed plate and spring, through the effect of spring, can carry out spacing protection's effect in to 5G network hardware equipment, prevents that the collision from causing the damage to it.
2. The fan through the connecting box inside inhales the connecting box with the produced heat of 5G network hardware equipment in the installation box, can effectually collect the heat and carry out heat recovery utilization in entering into the collection box through communicating pipe, and environmental protection performance is high, avoids extravagant, and is provided with first filter screen and second filter screen in the connecting box, impurity that exists in can effectual filtered air.
Drawings
FIG. 1 is a schematic structural diagram of a novel 5G system installation device;
FIG. 2 is an enlarged view of portion A of FIG. 1;
FIG. 3 is an enlarged view of portion B of FIG. 1;
FIG. 4 is a schematic diagram of a heat recovery module in a novel 5G system installation.
In the figure: 1. a rain cover; 2. a flat cable assembly; 3. a heat recovery assembly; 4. a first separator; 5. connecting holes; 6. a second separator; 7. a limiting component; 8. installing a box; 21. a first fixing plate; 22. a protective layer; 23. a limiting buckle; 24. a second fixing plate; 25. a spring; 71. a movable sleeve; 72. a movable plate; 73. a through hole; 74. a bolt; 31. a connecting box; 32. a first filter screen; 33. a second filter screen; 34. a fan; 35. a communicating pipe; 36. and (6) a recycling bin.
Detailed Description
Referring to fig. 1 to 4, in the embodiment of the present invention, a novel 5G system installation apparatus includes an installation box 8, a rain-proof cover 1 is fixedly installed above the installation box 8, a second partition plate 6 and a first partition plate 4 are respectively movably installed inside the installation box 8 from top to bottom, connection holes 5 are opened on the upper surfaces of the second partition plate 6 and the first partition plate 4, a flat cable assembly 2 is fixedly installed on the inner wall of the installation box 8 near the upper portions of the second partition plate 6 and the first partition plate 4, the flat cable assembly 2 includes a first fixing plate 21, a protective layer 22, a second fixing plate 24 and a spring 25, two ends of the spring 25 are respectively embedded inside the first fixing plate 21 and the second fixing plate 24, one side of the first fixing plate 21 is connected with a limit buckle 23, the limit buckle 23 is in a semicircular arrangement, the protective layer 22 is made of a sponge material, the opening of the limit buckle 23 is fixedly installed with the protective layer, can carry out reasonable distribution to the wire rod that 5G network hardware equipment used through winding displacement subassembly 2 for the time that managers combed the wire rod, its work efficiency of effectual improvement, and one side of spacing buckle 23 is provided with first fixed plate 21, second fixed plate 24 and spring 25, and through spring 25's effect, can carry out spacing protection's effect in to 5G network hardware equipment, prevent that the collision from leading to the fact the damage to it.
In fig. 3 and 4: the front surface of the installation box 8 is provided with a limiting component 7, the limiting component 7 comprises a movable sleeve 71, a movable plate 72, a through hole 73 and a bolt 74, the movable plate 72 is movably installed outside the movable sleeve 71, the movable plate 72 is arranged in a rectangular shape, the front surface of the movable plate 72 is provided with the through hole 73, the bolt 74 is fixedly installed inside the through hole 73, the first partition plate 4 and the second partition plate 6 can be effectively limited by the limiting component 7, the bottom of the installation box 8 is fixedly provided with a heat recovery component 3, the heat recovery component 3 comprises a connection box 31, a first filter screen 32, a second filter screen 33, a fan 34, a communication pipe 35 and a recovery box 36, the inside of the connection box 31 is respectively provided with the first filter screen 32 and the second filter screen 33 from top to bottom, the first filter screen 32 is a filter screen made of HPEA material, the second filter screen 33 is made of activated carbon material, and the bottom of, one side through connection of joint box 31 has communicating pipe 35, the other end of communicating pipe 35 runs through the inside of collection box 36, inhale the joint box 31 from install bin 8 through the inside fan 34 of joint box 31 with the produced heat of 5G network hardware equipment, can effectually collect the heat and carry out heat recovery and utilize in entering into collection box 36 through communicating pipe 35, the feature of environmental protection is high, avoid extravagant, and be provided with first filter screen 32 and second filter screen 33 in the joint box 31, impurity that can exist in the effectual filtered air.
The utility model discloses a theory of operation is: when the cable assembly is used, the cable assemblies 2 are arranged on two sides above the first partition plate 4 and the second partition plate 6, when 5G network hardware equipment is placed on the first partition plate 4 and the second partition plate 6, the springs 25 in the cable assemblies 2 are extruded to deform, so that an opposite force is generated to enable the first fixing plate 21 and the limiting buckle 23 arranged on one side of the springs 25 to extrude and fix the 5G network hardware equipment, the two ends of the limiting buckle 23 are provided with the protective layers 22, the protective layers 22 can protect the 5G network hardware equipment and prevent the 5G network hardware equipment from scratching, when the 5G network hardware equipment is linearly connected, wires of the 5G network hardware equipment are arranged in a limiting and orderly mode through the limiting buckle 23, the cable assemblies 2 are arranged in the horizontal direction of the inner wall of the installation box 8, and the wires used by the 5G network hardware equipment can be reasonably distributed through the cable assemblies 2, the time of carding wires by managers is accelerated, the working efficiency of the wire carding machine is effectively improved, when 5G network hardware equipment is damaged, the first partition plate 4 and the second partition plate 6 are drawn out in the installation box 8, namely, a sliding groove is formed in the inner wall of the installation box 8, sliding blocks are arranged on two sides of the first partition plate 4 and the second partition plate 6, the first partition plate 4 and the second partition plate 6 are drawn out through the sliding of the sliding blocks in the sliding groove, so that the 5G network hardware equipment is detected and maintained more quickly, the maintained 5G network hardware equipment is put into the first partition plate 4 and the second partition plate 6 again, the first partition plate 4 and the second partition plate 6 are pushed into the installation box 8, then the movable plate 72 is rotated on the movable sleeve 71, so that the movable plate 72 and the first partition plate 4 and the second partition plate 6 are horizontally placed, and the bolt 74 is screwed down, so that the first partition plate 4 and the second partition plate 6 are effectively fixed, the 5G network hardware equipment on the first partition plate 4 and the second partition plate 6 can be conveniently and rapidly detected and maintained through the arrangement of the limiting assembly 7, when the 5G network hardware equipment works, large heat can be generated, the connecting holes 5 are formed in the first partition plate 4 and the second partition plate 6, the fan 34 in the connecting box 31 arranged at the bottom of the installation box 8 works, so that the heat generated by the 5G network hardware equipment is sucked into the connecting box 31 from the connecting holes 5, the first filter screen 32 and the second filter screen 33 are arranged in the connecting box 31, air entering the connecting box 31 firstly passes through the first filter screen 32 and the second filter screen 33 due to the suction force of the fan 34, thereby impurities in the air can be effectively removed and filtered, the filtered gas with the heat enters the recovery box 36 from the communicating pipe 35, and the recovery box 36 can recycle the heat, the environmental protection performance is high, avoids the waste of heat loss.
The above-mentioned, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. The utility model provides a novel 5G system installation equipment, includes install bin (8), its characterized in that, the top fixed mounting of install bin (8) has rain-proof cover (1), and the inside from the top down respectively the activity of install bin (8) is provided with second baffle (6) and first baffle (4), connecting hole (5) have been seted up to the upper surface of second baffle (6) and first baffle (4), the inner wall of install bin (8) is close to the top fixed mounting of second baffle (6) and first baffle (4) has winding displacement subassembly (2), and the front surface of install bin (8) is provided with spacing subassembly (7), the bottom fixed mounting of install bin (8) has heat recovery subassembly (3).
2. The novel 5G system installation device according to claim 1, wherein the flat cable assembly (2) comprises a first fixing plate (21), a protective layer (22), a second fixing plate (24) and a spring (25), two ends of the spring (25) are respectively embedded in the first fixing plate (21) and the second fixing plate (24), one side of the first fixing plate (21) is connected with a limiting buckle (23), and the protective layer (22) is fixedly installed at an opening of the limiting buckle (23).
3. The novel 5G system installation device as claimed in claim 2, wherein the limiting buckle (23) is in a semicircular arrangement, and the protective layer (22) is made of sponge material.
4. The novel 5G system installation device according to claim 1, wherein the limiting assembly (7) comprises a movable sleeve (71), a movable plate (72), a through hole (73) and a bolt (74), the movable plate (72) is movably installed outside the movable sleeve (71), the through hole (73) is formed in the front surface of the movable plate (72), and the bolt (74) is fixedly installed inside the through hole (73).
5. The new 5G system installation apparatus according to claim 4, wherein the movable plate (72) is rectangular in shape.
6. The novel 5G system installation device according to claim 1, wherein the heat recovery assembly (3) comprises a connection box (31), a first filter screen (32), a second filter screen (33), a fan (34), a communication pipe (35) and a recovery box (36), the first filter screen (32) and the second filter screen (33) are respectively arranged in the connection box (31) from top to bottom, the fan (34) is fixedly installed at the bottom of the connection box (31), the communication pipe (35) is connected to one side of the connection box (31) in a penetrating manner, and the other end of the communication pipe (35) penetrates through the interior of the recovery box (36).
7. The novel 5G system installation device as claimed in claim 6, wherein the first filter (32) is a filter of HPEA material, and the second filter (33) is a filter of activated carbon material.
CN201921523820.3U 2019-09-13 2019-09-13 Novel 5G system installation equipment Expired - Fee Related CN210491476U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921523820.3U CN210491476U (en) 2019-09-13 2019-09-13 Novel 5G system installation equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921523820.3U CN210491476U (en) 2019-09-13 2019-09-13 Novel 5G system installation equipment

Publications (1)

Publication Number Publication Date
CN210491476U true CN210491476U (en) 2020-05-08

Family

ID=70540123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921523820.3U Expired - Fee Related CN210491476U (en) 2019-09-13 2019-09-13 Novel 5G system installation equipment

Country Status (1)

Country Link
CN (1) CN210491476U (en)

Similar Documents

Publication Publication Date Title
CN217241010U (en) Anti-static dust removal structure of electrical control cabinet
CN105924837A (en) Environment-friendly data cable
CN210491476U (en) Novel 5G system installation equipment
CN209913446U (en) Quick heat dissipation type bus duct
CN209845618U (en) Outdoor electronic information synchronous transmission wind power heat extraction device structure
CN214202121U (en) Internet of things controller based on wisdom agriculture
CN212753078U (en) Lightning protection device for collection station
CN210468494U (en) Dustproof distribution box
CN211017900U (en) Low-voltage outdoor distribution box with dustproof heat dissipation function
CN218487255U (en) Perforating device is used in processing of aluminum alloy chute
CN208529043U (en) A kind of electrical equipment installation tool puts in order trolley
CN209981824U (en) Power equipment box with dampproofing dust absorption function
CN220363242U (en) Protection device of new forms of energy fills electric pile
CN218549092U (en) Safety protection device
CN211531484U (en) Communication equipment box
CN218223982U (en) Recovery equipment for cyclone dust removal environment-friendly device
CN217306880U (en) Lightning protection earth connection auxiliary device among water and electricity installation engineering
CN214207765U (en) Assembled film and television wall placing cabinet assembling structure
CN211529795U (en) Medium-voltage power capacitor
CN213834101U (en) Terminal equipment for intelligent ladder resistance management and control system
CN218049566U (en) Dust keeper for die bonder
CN214851945U (en) Protection device structure with TVS/ESD
CN211127597U (en) Photovoltaic inverter mounting structure
CN215645786U (en) Novel multifunctional box-type substation
CN216010096U (en) Photovoltaic power plant is with wisdom efficiency monitoring system based on thing networking

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200508

Termination date: 20200913