CN210486550U CN201921543691.4U CN201921543691U CN210486550U CN 210486550 U CN210486550 U CN 210486550U CN 201921543691 U CN201921543691 U CN 201921543691U CN 210486550 U CN210486550 U CN 210486550U
Authority
CN
China
Prior art keywords
condensation
fixed
condenser
groups
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921543691.4U
Other languages
Chinese (zh)
Inventor
蔡章吉
周镔彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Jinlai Chemical Co.,Ltd.
Original Assignee
Ningbo Jinlai Chemical Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Jinlai Chemical Co ltd filed Critical Ningbo Jinlai Chemical Co ltd
Priority to CN201921543691.4U priority Critical patent/CN210486550U/en
Application granted granted Critical
Publication of CN210486550U publication Critical patent/CN210486550U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Vaporization, Distillation, Condensation, Sublimation, And Cold Traps (AREA)

Abstract

The utility model discloses a refining tower condenser, including going out water condensation pipe case and water inlet condensation pipe case, the delivery port has been seted up to the left end of going out water condensation pipe case, the inside of delivery port is inserted and is equipped with out the water pipe, the bottom mounting welding of going out water condensation pipe case has the vacuum chamber, all fixed welding has fixed baffling board, three groups on the left and right sides inner wall of vacuum chamber fixed slot has all been seted up to the inside of fixed baffling board. This refining tower condenser is through the one-way rotation nature of rotating the door, make unnecessary rivers can not flow back, the rivers that make the entering that can be good through two devices can not flow back and lead to the exterior structure to damage, it is simple and convenient, install on the condensation nozzle stub through adding the multiunit conducting strip, and under the combined action of the water conservancy diversion baffling board that two sets of upper end outside fixed of condensation nozzle stub have the capillary groove, condensation nozzle stub and gaseous area of contact has been increased, thereby condensation effect has been improved, the cooling time has been shortened.

Description

Refining tower condenser
Technical Field
The utility model relates to an anchor clamps technical field specifically is refining tower condenser.
Background
The refining tower is widely used for distilling and purifying substances, when a factory needs purer substances, the factory needs to evaporate liquid substances into gas through high temperature through the refining tower to take out impurities, and then the gas is liquefied into purer liquid when meeting cold.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a refining tower condenser to solve traditional condenser that proposes in the above-mentioned background art when the high temperature gas heat absorption liquefaction, the scope of ability radiation is less, leads to the effect of condensation to reduce, makes the time of condensation lengthen, and the condenser still can lead to the problem that the condition of liquid reflux takes place after intaking.
In order to achieve the above object, the utility model provides a following technical scheme: the refining tower condenser comprises a water outlet condenser pipe box and a water inlet condenser pipe box, wherein a water outlet is formed in the left end of the water outlet condenser pipe box, a water outlet guide pipe is inserted into the water outlet, a vacuum chamber is fixedly welded at the bottom end of the water outlet condenser pipe box, fixed baffle plates are fixedly welded on the inner walls of the left side and the right side of the vacuum chamber, three groups of fixed baffle plates are fixedly inserted into the fixed baffle plates, a condensation guide pipe is fixedly inserted into the fixed slot, two groups of condensation guide pipes penetrate through a condensation short pipe fixedly connected to the bottom end of the vacuum chamber, a guide baffle plate is fixedly connected to the outer portion of the top end of the condensation short pipe, slots are formed in the bottom end of the condensation short pipe, nine groups of heat-conducting fins are inserted into the slots, a water inlet condenser pipe box is fixedly welded at the right end of the water outlet condenser pipe box, a water inlet is formed The slotted hole has been seted up to the bottom of pipe of intaking, the inside of slotted hole is inserted and is equipped with the depression bar, the fixed welding in bottom of depression bar has the preforming, the spring has been cup jointed to the outside of depression bar, the top of depression bar is fixed with sealed dish, all fixed welding has the fixed block on the upper and lower both ends inner wall of pipe of intaking, and is two sets of the inboard of fixed block all is fixed with the torsion spring shell, the inside all fixed mounting of torsion spring shell has torsion spring, and is two sets of torsion spring's one end is all fixed in the inside of fixed block, and the other end all fixes in the inside of revolving door.
Preferably, the pipe body of the condensation short pipe is U-shaped.
Preferably, three groups of fixed baffles are distributed on the inner walls of the two sides of the vacuum chamber in a staggered manner.
Preferably, the bottoms of the two groups of flow guide baffle plates are provided with capillary grooves.
Preferably, the length of the part of the nine groups of heat-conducting fins extending into the condensation short pipes is less than half of the length of the inner diameter of the condensation short pipes.
Preferably, the left ends of the two groups of fixed blocks are fixedly provided with limit blocks.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this refined tower condenser is provided with out water condenser pipe case and water inlet condenser pipe case, when carrying out work, pour into water from the water inlet, rivers open the turngate and flow in, will seal a dish top and flow in, after the rivers entering of capacity seal a dish, seal a dish can reconversion and seal the pipe body, prevent the backward flow, still remaining rivers can flow back, but the one-way rotation nature through the turngate, make unnecessary rivers can not flow back, rivers that make the entering that can be good through two devices can not flow back and lead to the exterior structure damage, and is simple and convenient.
2. This refined tower condenser is when rivers get into water condensation pipe case, during rivers got into the condensation nozzle stub through the condensation honeycomb duct, through installing multiunit conducting strip additional on the condensation nozzle stub to and under the combined action of the water conservancy diversion baffling board that two groups that the upper end outside of condensation nozzle stub was fixed have the capillary groove, increased the area of contact of condensation nozzle stub with gas, thereby improved the condensation effect, shortened cool time.
Drawings
FIG. 1 is a schematic sectional view of the front view of the structure of the present invention;
fig. 2 is an enlarged schematic structural view of a portion a in fig. 1 according to the present invention;
fig. 3 is an enlarged schematic structural diagram of a portion B in fig. 1 according to the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides an embodiment: the refining tower condenser comprises a water outlet condenser box 1 and a water inlet condenser box 2, wherein the left end of the water outlet condenser box 1 is provided with a water outlet 23, a water outlet guide pipe 24 is inserted into the water outlet 23, the bottom end of the water outlet condenser box 1 is fixedly welded with a vacuum chamber 3, the inner walls of the left side and the right side of the vacuum chamber 3 are fixedly welded with fixed baffle plates 4, three groups of fixed baffle plates 4 are distributed on the inner walls of the two sides of the vacuum chamber 3 in a staggered manner, so that the whole structure is more stable, the inner parts of the three groups of fixed baffle plates 4 are provided with fixed slots 5, the inner parts of the fixed slots 5 are fixedly inserted with condensation guide pipes 6, two groups of condensation guide pipes 6 penetrate through the bottom end of the vacuum chamber 3 and are fixedly connected with condensation short pipes 7, the pipe bodies of the condensation short pipes 7 are U-shaped, so, the bottoms of the two groups of flow guide baffle plates 8 are provided with capillary grooves 22, the area of a condensation part is enlarged through the capillary grooves 22, the bottom pipe body of the condensation short pipe 7 is provided with slots 9, the inside of the nine groups of slots 9 is inserted with heat conducting fins 10, the length of the part of the nine groups of heat conducting fins 10 extending into the condensation short pipe 7 is less than half of the length of the inner diameter of the condensation short pipe 7, when a better condensation effect is achieved, the right end of the condensation short pipe 7, which is provided with a water inlet condensation pipe box 1, is prevented from being blocked by the heat conducting fins 10 extending into the condensation short pipe 7 too long, is fixedly welded with a water inlet condensation pipe box 2, the inner side of the right end of the water inlet condensation box 2, which is provided with a water inlet 11 and a water outlet 23, is inserted with a bottom end of a water inlet pipe 12, which is provided with a slotted hole 13, a screw rod, the top of the screw rod 14 is fixed with the sealed dish 16, all fixed welding has the fixed block 17 on the upper and lower both ends inner wall of intake pipe 12, the left end of two sets of fixed blocks 17 all fixed mounting has stopper 19, prevent that the rivers impact force from leading to the big revolving door 21 directly to hit and cause the damage on the pipe wall of intake pipe 12, the guard action is provided, the inboard of two sets of fixed blocks 17 all is fixed with torsion spring shell 18, the inside of torsion spring shell 18 all fixed mounting has torsion spring 20, the inside at fixed block 17 is all fixed to the one end of two sets of torsion spring 20, the other end all is fixed in the inside of revolving door 21.
The working principle is as follows: this refined tower condenser is when carrying out the during operation, at first water is poured into from water inlet 11, rivers are opened the turngate 21 and are flowed in, will seal a dish 16 and push up and flow in, after sufficient rivers get into sealed dish 16, sealed dish 16 can the reconversion and seal the body, prevent the backward flow, still remaining rivers can flow back, but through the one-way rotation nature of turngate 21, make unnecessary rivers can not flow back, the rivers that make the entering that can be good through two devices can not flow back and lead to the exterior structure damage, and is simple and convenient.
This refined tower condenser is when rivers get into water condensation pipe case 2, rivers pass through condensation honeycomb duct 6 and get into condensation nozzle stub 7, install additional on condensation nozzle stub 7 through with multiunit conducting strip 10 to and under the combined action of two sets of water conservancy diversion baffling boards 8 that have capillary 22 of the upper end external fixation of condensation nozzle stub 7, increased the area of contact of condensation nozzle stub 7 with gas, thereby improved the condensation effect, shortened cooling time, the operation is to this end.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. Refining tower condenser is including going out water condenser pipe case (1) and intaking condenser pipe case (2), its characterized in that: a water outlet (23) is formed in the left end of the water outlet condenser pipe box (1), water outlet guide pipes (24) are inserted into the water outlet (23), a vacuum chamber (3) is fixedly welded at the bottom end of the water outlet condenser pipe box (1), fixed baffle plates (4) are fixedly welded on the inner walls of the left side and the right side of the vacuum chamber (3), three groups of fixed baffle plates (4) are provided with fixed slots (5), condensation guide pipes (6) are fixedly inserted into the fixed slots (5), two groups of condensation guide pipes (6) penetrate through the bottom end of the vacuum chamber (3) and are fixedly connected with condensation short pipes (7), the exterior of the top end of each condensation short pipe (7) is fixedly connected with a flow guide baffle plate (8), slots (9) are formed in the bottom end pipe bodies of the condensation short pipes (7), and heat-conducting fins (10) are inserted into the nine groups of slots (9), the water inlet condenser pipe box is characterized in that a water inlet condenser pipe box (2) is fixedly welded at the right end of the water outlet condenser pipe box (1), a water inlet (11) is formed in the right end of the water inlet condenser pipe box (2), a water inlet guide pipe (12) is inserted into the inner side of a water outlet (23), a slotted hole (13) is formed in the bottom end of the water inlet guide pipe (12), a screw rod (14) is inserted into the slotted hole (13), a screw pressing plate (15) is fixedly welded at the bottom of the screw rod (14), a spring (25) is sleeved outside the screw rod (14), a sealing disc (16) is fixed at the top end of the screw rod (14), fixed blocks (17) are fixedly welded on the inner walls of the upper end and the lower end of the water inlet guide pipe (12), two sets of torsion spring shells (18) are fixedly arranged on the inner sides of the fixed blocks (17), and torsion springs, one end of each of the two groups of torsion springs (20) is fixed inside the fixed block (17), and the other end of each of the two groups of torsion springs is fixed inside the rotating door (21).
2. The finishing column condenser of claim 1, wherein: the pipe body of the condensation short pipe (7) is U-shaped.
3. The finishing column condenser of claim 1, wherein: the three groups of fixed baffle plates (4) are distributed on the inner walls of the two sides of the vacuum chamber (3) in a staggered manner.
4. The finishing column condenser of claim 1, wherein: the bottoms of the two groups of the diversion baffle plates (8) are provided with capillary grooves (22).
5. The finishing column condenser of claim 1, wherein: the length of the part of the nine groups of heat-conducting fins (10) extending into the condensing short pipe (7) is less than half of the length of the inner diameter of the condensing short pipe (7).
6. The finishing column condenser of claim 1, wherein: and the left ends of the two groups of fixed blocks (17) are fixedly provided with limit blocks (19).
CN201921543691.4U 2019-09-17 2019-09-17 Refining tower condenser Active CN210486550U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921543691.4U CN210486550U (en) 2019-09-17 2019-09-17 Refining tower condenser

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921543691.4U CN210486550U (en) 2019-09-17 2019-09-17 Refining tower condenser

Publications (1)

Publication Number Publication Date
CN210486550U true CN210486550U (en) 2020-05-08

Family

ID=70540452

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921543691.4U Active CN210486550U (en) 2019-09-17 2019-09-17 Refining tower condenser

Country Status (1)

Country Link
CN (1) CN210486550U (en)

Similar Documents

Publication Publication Date Title
CN106766391A (en) For the tank-type heat exchanger of heat pump
CN112344365A (en) Boiler combustion furnace flue gas environmental protection and energy saving recovery unit
CN210486550U (en) Refining tower condenser
CN211345938U (en) Heat exchanger assembly, falling film heat exchanger and heat pump unit
CN213120221U (en) Heat pipe cooler
CN212006187U (en) Falling film evaporator for refrigeration air conditioner
CN205561272U (en) Water heater heat exchanger
CN111313122B (en) Battery thermal management and thermal safety protection device based on vibration enhancement
CN208865390U (en) A kind of lower resistance removes oil cooler
CN202744480U (en) Heat exchanger of low-bromine epoxy resin reaction kettle
CN206192157U (en) Novel waste heat of boiler flue gas recoverer
CN216790578U (en) Shell and tube condenser
CN216132301U (en) Gas condenser
CN219757062U (en) Steam waste heat recovery device
CN215864764U (en) Jacketed condenser
CN221051577U (en) Gas condensing device for solid oxide electrolytic cell hydrogen production system
CN214223852U (en) Pharmacy workshop steam cyclic utilization device
CN213901555U (en) Full aluminum alloy refrigeration evaporator
CN218120685U (en) High-efficiency condenser
CN219231440U (en) Progressive graphite sulfuric acid preparation evaporation concentration device
CN217155063U (en) Novel heat exchanger with liquid storage function
CN217736910U (en) Multilayer type heat-insulation fireproof leakage-prevention liquid hydrogen energy large-capacity storage device
CN211290634U (en) High-energy-efficiency window-opening evaporator
CN210980865U (en) Condenser for waste water evaporation
CN217988883U (en) Cooler in air drying system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 6 Guangxing Road, Binhai Industrial Park, xiaocao'e Town, Yuyao City, Ningbo City, Zhejiang Province

Patentee after: Ningbo Jinlai Chemical Co.,Ltd.

Address before: 6 Guangxing Road, Binhai Industrial Park, xiaocao'e Town, Yuyao City, Ningbo City, Zhejiang Province

Patentee before: NINGBO JINLAI CHEMICAL Co.,Ltd.