CN210419023U CN201921411007.7U CN201921411007U CN210419023U CN 210419023 U CN210419023 U CN 210419023U CN 201921411007 U CN201921411007 U CN 201921411007U CN 210419023 U CN210419023 U CN 210419023U
Authority
CN
China
Prior art keywords
tower crane
screw
crane standard
connecting bolt
nut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921411007.7U
Other languages
Chinese (zh)
Inventor
赵豹
朱秀密
黄用兵
张文超
王成华
朱旭
周奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Shuishui Shun'an Hoisting Equipment Installation Co Ltd
Anhui Water Resources Development Co Ltd
Original Assignee
Anhui Shuishui Shun'an Hoisting Equipment Installation Co Ltd
Anhui Water Resources Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Shuishui Shun'an Hoisting Equipment Installation Co Ltd, Anhui Water Resources Development Co Ltd filed Critical Anhui Shuishui Shun'an Hoisting Equipment Installation Co Ltd
Priority to CN201921411007.7U priority Critical patent/CN210419023U/en
Application granted granted Critical
Publication of CN210419023U publication Critical patent/CN210419023U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a tower crane standard festival straightness guide fixed knot that hangs down constructs, tower crane standard festival upper and lower part is equipped with a plurality of connecting sleeves respectively, and every connecting sleeve constitutes a set of connecting sleeve with the corresponding connecting sleeve of its adjacent tower crane standard festival, and a plurality of connecting bolts and a plurality of sets of connecting sleeves are one-to-one, and when the tower crane needs to rise from the rising to add, connecting bolts run through a set of connecting sleeve of two adjacent tower crane standard festival; the connecting bolt comprises a screw and at least one nut, the end part of the screw of the connecting bolt extends out of the outer side of the corresponding group of connecting sleeves, the end part of the screw of the connecting bolt is in a frustum shape, and the screw is matched with the nut. The technology of aligning the holes of the connecting sleeve of the standard joint by using the cone of the connecting bolt induces the holes of the connecting sleeve of the standard joint, the working efficiency of tower crane installation is improved greatly, and the accident potential caused by the problems of crane arm balance adjustment and rotation in the installation process is reduced.

Description

Tower crane standard festival straightness guide fixed knot that hangs down constructs
Technical Field
The utility model relates to a tower crane standard festival straightness guide fixed knot that hangs down constructs.
Background
The tower crane is the most common hoisting equipment on the building site, the tower crane standard knot is the basic component for building the tower crane, and at present, in the special equipment tower crane installation and disassembly operation of the building site, the tower crane standard knot needs to be hoisted and superposed, and the upper and lower two tower crane standard knots need to be aligned and fixed when being installed. However, when the existing tower crane standard knot is installed, eyelets of connecting sleeves of an upper adjacent tower crane standard knot and a lower adjacent tower crane standard knot are often misaligned, especially after the last standard knot is installed, eyelets of the upper sleeve and the lower sleeve cannot be completely aligned when a lower support of a slewing mechanism is connected with the standard knot, installers often operate against regulations, and the slewing action is utilized to level and align back and forth, so that danger is generated, and the working efficiency is greatly reduced.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that a tower crane standard festival straightness guide fixed knot that hangs down of simple structure, convenient to use is provided.
In order to solve the technical problem, the utility model provides a tower crane standard knot verticality guiding and fixing structure, wherein a plurality of connecting sleeves are respectively arranged at the upper part and the lower part of a tower crane standard knot, each connecting sleeve and the corresponding connecting sleeve of the adjacent tower crane standard knot form a group of connecting sleeves, a plurality of connecting bolts and a plurality of groups of connecting sleeves are in one-to-one correspondence, and when a tower crane needs to be lifted and added, the connecting bolts penetrate through a group of connecting sleeves of two adjacent tower crane standard knots;
the connecting bolt comprises a screw and at least one nut, the end part of the screw of the connecting bolt extends out of the outer side of the corresponding group of connecting sleeves, the end part of the screw of the connecting bolt is in a frustum shape, and the screw is matched with the nut.
After adopting such a structure, when the introduced standard knot is basically vertical to the lower tower body standard knot, the eyelets of the upper and lower connecting sleeves are basically aligned, and at the moment, a worker inserts the connecting bolt into the connecting sleeve and lightly beats the connecting bolt to enable the connecting bolt to quickly penetrate through the eyelets of each group of two connecting sleeves. Particularly, after the last standard knot is installed, the eyelets of the upper sleeve and the lower sleeve cannot be completely centered when the lower support of the rotary mechanism is connected with the standard knot, and the illegal operation that the alignment of the eyelets of the connecting sleeves is adjusted by using a rotary crane boom under the common condition is avoided. The technology of aligning the holes of the connecting sleeve of the standard joint by using the cone of the connecting bolt induces the holes of the connecting sleeve of the standard joint, the working efficiency of tower crane installation is improved greatly, and the accident potential caused by the problems of crane arm balance adjustment and rotation in the installation process is reduced.
The connecting bolt of the tower crane standard knot verticality guiding and fixing structure comprises two nuts, wherein the two nuts are respectively a locking nut and an anti-skidding nut, the locking nut is matched with a screw rod of the connecting bolt, the locking nut is abutted against a corresponding connecting sleeve, the anti-skidding nut is matched with the screw rod of the connecting bolt, and the anti-skidding nut is abutted against the locking nut; after adopting such structure, the antiskid nut can slow down lock nut and take place not hard up situation when daily use, increases this tower crane standard festival straightness guide fixed knot structure security of hanging down.
The side wall of each connecting sleeve of the tower crane standard knot verticality guiding and fixing structure is provided with a limiting pin shaft hole along the radial direction, the side wall of each connecting bolt is provided with a kidney-shaped hole, each U-shaped stud bolt comprises a stud bolt and two nuts, two end parts of the stud bolt of each U-shaped stud bolt respectively penetrate through the limiting pin shaft holes of each group of two connecting sleeves and the kidney-shaped hole of each connecting bolt, and the stud bolts are respectively matched with the two nuts; after adopting such structure, U-shaped stud runs through connecting sleeve and connecting bolt respectively and locks the two once more, further increases the fixity that two tower crane standard festival connect, promotes the security.
Drawings
FIG. 1 is a schematic structural diagram of one of the tower crane standard knot perpendicularity guiding and fixing structure embodiments.
Fig. 2 is a cross-sectional view of an enlarged view of a portion a of fig. 1.
Fig. 3 is a structural schematic diagram of the second of this tower crane standard festival straightness guide fixed knot structure embodiment.
Fig. 4 is a cross-sectional view of an enlarged view of a portion B of fig. 3.
FIG. 5 is a schematic diagram of two connecting bolts of this tower crane standard festival straightness guide fixed knot constructs embodiment.
Detailed Description
Example one
As shown in fig. 1 to 2
This tower crane standard festival straightness guide fixed knot that hangs down has four connecting sleeve 11 in tower crane standard festival 1 upper and lower part welding respectively, eight connecting sleeve 11 distribute in tower crane standard festival 1 inboardly, four connecting sleeve 11 of the upper and lower side are the rectangle form respectively and distribute in tower crane standard festival 1, every connecting sleeve 11 constitutes a set of connecting sleeve 11 with the corresponding connecting sleeve 11 of its adjacent tower crane standard festival 1, a plurality of connecting bolt are the one-to-one with a plurality of group connecting sleeve 11, connecting bolt runs through a set of connecting sleeve 11 of two adjacent tower crane standard festival 1.
The connecting bolt comprises a screw 12a and two nuts, the end of the screw 12a of the connecting bolt extends out of the corresponding group of connecting sleeves 11, the end of the screw 12a of the connecting bolt is in a frustum shape, the two nuts are respectively a locking nut 12b and an anti-slip nut 12c, the locking nut 12b is matched with the screw 12a of the connecting bolt, the locking nut 12b is abutted against the corresponding connecting sleeve 11, the anti-slip nut 12c is matched with the screw 12a of the connecting bolt, and the anti-slip nut 12c is abutted against the locking nut 12 b.
Before the tower crane is lifted, the sensing data of the balance sensor is transmitted to a display screen of a cab, a tower crane driver collects balance data and adjusts the counterweight of the luffing trolley according to the balance data, and the aim of quickly adjusting the balance of a crane boom is fulfilled.
The eyelets of the connecting sleeve 11 of the introduced tower crane standard knot 1 and the tower crane standard knot 1 below are basically aligned, but original flat head bolts cannot penetrate through the eyelets, at the moment, an installer can insert the connecting bolts into the eyelets of the connecting sleeve 11, the connecting bolts can be used for forcibly knocking the screw rods 12a of the connecting bolts to be completely inserted into the eyelets of the connecting sleeve 11, the connecting bolts are used for inducing the connecting sleeve 11 of the upper tower crane standard knot 1 and the lower tower crane standard knot 1 to be vertically aligned, therefore, the eyelets of the connecting sleeve 11 can be quickly aligned for normal operation, and serious accidents of tower crane overturn caused by large arm unbalance are avoided.
Example two
As shown in fig. 3 to 5
The present embodiment differs from the embodiments only in that: this tower crane standard festival straightness guide fixed knot that hangs down still includes U-shaped stud, and U-shaped stud includes threaded stud 13a and two nuts 13b, and threaded stud 13a is the U-shaped structure, and threaded stud 13a both sides tip is parallel to each other.
The side wall of each connecting sleeve 11 is provided with a limiting pin shaft hole 11a along the radial direction, the diameter of a stud 13a of each U-shaped stud is slightly smaller than the aperture of the limiting pin shaft hole 11a, the side wall of each connecting bolt 12a is provided with a waist-shaped hole 12d, and the length of each waist-shaped hole 12d is larger than the maximum distance between two end parts of the stud 13 a.
Two ends of a stud 13a of the U-shaped stud respectively penetrate through the limiting pin shaft holes 11a of each group of two connecting sleeves 11 of two adjacent tower crane standard sections 1 and the kidney-shaped holes 12d of the connecting bolts 12a, and the stud 13a is respectively matched with two nuts 13 b.
The above description is only one embodiment of the present invention, and it should be noted that, for those skilled in the art, a plurality of modifications and improvements can be made without departing from the principle of the present invention, and these should also be considered as belonging to the protection scope of the present invention.

Claims (3)

1. A tower crane standard knot verticality guiding and fixing structure is characterized in that a plurality of connecting sleeves are respectively arranged on the upper portion and the lower portion of a tower crane standard knot, each connecting sleeve and a corresponding connecting sleeve of an adjacent tower crane standard knot form a group of connecting sleeves, a plurality of connecting bolts are in one-to-one correspondence with the plurality of groups of connecting sleeves, and when a tower crane needs self-elevating and knot-adding, the connecting bolts penetrate through the group of connecting sleeves of the two adjacent tower crane standard knots;
it is characterized in that:
the connecting bolt comprises a screw and at least one nut, the end part of the screw of the connecting bolt extends out of the outer side of the corresponding group of connecting sleeves, the end part of the screw of the connecting bolt is in a frustum shape, and the screw is matched with the nut.
2. The tower crane standard knot verticality guiding and fixing structure of claim 1, which is characterized in that:
the connecting bolt comprises two nuts, the two nuts are respectively a locking nut and an anti-slip nut, the locking nut is matched with a screw rod of the connecting bolt, the locking nut is abutted against the corresponding connecting sleeve, the anti-slip nut is matched with the screw rod of the connecting bolt, and the anti-slip nut is abutted against the locking nut.
3. The tower crane standard knot verticality guiding and fixing structure of claim 1, which is characterized in that:
every connecting sleeve lateral wall is opened along its radial direction has spacing round pin shaft hole, and the connecting bolt lateral wall is opened there is waist type hole, and U-shaped stud includes threaded stud and two nuts, and two threaded stud both ends of U-shaped stud run through two connecting sleeve's of every group spacing round pin shaft hole and connecting bolt's waist type hole respectively to threaded stud cooperates with two nuts respectively.
CN201921411007.7U 2019-08-28 2019-08-28 Tower crane standard festival straightness guide fixed knot that hangs down constructs Active CN210419023U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921411007.7U CN210419023U (en) 2019-08-28 2019-08-28 Tower crane standard festival straightness guide fixed knot that hangs down constructs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921411007.7U CN210419023U (en) 2019-08-28 2019-08-28 Tower crane standard festival straightness guide fixed knot that hangs down constructs

Publications (1)

Publication Number Publication Date
CN210419023U true CN210419023U (en) 2020-04-28

Family

ID=70364830

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921411007.7U Active CN210419023U (en) 2019-08-28 2019-08-28 Tower crane standard festival straightness guide fixed knot that hangs down constructs

Country Status (1)

Country Link
CN (1) CN210419023U (en)

Similar Documents

Publication Publication Date Title
CN105858435A (en) Technology for hoisting strip-shaped inclined steel structures in place through single crane
CN101712436B (en) Steel truss hoisting tool
CN210419023U (en) Tower crane standard festival straightness guide fixed knot that hangs down constructs
CN203877731U (en) Hoisting and dragging device used in PHC (Pre-stress High-strength Concrete) pipe pile construction site
CN202252699U (en) Elevating rotary installation frame
CN109019371B (en) Turnover supporting device and tower crane climbing method
CN201247939Y (en) Anti-dance weight dropper of high voltage overhead transmission line
CN107758528A (en) Based on the method for improving dismounting safety of tower crane
CN211691536U (en) Simple lifting mechanism for bare concrete exterior wall cladding
CN204355947U (en) Large-scale without eye plate lifting beam device
CN205422583U (en) Lifting hook, hang assembly and hang hoisting accessory
CN205565514U (en) Change specialized tool of overhead earth wire suspension clamp and gold utensil
CN204355942U (en) For the suspension centre adjustable carrying pole beam construction of prefabricated panel lifting
CN112390171A (en) Hydraulic creeping formwork and chamfering formwork suspension mechanism thereof
CN105703271A (en) Special tool for replacing overhead ground wire suspension clamp and hardware fitting
CN214834649U (en) Safety protection structure for installing or dismantling outer frame
CN207030731U (en) A kind of more cabin piping lane adjustable horizontal boom hoistings
CN211594738U (en) Hoisting point device
CN206591845U (en) Suitable for the safety belt suspension device of scaffold
CN205034968U (en) Steel strand wires hoist and mount connecting tool
CN216235557U (en) Tower crane mark festival hoist of convenient operation formula
CN210418968U (en) T-shaped shed hoisting and fixing device
CN211622526U (en) Attached cantilever beam
CN107253677A (en) A kind of firm engineering tower crane of underframe
CN107244606A (en) A kind of many cabin piping lane adjustable horizontal boom hoistings

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant