CN210395712U - Assembled integral window frame wall - Google Patents

Assembled integral window frame wall Download PDF

Info

Publication number
CN210395712U
CN210395712U CN201920655243.7U CN201920655243U CN210395712U CN 210395712 U CN210395712 U CN 210395712U CN 201920655243 U CN201920655243 U CN 201920655243U CN 210395712 U CN210395712 U CN 210395712U
Authority
CN
China
Prior art keywords
wall body
window
window frame
upright posts
cross beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920655243.7U
Other languages
Chinese (zh)
Inventor
李忠辉
高军
李培奎
黄飞
田兆明
纪东昌
崔晓明
许爱华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rizhao Xingye Real Estate Development Co Ltd
Original Assignee
Rizhao Xingye Real Estate Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rizhao Xingye Real Estate Development Co Ltd filed Critical Rizhao Xingye Real Estate Development Co Ltd
Priority to CN201920655243.7U priority Critical patent/CN210395712U/en
Application granted granted Critical
Publication of CN210395712U publication Critical patent/CN210395712U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Door And Window Frames Mounted To Openings (AREA)

Abstract

An assembled integral window frame wall relates to the technical field of building construction, in particular to an assembled integral window frame wall. The window frame is formed by pouring upright posts and cross beams between the upright posts, each cross beam comprises an upper cross beam and a lower cross beam, a window lower wall body is poured between the upper cross beam and the lower cross beam, the window lower wall body is formed by pouring heat-insulation composite plates, fine stone concrete internally provided with bidirectional reinforcing mesh sheets, extruded polystyrene boards and fine stone concrete internally provided with the bidirectional reinforcing mesh sheets in sequence in the transition direction from the outdoor side to the indoor side, tongue-and-grooves are formed in the opposite sides of the upright posts, the upper cross beams and the window body, anchoring reinforcing steel bars extending to the concrete wall body at the part to be filled in a construction site are pre-buried in the upright posts, the anchoring reinforcing steel bars are arranged on the opposite sides of the upright posts and the concrete wall body at the part to be filled in the construction site, and lifting bolts extending to the outside are. The installation is simple, shorten engineering period and improve the positive effect of entrance to a cave standardization, avoid the infiltration.

Description

Assembled integral window frame wall
Technical Field
The utility model relates to a construction technical field especially belongs to a whole window frame wall body of assembled.
Background
The method is characterized in that the window opening of the external wall is not standard, and the sealant of the window is injected on the window frame and the external wall paint or heat preservation, so that the actual measurement of each window of the building is avoided, and the advanced production and processing according to the size of the window opening in the drawing are realized; and how to avoid sealant to beat and annotate and cause the window infiltration on keeping warm, reduce the owner's complaint in later stage, promote the problem that the building engineering product quality becomes the urgent need of trade and solves.
At present, after a window opening or a poured concrete wall column is built in a building main body, because manual operation is carried out on site, each side of a window has a construction error of 5-15mm more or less. Before the door and window factory produces the door and window, the actual measurement of each window needs to be carried out on site. In order to ensure that the window can be smoothly installed in the production process, manufacturers can reduce each side by 1 cm. A large amount of labor is consumed. And the material can be fed and produced only after the civil engineering window hole is finished and the door and window manufacturer actually measures the civil engineering window hole, so that the construction time is greatly prolonged.
The construction period is short, and the door and window measurement production period is long. Many buildings are not provided with windows, and the heat insulation construction of the external wall is carried out. When the external window is installed, the sealant of the window can only be injected on the heat preservation or external wall paint, so that water seepage is caused. Therefore, in recent years, many enterprises require to make a window opening tongue-and-groove or a steel attached frame. The manual operation of the tongue-and-groove has the following problems: (1) because the area is small and the number of corners is large, workers can only wipe two windows every day, money is struggled, and no one is willing to go to construction; (2) and the size of the window is reduced by making a tongue-and-groove later, and the standard of the window hole cannot be ensured by manual operation. After the window steel auxiliary frame is installed, plastering and waterproof treatment are still needed, and the application and popularization in a large range are not obtained in recent years.
In conclusion, in the traditional civil construction of the window opening, the standardization of the size of the opening is difficult to realize, the realization of the groove and tongue is labor-consuming and time-consuming, the window bottom is easy to seep water (due to the external wall heat preservation and the reversal of the window installation process), the glue joint is wide, the construction period is long, the material consumption is large, the mold lease period is long, and the whole image is not beautiful.
Disclosure of Invention
An object of the utility model is to provide a whole window frame wall body of assembled to reach and avoid the window infiltration, realize the standardized purpose in entrance to a cave.
The utility model provides an assembled integral window frame wall body, which is characterized in that the assembled integral window frame wall body comprises a window frame framework, the window frame framework is formed by pouring upright posts and cross beams between the upright posts, the cross beams comprise upper cross beams and lower cross beams, a lower window wall body is poured between the upper cross beam and the lower cross beam, the lower window wall body is formed by pouring heat-insulating composite boards, fine stone concrete internally provided with bidirectional reinforcing steel meshes, extruded polystyrene boards and fine stone concrete internally provided with bidirectional reinforcing steel meshes in the transition direction from the outdoor side to the indoor side in sequence, the opposite sides of the upright posts, the upper cross beam and the window body are provided with grooves and tongues, wherein, anchoring steel bars extending to the concrete wall body of the site to be filled are embedded in the upright posts, the anchoring reinforcing steel bars are arranged on the opposite sides of the upright posts and the concrete wall body of the part to be filled, and in addition, hoisting bolts extending to the outside are embedded in the top ends of the upright posts.
Furthermore, PVC water stop strips extending to the concrete wall body of the part to be filled are pre-embedded in the upright posts.
Furthermore, a groove is formed in the opposite side of the upright column and the concrete wall body of the part to be filled, and an extruded polystyrene board is arranged in the groove.
Furthermore, fixing bolts extending to the outside are embedded in the upper end and the lower end of each of the two vertical columns respectively, and the fixing bolts are matched with the other ends of the inclined supports, one ends of which are fixed on the floor plates, so that auxiliary fixing during assembling operation of the window frame framework is realized.
The utility model provides a whole window frame wall body of assembled, structural design is simple, reasonable, has following advantage:
1. the finished products can be directly manufactured outside the field in batches and transported to the field for installation, so that the time is saved, the installation effect is good, the efficiency is high, and the time and the labor are saved;
2. the problems of window sizing and hole standardization and the problem of water leakage caused by rain when sealant on the outer side of the window is applied to the outer wall for heat insulation are successfully solved, the door and window can be produced according to drawings, and each side of the window is reduced by 1cm without considering construction errors;
3. after the finished assembled integral window frame wall is used, because the device is cured in a factory, and the extruded polystyrene board is arranged in the groove formed in the opposite side of the upright post and the concrete wall at the part to be filled, the generation of cracks can be effectively avoided; meanwhile, PVC water stop strips extending to the concrete wall body of the part to be filled are pre-buried in the upright posts, so that the problem of water seepage of the outer wall is further avoided;
4. take 2.5 × 1.6 holes as an example: the weight of a common window is about 1.2 tons, the weight of a convex window is about 1.5 tons, and the building adopting the assembled stair and the laminated slab meets the lifting capacity requirement of a tower crane, so that the applicability is wide and the practicability is high. To sum up, the utility model discloses have the installation simple, shorten the engineering time limit for a project and improve the standardized positive effect of, avoiding the infiltration of entrance to a cave.
Drawings
The accompanying drawings partially disclose embodiments of the present invention, wherein
FIG. 1 is an elevation view of a conventional window embodiment of the present invention;
FIG. 2 is a cross-sectional view of the window lower wall of the present invention;
fig. 3 is a side view of the present invention applied to a bay window embodiment;
FIG. 4 is a partial schematic view of the present invention applied to a conventional window embodiment, wherein the upright post is connected to a concrete wall at a portion to be filled;
FIG. 5 is a partial schematic view of the pillar in the embodiment of the bay window of the present invention being connected to a concrete wall at a location to be filled;
fig. 6 is an application state diagram of the assembled type matched inclined support of the utility model.
Detailed Description
As shown in fig. 1-2, the utility model provides an assembled whole window frame wall, including the window frame skeleton, the window frame skeleton is pour by stand 1 and crossbeam 2 between the stand and is formed, the crossbeam includes entablature 2-1, bottom end rail 2-2, pour window lower wall 3 between entablature, bottom end rail, the window lower wall is pour by thermal-insulated composite panel 4, interior two-way reinforcing bar net piece's fine aggregate concrete 5, extruded polystyrene board 6, interior two-way reinforcing bar net piece's fine aggregate concrete 5 in proper order in outdoor side to indoor side transition direction and is formed, as shown in fig. 4, tongue-and-groove 7 has been seted up at stand, entablature and window form opposite side, retreat tongue-and-groove 5-8mm and pour the sealed glue when the window is installed, the heat preservation is done to the tongue-and-groove parallel and level, sealed glue has been stopped to pour on heat preservation or. The inner part of the upright post is pre-embedded with an anchoring steel bar 8 extending to a concrete wall 16 of a part to be filled, so that the assembly and fixation of the window frame are realized, specifically, the anchoring steel bar is arranged on the opposite side of the upright post and the concrete wall of the part to be filled, preferably, the opposite side of the upright post and the concrete wall of the part to be filled is provided with a groove 9, and an extruded polystyrene board is arranged in the groove, so that the generation of cracks can be effectively avoided when new and old concrete is combined; and PVC water stop strips 10 extending to the concrete wall body of the part to be filled are pre-buried in the upright posts, so that a better waterproof effect is realized. Furthermore, for the convenience to carry out the utility model discloses hoist and mount operation in the assembling process, the top of stand is inside still pre-buried to have and to extend to outside lifting by crane bolt 11.
As shown in fig. 3 and 5, the utility model discloses be applied to the embodiment of bay window, stand top and entablature top are outwards extended respectively and are had upper and lower two boards 12 of choosing, and the board of choosing is formed by the concrete placement of built-in anchor reinforcing bar, goes up the inside pre-buried anchor reinforcing bar of board of choosing and extends to the concrete beam who treats the filling position, and the board of choosing anchor is in the bottom end rail down. In the embodiment of the bay window, a protrusion 18 is formed outwards on one side of the upright post corresponding to the flip board, and the protrusion, the lower flip board and the opposite side of the window body are provided with a rabbet. It should be noted that the window frame and the lower wall are manufactured on the factory form. If the bay window is designed, the above-mentioned take-up plate is also produced and made on the factory mould table together.
In addition, as shown in fig. 6, fixing bolts 13 extending to the outside are respectively embedded in the positions of the upper end and the lower end of the two vertical columns, which are one third away from the upper end and the lower end, and in the assembling operation of the device, the fixing bolts are matched with the other end of the inclined support 15 with one end fixed on the floor plate 14, so as to realize auxiliary fixing in the assembling operation of the window frame framework, and preferably, the inclined support of phi 48 phi 60-2000 manufactured by the stannless odd-construction metal products limited company is selected.
This device is when using, reaches the job site through the car fortune, and unwrapping wire location recoil thick liquid 17 on the floor that needs the assembly, and the installation is lifted by crane the girder steel on the finished product window frame wall, places it to the assigned position of location unwrapping wire through the tower crane, and in the assembling process, supplementary fixed when realizing window frame skeleton assembly operation through the diagonal bracing, treats on-the-spot both sides template installation after, about 3 days after the pouring concrete, demolishs the diagonal bracing, and the installation of the whole window frame wall body of assembled is accomplished.

Claims (4)

1. An assembled integral window frame wall body is characterized by comprising a window frame framework, wherein the window frame framework is formed by pouring upright posts (1) and cross beams (2) between the upright posts, each cross beam comprises an upper cross beam (2-1) and a lower cross beam (2-2), a window lower wall body (3) is poured between the upper cross beam and the lower cross beam, the window lower wall body is formed by pouring heat-insulation composite plates (4), fine stone concrete (5) internally provided with bidirectional reinforcing mesh sheets, extruded polystyrene plates (6) and fine stone concrete (5) internally provided with bidirectional reinforcing mesh sheets in sequence in the transition direction from the outdoor side to the indoor side, grooves and notches (7) are formed in the opposite sides of the upright posts, the upper cross beams and a window body, anchoring reinforcing steel bars (8) extending to a concrete wall body (16) to be filled in a construction site are embedded in the upright posts, and are arranged on the opposite sides of the upright posts and the concrete wall body to be filled, in addition, a lifting bolt extending to the outside is embedded in the top end of the upright column.
2. The assembled integrated window frame wall body of claim 1, wherein the PVC water stop strips (10) extending into the concrete wall body to be filled are embedded inside the vertical columns.
3. The assembled integrated window frame wall body of claim 1, wherein the side of the upright post opposite to the concrete wall body to be filled is provided with a groove (9), and the extruded polystyrene board (6) is arranged in the groove.
4. The assembled integral window frame wall body as claimed in claim 1, wherein fixing bolts (13) extending to the outside are embedded in the upper and lower ends of the two vertical columns respectively, and the fixing bolts are matched with the other ends of the inclined supports (15) with one ends fixed on the floor plates (14) to realize auxiliary fixing during the assembling operation of the window frame framework.
CN201920655243.7U 2019-05-09 2019-05-09 Assembled integral window frame wall Expired - Fee Related CN210395712U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920655243.7U CN210395712U (en) 2019-05-09 2019-05-09 Assembled integral window frame wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920655243.7U CN210395712U (en) 2019-05-09 2019-05-09 Assembled integral window frame wall

Publications (1)

Publication Number Publication Date
CN210395712U true CN210395712U (en) 2020-04-24

Family

ID=70345369

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920655243.7U Expired - Fee Related CN210395712U (en) 2019-05-09 2019-05-09 Assembled integral window frame wall

Country Status (1)

Country Link
CN (1) CN210395712U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115341695A (en) * 2022-08-19 2022-11-15 宁夏大学 Desert sand lightweight aggregate concrete fabricated shear wall structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115341695A (en) * 2022-08-19 2022-11-15 宁夏大学 Desert sand lightweight aggregate concrete fabricated shear wall structure

Similar Documents

Publication Publication Date Title
CN102959162B (en) Prefabricated wall panels
US20090113820A1 (en) Prefabricated wall panel system
CN101368428B (en) Prefabricated component house and its construction method
CN212535440U (en) Integrally prefabricated external window, connected node of wafing
CN111927248A (en) Integrally prefabricated external hanging bay window, connecting node and manufacturing method
CN210421424U (en) Assembled steel structure building
CN210395712U (en) Assembled integral window frame wall
CN100451257C (en) Concrete complex building of steel meshwork framework, and construction procedure
CN112695914B (en) Assembly type shear wall structure system and construction method thereof
CN103556758A (en) Lightweight steel construction lightweight concrete cast-in-place wall and construction method
CN103362235B (en) Integrally-poured building house with wallboards integrating thermal insulating and templates
CN203583720U (en) Light-weight steel structure and light-weight concrete cast-in-place wall body
CN203412312U (en) Thermal-insulating integrated template wallboard construction building
CN212336033U (en) A prefabricated foundation ditch for installing elevator additional and template is pour thereof
CN212613041U (en) Modular ultra-low energy consumption concrete prefabricated building system
CN212562928U (en) Integrally prefabricated embedded bay window and connecting joint
CN211037527U (en) Take vertical connected node structure of floor is assembled to full assembled of hidden beam
CN203320739U (en) Formwork thermal insulation integrated wallboard and integrally-poured construction building
CN104652662B (en) Prefabricated panel system
CN215253404U (en) Modular mobile house combined structure
CN216641128U (en) Prefabricated reinforced concrete n-shaped component and building structure thereof
CN220414582U (en) Precast concrete bay window, precast wall body, precast room module and modularized building
CN217974823U (en) Waterproof envelope of assembled
CN211007179U (en) Steel rib-fiber concrete wall structure
CN216156944U (en) Prefabricated reinforced concrete U-shaped component and building structure thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200424