CN210395352U - Steel pipe column guiding device - Google Patents

Steel pipe column guiding device Download PDF

Info

Publication number
CN210395352U
CN210395352U CN201920886393.9U CN201920886393U CN210395352U CN 210395352 U CN210395352 U CN 210395352U CN 201920886393 U CN201920886393 U CN 201920886393U CN 210395352 U CN210395352 U CN 210395352U
Authority
CN
China
Prior art keywords
pipe column
steel pipe
steel
fixed mounting
positioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920886393.9U
Other languages
Chinese (zh)
Inventor
张殿忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920886393.9U priority Critical patent/CN210395352U/en
Application granted granted Critical
Publication of CN210395352U publication Critical patent/CN210395352U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a just ware is led to steel-pipe column relates to construction auxiliary devices technical field, include the base, install automatic adjustment platform on the base with install the tight positioning mechanism of clamp of automatic adjustment platform top, the automatic adjustment platform includes four bottom fixed mounting leveling cylinder on the base and with four leveling cylinder output articulated landing slab, four the leveling cylinder is relative the center pin evenly distributed of landing slab, press from both sides tight positioning mechanism and include that two set up relatively and fixed mounting be in positioning cylinder and two relative settings on the landing slab and respectively fixed mounting are two the location binding clasp of positioning cylinder output. The utility model discloses a steel-pipe column is led and is just managed simple structure, low in manufacturing cost, workman easy operation is convenient, can provide leading of steel-pipe column and just install, has ensured construction quality, has improved the efficiency of construction.

Description

Steel pipe column guiding device
Technical Field
The utility model relates to a construction auxiliary devices technical field, in particular to steel-pipe column leads positive ware.
Background
The known method for steel pipe column guiding construction in the prior art mainly adopts two positioning modes of steel structure positioning frame positioning and steel casing positioning; firstly, the steel structure positioning frame is positioned: and (4) centering the steel pipe column through a positioning frame on the ground and measuring the verticality of the steel pipe column. Firstly, centering and leveling the position of a positioning frame; then, hoisting the steel pipe column into a positioning frame by using a large crawler crane; then slowly lowering the steel pipe column into the hole, clamping the first telescopic double balls at the bottom, measuring the central position of the column body of the steel pipe column, and positioning the steel pipe column by utilizing the scalability of the balls; clamping a second adjustable double-ball at the top, aligning the steel pipe column, retesting the central position of the column body and measuring the verticality of the steel pipe column; re-measuring the perpendicularity and the central position of the column body of the steel pipe column again, adjusting the length of the telescopic spiral ball until the position and the perpendicularity of the column body are adjusted to meet the design requirements, and continuing to lower and install; finally, the steel pipe column is installed, after the concrete of the foundation pile reaches the design strength, 4 cross beams and a tripod are arranged to fix the steel pipe column, and a positioning frame is removed, so that the steel structure positioning frame is complex in structure, high in operation difficulty of workers, complex in process and low in efficiency; secondly, positioning the steel casing: the position of the steel pipe column is adjusted by 4 hydraulic jacks arranged on the pile casing. Vertical perpendicularity of the steel pipe column in the pile casing is measured through the length of the pile casing, so that the perpendicularity of the whole steel pipe column is controlled, and the steel pile casing is positioned, although the operation is simple, the perpendicularity is out of tolerance, the centering is not accurate, and waste piles are easily caused.
SUMMERY OF THE UTILITY MODEL
The utility model provides a steel-pipe column is led and is just managed to overcome the above-mentioned problem that exists among the prior art.
In order to achieve the above object, the present invention provides the following technical solutions: the utility model provides a just ware is led to steel-pipe column, includes the base, installs automatic adjustment platform on the base with install the tight positioning mechanism of clamp of automatic adjustment platform top, the automatic adjustment platform includes four bottom fixed mounting leveling cylinder on the base and with four leveling cylinder output end articulated landing slab, four the leveling cylinder is relative the center pin evenly distributed of landing slab, press from both sides tight positioning mechanism and include two relative settings and fixed mounting location cylinder and two relative settings on the landing slab and respectively fixed mounting two the location binding clasp of location cylinder output, two the location binding clasp all can the landing slab up end horizontal slip.
Preferably, the base comprises a floor and a positioner fixedly mounted at the central position of the floor, the steel pipe column can penetrate through the positioner, and the four leveling oil cylinders are fixedly mounted on the floor.
Preferably, two rows of sliding rails are arranged on the platform plate.
Preferably, the positioning clamp comprises a sliding plate in sliding connection with the two rows of sliding rails and two clamps vertically and fixedly mounted on the sliding plate, and the two clamps of the two positioning clamps can clamp the steel pipe column.
Preferably, the center of the platform plate is provided with a through hole which avoids the insertion of the steel pipe column.
Preferably, the platform board both sides are equipped with the relative extension ear that sets up, two positioning cylinder fixed mounting is respectively two extend on the ear.
The technical scheme has the following advantages or beneficial effects:
the utility model discloses just ware is led to steel-pipe column of structure, simple structure, low in manufacturing cost, workman easy operation, the hydraulic means that digs the rig soon in the time of can directly utilizing the construction provides hydraulic power source, and is very convenient, and the installation is just led to steel-pipe column that can be fine provides, when having ensured construction quality, has improved the efficiency of construction greatly.
Drawings
The invention and its features, aspects and advantages will become more apparent from a reading of the following detailed description of non-limiting embodiments with reference to the attached drawings. The drawings, in which like reference numerals refer to like parts throughout the several views, are not intended to be drawn to scale, emphasis instead being placed upon illustrating the principles of the invention.
Fig. 1 is a schematic view of a three-dimensional structure of a steel pipe column guide provided in embodiment 1 of the present invention in a state of being placed in a steel pipe column;
fig. 2 is a schematic sectional view of the steel pipe column guide provided in embodiment 1 of the present invention in a construction state.
Detailed Description
The following detailed description of the embodiments of the present invention will be given with reference to the accompanying drawings for the purpose of promoting a person skilled in the art to more fully, accurately and deeply understand the concept and technical solution of the present invention and to facilitate its implementation, but not to limit the present invention.
Example 1:
as shown in fig. 1 and 2, the embodiment 1 of the utility model provides a steel-pipe column is led and is just moved, the on-line screen storage device comprises a base 1, install automatic adjustment platform 2 on base 1 and install the tight positioning mechanism 3 of clamp above automatic adjustment platform 2, automatic adjustment platform 2 includes four bottom fixed mounting leveling cylinder 21 on base 1 and with four leveling cylinder 21 output articulated landing slab 22, the relative landing slab 22's of four leveling cylinder 21 center pin evenly distributed, press from both sides tight positioning mechanism 3 and include two relative setting and fixed mounting positioning cylinder 31 on landing slab 22 and two relative setting and respectively fixed mounting at the location binding clasp 32 of two positioning cylinder 31 outputs, two location binding clasps 32 all can be at landing slab 22 up end horizontal slip. It should be noted that the output ends of the four leveling cylinders 21 are hinged to the platform plate 22, but are not shown in the drawings.
Further, the base 1 comprises a floor 11 and a positioner 12 fixedly installed at the central position of the floor 11, the steel pipe column 4 can pass through the positioner 12, and the four leveling cylinders 21 are all fixedly installed on the floor 11. The locator 12 is used for aligning and inserting into the steel casing 6 to realize the relative fixation of the pilot.
Further, two rows of slide rails 222 are disposed on the platform board 22. The positioning clamp 32 comprises a sliding plate 321 which is movably connected with the two rows of sliding rail slides 222 and two clamps 322 which are vertically and fixedly installed on the sliding plate 321 through screws, and the two clamps 322 of the two positioning clamps 32 can clamp the steel pipe column 4. The clamp 322 is designed to be attached to the steel pipe column 4 and is clamped against the side wall of the steel pipe column 4.
Further, a through hole 221 into which the steel pipe column 4 is inserted is provided in the center of the deck plate 22.
Furthermore, two sides of the platform plate 22 are provided with extending lugs 223 which are oppositely arranged, and the two positioning oil cylinders 31 are respectively and fixedly installed on the two extending lugs 223.
The embodiment 1 of the utility model provides a principle and working process of steel-pipe column guide is specifically as follows:
the utility model discloses steel-pipe column guider of embodiment 1, in order to prevent that the hole of collapsing can bury steel casing 6 in the sand 5 in foundation pile hole when digging foundation pile hole, pour into the concrete in advance in the steel casing 6, when installing steel-pipe column 4, aim at steel casing 6 with locator 12 and install, make locator 12 aim at and insert in steel casing 6, floor 11 will hug closely the sand 5 face in foundation pile hole, thereby make landing slab 22 be in the horizontality through adjusting four leveling hydro-cylinders 21 afterwards, through two positioning hydro-cylinders 31 dorsad pulling separately connected location binding clasp 32, thereby open two binding clasp 322, later put into from between two binding clasps 322 through hoisting machine steel-pipe column 4, and slowly pass steel-pipe perforation 221 and locator 12 from the pipe, then drive two binding clasps 322 through two positioning hydro-cylinders 31 and press from both sides tight steel-pipe column 4, thereby guarantee the straightness that hangs down of steel-pipe column 4 when realizing fixing a position steel-pipe column 4 (guarantee that the relative horizontal plane of steel-pipe column 4 hangs down promptly Straight), two binding clasp 322 have actually played the spacing effect in location to steel-pipe column 4, and not the tight death of complete clamp, utilize the drilling rod side head cover that digs the rig soon afterwards to entangle the instrument festival square head of steel-pipe column 4, push down the steel-pipe column when the drilling rod is rotatory, thereby impress the steel-pipe column by force in the concrete of pouring in advance, wait to the concrete solidification back of foundation pile, alright with pull down the leading installation that the leading of leading positive ware carries out next steel-pipe column 4, in the work progress, leveling hydro-cylinder 21 and positioning oil cylinder 31 all can directly utilize the hydraulic means who digs the rig soon, the utility model discloses a steel-pipe column leads positive ware's simple structure, low in manufacturing cost, workman easy operation, can be fine provide leading installation to steel-pipe column 4, when having ensured construction quality, construction efficiency has been improved greatly.
Those skilled in the art will appreciate that variations may be implemented by those skilled in the art in combination with the prior art and the above-described embodiments, and will not be described in detail herein. Such variations do not affect the essence of the present invention and are not described herein.
The above description is of the preferred embodiment of the invention. It is to be understood that the invention is not limited to the particular embodiments described above, in that devices and structures not described in detail are understood to be implemented in a manner common in the art; it will be understood by those skilled in the art that various changes and modifications may be made, or equivalents may be modified, without departing from the spirit of the invention. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention are still within the scope of the protection of the technical solution of the present invention, unless the contents of the technical solution of the present invention are departed.

Claims (6)

1. The utility model provides a steel-pipe column leads positive ware which characterized in that: including the base, install automatic adjustment platform on the base with install the tight positioning mechanism of clamp of automatic adjustment platform top, the automatic adjustment platform includes four bottom fixed mounting leveling cylinder on the base and with four leveling cylinder output end articulated landing slab, four leveling cylinder is relative the center pin evenly distributed of landing slab, press from both sides tight positioning mechanism and include two relative settings and fixed mounting and two relative settings and respectively fixed mounting two of positioning cylinder on the landing slab the location binding clasp of positioning cylinder output, two the location binding clasp all can the landing slab up end horizontal slip.
2. The steel pipe column guide of claim 1, wherein: the base comprises a floor and a positioner fixedly mounted in the center of the floor, the steel pipe column can penetrate through the positioner, and the four leveling oil cylinders are fixedly mounted on the floor.
3. The steel pipe column guide of claim 1, wherein: two rows of sliding rails are arranged on the platform plate.
4. The steel pipe column guide according to claim 3, wherein: the positioning clamping device comprises sliding plates in sliding connection with the two rows of sliding rails and clamping devices vertically and fixedly installed on the sliding plates, and the two clamping devices of the two positioning clamping devices can clamp the steel pipe column.
5. The steel pipe column guide of claim 1, wherein: and a through hole for avoiding the steel pipe column from being inserted is formed in the center of the platform plate.
6. The steel pipe column guide of claim 1, wherein: platform board both sides are equipped with the relative extension ear that sets up, two positioning cylinder fixed mounting is respectively two extend on the ear.
CN201920886393.9U 2019-06-13 2019-06-13 Steel pipe column guiding device Active CN210395352U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920886393.9U CN210395352U (en) 2019-06-13 2019-06-13 Steel pipe column guiding device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920886393.9U CN210395352U (en) 2019-06-13 2019-06-13 Steel pipe column guiding device

Publications (1)

Publication Number Publication Date
CN210395352U true CN210395352U (en) 2020-04-24

Family

ID=70348950

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920886393.9U Active CN210395352U (en) 2019-06-13 2019-06-13 Steel pipe column guiding device

Country Status (1)

Country Link
CN (1) CN210395352U (en)

Similar Documents

Publication Publication Date Title
CN109487822B (en) Method for installing and adjusting steel pipe column in reverse construction and control device
CN112900450A (en) Rotary drilling and full-rotation combined back-inserting method positioning method for steel pipe structure pile by reverse construction method
CN103541735B (en) Tunneling machine stepping pushing supporting device and construction method
CN210976662U (en) Steel-pipe column transfers device that hangs down
CN203822175U (en) Drilling machine rack
CN112049119B (en) Sliding type steel support erecting device
CN104372798A (en) Construction method of all-casing all-direction drilling rig
CN114277803B (en) Post-insertion method positioning construction method for reverse construction method steel pipe structural column
CN210395352U (en) Steel pipe column guiding device
CN211714567U (en) Interval adjustable creeping formwork device
CN111456009A (en) Engineering pile guiding device in piling construction and using method thereof
CN108179749B (en) Lattice column positioner and positioning method thereof
CN113585079B (en) Method for quickly installing steel structure stand column
CN213267538U (en) Leading hole platform for U-shaped sandstone riverbed steel trestle on shoal
CN212742614U (en) Foundation inner stand column positioning and mounting structure
CN210238492U (en) Crown beam type miniature pile construction formwork capable of being circulated
CN210827478U (en) Deep foundation pit underground structure reverse construction method steel pipe column positioning device
CN211736514U (en) Interior landing stage board construction system that supports
JP3750042B2 (en) Construction pillar erection device
CN113235568A (en) Channel type cutting assembly type underground continuous wall construction guide frame and construction method
JPH10331427A (en) Vibration isolation device installation jig and vibration isolation device installation method using the same
CN111751069A (en) Mounting device and mounting method for embedded panel of vertical actuator of vibrating table
CN213297849U (en) Centering adjusting structure of full-slewing drilling machine
CN220705734U (en) Template mechanism convenient to ore deposit wall of a well stock location
CN217150251U (en) Digital verticality adjusting system for reverse steel stand column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant