CN210370703U - Shield constructs quick-witted section of thick bamboo frock - Google Patents
Shield constructs quick-witted section of thick bamboo frock Download PDFInfo
- Publication number
- CN210370703U CN210370703U CN201921024669.9U CN201921024669U CN210370703U CN 210370703 U CN210370703 U CN 210370703U CN 201921024669 U CN201921024669 U CN 201921024669U CN 210370703 U CN210370703 U CN 210370703U
- Authority
- CN
- China
- Prior art keywords
- bearing
- arc plate
- bearing block
- steel pipe
- lateral partition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The utility model relates to the technical field of shield machine equipment, and discloses a shield machine pipe sheet tool, which comprises a steel pipe sheet, a lifting baffle, a bearing block and a bearing bolt strip; the steel pipe piece comprises a bottom arc plate, a transverse arc plate and a lateral partition plate, wherein the transverse arc plate and the lateral partition plate are arranged on the bottom arc plate and enclose a plurality of bearing grooves; the middle of the bottom plate is provided with a threaded base; a plurality of fixing holes are formed in the lateral partition plate; the bearing block is arranged in the bearing groove, and a plurality of bearing holes which penetrate through the bearing block and correspond to the fixing holes are formed in the bearing block; the lifting baffle is provided with a lifting hole matched with the threaded base and is arranged on the steel pipe sheet; the bearing bolt strip passes through the bearing hole and the fixing hole. The utility model discloses a section of jurisdiction frock dress is dismantled conveniently, the firm damage of installation takes place to drop.
Description
Technical Field
The utility model relates to a shield constructs quick-witted equipment field, concretely designs a shield constructs quick-witted section of jurisdiction frock.
Background
Shield tunnel boring machine, shield machine for short. Is a special engineering machine for tunneling. The shield segment is a main assembly component for shield machine construction, is an outermost shield of a tunnel, plays a role in resisting soil layer pressure, underground water pressure and some special loads, and has important issues concerned by domestic and foreign shield companies for quality safety. Therefore, the steel duct piece is designed, is suitable for 6-7 m series shield machines, achieves the purpose of testing different loads in the debugging process of the erector by increasing and decreasing the balancing weights, improves the working efficiency and ensures the personnel and property safety in the debugging process.
The shield constructs the machine at workshop final assembly debugging in-process, and the debugging personnel need to snatch the cement section of jurisdiction and carry out load test when carrying out the erector action test, has the phenomenon that the section of jurisdiction slightly rocked often in this action test in-process, need to break the debugging process and carry out detailed investigation to the cement section of jurisdiction for the erector and debugging. The reason that slight shaking occurs in the grabbing and lifting process is found through inspection to be that the thread clearance between the segment bolt and the segment is too large, and the segment bolt are caused by relative movement in the grabbing and lifting process.
The cement segment that the debugging of shield constructs the machine and adopts is unanimous with the segment when the tunnel was built, and the screw thread of this type of segment hoist and mount adopts engineering plastics preparation, only needs once to assemble in the use, does not exist when assembling and rocks the phenomenon. The phenomenon that the pipe piece is slightly shaken in the grabbing and lifting process is caused by the fact that the existing pipe piece is deformed due to the fact that the threads for hoisting are used for multiple times and the pipe piece is abraded too much to lose the fastening effect. Thereby influencing normal equipment debugging work and causing potential safety hazards of property personnel.
According to analysis, the segment is hidden safely in the following situations: unqualified manufacturing process, unreasonable storage position and long-term use. And the section of jurisdiction that the debugging process goes wrong has the phenomenon of long-term use, and the section of jurisdiction generally uses fork truck to go on when handling, and does not adopt special fixture, and the section of jurisdiction bumps the phenomenon and takes place occasionally, leads to the outward appearance of section of jurisdiction impaired. The hoisting threaded hole of the cement segment is deformed due to abrasion caused by long-term use, the fastening effect is lost, a plurality of parts are damaged by collision, and the potential safety hazard is not small.
The utility model has the following contents:
not enough to prior art, the utility model provides a shield constructs quick-witted section of jurisdiction frock that convenient, the firm damage of installation of unloading takes place to drop is installed to installing and removing.
The utility model discloses the technical problem that will solve adopts following technical scheme to realize:
a shield machine pipe sheet tool comprises a steel pipe sheet, a lifting baffle, a bearing block and a bearing bolt strip;
the steel pipe piece comprises a bottom arc plate, a transverse arc plate and a lateral partition plate, wherein the transverse arc plate and the lateral partition plate are arranged on the bottom arc plate and enclose a plurality of bearing grooves; the middle of the bottom arc plate is provided with a threaded base; a plurality of fixing holes are formed in the lateral partition plate;
the bearing block is arranged in the bearing groove, and a plurality of bearing holes which penetrate through the bearing block and correspond to the fixing holes are formed in the bearing block;
the lifting baffle is provided with a lifting hole matched with the threaded base and is arranged on the steel pipe sheet;
the bearing bolt strip passes through the bearing hole and the fixing hole.
As an optimization of the utility model, the quantity of bearing groove is 12.
As an optimization of the utility model, the one end of bearing gib is provided with increase portion, and the other end sets up the nut.
The utility model provides a pair of shield constructs quick-witted section of jurisdiction frock, it has following beneficial effect:
(1) the utility model discloses a shield constructs quick-witted section of jurisdiction frock when using, the steel-pipe piece can increase and decrease the bearing block according to different models and reach the section of jurisdiction weight on the fitting, has improved production efficiency, and overall structure is simple reliable, easy dismounting, and maintenance efficiency is high.
(2) The utility model discloses a shield constructs quick-witted section of jurisdiction frock can use removable threaded base for a long time when using, avoids smooth tooth phenomenon to and stop the phenomenon that cement peeled off appears in conventional section of jurisdiction, guarantee debugging process property personnel safety.
(3) The utility model discloses a shield constructs quick-witted section of thick bamboo frock, the preparation is simple and easy, and material source is conventional, and the cost of manufacture is low, repeatedly usable.
(4) The utility model discloses a shield constructs quick-witted section of thick bamboo frock when using, guarantees to operate simply, avoids the operation regulation to complicate.
Drawings
Fig. 1 is a schematic structural view of a steel pipe sheet of the pipe sheet tool of the shield tunneling machine of the present invention;
fig. 2 is a schematic view of the internal structure of a steel pipe sheet of the pipe sheet tool of the shield tunneling machine of the present invention;
fig. 3 is a schematic structural view of a bearing block of the pipe sheet tool of the shield tunneling machine of the present invention;
fig. 4 is the bearing bolt strip structure schematic diagram of the pipe sheet tool of the shield tunneling machine of the present invention.
Reference numerals: 1. a nut; 2. lifting the baffle; 3. a bearing block; 4. a load-bearing gib; 5. a load bearing groove; 6. a bottom arc plate; 7. a transverse arc plate; 8. a lateral partition plate; 9. a threaded base; 10. lifting holes; 11. a bearing hole; 12. a fixing hole; 13. and an enlarged portion.
Detailed Description
The invention will be further described with reference to the accompanying drawings and specific embodiments:
referring to fig. 1, 2, 3 and 4, a shield machine pipe sheet tool comprises a steel pipe sheet, a lifting baffle 2, a bearing block 3 and a bearing bolt strip 4;
the steel pipe sheet comprises a bottom arc plate 6, a transverse arc plate 7 and a lateral partition plate 8, wherein the transverse arc plate 7 and the lateral partition plate 8 are installed on the bottom arc plate 6 and enclose a plurality of bearing grooves 5; the middle of the bottom arc plate 6 is provided with a threaded base 9; a plurality of fixing holes 12 are formed in the lateral partition plate 8;
the bearing block 3 is arranged in the bearing groove 5, and a plurality of bearing holes 11 which penetrate through the bearing block 3 and correspond to the fixing holes 12 are formed in the bearing block 3;
the lifting baffle 2 is provided with a lifting hole 10 matched with the threaded base 9, and the lifting baffle 2 is arranged on the steel pipe sheet;
the bearing bolt 4 passes through the bearing hole 11 and the fixing hole 12.
Specifically, when the pipe piece tool of the shield machine is used, the weight of the pipe piece for debugging can be met by increasing or decreasing the bearing blocks 3 according to different machine types of the steel pipe piece, the production efficiency is improved, the whole structure is simple and reliable, the assembly and the disassembly are convenient, and the maintenance efficiency is high; the replaceable threaded base 9 can be used for a long time, so that the phenomenon of tooth slipping is avoided, the phenomenon of cement peeling of the conventional duct piece is avoided, and the safety of property personnel in the debugging process is ensured; meanwhile, the manufacturing is simple, the material source is conventional, the manufacturing cost is low, the material can be repeatedly used, the simplicity of operation is ensured, and the complication of operation rules is avoided.
Preferably, the number of the bearing grooves 5 is 12.
Preferably, one end of the bearing bolt strip 4 is provided with an enlarged part 13, and the other end is provided with a nut 1.
Various other modifications and changes may be made by those skilled in the art based on the above-described technical solutions and concepts, and all such modifications and changes are intended to fall within the scope of the claims.
Claims (3)
1. The utility model provides a shield constructs quick-witted section of thick bamboo frock which characterized in that: the hoisting device comprises a steel pipe sheet, a hoisting baffle, a bearing block and a bearing bolt strip;
the steel pipe piece comprises a bottom arc plate, a transverse arc plate and a lateral partition plate, wherein the transverse arc plate and the lateral partition plate are arranged on the bottom arc plate and enclose a plurality of bearing grooves; the middle of the bottom arc plate is provided with a threaded base; a plurality of fixing holes are formed in the lateral partition plate;
the bearing block is arranged in the bearing groove, and a plurality of bearing holes which penetrate through the bearing block and correspond to the fixing holes are formed in the bearing block;
the lifting baffle is provided with a lifting hole matched with the threaded base and is arranged on the steel pipe sheet;
the bearing bolt strip passes through the bearing hole and the fixing hole.
2. The shield tunneling machine segment tooling of claim 1, which is characterized in that: the number of the bearing grooves is 12.
3. The shield tunneling machine segment tooling of claim 1, which is characterized in that: one end of the bearing bolt strip is provided with an enlarged part, and the other end of the bearing bolt strip is provided with a nut.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921024669.9U CN210370703U (en) | 2019-07-02 | 2019-07-02 | Shield constructs quick-witted section of thick bamboo frock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921024669.9U CN210370703U (en) | 2019-07-02 | 2019-07-02 | Shield constructs quick-witted section of thick bamboo frock |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210370703U true CN210370703U (en) | 2020-04-21 |
Family
ID=70268975
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921024669.9U Active CN210370703U (en) | 2019-07-02 | 2019-07-02 | Shield constructs quick-witted section of thick bamboo frock |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210370703U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112324473A (en) * | 2020-10-23 | 2021-02-05 | 中铁十四局集团有限公司 | Telescopic steel pipe sheet matched with tunnel connection channel construction and installation method |
CN113420482A (en) * | 2021-06-24 | 2021-09-21 | 北京安捷工程咨询有限公司 | Segment load orthogonal numerical inversion method based on structural internal force monitoring value |
CN113447340A (en) * | 2021-06-21 | 2021-09-28 | 上海隧道工程有限公司 | Method for manufacturing shield segment for test |
-
2019
- 2019-07-02 CN CN201921024669.9U patent/CN210370703U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112324473A (en) * | 2020-10-23 | 2021-02-05 | 中铁十四局集团有限公司 | Telescopic steel pipe sheet matched with tunnel connection channel construction and installation method |
CN112324473B (en) * | 2020-10-23 | 2022-02-11 | 中铁十四局集团有限公司 | Telescopic steel pipe sheet matched with tunnel connection channel construction and installation method |
CN113447340A (en) * | 2021-06-21 | 2021-09-28 | 上海隧道工程有限公司 | Method for manufacturing shield segment for test |
CN113420482A (en) * | 2021-06-24 | 2021-09-21 | 北京安捷工程咨询有限公司 | Segment load orthogonal numerical inversion method based on structural internal force monitoring value |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210370703U (en) | Shield constructs quick-witted section of thick bamboo frock | |
CN102691784B (en) | Input planet carrierin gearbox of high-power wind driven generator | |
CN201045114Y (en) | Novel bucket grab coupling device | |
CN203639818U (en) | Self speed-regulation cable robot | |
CN203245570U (en) | Tool for demounting shaft | |
CN203285795U (en) | Clamp of Christmas tree | |
CN202367655U (en) | Tool for assembling round nuts inside bearing pedestal of high-pressure isolation switch | |
CN202955090U (en) | Crane pin shaft | |
CN210855030U (en) | Gantry hanging bracket | |
CN204569127U (en) | Steel upright post hoisting jig | |
CN208666969U (en) | MC nylon wheel series JDB strength coaster | |
CN206425419U (en) | Workbench and its support component | |
CN203833539U (en) | Assembly-type pulley structure of crane | |
CN205370900U (en) | Asymmetric oil circuit cross head pin of JB6M50 compressor | |
CN205183328U (en) | Restoration type terminal surface tooth roll axle | |
CN203791951U (en) | Special tool for pulling out square tenon of coal mining machine | |
CN204980894U (en) | Hoist fixed pulley fixing device | |
CN209164307U (en) | A kind of high-strength flour milling bolt of self-locking function | |
CN219633689U (en) | Fan blade bolt disassembling tool | |
CN219708896U (en) | Frock is used in standing up of wind-powered electricity generation tubular pile flange section | |
CN208451517U (en) | Hydraulic turbine main shaft flange bolt decomposes specific purpose tool | |
CN205712246U (en) | With detachable tooth block structured grab bucket strut | |
CN102900750B (en) | Crane pin shaft and using method thereof | |
CN203509241U (en) | Efficient workpiece tapping machine | |
CN220265030U (en) | Bridge crane end beam connection structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |