CN210313376U - Prefabricated section is handling device in batches - Google Patents

Prefabricated section is handling device in batches Download PDF

Info

Publication number
CN210313376U
CN210313376U CN201921129686.9U CN201921129686U CN210313376U CN 210313376 U CN210313376 U CN 210313376U CN 201921129686 U CN201921129686 U CN 201921129686U CN 210313376 U CN210313376 U CN 210313376U
Authority
CN
China
Prior art keywords
jacking
frame
handling device
precast block
support frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921129686.9U
Other languages
Chinese (zh)
Inventor
陈巍峰
郑海忠
邹文才
吴良文
张铎谕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Communications Construction Group Co Ltd
Original Assignee
Zhejiang Communications Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Communications Construction Group Co Ltd filed Critical Zhejiang Communications Construction Group Co Ltd
Priority to CN201921129686.9U priority Critical patent/CN210313376U/en
Application granted granted Critical
Publication of CN210313376U publication Critical patent/CN210313376U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to the technical field of precast block transportation, in particular to a precast block batch transportation device, which comprises a support frame, a connecting piece and a transportation frame; the carrying frame is connected with the supporting frame, and the supporting frame is detachably connected with a bracket of the forklift through a connecting piece; the carrying frame comprises a plurality of first jacking supports arranged in parallel, the precast blocks to be carried are positioned in the moulds, and a plurality of moulds are placed between the adjacent first jacking supports. The conveying frame of the utility model can convey a plurality of precast blocks once through the forklift, has high conveying efficiency, high degree of mechanization and high working efficiency, releases workers from heavy physical labor and ensures the safety of the construction process; simultaneously, handling device and the detachable connection of fork truck bracket, installation loading and unloading are convenient, can further improve work efficiency.

Description

Prefabricated section is handling device in batches
Technical Field
The utility model relates to a prefabricated section transport technical field, concretely relates to is a prefabricated section is handling device in batches.
Background
With the vigorous popularization of prefabricated components and assembly type embankment protection engineering processes in China and the push of assembly type components, precast blocks are mostly adopted for protection of the existing embankment. The precast block used by the embankment is used for protecting soil slopes which are easy to be damaged by natural action and have slope deformation in embankment protection engineering, such as sod laying, guniting, plastering, wall protection, slope protection and intercepting and shielding buildings built for preventing collapse and falling rocks.
At present, the prefabricated blocks required by the embankment are all prefabricated by automatic processing, but a better solution is not provided during transportation, the prefabricated blocks are transported one by manpower, the labor intensity of workers is huge, the operation process is not economical, the labor cost is higher, and the rapid transportation is not facilitated.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem that the used prefabricated section of current embankment still adopts the manual work to carry, and work intensity of operation is big, and is with high costs, and handling efficiency is low, has provided a prefabricated section is handling device in batches.
In order to realize the technical purpose, the utility model adopts the following technical scheme:
a precast block batch carrying device comprises a supporting frame, a connecting piece and a carrying frame; the carrying frame is connected with the supporting frame, and the supporting frame is detachably connected with a bracket of the forklift through a connecting piece; the carrying frame comprises a plurality of first jacking supports arranged in parallel, the precast blocks to be carried are positioned in the moulds, and a plurality of moulds are placed between the adjacent first jacking supports.
Further, the connecting piece is a clamping groove; the support frame is located to the draw-in groove, and the support frame passes through the draw-in groove and is connected with fork truck's bracket is detachable.
Furthermore, the carrying frame further comprises a second jacking, the first jacking is arranged on the second jacking and is uniformly distributed along the length direction of the second jacking, and the support frame is connected with the carrying frame through the second jacking.
Furthermore, the carrying frame also comprises an oblique reinforcement which is arranged at the joint of the first jacking and the second jacking; one end of the oblique reinforcement is positioned on the first jacking, and the other end of the oblique reinforcement is positioned on the second jacking.
Furthermore, the support frame still includes the several diagonal draw bar, and the support frame passes through diagonal draw bar and is connected with the second top support.
Further, the support frame still includes fastening bolt, and support frame, bracket all are equipped with the bolt hole corresponding with fastening bolt.
Further, the first jacking is a hollow square pipe; the second top support and the first top support are horizontally arranged, and the second top support is vertical to the first top support.
Furthermore, the material of the mould is plastic; the one side of mould and prefabricated section laminating is the internal surface, and the mould is the surface with the relative one side of internal surface, and the surface is equipped with the reinforcement rib.
Further, the prefabricated section is hexagonal hollow brick, the mould is hexagonal hollow brick prefabricated mould.
Compared with the prior art, the beneficial effects of the utility model are that:
the conveying frame of the utility model can convey a plurality of precast blocks at one time through the forklift, has high conveying efficiency, high degree of mechanization and high working efficiency, releases workers from heavy physical labor and ensures the safety of the construction process; simultaneously, handling device and the detachable connection of fork truck bracket, installation loading and unloading are convenient, can further improve work efficiency.
Two, the utility model discloses simple structure, construction are convenient, easy operation, loading and unloading are light and handy, have good economic benefits and security benefit, but wide application in the transport work of embankment protection engineering concrete prefabricated section.
Drawings
FIG. 1 is a schematic diagram of a device for batch-transferring precast blocks according to the present embodiment;
fig. 2 is a partial structure view of the truck of the present embodiment.
In the figure, 1 a support frame, 11 clamping grooves, 12 diagonal draw bars, 13 fastening bolts, 2 a conveying frame, 21 a first jacking, 22 a second jacking, 23 diagonal reinforcement, 3 a mould and 31 a reinforcement rib.
Detailed Description
The invention will be further described with reference to specific examples, but the scope of the invention is not limited thereto.
As shown in fig. 1-2, the apparatus for bulk handling of precast blocks of this embodiment includes a supporting frame 1, a connecting member and a handling frame 2. The carrying frame 2 is connected with the support frame 1, and the support frame 1 is detachably connected with a bracket of a forklift through a connecting piece. The carrying frame 2 comprises a plurality of first jacking brackets 21 which are arranged in parallel, the precast block to be carried is positioned in the moulds 3, and a plurality of moulds 3 are arranged between the adjacent first jacking brackets 21. The transport frame 2 of this embodiment once can carry a plurality of prefabricated sections through fork truck, and handling efficiency is high, and degree of mechanization is high, and work efficiency is high, releases the workman from heavy physical labor, can ensure the security of work progress. Simultaneously, handling device and the detachable connection of fork truck bracket, installation loading and unloading are convenient, can further improve work efficiency.
In order to facilitate the detachment of the carrying device from the bracket, the connecting piece is designed into a shape of a clamping groove 11. Support frame 1 is located to draw-in groove 11, and support frame 1 passes through draw-in groove 11 and is connected with fork truck's bracket is detachable. During connection, the clamping groove 11 only needs to be hung on a bracket of the forklift, and the lifting of the carrying device is driven by driving the lifting of the bracket. When the conveying device is not used, the conveying device can be directly taken down from the bracket. Therefore, this embodiment simple structure, construction are convenient, easy operation, loading and unloading are light and handy.
The carrying frame 2 further comprises a second top support 22, the first top support 21 is arranged on the second top support 22 and is uniformly distributed along the length direction of the second top support 22, and the support frame 1 is connected with the carrying frame 2 through the second top support 22. In this embodiment, according to the size of the mold 3, the corresponding first supporting members 21 are manufactured and the distance between the adjacent first supporting members 21 is set, so that the first supporting members 21 can be accurately lifted up the mold 3. In order to enhance the stability and the use strength of the carrier 2, the carrier 2 further includes an oblique reinforcement 23, and the oblique reinforcement 23 is used for connecting the first top support 21 and the second top support 22, so as to enhance the connection stability of the first top support 21 and the second top support 22. The oblique reinforcement 23 is provided at the joint of the first top bracket 21 and the second top bracket 22. The oblique reinforcement 23 has one end located at the first jacking 21 and the other end located at the second jacking 22. One end of the first top support 21 is located on the second top support 22, and the other end is a free end. The number of the oblique reinforcing members 23 is the same as that of the first jacking 21. In this embodiment, six first top holders 21, one second top holder 22, and six oblique reinforcements 23 are uniformly arranged at the end portions corresponding to the first top holders 21.
In order to increase the firmness between the carrying frame 2 and the supporting frame 1, the supporting frame 1 further comprises a plurality of diagonal draw bars 12, and the supporting frame 1 is connected with the second jacking 22 through the diagonal draw bars 12. The supporting frame 1 further comprises fastening bolts 13, bolt holes corresponding to the fastening bolts 13 are formed in the supporting frame 1 and the bracket, when the carrying device is used, the carrying device is placed on a forklift, the carrying device is fastened on the bracket of the forklift through the fastening bolts 13, and the purpose that the carrying device can control the forklift to move up and down is achieved. At the same time, the fastening bolt 13 can tighten or loosen the space between the carrier and the bracket.
First top support 21 is hollow square pipe, and its main function is used for dragging and lifts mould 3, and the lifting in the time of conveniently carrying can alleviate handling device's weight simultaneously. The second top support 22 and the first top support 21 are both horizontally arranged, and the second top support 22 is perpendicular to the first top support 21, so that the first top support 21 can conveniently extend into a gap between two adjacent rows of dies 3. The mould 3 is made of plastic. The surface of mould 3 and prefabricated section laminating is the internal surface, and the mould 3 is the surface with the internal surface relative, and the surface is equipped with reinforcing rib 31. The reinforcing rib 31 serves to reinforce the mold 3 made of plastic material, preventing the mold 3 from being damaged after a plurality of times of pouring and removal. The precast block in this embodiment is hexagonal hollow brick, and mould 3 is hexagonal hollow brick precast mould, and corresponding size's handling device can also be made according to the precast block of other shapes to this embodiment.
The specific use steps of this embodiment are: firstly, placing the carrying device on a forklift, hanging the carrying device on a bracket of the forklift through a clamping groove 11 so as to fix the carrying device and the forklift, and tightening a fastening bolt 13 to ensure that the carrying device cannot be separated; after the prefabricated blocks are prefabricated in the molds 3, the prefabricated blocks are placed on the ground in advance and are arranged in order, a forklift is driven to move forwards to the positions of the molds 3, the first jacking supports 21 are driven to extend into the space between two adjacent rows of the molds 3 by the forklift, then the brackets are jacked upwards by the forklift, and the carrying device with the molds 3 is improved; driving the forklift to move backwards, moving to a specified position, lowering the carrying device through the forklift, and after the mold 3 contacts the ground, further lowering the carrying device through the forklift and moving backwards so that the first jacking 21 extends out from between two adjacent rows of precast blocks; completing the operation after the first jacking 21 is completely extended out; and (4) stopping the forklift and the conveying device in a designated area, and waiting for the next operation.
This embodiment uses fork truck as the access point, adds a device that is used for carrying the prefabricated section in batches when guaranteeing fork truck's each function, mainly utilizes the anterior jacking device of repacking fork truck, changes the jacking device into handling device, reforms transform through this, can satisfy disposable 10 prefabricated sections of transport. The structural integrity of the forklift can be maintained while the ease of use of the handling device is maintained. Only need be connected handling device and fork truck when the operation, need not artifical transport when just can guaranteeing the transport, handling efficiency is high, and degree of mechanization is high, and work efficiency is high, releases the workman from heavy physical labor. The embodiment has the advantages of simple structure, convenience and quickness in construction, simplicity in operation, light and handy loading and unloading, good economic benefit and safety benefit, provides good technical support for carrying industrial precast blocks in future, and can be widely applied to carrying work of concrete precast blocks in embankment protection engineering.
The embodiments of the present invention have been described in detail, and those skilled in the art can easily understand that there are various changes in the embodiments according to the idea of the present invention, and such changes should be considered as the protection scope of the present invention.

Claims (9)

1. The utility model provides a prefabricated section is handling device in batches which characterized in that:
comprises a supporting frame (1), a connecting piece and a carrying frame (2);
the carrying frame (2) is connected with the support frame (1), and the support frame (1) is detachably connected with a bracket of a forklift through a connecting piece;
the carrying frame (2) comprises a plurality of first jacking supports (21) which are arranged in parallel, the precast block to be carried is positioned in the moulds (3), and a plurality of moulds (3) are arranged between the adjacent first jacking supports (21).
2. The precast block batch handling device according to claim 1, characterized in that: the connecting piece is a clamping groove (11); the support frame (1) is arranged in the clamping groove (11), and the support frame (1) is detachably connected with a bracket of a forklift through the clamping groove (11).
3. The precast block batch handling device according to claim 1, characterized in that: the carrying frame (2) further comprises a second jacking (22), the first jacking (21) is arranged on the second jacking (22) and is uniformly distributed along the length direction of the second jacking (22), and the support frame (1) is connected with the carrying frame (2) through the second jacking (22).
4. The precast block batch handling device of claim 3, wherein: the conveying frame (2) further comprises an oblique reinforcement (23), and the oblique reinforcement (23) is arranged at the connecting position of the first jacking (21) and the second jacking (22); one end of the oblique reinforcement (23) is positioned on the first jacking (21), and the other end is positioned on the second jacking (22).
5. The precast block batch handling device of claim 3, wherein: the support frame (1) also comprises a plurality of diagonal draw bars (12), and the support frame (1) is connected with the second jacking (22) through the diagonal draw bars (12).
6. The precast block batch handling device of claim 5, wherein: the support frame (1) further comprises a fastening bolt (13), and bolt holes corresponding to the fastening bolt (13) are formed in the support frame (1) and the bracket.
7. The precast block batch conveying device according to any one of claims 3 to 5, characterized in that: the first top support (21) is a hollow square tube; the second top support (22) and the first top support (21) are both horizontally arranged, and the second top support (22) is vertical to the first top support (21).
8. The precast block batch handling device according to claim 1, characterized in that: the mould (3) is made of plastic; the surface that mould (3) and prefabricated section laminating are the internal surface, and mould (3) and the relative one side of internal surface are the surface, and the surface is equipped with reinforcing rib (31).
9. The preform block batch handling device of claim 8, wherein: the precast block is a hexagonal hollow brick, and the die (3) is a hexagonal hollow brick precast die.
CN201921129686.9U 2019-07-18 2019-07-18 Prefabricated section is handling device in batches Active CN210313376U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921129686.9U CN210313376U (en) 2019-07-18 2019-07-18 Prefabricated section is handling device in batches

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921129686.9U CN210313376U (en) 2019-07-18 2019-07-18 Prefabricated section is handling device in batches

Publications (1)

Publication Number Publication Date
CN210313376U true CN210313376U (en) 2020-04-14

Family

ID=70124078

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921129686.9U Active CN210313376U (en) 2019-07-18 2019-07-18 Prefabricated section is handling device in batches

Country Status (1)

Country Link
CN (1) CN210313376U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113880009A (en) * 2020-07-03 2022-01-04 北京广利核系统工程有限公司 Elevating platform for installing display

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113880009A (en) * 2020-07-03 2022-01-04 北京广利核系统工程有限公司 Elevating platform for installing display

Similar Documents

Publication Publication Date Title
CN209815081U (en) Hollow brick conveyer
CN203527464U (en) Stacking mechanical arm
CN210313376U (en) Prefabricated section is handling device in batches
CN210914947U (en) Hoisting and turning-over system suitable for large prefabricated stand board
CN111115461B (en) Reinforcing steel bar and mould transportation and automatic assembling equipment
CN109335956B (en) Prefabricated ditch apron hoisting accessory
CN103692550B (en) A kind of casting method of seabed tunnel immersed tube
CN214692858U (en) Floor transportation frock
CN114293569B (en) Cutting support lifting device for deep foundation pit inner support beam and construction method
CN213893292U (en) Platform is deposited to portable reinforcing bar
CN210509230U (en) Horizontal splicing device for circular steel lining
CN213829568U (en) Rapid demoulding system for manufacturing elastic supporting block
CN110498238B (en) Split type lifting platform capable of realizing palletless stacking of building blocks and stacking method using device
CN210683055U (en) Device convenient to building material transport
CN206607606U (en) A kind of combined type piping lane moving lifting support day face die plate
CN214419141U (en) Efficient cable duct drawing of patterns frock
CN104555700A (en) Cement precast slab loading and unloading device
CN220281426U (en) Material transport vehicle
CN218715137U (en) Large building frame construction structure capable of rapidly clearing and retreating materials
CN219362957U (en) Quick hoist and mount handling device of brick body
CN214195600U (en) High-rise building construction discharge apparatus
CN218040588U (en) Simple and easy light-duty cable tray
CN218614687U (en) Integrated workbench integrating box girder reinforcing steel bar processing, transporting and binding
CN216239713U (en) Hydraulic type automatic lifting template supporting and protecting integrated frame
CN214456352U (en) Hollow brick lifting device for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant