CN210086988U CN201920493035.1U CN201920493035U CN210086988U CN 210086988 U CN210086988 U CN 210086988U CN 201920493035 U CN201920493035 U CN 201920493035U CN 210086988 U CN210086988 U CN 210086988U
Authority
CN
China
Prior art keywords
square platform
recycled concrete
concrete construction
adjacent
supporting component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920493035.1U
Other languages
Chinese (zh)
Inventor
蒋业浩
王威
肖成会
宋志雄
姜艳艳
魏兆峰
吕燕
魏兆岭
唐亮
沙瑞媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangzhou Huimin Renewable Resources Co Ltd
Yangzhou Polytechnic College Yangzhou Radio and TV University
Original Assignee
Yangzhou Huimin Renewable Resources Co Ltd
Yangzhou Polytechnic College Yangzhou Radio and TV University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangzhou Huimin Renewable Resources Co Ltd, Yangzhou Polytechnic College Yangzhou Radio and TV University filed Critical Yangzhou Huimin Renewable Resources Co Ltd
Priority to CN201920493035.1U priority Critical patent/CN210086988U/en
Application granted granted Critical
Publication of CN210086988U publication Critical patent/CN210086988U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses an assembled recycled concrete construction is with enclosing fender, including multiunit supporting component and the oblique lamina of connecting two liang of adjacent supporting component, supporting component comprises base and stand, and the stand cartridge links to each other through oblique lamina between the adjacent coexistence post in the base, and the top of adjacent coexistence post links to each other through the fixed plate, accomplishes the fixed of adjacent coexistence post, the utility model discloses use assembled structure to accomplish to enclose putting up of fender and make to enclose to put up and demolish convenient and fast more, and the similar shutter structure of the assembly mode of oblique lamina can be used to in the middle of the engineering construction.

Description

Assembled recycled concrete construction is with enclosing fender
Technical Field
The utility model relates to a fender is enclosed in the construction, in particular to fender is enclosed to assembled.
Background
With the development of economy and technology, more and more urban engineering construction projects are developed. In the construction process, all construction sites need to be provided with construction barriers, and the construction barriers are important components of safe and civilized construction. The construction enclosure has important functions: the construction enclosure isolates the construction area from the personnel activity area and the pedestrian area, thereby ensuring the smooth construction; besides, the enclosure can beautify the construction environment. The enclosure not only represents the image of a construction unit, but also shows the level of the construction and building industries of a city, and directly influences the life of residents and the environment of the city.
The construction enclosure used in large scale at present mainly has two forms: firstly, building blocks are adopted for building, the method is time-consuming and labor-consuming, the construction enclosure is often used as a temporary structure, once construction is finished, the construction enclosure is dismantled, the dismantled building blocks are difficult to reuse, and the building blocks are often used as construction waste for treatment, so that environmental burden is caused; and secondly, a steel structure enclosure is adopted, galvanized corrugated boards and color steel tiles are often adopted as the enclosure in a construction side, the enclosure is high in manufacturing cost, poor in durability, poor in rigidity and easy to deform, and is often easy to damage when meeting the conditions of strong wind and the like, and the enclosure is difficult to ensure to be complete in the dismantling process after construction, is difficult to recycle, and causes resource waste.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an assembled recycled concrete construction is with enclosing fender, equipment convenient and fast more, also convenient and fast when demolising.
The purpose of the utility model is realized like this: the utility model provides an assembled recycled concrete construction is with enclosing fender, includes multiunit supporting component and connects two liang of adjacent supporting component's oblique acanthus leaf, supporting component comprises base and stand, the stand cartridge is in the base, links to each other through the oblique acanthus leaf between the adjacent two stands, the top of adjacent two stands links to each other through the fixed plate, accomplishes the fixed of adjacent two stands.
When the utility model is installed, the base is pre-buried under or fixed on the ground, the stand columns are inserted into the base, the inclined blade plates are sequentially inserted into the chutes on the two adjacent stand columns from bottom to top, and finally, the two ends of the fixing plate are inserted into the tops of the two adjacent stand columns to complete the fixed connection of the two adjacent stand columns, and the inclined blade plates are clamped in the chutes to complete the fixation; when the upright post is disassembled, the fixing plate is moved out firstly, the inclined blade plate is pulled out from the inclined groove, and finally the upright post is pulled out to complete the disassembly. Compared with the prior art, the beneficial effects of the utility model reside in that, the utility model discloses use assembled structure to accomplish to enclose putting up of fender and make to enclose to keep up to put up and demolish convenient and fast more, and the similar shutter structure of assembly mode of oblique vane, ventilation performance is better. The utility model discloses can be used to in the middle of the engineering construction.
In order to make the pedestal mounting more convenient, the base includes first square platform and second square platform, first square platform area is less than the second square platform, and first square platform sets up on the second square platform, the square hole that stretches into in the second square platform is seted up at second square platform center, and the dress stand is inserted in the square hole. The stability of two-layer square platform structure is higher when pre-buried in the bottom.
In order to enable the inclined blade plates to be more conveniently inserted into the stand column, a plurality of chutes for inserting the inclined blade plates are arranged from the upper right to the lower right of the side part of the stand column.
As a further limitation of the utility model, the depth of the chute is 20 plus or minus 2cm, and the thickness of the inclined blade plate is 20 plus or minus 2 cm.
In order to enable the fixing plate and the upright post to be assembled more conveniently and reliably, the top of the upright post is provided with a T-shaped notch for inserting the fixing plate, and two ends of the fixing plate are processed into T-shaped heads matched with the T-shaped notch.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic view of the structure of the center pillar of the present invention.
Fig. 3 is a schematic structural diagram of the middle fixing plate of the present invention.
Fig. 4 is a schematic view of the structure of the middle base of the present invention.
Fig. 5 is a schematic diagram of the structure of the middle inclined blade plate of the present invention.
Detailed Description
As shown in fig. 1-5, the assembled recycled concrete construction fence comprises a plurality of groups of supporting components and inclined vane plates 3 connecting two adjacent supporting components, each supporting component comprises a base 1 and an upright post 2, the upright posts 2 are inserted in the base 1, two adjacent upright posts 2 are connected through the inclined vane plates 3, a plurality of inclined grooves 2a for inserting the inclined vane plates 3 are arranged on the side portions of the upright posts 2 from top right to bottom, the depth of each inclined groove 2a is 20 +/-2 cm, the thickness of each inclined vane plate 3 is 20 +/-2 cm, the tops of two adjacent upright posts 2 are connected through fixing plates 4 to complete the fixing of the two adjacent upright posts 2, T-shaped notches 2B for inserting the fixing plates 4 are arranged on the tops of the upright posts 2, two ends of each fixing plate 4 are processed into T-shaped heads 4A matched with the T-shaped notches 2B, the base 1 comprises a first square platform 1a and a second square platform 1B, the area of the first square platform 1a is smaller than that of the second square platform 1B, and first square platform 1a sets up on second square platform 1B, and the square hole 1c that stretches into in second square platform 1B is seted up at second square platform 1B center, and dress stand 2 is inserted in the square hole 1c, can pre-buried steel sheet strengthen in T-slot notch 2B and the chute 2a, and the oblique lamina membranacea 3 can be prefabricated into middle trompil form to alleviate the dead weight.
When the utility model is installed, the base 1 is pre-buried under or fixed on the ground, the upright posts 2 are inserted into the base 1, the inclined blade plates 3 are sequentially inserted into the chutes 2a on the two adjacent upright posts 2 from bottom to top, and finally, the two ends of the fixing plate 4 are inserted into the tops of the two adjacent upright posts 2 to complete the fixed connection of the two adjacent upright posts 2, and the inclined blade plates 3 are clamped in the chutes 2a to complete the fixation; when the upright post is disassembled, the fixing plate 4 is moved out firstly, then the inclined blade plate 3 is pulled out from the inclined groove 2a, and finally the upright post 2 is pulled out to complete the disassembly.
The present invention is not limited to the above embodiments, and based on the technical solutions disclosed in the present invention, those skilled in the art can make some replacements and transformations for some technical features without creative labor according to the disclosed technical contents, and these replacements and transformations are all within the protection scope of the present invention.

Claims (5)

1. The utility model provides an assembled recycled concrete construction is with enclosing fender, its characterized in that, includes multiunit supporting component and connects two liang of adjacent supporting component's oblique acanthus leaf, supporting component comprises base and stand, the stand cartridge is in the base, links to each other through the oblique acanthus leaf between the two adjacent stands, the top of two adjacent stands links to each other through the fixed plate, accomplishes the fixed of two adjacent stands.
2. The assembly type recycled concrete construction enclosure according to claim 1, wherein the base comprises a first square platform and a second square platform, the area of the first square platform is smaller than that of the second square platform, the first square platform is arranged on the second square platform, a square hole extending into the second square platform is formed in the center of the second square platform, and a stand column is inserted into the square hole.
3. The fabricated recycled concrete construction fence as claimed in claim 1 or 2, wherein the side parts of the upright posts are provided with a plurality of chutes from top right to bottom for inserting the inclined blades.
4. The fabricated recycled concrete construction fence as recited in claim 3, wherein the depth of the inclined groove is 20 ± 2cm, and the thickness of the inclined blade plate is 20 ± 2 cm.
5. The assembly type recycled concrete construction fence as claimed in claim 1 or 2, wherein a T-shaped notch for inserting a fixing plate is formed at the top of the upright column, and two ends of the fixing plate are processed into T-shaped heads matched with the T-shaped notch.
CN201920493035.1U 2019-04-12 2019-04-12 Assembled recycled concrete construction is with enclosing fender Active CN210086988U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920493035.1U CN210086988U (en) 2019-04-12 2019-04-12 Assembled recycled concrete construction is with enclosing fender

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920493035.1U CN210086988U (en) 2019-04-12 2019-04-12 Assembled recycled concrete construction is with enclosing fender

Publications (1)

Publication Number Publication Date
CN210086988U true CN210086988U (en) 2020-02-18

Family

ID=69474193

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920493035.1U Active CN210086988U (en) 2019-04-12 2019-04-12 Assembled recycled concrete construction is with enclosing fender

Country Status (1)

Country Link
CN (1) CN210086988U (en)

Similar Documents

Publication Publication Date Title
CN111734031A (en) Fast-assembling and fast-disassembling formwork system of building multi-ribbed structure and construction process thereof
CN104806008B (en) Assembly method of general composite steel formwork device for concrete firewall
CN210086988U (en) Assembled recycled concrete construction is with enclosing fender
CN106351429B (en) A kind of Process for Heavy Support system and its construction method
CN217232907U (en) Folding fan-shaped classical landscape corridor frame
CN215803723U (en) But reuse's assembled steel encloses fender
CN210818054U (en) Adjustable jig frame for positioning precast beam guardrail reinforcing steel bars
CN210685597U (en) Novel buckle pressing type building enclosure
CN216076213U (en) Cantilever formwork platform mounting structure
CN219431452U (en) Combined steel lattice column for supporting
CN215246819U (en) Prefabricated wall body inserting frame capable of being used for people
CN209942384U (en) Assembled enclosure wall unit structure and assembled enclosure wall
CN214530760U (en) Precast concrete equipment basis side forms
CN110593081A (en) Component hoisting walking foundation for large railway station house under complex environment and construction method
CN213330154U (en) Energy-saving building supporting structure
CN212535326U (en) Assembled fender
CN210201668U (en) Combined stator core lamination auxiliary platform
CN218715808U (en) Assembled construction enclosure
CN218816757U (en) Fan mounting system on roof with structural beams
CN217500525U (en) Mobile box house with excellent anti-seismic effect
CN211369072U (en) High and cold area barracks base girder framework
CN217205838U (en) Assembled fender of building site
CN214614983U (en) Environment-friendly energy-saving steel structure assembled wallboard
CN214996323U (en) Modularization support piece for building
CN215165640U (en) Adopt supporting construction of UHPC and Larsen steel sheet pile combination

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant