CN210074185U - 一种电力施工用接地装置 - Google Patents
一种电力施工用接地装置 Download PDFInfo
- Publication number
- CN210074185U CN210074185U CN201921383215.0U CN201921383215U CN210074185U CN 210074185 U CN210074185 U CN 210074185U CN 201921383215 U CN201921383215 U CN 201921383215U CN 210074185 U CN210074185 U CN 210074185U
- Authority
- CN
- China
- Prior art keywords
- grounding
- wire
- support frame
- electric power
- power construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 19
- 230000005611 electricity Effects 0.000 claims abstract description 16
- 239000000789 fastener Substances 0.000 claims abstract description 12
- 108010034748 copper-binding protein Proteins 0.000 claims description 3
- 239000010985 leather Substances 0.000 claims description 3
- 239000004593 Epoxy Substances 0.000 claims description 2
- 229910000831 Steel Inorganic materials 0.000 claims description 2
- 125000003700 epoxy group Chemical group 0.000 claims description 2
- 239000011521 glass Substances 0.000 claims description 2
- 239000000463 material Substances 0.000 claims description 2
- 239000010959 steel Substances 0.000 claims description 2
- 238000004804 winding Methods 0.000 abstract description 9
- 230000002349 favourable Effects 0.000 abstract description 3
- RYGMFSIKBFXOCR-UHFFFAOYSA-N copper Chemical compound data:image/svg+xml;base64,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 data:image/svg+xml;base64,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 [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 6
- 229910052802 copper Inorganic materials 0.000 description 6
- 239000010949 copper Substances 0.000 description 6
- 238000000034 method Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 239000003822 epoxy resin Substances 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 229920000647 polyepoxide Polymers 0.000 description 2
- 229910000838 Al alloy Inorganic materials 0.000 description 1
- 210000003128 Head Anatomy 0.000 description 1
- 210000001503 Joints Anatomy 0.000 description 1
- 210000001331 Nose Anatomy 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 230000000739 chaotic Effects 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 201000010099 disease Diseases 0.000 description 1
- 239000011152 fibreglass Substances 0.000 description 1
- 230000004301 light adaptation Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006011 modification reaction Methods 0.000 description 1
- MYMOFIZGZYHOMD-UHFFFAOYSA-N oxygen Chemical compound data:image/svg+xml;base64,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 data:image/svg+xml;base64,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 O=O MYMOFIZGZYHOMD-UHFFFAOYSA-N 0.000 description 1
- 229910052760 oxygen Inorganic materials 0.000 description 1
- 239000001301 oxygen Substances 0.000 description 1
- 239000002965 rope Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000004381 surface treatment Methods 0.000 description 1
Abstract
本实用新型公开了一种电力施工用接地装置,包括接地装置和收容装置,所述接地装置包括接地桩以及接地桩上桩头螺纹连接的导线,所述导线远离接地桩的一端固定连接有线夹,所述线夹的上表面固定连接有验电针,所述线夹的底部固定连接有绝缘操作杆,所述绝缘操作杆靠近线夹的位置固定连接有验电器,所述验电器的正面设置有自检开关。通过设置验电器,可以将验电、挂接地两个步骤合二为一,提高了工作效率,通过设置收容装置,可以轻松地将接地线通过绕线柱规整的绕在收容装置上,同时有效地防止因杂乱无章的缠绕造成的接线端子处连接不牢固、导线断股等问题,从而有利于接地线的保养也降低了安全隐患。
Description
技术领域
本实用新型涉及电力施工技术领域,具体为一种电力施工用接地装置。
背景技术
接地线就是直接连接地球的线,也可以称为安全回路线,危险时它就把高压直接转嫁给地球,算是一根生命线,其作用是对设备进行停电检修或进行其他工作时,在已停电的设备和线路上意外地出现电压时保证工作人员安全的重要工具,同时泄放断电设备的剩余电荷,接地线主要有三部分构成,接地端、导线、线夹,目前普遍应用的携带型短路接地线由绝缘操作杆、导线夹组成,导线夹采用优质铝合金压铸,强度高,再经表面处理使线夹表面不宜氧气,操作棒用进口环氧树脂精制成彩色管,绝缘性能好,强度高、重量轻、色彩鲜明、外表光滑。
在涉及停电的施工作业过程中,应当按照停电、验电、装设接地线的顺序逐步操作,根据《安规》规定监护人员是不允许在杆塔下传递工具的,所以在装设接地线的过程中就需要三个人才能完成,为了防止高空坠物,杆上作业人员在验电后不得不先将验电器用绳索传递给地勤人员再进行挂接地操作,导致工作繁琐且工作效率低下;此外,目前的接地线在取下整理时,通常都是将绝缘操作杆和接地桩并在一起,然后将导线用缠绕的方式绕在操作杆和接地桩上,这样不仅十分不方便,而且容易造成接线铜鼻子处松动或导线分股处断股,从而不利于安全工器具的日常保养并留下安全隐患。
实用新型内容
本实用新型的目的在于提供一种电力施工用接地装置,以解决上述背景技术中提出的问题。
为实现上述目的,本实用新型提供如下技术方案:一种电力施工用接地装置,包括接地装置和收容装置,所述接地装置包括接地桩以及接地桩上桩头螺纹连接的导线,所述导线远离接地桩的一端固定连接有线夹,所述线夹的上表面固定连接有验电针,所述线夹的底部固定连接有绝缘操作杆,所述绝缘操作杆靠近线夹的位置固定连接有验电器,所述验电器的正面设置有自检开关;所述收容装置包括第一支撑架和第二支撑架且两者之间转动连接有转轴,所述转轴表面固定连接有绕线柱,所述转轴的左右两端与第一支撑架和第二支撑架的连接处均设置有轴承,所述转轴的左侧延伸至第一支撑架的左侧且固定连接有摇把。
优选的,所述导线与线夹的连接处以及导线与接地桩的连接处均固定连接有铜接线端子,所述铜接线端子与线夹和接地桩之间用双螺帽螺纹连接。
优选的,所述验电器为声光型验电器,所述绝缘操作杆为可伸缩杆,该绝缘操作杆的材质为玻璃钢环氧树脂杆且其底部固定连接有绝缘握把。
优选的,所述第一支撑架与第二支撑架的顶部之间固定连接有提手。
优选的,所述第一支撑架的顶部右侧固定连接有导线挂钩,所述导线挂钩的表面包裹有皮革。
优选的,所述第二支撑架的顶部开设有储放槽,所述储放槽的长度与绝缘操作杆的长度相适配。
有益效果
本实用新型提供了一种电力施工用接地装置,具备以下有益效果:
1.该一种电力施工用接地装置,通过设置验电器,使得作业人员在涉及停电的作业任务中,不需要在杆塔上反复传递安全工器具,而是通过接地线上的绝缘操作杆进行验电,可以将验电、挂接地两个步骤合二为一,从而提高了工作效率。
2.该一种电力施工用接地装置,通过设置收容装置,使得作业人员在作业任务完成后可以轻松地将接地线通过绕线柱规整的绕在收容装置上,让下次使用接地线时能更加方便地取出,同时收容装置能够有效地防止因杂乱无章的缠绕造成的接线端子处连接不牢固、导线断股等问题,从而有利于接地线的保养也降低了安全隐患。
附图说明
图1为本实用新型正剖结构示意图;
图2为本实用新型接地装置结构示意图。
图中:1接地桩、2导线、3线夹、4验电针、5绝缘操作杆、6验电器、7自检开关、8第一支撑架、9第二支撑架、10转轴、11绕线柱、12轴承、13摇把、14铜接线端子、15绝缘握把、16提手、17导线挂钩、18储放槽。
具体实施方式
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。
请参阅图1-2,本实用新型提供一种技术方案:一种电力施工用接地装置,包括接地装置和收容装置,接地装置包括接地桩1以及接地桩1上桩头螺纹连接的导线2,导线2远离接地桩1的一端固定连接有线夹3,线夹3的上表面固定连接有验电针4,线夹3的底部固定连接有绝缘操作杆5,绝缘操作杆5靠近线夹3的位置固定连接有验电器6,验电器6的正面设置有自检开关7,通过设置验电器6,使得作业人员在涉及停电的作业任务中,不需要在杆塔上反复传递安全工器具,而是通过接地线上的绝缘操作杆5进行验电,可以将验电、挂接地两个步骤合二为一,从而提高了工作效率。
收容装置包括第一支撑架8和第二支撑架9且两者之间转动连接有转轴10,所述转轴10表面固定连接有绕线柱11,转轴10的左右两端与第一支撑架8和第二支撑架9的连接处均设置有轴承12,转轴10的左侧延伸至第一支撑架8的左侧且固定连接有摇把13,导线2与线夹3的连接处以及导线2与接地桩1的连接处均固定连接有铜接线端子14,铜接线端子14与线夹3和接地桩1之间用双螺帽螺纹连接,验电器6为声光型验电器,绝缘操作杆5为可伸缩杆,该绝缘操作杆5的材质为玻璃钢环氧树脂杆且其底部固定连接有绝缘握把15,第一支撑架8与第二支撑架9的顶部之间固定连接有提手16,第一支撑架8的顶部右侧固定连接有导线挂钩17,导线挂钩16的表面包裹有皮革,第二支撑架9的顶部开设有储放槽18,储放槽18的长度与绝缘操作杆5的长度相适配,通过设置收容装置,使得作业人员在作业任务完成后可以轻松地将接地线通过绕线柱8规整的绕在收容装置上,让下次使用接地线时能更加方便地取出,同时,收容装置能够有效地防止因杂乱无章的缠绕造成的铜接线端子13处连接不牢固、导线断股等问题,从而有利于接地线的保养也降低了安全隐患。
工作原理:一种电力施工用接地装置在使用时,从储放槽18中取出绝缘操作杆5和接地桩1,将接地桩1插入大地,按下自检开关7判断验电器6是否工作正常,将绝缘操作杆5完全拉伸出,在完成验电后将线夹3分别卡进工作线路中的接地线夹上,在工作结束后将绝缘操作杆5和接地桩1放进储放槽18,转动摇把13将导线2绕在绕线柱11上,从而使作业过程中的安全性得到提高也让收放接地线更为方便。
尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。
Claims (6)
1.一种电力施工用接地装置,包括接地装置和收容装置,其特征在于:所述接地装置包括接地桩(1)以及接地桩(1)上桩头螺纹连接的导线(2),所述导线(2)远离接地桩(1)的一端固定连接有线夹(3),所述线夹(3)的上表面固定连接有验电针(4),所述线夹(3)的底部固定连接有绝缘操作杆(5),所述绝缘操作杆(5)靠近线夹(3)的位置固定连接有验电器(6),所述验电器(6)的正面设置有自检开关(7);所述收容装置包括第一支撑架(8)和第二支撑架(9)且两者之间转动连接有转轴(10),所述转轴(10)表面固定连接有绕线柱(11),所述转轴(10)的左右两端与第一支撑架(8)和第二支撑架(9)的连接处均设置有轴承(12),所述转轴(10)的左侧延伸至第一支撑架(8)的左侧且固定连接有摇把(13)。
2.根据权利要求1所述的一种电力施工用接地装置,其特征在于:所述导线(2)与线夹(3)的连接处以及导线(2)与接地桩(1)的连接处均固定连接有铜接线端子(14),所述铜接线端子(14)与线夹(3)和接地桩(1)之间用双螺帽螺纹连接。
3.根据权利要求1所述的一种电力施工用接地装置,其特征在于:所述验电器(6)为声光型验电器,所述绝缘操作杆(5)为可伸缩杆,该绝缘操作杆(5)的材质为玻璃钢环氧树脂杆且其底部固定连接有绝缘握把(15)。
4.根据权利要求1所述的一种电力施工用接地装置,其特征在于:所述第一支撑架(8)与第二支撑架(9)的顶部之间固定连接有提手(16)。
5.根据权利要求1所述的一种电力施工用接地装置,其特征在于:所述第一支撑架(8)的顶部右侧固定连接有导线挂钩(17),所述导线挂钩(17)的表面包裹有皮革。
6.根据权利要求1所述的一种电力施工用接地装置,其特征在于:所述第二支撑架(9)的顶部开设有储放槽(18),所述储放槽(18)的长度与绝缘操作杆(5)的长度相适配。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921383215.0U CN210074185U (zh) | 2019-08-23 | 2019-08-23 | 一种电力施工用接地装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921383215.0U CN210074185U (zh) | 2019-08-23 | 2019-08-23 | 一种电力施工用接地装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210074185U true CN210074185U (zh) | 2020-02-14 |
Family
ID=69431263
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921383215.0U Active CN210074185U (zh) | 2019-08-23 | 2019-08-23 | 一种电力施工用接地装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210074185U (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112117563A (zh) * | 2020-09-18 | 2020-12-22 | 国网河南省电力公司栾川县供电公司 | 一种便携式电力施工接地装置 |
-
2019
- 2019-08-23 CN CN201921383215.0U patent/CN210074185U/zh active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112117563A (zh) * | 2020-09-18 | 2020-12-22 | 国网河南省电力公司栾川县供电公司 | 一种便携式电力施工接地装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210074185U (zh) | 一种电力施工用接地装置 | |
CN104868403A (zh) | 一种便携式120~400mm2钢芯铝绞线分流线卡具及使用方法 | |
CN202797769U (zh) | 110kV线路门型杆边相带电更换绝缘子工具 | |
CN201717173U (zh) | 220kv垂直开启式隔离开关分流装置 | |
CN201319480Y (zh) | 电缆头接地线装置 | |
CN207218127U (zh) | 一种高强度马道杆 | |
CN210490302U (zh) | 一种折叠式多功能电力施工用接线架 | |
CN209125795U (zh) | 一种基于集中器本地计算的低压台区管理作业平台结构 | |
CN201584691U (zh) | 220kv双回共塔线路进入耐张高压强电场的专用工具 | |
CN204167520U (zh) | 一种用于10kV配电网的带电临时搭头装置 | |
CN208479029U (zh) | 一种钢绞线拉线线夹 | |
CN110676607A (zh) | 一种可带电作业的并沟搭接器及其操作方法 | |
CN110661212A (zh) | 一种可带电作业的异型并沟搭接器及其操作方法 | |
CN110601095A (zh) | 一种可带电作业的复合型并沟搭接器及其操作方法 | |
CN202487794U (zh) | 接地线连接器 | |
CN214192314U (zh) | 一种35kV变电站10kV柱上断路器吊装工具 | |
CN214046942U (zh) | 便携式树木倒向控制工具 | |
CN214754624U (zh) | 一种装拆三相短路接地线的绝缘辅助工具 | |
CN213935786U (zh) | 一种高压输电线路用组合式绝缘子 | |
CN203466502U (zh) | 一种电力安装紧线装置 | |
CN214493345U (zh) | 一种用于无人机的伸缩杆式吊爪装置 | |
CN202888772U (zh) | 一种应用于挂钩式接地线的展放缠绕车 | |
CN202689667U (zh) | 用于环形钢筋混凝土结构通信杆塔馈线架装置 | |
CN214068916U (zh) | 一种新型10kV电缆户外终端头接地挂环 | |
CN203466399U (zh) | 一种用于滑触线分段装置指示灯的接线装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |