CN210066510U - Stride interim bearing structure of girder steel of existing circuit - Google Patents

Stride interim bearing structure of girder steel of existing circuit Download PDF

Info

Publication number
CN210066510U
CN210066510U CN201920537023.4U CN201920537023U CN210066510U CN 210066510 U CN210066510 U CN 210066510U CN 201920537023 U CN201920537023 U CN 201920537023U CN 210066510 U CN210066510 U CN 210066510U
Authority
CN
China
Prior art keywords
steel beam
existing line
steel
stringer
longitudinal beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920537023.4U
Other languages
Chinese (zh)
Inventor
徐永
李桐
周超
傅存海
童清
徐德森
王作轩
刘静静
祁经炜
周俊韬
王彦辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Science and Industry Rail Transit Equipment Co Ltd
Original Assignee
China Railway Science and Industry Rail Transit Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Science and Industry Rail Transit Equipment Co Ltd filed Critical China Railway Science and Industry Rail Transit Equipment Co Ltd
Priority to CN201920537023.4U priority Critical patent/CN210066510U/en
Application granted granted Critical
Publication of CN210066510U publication Critical patent/CN210066510U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型公开了一种跨既有线路的钢梁临时支撑结构,包括两组支撑系统,以及承托架;两组支撑系统对称分设于既有线路的两侧,支撑系统的下端设于地面上;所述承托架横跨既有线路且安装于两个支撑系统上;待安装的钢梁分段吊装于承托架上。一种跨既有线路的钢梁段施工方法。本实用新型的有益效果为:本实用新型所述临时支撑结构及钢梁施工方法,在不妨碍既有线路正常通行的情况下,即可完成跨既有线路钢梁的吊装,这种直接利用吊车分块吊装的方法弥补了传统顶推法使用过程中的不足之处和局限性;并且本实用新型还适用于钢梁整联超重无法整体吊装而只能分片吊装的情况,以及待施工钢梁位于半径和弧度线型相对较大的圆曲线上等情况。

Figure 201920537023

The utility model discloses a temporary support structure of a steel beam spanning an existing line, comprising two sets of support systems and a bearing bracket; the two sets of support systems are symmetrically arranged on both sides of the existing line, and the lower end of the support system is arranged on the ground The bearing bracket spans the existing line and is installed on two support systems; the steel beam to be installed is hoisted on the bearing bracket in sections. A construction method of a steel beam section spanning an existing line. The beneficial effects of the utility model are as follows: the temporary support structure and the steel beam construction method of the utility model can complete the hoisting of the steel beam across the existing line without hindering the normal passage of the existing line. The method of hoisting the crane in blocks makes up for the deficiencies and limitations of the traditional jacking method; and the utility model is also suitable for the situation where the steel beam is overweight and cannot be hoisted as a whole but can only be hoisted in pieces, and the construction The steel beam is located on a circular curve with a relatively large radius and radian line type, etc.

Figure 201920537023

Description

一种跨既有线路的钢梁临时支撑结构A Temporary Support Structure of Steel Beams Across Existing Lines

技术领域technical field

本实用新型涉及桥梁施工技术领域,具体涉及一种跨既有线路的钢梁临时支撑结构。The utility model relates to the technical field of bridge construction, in particular to a temporary support structure of steel beams spanning existing lines.

背景技术Background technique

随着我国基础设施建设和交通运输行业的快速发展,跨海跨河以及陆地上的公路铁路桥梁的修建也越来越多,各种桥梁施工架设的复杂环境和工况也成为了不小的挑战。不同的桥梁由于施工环境各有差别决定了不同的施工方法,涉及不同临时支撑和安装技术。此外,由于考虑到工程进度与施工速度、安全性以及经济性等因素,故在桥梁的建设安装过程中,如何在满足技术需要及经济要求的条件下优选临时支撑及其施工方法是关键所在,也是继续解决的重点技术问题。With the rapid development of infrastructure construction and transportation industry in China, more and more road and railway bridges are being built across seas, rivers and on land, and the complex environment and working conditions of various bridge construction have also become a big problem. challenge. Different bridges have different construction methods due to their different construction environments, involving different temporary support and installation techniques. In addition, due to factors such as project schedule, construction speed, safety and economy, during the construction and installation of bridges, how to select temporary supports and construction methods under the conditions of meeting technical and economic requirements is the key. It is also a key technical problem that continues to be solved.

目前,国内比较成熟的钢梁架设方案主要有:膺架法、浮吊架设法及顶推架设法,膺架法简言之就是让混凝土桥在落地式膺架(也称脚手架)上现浇或拼装预制节段;而浮吊架设法则主要用于水上施工;顶推架设法是指当结构物要在既有线的路堤下方通过时,为了不扰动既有线,可以在路堤一侧将结构物分段建成,再用千斤顶顶推,使之穿过路堤的方法。At present, the more mature steel beam erection schemes in China mainly include: the scaffolding method, the floating hanger method and the jacking frame method. Or assemble prefabricated segments; while the floating hanger method is mainly used for water construction; the jacking frame method means that when the structure is to pass under the embankment of the existing line, in order not to disturb the existing line, the structure can be placed on the side of the embankment. It is built in sections and then pushed with a jack to make it pass through the embankment.

传统的跨既有线路的钢梁施工,一般采用顶推架设法施工,顶推施工时不影响桥下交通,不需要大型起重设备,也没有高空作业,特别适合于城市桥梁特大跨度桥梁,长线引桥或立体交叉的施工;由于梁段在固定场地上周期性施工,因此施工质量和施工进度容易保证。但是,顶推施工法存在以下明显缺陷:对桥梁结构的几何外形限制较多,变截面梁段、曲线型梁轴和变坡度桥梁均无法采用顶推施工;由于顶推过程中桥跨结构的受力不断变化,将会增加梁高和材料用量,特别是预应力钢筋的用量,受顶推悬臂弯矩的限制,顶推跨径大于70~80米不经济;顶推过程中的反复应力,使梁高取值大,临时束多,张拉工序繁琐;此外,顶推施工最多也只能有两个工作面,也限制了顶推施工的速度。The traditional construction of steel beams spanning existing lines is generally constructed by using jacking frames. During jacking construction, it does not affect the traffic under the bridge, does not require large lifting equipment, and does not require high-altitude operations. It is especially suitable for urban bridges with extra-large spans. Construction of long-term approach bridges or three-dimensional crossings; since the beam sections are constructed periodically on a fixed site, the construction quality and construction progress can be easily guaranteed. However, the jacking construction method has the following obvious defects: there are many restrictions on the geometric shape of the bridge structure. The constant change of the force will increase the beam height and the amount of materials, especially the amount of prestressed steel bars. Due to the limitation of the bending moment of the jacking cantilever, it is uneconomical for the jacking span to exceed 70-80 meters; the repeated stress during the jacking process , so that the beam height is large, there are many temporary beams, and the tensioning process is cumbersome; in addition, the jacking construction can only have two working faces at most, which also limits the speed of the jacking construction.

发明内容SUMMARY OF THE INVENTION

本实用新型的目的在于,针对现有技术的不足,提供一种跨既有线路的钢梁安装临时支撑结构。The purpose of the utility model is to provide a temporary support structure for installing a steel beam across an existing line in view of the deficiencies of the prior art.

本实用新型采用的技术方案为:一种跨既有线路的钢梁临时支撑结构,包括两组支撑系统,以及承托架;两组支撑系统对称分设于既有线路的两侧,支撑系统的下端设于地面上;所述承托架横跨既有线路且安装于两个支撑系统上;待安装的钢梁分段吊装于承托架上。The technical scheme adopted by the utility model is as follows: a temporary support structure of steel beams spanning an existing line, comprising two sets of support systems and a bearing bracket; the two sets of support systems are symmetrically arranged on both sides of the existing line, The lower end is set on the ground; the bearing bracket spans the existing line and is installed on two support systems; the steel beam to be installed is hoisted on the bearing bracket in sections.

按上述方案,所述承托架为由若干横向等间距布置的横梁,以及若干纵向等间距布置的纵梁相互连接形成稳定的框架架构。According to the above solution, the support bracket is formed by a plurality of horizontal beams arranged at equal intervals and a plurality of longitudinal beams arranged at equal intervals in the longitudinal direction to form a stable frame structure.

按上述方案,所述纵梁包括纵梁主体、纵梁面板和纵梁腹板,所述纵梁面板固定于纵梁主体的上表面和下表面,纵梁腹板固定于纵梁主体的两个外侧面。According to the above solution, the longitudinal beam includes a longitudinal beam main body, a longitudinal beam panel and a longitudinal beam web, the longitudinal beam panel is fixed to the upper surface and the lower surface of the longitudinal beam main body, and the longitudinal beam web is fixed to the two sides of the longitudinal beam main body. an outer side.

按上述方案,所述纵梁主体包括若干沿纵梁长度方向间隔布置的纵梁隔板,以及多个纵梁加强肋;所述纵梁隔板为框型结构,纵梁隔板上开设与纵梁加强肋数量和位置匹配的安装孔;纵梁加强肋依次穿过所有纵梁隔板对应位置的安装孔,纵梁隔板和纵梁加强肋共同形成纵梁主体结构。According to the above scheme, the longitudinal beam main body includes a plurality of longitudinal beam partitions arranged at intervals along the longitudinal direction of the longitudinal beam, and a plurality of longitudinal beam reinforcement ribs; the longitudinal beam partitions are frame-shaped structures, and the longitudinal beam partitions are provided with The number and position of the longitudinal beam reinforcement ribs are matched with the installation holes; the longitudinal beam reinforcement ribs pass through the installation holes at the corresponding positions of all the longitudinal beam partition plates in turn, and the longitudinal beam partition plates and the longitudinal beam reinforcement ribs together form the longitudinal beam main structure.

按上述方案,每个支撑系统包括多个沿既有线路长度方向间隔安装的支腿结构,每个支腿结构包括预埋基座、若干立杆及搭接结构,所有立杆的下端均与预埋基座固定相连,所有立杆的上端均与搭接结构相连.According to the above scheme, each support system includes a plurality of outrigger structures installed at intervals along the length of the existing line, each outrigger structure includes a pre-embedded base, a number of vertical rods and a lap joint structure, and the lower ends of all the vertical rods are connected to the The pre-embedded bases are fixedly connected, and the upper ends of all vertical poles are connected with the lap joint structure.

按上述方案,相邻两根立杆之间沿轴线方向间隔安装若干立杆横撑;所述承托架的两侧分别固定在搭接结构上。According to the above scheme, a number of vertical rod cross braces are installed at intervals along the axis direction between two adjacent vertical rods; the two sides of the bearing bracket are respectively fixed on the overlapping structure.

按上述方案,所述搭接结构包括两根平行的短杆,以及固定于两根连杆上部的支座横撑;所述连杆固定于连接同列/同行立杆上端的垫板上,支座横撑的两侧设多个竖向加劲板;所述承托架固定于支座横撑上。According to the above scheme, the lap joint structure includes two parallel short rods, and a support cross brace fixed on the upper part of the two connecting rods; A plurality of vertical stiffening plates are arranged on both sides of the cross support of the seat; the bearing bracket is fixed on the cross support of the support.

按上述方案,在立杆的上端安装水平的垫板,且垫板的外沿径向向外延伸;垫板的延伸段与立杆的外壁之间设多个沿周向间隔布置的三角筋板。According to the above scheme, a horizontal backing plate is installed on the upper end of the vertical rod, and the outer edge of the backing plate extends radially outward; a plurality of triangular ribs arranged at intervals in the circumferential direction are arranged between the extended section of the backing plate and the outer wall of the vertical rod plate.

本实用新型的有益效果为:本发明所述临时支撑结构,在不妨碍既有线路正常通行的情况下,即可完成跨既有线路钢梁的吊装,这种直接利用吊车分块吊装的方法弥补了传统顶推法使用过程中的不足之处和局限性;并且本发明还适用于钢梁整联超重无法整体吊装而只能分片吊装的情况,以及待施工钢梁位于半径和弧度线型相对较大的圆曲线上等情况;本发明中的临时支撑结构整体性能高、稳定性强,安全可靠,同时搭设及拆卸方便迅速,施工速度快;临时支撑结构采用钢管柱、槽钢、工字钢、自制简梁等通用性较高的材料制成,成本较低,拆卸后的材料可重复利用。The beneficial effects of the present invention are as follows: the temporary support structure of the present invention can complete the hoisting of the steel beam across the existing line without hindering the normal passage of the existing line. It makes up for the shortcomings and limitations of the traditional jacking method; and the invention is also applicable to the situation where the steel beam is overweight and cannot be hoisted as a whole but can only be hoisted in pieces, and the steel beam to be constructed is located on the radius and radian lines. The overall performance of the temporary support structure in the present invention is high, the stability is strong, safe and reliable, and the erection and disassembly are convenient and rapid, and the construction speed is fast; the temporary support structure adopts steel pipe columns, channel steel, It is made of materials with high versatility such as I-beam and self-made simple beams, and the cost is low, and the disassembled materials can be reused.

附图说明Description of drawings

图1为本实用新型一个具体实施例中临时支撑结构与既有线路的位置示意图。FIG. 1 is a schematic diagram of the positions of a temporary support structure and an existing line in a specific embodiment of the present invention.

图2为临时支撑结构的整体示意图。FIG. 2 is an overall schematic diagram of the temporary support structure.

图3为本实施例中支腿结构的示意图。FIG. 3 is a schematic diagram of the structure of the legs in this embodiment.

图4为本实施例中支腿结构与搭接结构的连接示意图。FIG. 4 is a schematic diagram of the connection between the leg structure and the overlapping structure in this embodiment.

图5为本实施例中立杆横撑的结构示意图。FIG. 5 is a schematic structural diagram of a vertical pole cross brace in this embodiment.

图6为本实施例中纵杆的结构示意图。FIG. 6 is a schematic structural diagram of a vertical rod in this embodiment.

图7为本实施例中既有线路与待施工钢梁位置示意图。FIG. 7 is a schematic diagram of the positions of existing lines and steel beams to be constructed in this embodiment.

图8为本实施例中两墩柱之间钢梁分段示意图。FIG. 8 is a schematic diagram of a section of a steel beam between two pier columns in this embodiment.

图9为本实施例中钢梁段A的分块示意图。FIG. 9 is a block schematic diagram of the steel beam section A in this embodiment.

图10为本实施例中钢梁块A分区内各片吊装时吊车位置示意图一(左区)。FIG. 10 is a schematic diagram 1 (left area) of the position of the crane when each piece of the steel beam block A is hoisted in this embodiment.

图11为本实施例中钢梁块A分区内各片吊装时吊车位置示意图二(右区)。FIG. 11 is a schematic diagram 2 (right area) of the position of the crane when each piece of the steel beam block A is hoisted in this embodiment.

图12为本实施例中吊车吊装钢梁段A时的位置示意图。FIG. 12 is a schematic diagram of the position of the crane when the steel beam section A is hoisted in this embodiment.

图13为本实施例中吊车吊装钢梁段B时的位置示意图。FIG. 13 is a schematic diagram of the position when the steel beam section B is hoisted by a crane in this embodiment.

图14为本实施例中吊车吊装钢梁段C和钢梁段D时的位置示意图。FIG. 14 is a schematic diagram of the position of the crane when the steel beam section C and the steel beam section D are hoisted in this embodiment.

图15为本实施例中吊车吊装钢梁段E和钢梁段F时的位置示意图。FIG. 15 is a schematic diagram of the position of the crane when the steel beam section E and the steel beam section F are hoisted in this embodiment.

其中:1、既有线路;2、临时支撑结构;3、支撑系统;4、横梁;5、纵梁;6、支座横撑,7、短杆,8、垫板;9、立杆;10、立杆横撑;11预埋基座;12、竖向加劲板;13、三角筋板;14、连杆;15、端部连接板;16、纵梁加劲肋;17、纵梁隔板;18、纵梁连接板;19、纵梁腹板;20、纵梁面板;21、墩柱;22、支架结构;23、吊车;24、已完工钢梁。Among them: 1. Existing line; 2. Temporary support structure; 3. Support system; 4. Beam; 5. Longitudinal beam; 10. Vertical rod cross brace; 11. Pre-embedded base; 12. Vertical stiffening plate; 13. Triangular rib plate; 14. Connecting rod; 15. End connecting plate; plate; 18, longitudinal beam connecting plate; 19, longitudinal beam web; 20, longitudinal beam panel; 21, pier column; 22, support structure; 23, crane; 24, completed steel beam.

具体实施方式Detailed ways

为了更好地理解本实用新型,下面结合附图和具体实施例对本实用新型作进一步地描述。In order to better understand the present utility model, the present utility model will be further described below with reference to the accompanying drawings and specific embodiments.

如图1和图2所示的一种跨既有线路的钢梁临时支撑结构,包括两组支撑系统,以及承托架;两组支撑系统对称分设于既有线路的两侧,支撑系统的下端设于地面上;所述承托架横跨既有线路且安装于两个支撑系统上;待安装的钢梁分段吊装于承托架上。As shown in Figures 1 and 2, a temporary support structure of steel beams across an existing line includes two sets of support systems and bearing brackets; the two sets of support systems are symmetrically arranged on both sides of the existing line, and the The lower end is set on the ground; the bearing bracket spans the existing line and is installed on two support systems; the steel beam to be installed is hoisted on the bearing bracket in sections.

优选地,所述承托架为由若干横向等间距布置的横梁,以及若干纵向等间距布置的纵梁相互连接形成稳定的框架架构。如图6所示,所述纵梁包括纵梁主体、纵梁面板和纵梁腹板,所述纵梁面板固定于纵梁主体的上表面和下表面,纵梁腹板固定于纵梁主体的两个外侧面;所述纵梁主体包括若干沿纵梁长度方向间隔布置的纵梁隔板,以及多个纵梁加强肋;所述纵梁隔板为框型结构,纵梁隔板上开设与纵梁加强肋数量和位置匹配的安装孔;纵梁加强肋依次穿过所有纵梁隔板对应位置的安装孔,纵梁隔板和纵梁加强肋共同形成纵梁主体结构。Preferably, the support bracket is formed by a plurality of transverse beams arranged at equal intervals and a plurality of longitudinal beams arranged at equal intervals in the longitudinal direction to form a stable frame structure. As shown in FIG. 6 , the longitudinal beam includes a longitudinal beam main body, a longitudinal beam panel and a longitudinal beam web, the longitudinal beam panel is fixed to the upper surface and the lower surface of the longitudinal beam main body, and the longitudinal beam web is fixed to the longitudinal beam main body the two outer sides of the longitudinal beam; the longitudinal beam main body includes a number of longitudinal beam partitions spaced along the longitudinal direction of the longitudinal beam, and a plurality of longitudinal beam reinforcement ribs; The installation holes matching the number and position of the longitudinal beam reinforcement ribs are opened; the longitudinal beam reinforcement ribs pass through the installation holes at the corresponding positions of all the longitudinal beam partition plates in turn, and the longitudinal beam partition plates and the longitudinal beam reinforcement ribs together form the longitudinal beam main structure.

优选地,每个支撑系统包括多个沿既有线路长度方向间隔安装的支腿结构,如图4所示,每个支腿结构包括预埋基座、若干立杆及搭接结构,所有立杆的下端均与预埋基座固定相连,所有立杆的上端均与搭接结构相连;相邻两根立杆之间沿轴线方向间隔安装若干立杆横撑;所述承托架的两侧分别固定在搭接结构上。Preferably, each support system includes a plurality of outrigger structures installed at intervals along the length of the existing line. As shown in FIG. 4 , each outrigger structure includes a pre-embedded base, a number of vertical rods and a lap joint structure. The lower ends of the rods are fixedly connected to the pre-embedded bases, and the upper ends of all the vertical rods are connected to the lap joint structure; a number of vertical rod cross braces are installed at intervals along the axis direction between two adjacent vertical rods; respectively fixed on the overlapping structure.

优选地,在立杆的上端安装水平的垫板,且垫板的外沿径向向外延伸;垫板的延伸段与立杆的外壁之间设多个沿周向间隔布置的三角筋板。如图5所示,所述搭接结构包括两根平行的短杆,以及固定于两根连杆上部的支座横撑;所述连杆固定于连接同列/同行立杆上端的垫板上,支座横撑的两侧设多个竖向加劲板;所述承托架固定于支座横撑上。Preferably, a horizontal backing plate is installed on the upper end of the upright rod, and the outer portion of the backing plate extends radially outward; a plurality of triangular rib plates spaced in the circumferential direction are arranged between the extending section of the backing plate and the outer wall of the upright rod . As shown in FIG. 5 , the overlapping structure includes two parallel short rods and a support cross brace fixed on the upper part of the two connecting rods; the connecting rods are fixed on the backing plate connected to the upper ends of the vertical rods in the same row/column , a plurality of vertical stiffening plates are arranged on both sides of the horizontal support of the support; the support bracket is fixed on the horizontal support of the support.

本实施例中,横梁与纵梁各设三根,其中纵梁沿既有线路的宽度方向间隔布置,横梁沿既有线路的长度方向间隔布置。当既有线路较宽时,所需纵梁较长,可将两根纵梁采用连接板栓接成一体。所述横梁为H型钢。每个支撑系统包括三个沿既有线路长度方向间隔安装的支腿结构,每个支腿结构的预埋基座设两行两列布置的四根立杆,立杆的上端固定搭接结构;两根立杆之间沿立杆轴线方向间隔设置三组立杆横撑,立杆横撑的两端分别连接两根立杆,且立杆横撑的长度方向垂直于立杆的轴线方向。所述立杆采用螺旋钢管制成;连杆为槽钢,短杆为工字钢。立杆横撑包括连杆及连杆两端的端部连接板,连杆通过端部连接板与立杆的外壁相连。In this embodiment, there are three transverse beams and three longitudinal beams, wherein the longitudinal beams are arranged at intervals along the width direction of the existing line, and the transverse beams are arranged at intervals along the length direction of the existing line. When the existing line is wide, the required longitudinal beams are longer, and the two longitudinal beams can be bolted into one body by connecting plates. The beam is H-beam. Each support system includes three outrigger structures that are installed at intervals along the length of the existing line, the pre-embedded base of each outrigger structure is provided with four vertical rods arranged in two rows and two columns, and the upper ends of the vertical rods are fixed with overlapping structures; Three sets of vertical pole cross braces are arranged between the two vertical poles along the axis direction of the vertical pole. The vertical rod is made of spiral steel pipe; the connecting rod is channel steel, and the short rod is I-beam. The vertical rod cross brace includes a connecting rod and end connecting plates at both ends of the connecting rod, and the connecting rod is connected with the outer wall of the vertical rod through the end connecting plates.

钢梁施工时,两个墩柱之间的钢梁通常长度较长时可分段分块吊装。当钢梁段位于无障碍区域时,可采用常规方法施工;当钢梁段位于既有线路的上方时,则采用如下所述方法施工。本发明中两个墩柱分设于既有线路的两侧。During the construction of steel beams, the steel beams between the two pier columns can usually be hoisted in sections and blocks when the length is long. When the steel beam section is located in the barrier-free area, the conventional method can be used for construction; when the steel beam section is located above the existing line, the construction method described below is used. In the present invention, the two piers are arranged on both sides of the existing line.

一种跨既有线路的钢梁段施工方法,包括以下步骤:A construction method for a steel beam section spanning an existing line, comprising the following steps:

步骤一、在两个墩柱之间搭设支撑结构:两个钢梁墩柱外侧的钢梁吊装完成后,在非既有线路区域内按常规方法搭设辅助支架结构,在既有线路区域内搭设如上所述临时支撑结构,要求临时支撑结构既不妨碍既有线路的正常使用,又能满足既有线路上方待施工钢梁段的施工要求;Step 1. Set up a support structure between the two piers and columns: After the steel beams on the outer sides of the two steel beams and piers are hoisted, the auxiliary support structure is erected in the non-existing line area according to the conventional method, and the auxiliary support structure is erected in the existing line area. As mentioned above, the temporary support structure requires that the temporary support structure not hinder the normal use of the existing line, but also meet the construction requirements of the steel beam section to be constructed above the existing line;

步骤二、将吊车移动至既有线路的一侧;同时,吊车的吊臂竖立,复核吊车的回转半径;Step 2. Move the crane to one side of the existing line; at the same time, the boom of the crane is erected, and the radius of gyration of the crane is reviewed;

步骤三、对两个墩柱之间的钢梁分段分块预制并运至施工区域内:本实施例中,既有线路上方需施工若干钢梁段,由于钢梁段较宽,每一钢梁段沿钢梁宽度方向分为多块预制处理,再运至待施工地点;Step 3: Prefabricate the steel beams between the two piers in sections and transport them to the construction area: In this embodiment, several steel beam sections need to be constructed above the existing line. The steel beam section is divided into multiple prefabricated pieces along the width direction of the steel beam, and then transported to the construction site;

步骤四、在钢梁块上安装吊具并试吊,调整吊车的最佳起吊位置;Step 4. Install the spreader on the steel beam block and try to lift it, and adjust the best lifting position of the crane;

步骤五、依次将钢梁段各块吊装至临时支撑结构及支架结构上并初步固定定位,吊车的位置根据吊装的钢梁段实时调整:沿钢梁长度方向,各钢梁段按照先中间后两边的原则依次吊装;沿钢梁的宽度方向,同一钢梁段中间分区,吊车一侧分区先吊装,同区内按先中间后两边的原则依次吊装;Step 5. Hoist each piece of the steel beam section to the temporary support structure and the support structure in turn and fix the positioning initially. The position of the crane is adjusted in real time according to the steel beam section to be hoisted: along the length of the steel beam, each steel beam section is first in the middle and then in the middle. The two sides are hoisted in sequence; along the width direction of the steel beam, the middle section of the same steel beam section, one side of the crane is hoisted first, and the same area is hoisted in turn according to the principle of the middle first and then the two sides;

步骤六、待所有钢梁段各块吊装完毕且位置复核无误后焊接固定,并将最外端的两个钢梁段与已施工完成的钢梁焊接固定;Step 6. After all the steel beam sections are hoisted and the positions are checked correctly, they are welded and fixed, and the two outermost steel beam sections are welded and fixed with the completed steel beam;

步骤七、拆除吊装索具撤回吊臂,将吊车移动至下一钢梁段施工处;Step 7. Remove the hoisting rigging and withdraw the boom, and move the crane to the construction site of the next steel beam section;

步骤八、拆除临时支撑结构和支架结构。Step 8. Remove the temporary support structure and the support structure.

本发明所述施工方法对于不同曲率的钢梁均适用。The construction method of the present invention is applicable to steel beams with different curvatures.

实施例:如7图所示环线互通枢纽高架桥梁的安装架设,所需安装钢梁段都位于半径和弧度线型相对较大的圆曲线上,且钢箱梁顶、底板有双向横坡,立面有较大纵坡且在半径较大的凸形竖曲线上。钢架桥梁横跨既有线路上方;如图8所示,在既有线路两侧设有用于支撑钢梁的墩柱,以及采用传统方法搭设用于辅助支撑的支架系统;两组墩柱之间的钢梁分为6个轴对称布置的钢梁段,分别以A、B、C、D、E、F表示,中间钢梁段A和钢梁段B位于既有线路的上方,由本发明所述临时支撑结构支撑;钢梁段C和钢梁段D设于所述临时支撑结构及支架系统之间,由所述临时支撑结构及支架系统共同支撑;钢梁段E和钢梁段F设于支架系统与墩柱之间,由支架系统及墩柱共同支撑。钢梁宽度较大各钢梁段分片预制,以钢梁段A为例,钢梁段A沿钢梁宽度方向分为A1、A2、A3、A4、A5、A6、A7这七块,同一个分区内的钢梁块遵循先中间后两边的原则进行吊装。施工区域内若有燃气管道等应按要求施工。两组墩柱之间的钢梁,其跨既有线路的具体施工方法,包括以下步骤:Example: As shown in Figure 7, for the installation and erection of the elevated bridge of the ring-line interchange hub, the steel beam sections required to be installed are all located on a circular curve with a relatively large radius and radian, and the top and bottom of the steel box girder have two-way transverse slopes. The facade has a large longitudinal slope and is on a convex vertical curve with a large radius. The steel frame bridge spans over the existing line; as shown in Figure 8, there are piers on both sides of the existing line for supporting steel beams, and a traditional method is used to erect a bracket system for auxiliary support; one of the two sets of piers The steel beam in the middle is divided into 6 axisymmetrically arranged steel beam sections, which are represented by A, B, C, D, E, and F respectively. The middle steel beam section A and the steel beam section B are located above the existing line. The temporary support structure supports; the steel beam section C and the steel beam section D are arranged between the temporary support structure and the bracket system, and are jointly supported by the temporary support structure and the bracket system; the steel beam section E and the steel beam section F It is located between the support system and the pier column, and is supported by the support system and the pier column. The steel beams with larger width are prefabricated in pieces. Taking steel beam A as an example, steel beam A is divided into seven pieces A1, A2, A3, A4, A5, A6, and A7 along the width of the steel beam. The steel beam blocks in a partition are hoisted according to the principle of the middle first and then the two sides. If there is a gas pipeline in the construction area, it shall be constructed according to the requirements. The specific construction method of the steel beam between the two groups of piers and its spanning the existing line includes the following steps:

步骤一、在两个墩柱之间搭设支撑结构并检查所述临时支撑结构的稳定性:两个钢梁墩柱外侧的钢梁吊装完成后,在非既有线路区域内按常规方法搭设辅助支架结构,在既有线路区域内搭设如上所述临时支撑结构,要求临时支撑结构既不妨碍既有线路的正常使用,又能满足既有线路上方待施工钢梁段的施工要求;Step 1. Set up a support structure between two piers and check the stability of the temporary support structure: After the steel beams on the outer sides of the two steel beams and the piers are hoisted, set up auxiliary structures in the non-existing line area according to the conventional method. For the support structure, the above temporary support structure is erected in the existing line area, and the temporary support structure is required not to hinder the normal use of the existing line, but also to meet the construction requirements of the steel beam section to be constructed above the existing line;

步骤二、将吊车移动至既有线路的一侧;同时,吊车的吊臂竖立,并复核吊车的回转半径;Step 2. Move the crane to one side of the existing line; at the same time, the boom of the crane is erected, and the radius of gyration of the crane is reviewed;

步骤三、两个墩柱之间的钢梁延顺桥向分为A、B、C、D、E、F这六段,如图8所示,每个钢梁段延横梁向分为七块,如钢梁段A延横桥向分为A1、A2、A3、A4、A5、A6、A7这七块,如图9所述,分块预制后运至施工区域内:Step 3. The steel beam between the two piers is divided into six sections A, B, C, D, E, and F along the bridge direction. As shown in Figure 8, each steel beam section is divided into seven pieces along the transverse beam direction, such as steel Beam section A is divided into seven blocks A1, A2, A3, A4, A5, A6, and A7 along the transverse bridge direction, as shown in Figure 9, which are prefabricated in blocks and transported to the construction area:

步骤四、在钢梁块上安装吊具并试吊,调整吊车的最佳起吊位置;Step 4. Install the spreader on the steel beam block and try to lift it, and adjust the best lifting position of the crane;

步骤五、依次将钢梁段各块吊装至临时支撑结构及支架结构上并初步固定定位,吊车的位置根据吊装的钢梁段实时调整:沿钢梁长度方向,各钢梁段按照先中间后两边的原则依次吊装;沿钢梁的宽度方向,按先中间后两边的原则依次吊装,具体地,以钢梁段A为例,钢梁块A1、A2、A3同区,钢梁块A4、A5、A6、A7同区,先利用吊车依次将钢梁块A3、A2、A1、A4、A5、A6、A7,完成钢梁段A的吊装并初步固定,吊装钢梁块A3、A2、A1时吊车位置如图10所示,吊装钢梁块A4、A5、A6、A7时吊车位置如图11所示;再按上述方法依次吊装钢梁段A、B、D、F、C、E、并初步固定,各钢梁段吊装时吊车的位置示意图如图12~15所示;Step 5. Hoist each piece of the steel beam section to the temporary support structure and the support structure in turn and fix the positioning initially. The position of the crane is adjusted in real time according to the steel beam section to be hoisted: along the length of the steel beam, each steel beam section is first in the middle and then in the middle. The two sides are hoisted in sequence; along the width direction of the steel beam, hoist in sequence according to the principle of the middle first and the two sides. A5, A6, and A7 are in the same area. First, use the crane to hoist the steel beam blocks A3, A2, A1, A4, A5, A6, and A7 in turn to complete the hoisting and preliminary fixing of the steel beam section A, and hoist the steel beam blocks A3, A2, and A1. The position of the crane is shown in Figure 10, and the position of the crane when the steel beam blocks A4, A5, A6, and A7 are hoisted is shown in Figure 11; Figure 12-15 shows the schematic diagram of the position of the crane when each steel beam section is hoisted;

步骤六、待所有钢梁段各块吊装完毕且位置复核无误后焊接固定,并将最外端的两个钢梁段与已施工完成的钢梁焊接固定;Step 6. After all the steel beam sections are hoisted and the positions are checked correctly, they are welded and fixed, and the two outermost steel beam sections are welded and fixed with the completed steel beam;

步骤七、拆除吊装索具撤回吊臂,将吊车移动至下一钢梁段施工处;Step 7. Remove the hoisting rigging and withdraw the boom, and move the crane to the construction site of the next steel beam section;

步骤八、拆除临时支撑结构和支架结构。Step 8. Remove the temporary support structure and the support structure.

最后应说明的是,以上仅为本发明的优选实施例而已,并不用于限制本发明,尽管参照实施例对本发明进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换,但是凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。Finally, it should be noted that the above are only preferred embodiments of the present invention, and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the embodiments, those skilled in the art can still understand the above The technical solutions recorded in each embodiment are modified, or some technical features thereof are equivalently replaced, but any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the present invention. within the scope of protection.

Claims (8)

1. A temporary support structure for a steel beam spanning an existing line is characterized by comprising two groups of support systems and a bearing bracket; the two groups of supporting systems are symmetrically arranged on two sides of the existing line, and the lower ends of the supporting systems are arranged on the ground; the support bracket spans the existing line and is arranged on the two support systems; the steel beam to be installed is hoisted on the bearing bracket in sections.
2. A temporary support structure for steel beams spanning an existing line according to claim 1, wherein the support brackets are formed by a plurality of transverse beams arranged at equal intervals and a plurality of longitudinal beams arranged at equal intervals and connected with each other to form a stable frame structure.
3. A steel beam temporary support structure spanning an existing line according to claim 2, wherein the stringer includes a stringer body, stringer panels fixed to upper and lower surfaces of the stringer body, and stringer webs fixed to both outer sides of the stringer body.
4. A steel beam temporary support structure spanning an existing line according to claim 3, wherein said stringer body includes a plurality of stringer bulkheads spaced along a length of the stringer, and a plurality of stringer reinforcing ribs; the longitudinal beam partition plate is of a frame structure, and mounting holes matched with the number of the longitudinal beam reinforcing ribs are formed in the longitudinal beam partition plate at intervals along the axis; the longitudinal beam reinforcing ribs sequentially penetrate through the mounting holes in the corresponding positions of all the longitudinal beam partition plates, and the longitudinal beam partition plates and the longitudinal beam reinforcing ribs jointly form a longitudinal beam main body structure.
5. The temporary steel beam supporting structure spanning the existing line according to claim 1, wherein each supporting system comprises a plurality of supporting leg structures installed at intervals along the length direction of the existing line, each supporting leg structure comprises a pre-embedded base, a plurality of vertical rods and an overlapping structure, the lower ends of all the vertical rods are fixedly connected with the pre-embedded base, and the upper ends of all the vertical rods are connected with the overlapping structure.
6. The temporary support structure for the steel beam across the existing line according to claim 5, wherein a plurality of vertical rod wales are installed between two adjacent vertical rods at intervals along the axial direction; the two sides of the support bracket are respectively fixed on the lapping structure.
7. A steel beam temporary support structure across an existing line according to claim 5, wherein the lap joint structure includes two parallel short bars, and a support wale fixed to upper portions of the two connection bars; the connecting rods are fixed on a base plate connected with the upper ends of the same-row/same-row upright rods, and a plurality of vertical stiffening plates are arranged on two sides of the support cross brace; the support bracket is fixed on the support cross brace.
8. A steel beam temporary support structure for steel girders over existing lines as claimed in claim 5, wherein a horizontal pad is installed at the upper end of the vertical pole, and the outer edge of the pad extends radially outward; a plurality of triangular rib plates which are arranged at intervals along the circumferential direction are arranged between the extension section of the base plate and the outer wall of the upright rod.
CN201920537023.4U 2019-04-19 2019-04-19 Stride interim bearing structure of girder steel of existing circuit Expired - Fee Related CN210066510U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920537023.4U CN210066510U (en) 2019-04-19 2019-04-19 Stride interim bearing structure of girder steel of existing circuit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920537023.4U CN210066510U (en) 2019-04-19 2019-04-19 Stride interim bearing structure of girder steel of existing circuit

Publications (1)

Publication Number Publication Date
CN210066510U true CN210066510U (en) 2020-02-14

Family

ID=69437714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920537023.4U Expired - Fee Related CN210066510U (en) 2019-04-19 2019-04-19 Stride interim bearing structure of girder steel of existing circuit

Country Status (1)

Country Link
CN (1) CN210066510U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110241728A (en) * 2019-04-19 2019-09-17 中铁科工集团轨道交通装备有限公司 Temporary support structure of steel girders spanning existing lines and construction method of steel girders
CN111335089A (en) * 2020-03-05 2020-06-26 中铁十九局集团广州工程有限公司 Construction method of traffic door opening in bridge road cross-line construction

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110241728A (en) * 2019-04-19 2019-09-17 中铁科工集团轨道交通装备有限公司 Temporary support structure of steel girders spanning existing lines and construction method of steel girders
CN110241728B (en) * 2019-04-19 2024-12-20 中铁科工集团轨道交通装备有限公司 A temporary steel beam support structure across an existing line and a steel beam construction method
CN111335089A (en) * 2020-03-05 2020-06-26 中铁十九局集团广州工程有限公司 Construction method of traffic door opening in bridge road cross-line construction
CN111335089B (en) * 2020-03-05 2021-06-08 中铁十九局集团广州工程有限公司 Construction method of traffic door opening in bridge road cross-line construction
WO2021114689A1 (en) * 2020-03-05 2021-06-17 中铁十九局集团广州工程有限公司 Construction method for traffic gate in bridge road flyover construction

Similar Documents

Publication Publication Date Title
CN102777047B (en) Assembling and splicing installation method of large-span tube-truss roof beam
CN109853353B (en) Spatial special-shaped arch bridge and construction method thereof
CN102154988B (en) Construction method of long-span steel box stacked arch bridge with girder first and then arch
CN110004832B (en) Large-span cantilever truss type bent cap bracket system and construction method
CN209941511U (en) Supporting device for high-altitude folding of bridge steel box girder by section hoisting
CN111794119B (en) Temporary supporting system and hoisting method for basket type steel box tie bar arch
CN114214920B (en) Large-span double-layer built-up steel truss arch bridge and construction method thereof
CN216640288U (en) Tower-passing sliding platform for steel box girder of cable-stayed bridge
CN110847062A (en) Construction method for whole-hole assembly double-width erection in 80-meter-span wide steel box girder factory
CN206538672U (en) Novel fabricated truss steel trestle
CN114263114A (en) Construction system and construction method of large-section steel box girder
CN109778700B (en) Cast-in-place trough beam three-point sliding pushing construction method for crossing existing road
CN111945569A (en) Small-angle inclined steel arch tower support-free in-situ assembly type asymmetric tensioning assembly construction method
CN210066510U (en) Stride interim bearing structure of girder steel of existing circuit
CN112726411B (en) Integral dragging construction method for single-hole large cantilever steel truss girder
CN210066504U (en) Large-span cantilever truss type bent cap support system
CN110241728A (en) Temporary support structure of steel girders spanning existing lines and construction method of steel girders
CN114134820A (en) Formwork support and construction method for cast-in-place bridge deck of I-shaped composite beam
CN209816632U (en) Arch foot structure for special-shaped space arch bridge
CN111172819B (en) Platform for assembling and walking shield trailer and construction method thereof
CN112211112A (en) Steel box girder installation method adopting double-guide-girder erection machine on existing bridge
CN216040719U (en) Template support cantilever bearing structure
CN211171637U (en) Steel box girder installation system
CN115094788A (en) Steel pipe lattice pier for pier and bridge repairing operation and construction method thereof
CN114991006A (en) Basket device is hung with rhombus to construction of super wide bridge floor of many trusses formula

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200214

CF01 Termination of patent right due to non-payment of annual fee