CN210049823U - Piling device for constructional engineering - Google Patents
Piling device for constructional engineering Download PDFInfo
- Publication number
- CN210049823U CN210049823U CN201920743973.2U CN201920743973U CN210049823U CN 210049823 U CN210049823 U CN 210049823U CN 201920743973 U CN201920743973 U CN 201920743973U CN 210049823 U CN210049823 U CN 210049823U
- Authority
- CN
- China
- Prior art keywords
- fixedly connected
- box
- motor
- box body
- sliding sleeve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model discloses a pile device for building engineering, the power distribution box comprises a box body, the axis fixedly connected with cylinder of department at box inner chamber top, the flexible end fixedly connected with motor of cylinder, the output fixedly connected with connecting axle of motor, the bottom of connecting axle is provided with the drill bit, the bottom of drill bit runs through the box and extends to the bottom of box, the left top fixedly connected with handle of box, the left axis fixedly connected with controller of department of box, the both sides of bottom half all are provided with moving mechanism, the both sides at box inner chamber top and the equal fixedly connected with slide bar in both sides of bottom. The utility model discloses a cooperation of cylinder, motor, connecting axle, connecting valve, drill bit, slide bar, first sliding sleeve, connecting rod, second sliding sleeve, fixed plate and cushion is used, and it is very complicated to have solved current pile device for building engineering, inconvenient operation for the device work effect is low, the problem of inconvenient use.
Description
Technical Field
The utility model relates to a building engineering pile technical field specifically is a building engineering is with pile device.
Background
The construction engineering refers to an engineering entity formed by the construction of various building structures and their auxiliary facilities and the installation activities of lines, pipes and equipments matched with them, wherein the building structures refer to the top cover, beam column, wall, foundation and the engineering which can form the internal space and meet the requirements of people for production, living, study and public activities, because if the ground building is built on the ground, the ground must bear a great pressure, and it is often difficult to achieve the strength of enough resisting the pressure, so the ground bearing the building must be reinforced or the bearing mode of the ground must be improved, so it is thought to pile on the foundation, most of the weight of the building is transmitted to the deep position under the ground through the pile, because the foundation of the position has a great bearing capacity than the ground, however, the existing pile driving device for the construction engineering is very complex, the device is inconvenient to operate, so that the device has low working effect and is inconvenient to use, and therefore, the piling device for the building engineering is provided.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model provides a not enough to prior art, the utility model provides a building engineering is with pile device possesses convenient operation and the high advantage of work efficiency, has solved current building engineering is with pile device ten minutes complicacies, inconvenient operation for the device working effect is low, the problem of inconvenient use.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a pile driving device for building engineering, includes the box, the axis fixedly connected with cylinder of department at box inner chamber top, the flexible end fixedly connected with motor of cylinder, the output fixedly connected with connecting axle of motor, the bottom of connecting axle is provided with the drill bit, the bottom of drill bit runs through the box and extends to the bottom of box, the left top fixedly connected with handle of box, the left axis department fixedly connected with controller of box, the both sides of bottom half all are provided with moving mechanism.
Preferably, the both sides at box inner chamber top and the equal fixedly connected with slide bar in both sides of bottom, the top sliding connection on slide bar surface has first sliding sleeve, the equal fixedly connected with connecting rod in both sides of motor, one side and first sliding sleeve fixed connection that the motor was kept away from to the connecting rod, the axis department fixedly connected with second sliding sleeve on slide bar surface, the surface cover of connecting axle is equipped with the fixed plate, the both sides of fixed plate all with second sliding sleeve fixed connection.
Preferably, the bottom of the surface of the sliding rod is provided with a buffer pad, and the bottom of the buffer pad is fixedly connected with the box body.
Preferably, the front surface of the box body is movably connected with a movable door, and the front surface of the movable door is provided with a visual window.
Preferably, the connecting shaft is fixedly connected with the drill bit through a connecting valve, and a through hole matched with the drill bit, the connecting valve and the connecting shaft is formed in the middle shaft at the bottom of the box body.
(III) advantageous effects
Compared with the prior art, the utility model provides a building engineering is with pile device possesses following beneficial effect:
1. the utility model discloses a cooperation of cylinder, motor, connecting axle, connecting valve, drill bit, slide bar, first sliding sleeve, connecting rod, second sliding sleeve, fixed plate and cushion is used, and it is very complicated to have solved current pile device for building engineering, inconvenient operation for the device work effect is low, the problem of inconvenient use.
2. The utility model discloses a set up slide bar and first sliding sleeve, the work of motor has been stabilized, the balance support has been carried out to the motor, avoided the motor during operation to rock, through setting up slide bar and second sliding sleeve, the work of connecting axle has been stabilized, the balance support has been carried out to the connecting axle, the connecting axle has been avoided removing the in-process unstable phenomenon of appearing, through setting up the blotter, the absorbing effect has been played to the second sliding sleeve, the phenomenon of second sliding sleeve and box bump has been avoided, through setting up visual window and dodge gate, the box internals has been made things convenient for after damaging, the user can carry out quick maintenance to damaging the part, it is troublesome to have avoided maintaining, thereby influence the device and use.
Drawings
FIG. 1 is a schematic sectional view of the present invention;
fig. 2 is a schematic view of the structure of the present invention.
In the figure: the device comprises a box body 1, a cylinder 2, a motor 3, a connecting shaft 4, a connecting valve 5, a drill bit 6, a sliding rod 7, a first sliding sleeve 8, a connecting rod 9, a second sliding sleeve 10, a fixing plate 11, a handle 12, a controller 13, a cushion pad 14, a moving mechanism 15, a movable door 16 and a visual window 17.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to be referred must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted", "provided", "connected", and the like are to be construed broadly, such as "connected", which may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The utility model discloses a box 1, cylinder 2, motor 3, connecting axle 4, connecting valve 5, drill bit 6, slide bar 7, first sliding sleeve 8, connecting rod 9, second sliding sleeve 10, fixed plate 11, handle 12, controller 13, blotter 14, moving mechanism 15, dodge gate 16 and visual window 17 part are the general standard or the part that technical staff in the field knows, and its structure and principle all are that this technical staff all can learn through the technical manual or learn through conventional experimental method.
Referring to fig. 1-2, a piling device for construction engineering, comprising a box body 1, a movable door 16 movably connected to the front surface of the box body 1, a visual window 17 arranged on the front surface of the movable door 16, and a motor 3 fixedly connected to the telescopic end of the cylinder 2, a slide bar 7 fixedly connected to both sides of the top and bottom of the inner cavity of the box body 1, a first sliding sleeve 8 slidably connected to the top of the surface of the slide bar 7, a connecting bar 9 fixedly connected to both sides of the motor 3, a sliding rod 7 fixedly connected to the first sliding sleeve 8 by arranging the slide bar 7 and the first sliding sleeve 8, the work of the motor 3 is stabilized, the motor 3 is supported in a balanced manner, the shaking of the motor 3 during the work is avoided, the output end of the motor 3 is fixedly connected with the connecting shaft 4, the middle shaft on the surface of the sliding rod 7 is fixedly connected with the second sliding sleeve 10, the surface of the connecting shaft 4 is sleeved with the fixing plate 11, two sides of the fixing plate 11 are fixedly connected with the second sliding sleeve 10, the work of the connecting shaft 4 is stabilized by arranging the sliding rod 7 and the second sliding sleeve 10, the connecting shaft 4 is supported in a balanced manner, the unstable phenomenon in the moving process of the connecting shaft 4 is avoided, the bottom of the surface of the sliding rod 7 is provided with the buffer cushion 14, the bottom of the buffer cushion 14 is fixedly connected with the box body 1, the second sliding sleeve 10 is damped by arranging the buffer cushion 14, the phenomenon that the second sliding sleeve 10 collides with the box body 1 is avoided, the drill bit 6 is arranged at the bottom of the, the through-hole that cooperation drill bit 6, connecting valve 5 and connecting axle 4 used has been seted up to the axis department of box 1 bottom, and the bottom of drill bit 6 runs through box 1 and extends to the bottom of box 1, the left top fixedly connected with handle 12 of box 1, the left axis department fixedly connected with controller 13 of box 1, and the both sides of box 1 bottom all are provided with moving mechanism 15.
When using, remove the device to operating position, make the device remain stable, switch on, work simultaneously with motor 3 through controller 13 control cylinder 2, cylinder 2 passes through motor 3, the cooperation of connecting axle 4 and connecting valve 5, it removes to drive drill bit 6, motor 3 passes through the cooperation of connecting axle 4 and connecting valve 5, it rotates to drive drill bit 6, pile, convenient operation has been reached, the effect that work efficiency is high, it is very complicated to have solved current pile device for building engineering, inconvenient operation, make the device work effect low, the problem of inconvenient use.
In summary, the following steps: this pile device for building engineering uses through the cooperation of cylinder 2, motor 3, connecting axle 4, connecting valve 5, drill bit 6, slide bar 7, first sliding sleeve 8, connecting rod 9, second sliding sleeve 10, fixed plate 11 and cushion 14, has solved current pile device for building engineering very complicated, inconvenient operation for the device working effect is low, the problem of inconvenient use.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (5)
1. The utility model provides a pile driving device for building engineering, includes box (1), its characterized in that: the improved box is characterized in that a cylinder (2) is fixedly connected to the middle shaft at the top of an inner cavity of the box body (1), a motor (3) is fixedly connected to the telescopic end of the cylinder (2), a connecting shaft (4) is fixedly connected to the output end of the motor (3), a drill bit (6) is arranged at the bottom of the connecting shaft (4), the bottom of the drill bit (6) penetrates through the box body (1) and extends to the bottom of the box body (1), a handle (12) is fixedly connected to the left top of the box body (1), a controller (13) is fixedly connected to the left middle shaft of the box body (1), and moving mechanisms (15) are arranged on two sides of the bottom.
2. A piling device for construction engineering according to claim 1, wherein: the utility model discloses a motor, including box (1), the equal fixedly connected with slide bar (7) in both sides and the both sides of bottom at inner chamber top of box (1), the top sliding connection on slide bar (7) surface has first sliding sleeve (8), the equal fixedly connected with connecting rod (9) in both sides of motor (3), one side and first sliding sleeve (8) fixed connection of motor (3) are kept away from in connecting rod (9), well axle department fixedly connected with second sliding sleeve (10) on slide bar (7) surface, the surface cover of connecting axle (4) is equipped with fixed plate (11), the both sides of fixed plate (11) all with second sliding sleeve (10) fixed connection.
3. A piling device for construction engineering according to claim 2, wherein: the bottom of the surface of the sliding rod (7) is provided with a cushion pad (14), and the bottom of the cushion pad (14) is fixedly connected with the box body (1).
4. A piling device for construction engineering according to claim 1, wherein: the front surface of the box body (1) is movably connected with a movable door (16), and the front surface of the movable door (16) is provided with a visual window (17).
5. A piling device for construction engineering according to claim 1, wherein: the connecting shaft (4) is fixedly connected with the drill bit (6) through a connecting valve (5), and a through hole matched with the drill bit (6), the connecting valve (5) and the connecting shaft (4) is formed in the middle shaft at the bottom of the box body (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920743973.2U CN210049823U (en) | 2019-05-22 | 2019-05-22 | Piling device for constructional engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920743973.2U CN210049823U (en) | 2019-05-22 | 2019-05-22 | Piling device for constructional engineering |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210049823U true CN210049823U (en) | 2020-02-11 |
Family
ID=69395691
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920743973.2U Expired - Fee Related CN210049823U (en) | 2019-05-22 | 2019-05-22 | Piling device for constructional engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210049823U (en) |
-
2019
- 2019-05-22 CN CN201920743973.2U patent/CN210049823U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210049823U (en) | Piling device for constructional engineering | |
CN213448471U (en) | Road and bridge engineering is with effectual vibration pile driver of antidetonation | |
CN212134131U (en) | Building engineering manages with concrete drilling coring device | |
CN110485420B (en) | Self-propelled geotechnical engineering reconnaissance static pressure equipment's platform strutting arrangement | |
CN211074228U (en) | Drilling machine for hydraulic engineering | |
CN208280900U (en) | A kind of geology planning and designing prospecting drilling rig | |
CN216008388U (en) | Shallow rock-soil drilling equipment | |
CN201459727U (en) | Pile driving frame of vibratory pile hammer | |
CN212176672U (en) | Building site is with knocking wall device | |
CN211900486U (en) | Miniature foundation stabilization drilling machine | |
CN212104072U (en) | Constructional engineering pile device | |
CN211081699U (en) | Drilling rig for geotechnical engineering investigation | |
CN210827520U (en) | Hydraulic engineering foundation ditch drainage support | |
CN211306950U (en) | Efficient concrete slab drilling equipment for construction | |
CN210317144U (en) | A combination formula perforating device for water conservancy construction | |
CN209243723U (en) | A kind of electronics piling location device for building | |
CN216082093U (en) | Sampling device for rock soil detection | |
CN213508451U (en) | Stable pile driver for traffic engineering construction | |
CN211472831U (en) | A portable mound base device for civil engineering construction | |
CN215829640U (en) | Movable board house convenient to remove | |
CN217802534U (en) | Tunnel vault is punched and is verified support and dust keeper | |
CN213267819U (en) | Foundation tamping device for civil engineering | |
CN214567628U (en) | Building engineering measuring device places case | |
CN219315725U (en) | Pile driver convenient to remove | |
CN214097832U (en) | Base system for underground water exploration |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200211 |