CN210002457U CN201920396343.2U CN201920396343U CN210002457U CN 210002457 U CN210002457 U CN 210002457U CN 201920396343 U CN201920396343 U CN 201920396343U CN 210002457 U CN210002457 U CN 210002457U
Authority
CN
China
Prior art keywords
foundation pile
connecting frame
pile body
civil construction
location
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920396343.2U
Other languages
Chinese (zh)
Inventor
李伟中
黄科成
刘文斌
刘锦钏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Chenji Construction Engineering Co Ltd
Original Assignee
Guangdong Chenji Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Chenji Construction Engineering Co Ltd filed Critical Guangdong Chenji Construction Engineering Co Ltd
Priority to CN201920396343.2U priority Critical patent/CN210002457U/en
Application granted granted Critical
Publication of CN210002457U publication Critical patent/CN210002457U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a location foundation pile for civil construction relates to architectural equipment technical field, it includes foundation pile body and second foundation pile body, it is fixed through the connecting piece between foundation pile body and the second foundation pile body, the connecting piece includes link, the second link and be used for connecting the extension spring of link and second link, this location foundation pile for civil construction, through the locate mode with traditional location foundation piles adoption artifical chi volume, change into and carry out two foundation pile bodies of fixed matching by the connecting piece, can alternate segregation between two foundation pile bodies, and by the extension spring automatic re-setting who sets up, can carry out the accurate positioning to the ground of civil construction according to compasses design principle, avoid the long problem consuming time that artifical measurement location ground brought, it is accurate to have the location, control advantages such as convenience, and simultaneously, whole location foundation pile is collected the transport convenience, moreover, the steam generator is simple in structure, economical and practical.

Description

Positioning foundation pile for civil construction
Technical Field
The utility model relates to a construction equipment technical field specifically is positioning foundation pile for civil construction.
Background
Along with the development of economy and the improvement of living standard, people have higher requirements on the appearance and the use function of a building, the shape of the building is more and more complex, the arrangement of a building shaft network is irregular, the arrangement of foundation piles is more complex, particularly, when a mechanical equipment is erected in a construction frame body, the field visibility condition is poor, the construction difficulty is increased for pile position lofting, the building construction measurement is work which is the most basic and the most critical in the building construction, the quality of the construction measurement is greatly related to the whole engineering quality, when all the axes in the shaft network are irregularly distributed, the coordinate system is calculated by using a coordinate conversion principle, the calculation speed and the calculation precision are improved by using EXCEL software, and the positioning quality of the foundation pile measurement can be improved by steps.
The invention discloses a foundation pile measuring and positioning construction method, which belongs to the technical field of building construction and comprises the following steps of establishing a project coordinate system, a project measurement control network and a foundation pile partition and establishing a partition coordinate system, correspondingly converting the coordinate values of the partition coordinate system and the project coordinate system, calculating polar coordinates according to EXCEL software, and carrying out measuring, positioning and rechecking on a construction site according to data of the polar coordinates to obtain a method for accurately positioning the foundation pile in a drawing on the construction site.
The patent actually provides theoretical foundation pile measurement location construction methods, this technical means relies on the calculation function of EXCEL software, though have efficient computational efficiency and accurate positioning method, nevertheless measure the ground directly for the staff mostly at the actual job site, theoretical algorithm is comparatively inconvenient in actual construction, and need professional technical staff to calculate, influence the time limit for a project easily, even after calculating accurately, the later stage still needs constructor to adopt basic foundation pile to operate according to the drawing, do not bring the change of foundation pile equipment from the essence, still exist because error and the low scheduling problem of efficiency of construction that artifical measurement location brought.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a purpose adopts the locate mode of artifical chi volume with traditional location foundation piles, changes into and fixes two foundation pile bodies that match by the connecting piece, realizes ground accurate positioning according to compasses design principle, avoids the artifical longer consuming time that measures the location ground and bring, the low scheduling problem of efficiency of construction.
The positioning foundation pile for the civil construction comprises an th foundation pile body and a second foundation pile body, wherein the th foundation pile body and the second foundation pile body are fixed through a connecting piece, the connecting piece comprises a 0 th connecting frame, a second connecting frame and a tension spring for connecting the 1 th connecting frame and the second connecting frame, the closed end of the th connecting frame is fixedly welded with the th foundation pile body, the closed end of the second connecting frame is fixedly welded with the second foundation pile body, the tension spring is arranged in a cavity between the th connecting frame and the second connecting frame, the end of the tension spring is fixedly welded on the inner wall of the closed end of the th connecting frame, the other end of the tension spring is fixedly welded on the inner wall of the closed end of the second connecting frame, the th connecting frame is slidably embedded in the second connecting frame, a slide bar is welded on the connecting position of the th connecting frame with the second connecting frame, and a slide groove matched with the slide bar is formed in the inner wall of the second connecting frame.
Preferably, the th foundation pile body and the second foundation pile body are both composed of a tapered drill rod and a transverse lever, the transverse lever is fixedly welded on the tapered drill rod, an oblique angle support is connected between the tapered drill rod and the transverse lever, and a foundation pile compression leg is fixed at the upper end of the transverse lever.
Preferably, the length of the th connecting frame and the second connecting frame can be set according to the actual construction requirement.
Preferably, the th connecting frame and the second connecting frame are semi-closed cuboid members, and the cross-sectional area of the th connecting frame is smaller than that of the second connecting frame.
Preferably, the th link bracket and the second link bracket are respectively provided with a ring buckle at the inner wall of the closed end for fixing the extension spring.
Preferably, the slide bar is provided with a limiting block at the tail end connected with the sliding groove.
Preferably, a graduated scale is printed on the front section of the second connecting frame.
The utility model provides a location foundation pile for civil construction, this location foundation pile for civil construction, through the locate mode with traditional location foundation piles adoption artifical chi volume, change into two foundation pile bodies that carry out fixed matching by the connecting piece, can the alternate segregation between two foundation pile bodies, and by the extension spring automatic re-setting who sets up, can carry out the accurate positioning to the ground of civil construction according to compasses design principle, avoid the long problem consuming time that artifical measurement location ground brought, it is accurate to have the location, control advantages such as convenient, and simultaneously, the transport convenience is collected to whole location foundation pile, moreover, the steam generator is simple in structure, economical and practical.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a diagram illustrating the usage of the present invention;
fig. 3 is a structural schematic view of an th connecting frame of the present invention;
fig. 4 is a schematic structural view of a second connecting frame of the present invention.
In the figure, 1 st foundation pile body, 2 second foundation pile body, 3 connecting pieces, 301 st connecting frame, 302 second connecting frame, 303 extension spring, 304 ring buckle, 305 slide bar, 306 sliding chute, 307 graduated scale, 4 tapered drill rod, 5 transverse stretcher rods, 6 bevel angle support and 7 foundation pile compression leg.
Detailed Description
Referring to fig. 1-4, the utility model provides technical solutions, the foundation pile for civil construction includes foundation pile body 1 and second foundation pile body 2, 0 foundation pile body 1 and second foundation pile body 2 are fixed through connecting piece 3, connecting piece 3 includes 1 th connecting frame 301, second connecting frame 302 and extension spring 303 for connecting 2 th connecting frame 301 and second connecting frame 302, the closed end of th connecting frame 301 is fixedly welded with th foundation pile body 1, the closed end of second connecting frame 302 is fixedly welded with second foundation pile body 2, extension spring 303 is arranged in the cavity of th connecting frame 301 and second connecting frame 302, end of extension spring 303 is fixedly welded at the inner wall of th connecting frame 301, another end of extension spring 303 is fixedly welded at the inner wall of second connecting frame 302, th connecting frame 301 is slidably embedded in second connecting frame 301, th connecting frame 302 is welded with the sliding strip connecting frame 305, and the sliding strip connecting groove 306 of sliding strip connecting frame 305 is arranged at the closed end of second connecting frame 302.
In this embodiment, the th foundation pile body 1 and the second foundation pile body 2 are both composed of a tapered drill rod 4 and a transverse lever 5, the transverse lever 5 is fixedly welded on the tapered drill rod 4, an oblique angle support 6 is connected between the tapered drill rod 4 and the transverse lever 5, a foundation pile press column 7 is fixed at the upper end of the transverse lever 5, and the whole th foundation pile body 1 and the second foundation pile body 2 are respectively fixed on the ground by pressing the foundation pile press column 7.
In this embodiment, the lengths of the th connecting frame 301 and the second connecting frame 302 can be set according to the actual construction requirements, so as to meet the use requirements of the actual civil engineering construction.
In this embodiment, the th link frame 301 and the second link frame 302 are configured as semi-closed rectangular parallelepiped members, and the cross-sectional area of the th link frame 301 is smaller than that of the second link frame 302, so that the th link frame 301 can be inserted into the second link frame 302 to facilitate the separation of the th link frame 301 from the second link frame 302.
In this embodiment, the th connecting frame 301 and the second connecting frame 302 are respectively provided with a ring buckle 304 at the inner wall of the closed end for fixing the extension spring 303.
In this embodiment, the slider 305 is provided with the stopper at the end of being connected with spout 306, prevents that link 301 from exceeding the biggest spacing in with the tensile process of second link 302 and marking off, influences the effect of later stage measurement location.
In this embodiment, a graduated scale 307 is printed on the front cross section of the second connecting frame 302, so that the constructor can observe the positioning distance of the foundation pile body.
During the use, adopt foundation pile body 1 location building construction's the foundation pile position, then stimulate second foundation pile body 2, second foundation pile body 2 atress pulling extension spring 303, make simultaneously the second link 302 that is connected with second foundation pile body 2 to the direction extension of atress, at this moment, second link 302 takes place the change of relative position with link 301, second link 302 slides along link 301, until second foundation pile body 2 location to suitable foundation pile position, the distance that second link 302 slided is recorded through graduated scale 308 on the second link 302 this moment, thereby differentiate the relative position of second foundation pile body 2 and the foundation pile body 1, and carry out the mark, for follow-up civil construction has brought very big facility, it is accurate to have the location, advantages such as the convenience is controlled, simultaneously, after the foundation pile location is accomplished, go out foundation pile body 1 and second foundation pile body 2, foundation pile body 1 and second foundation pile body 2 are through the economic effect of drawing the original spring of retrieving the original position of being convenient for the whole foundation pile body of drawing, thereby the simple transport is convenient to carry.
The above only is the preferred embodiment of the present invention, not limiting the scope of the present invention, all the equivalent structures or equivalent flow changes made by the contents of the specification and the drawings, or directly or indirectly applied to other related technical fields, are included in the same way in the protection scope of the present invention.

Claims (7)

1. The positioning foundation pile for the civil construction comprises an th foundation pile body and a second foundation pile body and is characterized in that the th foundation pile body and the second foundation pile body are fixed through a connecting piece, the connecting piece comprises a 0 th connecting frame, a second connecting frame and a tension spring for connecting the 1 th connecting frame and the second connecting frame, the closed end of the th connecting frame is fixedly welded with the th foundation pile body, the closed end of the second connecting frame is fixedly welded with the second foundation pile body, the tension spring is arranged in a cavity between the th connecting frame and the second connecting frame, the end of the tension spring is fixedly welded on the inner wall of the closed end of the th connecting frame, the other end of the tension spring is fixedly welded on the inner wall of the closed end of the second connecting frame, the th connecting frame is slidably embedded in the second connecting frame, a slide bar is welded on the connecting position of the th connecting frame, and a slide groove matched with the slide bar is formed in the inner wall of the second connecting frame.
2. The foundation pile for civil construction according to claim 1, wherein said th foundation pile body and said second foundation pile body are each composed of a tapered drill rod and a transverse stretcher bar, the transverse stretcher bar is fixedly welded to the tapered drill rod, an oblique angle support is connected between the tapered drill rod and the transverse stretcher bar, and a foundation pile press column is fixed to the upper end of the transverse stretcher bar.
3. The foundation pile for civil construction according to claim 1, wherein the length of the th connecting frame and the second connecting frame can be set by itself according to actual construction requirements.
4. The spud according to claim 1, wherein the th connecting frame and the second connecting frame are semi-closed rectangular parallelepiped members, and the cross-sectional area of the th connecting frame is smaller than that of the second connecting frame.
5. The foundation pile for civil construction according to claim 1, wherein said th connecting frame and said second connecting frame are provided with a ring fastener for fixing an extension spring at the inner wall of the closed end, respectively.
6. The spud according to claim 1, characterized in that: the slide bar is provided with a limiting block at the tail end connected with the sliding groove.
7. The spud according to claim 1, characterized in that: and a graduated scale is printed on the front section of the second connecting frame.
CN201920396343.2U 2019-03-26 2019-03-26 Positioning foundation pile for civil construction Active CN210002457U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920396343.2U CN210002457U (en) 2019-03-26 2019-03-26 Positioning foundation pile for civil construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920396343.2U CN210002457U (en) 2019-03-26 2019-03-26 Positioning foundation pile for civil construction

Publications (1)

Publication Number Publication Date
CN210002457U true CN210002457U (en) 2020-01-31

Family

ID=69302185

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920396343.2U Active CN210002457U (en) 2019-03-26 2019-03-26 Positioning foundation pile for civil construction

Country Status (1)

Country Link
CN (1) CN210002457U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112252324A (en) * 2020-09-22 2021-01-22 芜湖质勉信息科技有限公司 Pile point positioning device convenient for lapping and extending for hydraulic engineering construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112252324A (en) * 2020-09-22 2021-01-22 芜湖质勉信息科技有限公司 Pile point positioning device convenient for lapping and extending for hydraulic engineering construction
CN112252324B (en) * 2020-09-22 2021-11-12 滨州市水利勘测设计研究院有限责任公司 Pile point positioning device convenient for lapping and extending for hydraulic engineering construction

Similar Documents

Publication Publication Date Title
CN210002457U (en) Positioning foundation pile for civil construction
CN204330399U (en) A kind of soil root sampler
CN113847948A (en) Dynamic compaction automatic monitoring and analyzing method and digital integrated system
CN201421330Y (en) Leveling device
CN207180683U (en) A kind of building construction formwork verticality measuring tool
CN103486954A (en) Coal mine roadway deformation measuring device and method
CN203256733U (en) Device for detecting pile top concrete elevation of cast-in-place pile
CN203893840U (en) High-precision fixed composite level gauge
CN209416230U (en) A kind of slab thickness measuring device
CN202255398U (en) Verticality measuring device of templates of walls and columns
CN104462202B (en) A kind of coefficient of consolidation model and method for building up of soil
CN110241735A (en) The positioning adjustment device and method of adjustment of Cable stayed Bridge Main Tower cable guide pipe
CN206709764U (en) A kind of plain type verticality measuring tool
CN201059933Y (en) Dome groove measurement mechanism
CN203657810U (en) Special perpendicularity detection device for frame column and shear wall
CN107883858A (en) Large-scale dell returns the measuring method of amount of fill
CN209512877U (en) A kind of portable mold plate verticality measuring appliance
CN208505323U (en) Easy verticality measuring tool
CN208983991U (en) Nursery stock chest ground diameter measuring tool
CN208443407U (en) A kind of shear wall formwork verticality measuring instrument
CN107101561B (en) Anchor lip type value measurer
CN203772262U (en) Sighting rod for measuring cross section of road
CN206037998U (en) Slope slope measurement device
CN203113792U (en) Rapid elevation marking device for buildings
CN203240990U (en) Double-purpose measuring stick used in setting up electric pole

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Positioning pile for civil construction

Effective date of registration: 20211019

Granted publication date: 20200131

Pledgee: Bank of China Limited by Share Ltd. Shunde branch

Pledgor: Guangdong Chenji Construction Engineering Co.,Ltd.

Registration number: Y2021980010916

PE01 Entry into force of the registration of the contract for pledge of patent right