CN209978621U - Furnace door locking device for preheating furnace - Google Patents

Furnace door locking device for preheating furnace Download PDF

Info

Publication number
CN209978621U
CN209978621U CN201921723276.7U CN201921723276U CN209978621U CN 209978621 U CN209978621 U CN 209978621U CN 201921723276 U CN201921723276 U CN 201921723276U CN 209978621 U CN209978621 U CN 209978621U
Authority
CN
China
Prior art keywords
locking
door
furnace
furnace gate
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921723276.7U
Other languages
Chinese (zh)
Inventor
陈扬
李景春
李志强
谭炜州
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Meishan Shida New Materials Co Ltd
Original Assignee
Meishan Shida New Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Meishan Shida New Materials Co Ltd filed Critical Meishan Shida New Materials Co Ltd
Priority to CN201921723276.7U priority Critical patent/CN209978621U/en
Application granted granted Critical
Publication of CN209978621U publication Critical patent/CN209978621U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model discloses a furnace gate locking device for preheater, including furnace gate and portal steel construction, be equipped with the electric block who lifts by crane the operation to the furnace gate on the portal steel construction, the side of furnace gate is equipped with the pulley, the portal is equipped with the latch segment just structurally, set up the locking door slide of being convenient for the pulley gliding and locking on the latch segment, locking door slide sliding connection on pulley and the latch segment. Compared with the prior art, the utility model discloses to the sealed requirement of preheater furnace gate, adopt the furnace gate dead weight as furnace gate locking force design, furnace gate locking device's locking force utilizes the furnace gate dead weight, does not need equipment such as cylinder or pneumatic cylinder, and corresponding electrical control element also need not additionally to increase, has reduced the fund input during the construction, and the running cost reduces.

Description

Furnace door locking device for preheating furnace
Technical Field
The utility model relates to a carbon industry dipping system preheater especially relates to a furnace gate locking device for preheater.
Background
A preheating furnace door locking device in an electrode dipping system in the domestic carbon industry is designed in a cylinder or hydraulic cylinder mode, the temperature of the position of a furnace door is high, the sealing of the cylinder or hydraulic cylinder is easy to age, the temperature of a working environment is high when the sealing is replaced, the lifting and the lowering of the furnace door need the locking device to work in a linkage mode, the capital investment of electric control elements is increased, and the overhaul capacity is correspondingly increased after equipment is increased.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a solve above-mentioned problem, the fund input when having reduced the equipment and having built has reduced the maintenance of equipment work, has reduced equipment running cost for the furnace gate locking device of preheater.
In order to realize the purpose, the utility model discloses a technical scheme is: the utility model provides a furnace gate locking device for preheater, includes furnace gate and portal steel construction, be equipped with the electric block who lifts by crane the operation to the furnace gate on the portal steel construction, the side of furnace gate is equipped with the pulley, the portal is equipped with the latch segment just structurally, set up the locking door slide of being convenient for the pulley gliding and locking on the latch segment, locking door slide sliding connection on pulley and the latch segment.
Preferably, the locking door slideway is divided into three sections from top to bottom, the three sections are sequentially a guide section, a lower sliding section and an inclined locking section, the guide section is in an open shape, the lower sliding section is vertically arranged, and the lower end of the locking section inclines towards the inner side of the hearth.
Preferably, the pulley has two middle upper parts and middle lower parts which are positioned on the side surface of the furnace door, and the locking block has two middle parts and two lower parts which are respectively positioned on the steel structure of the portal frame.
Preferably, the left side and the right side of the furnace door are respectively provided with four groups of pulleys, and the door frame steel structure is provided with a locking block matched with the door frame steel structure.
Preferably, the locking blocks are welded to the mast structure.
Compared with the prior art, the utility model has the advantages of: the utility model discloses to the sealed requirement of preheater furnace gate, adopt the furnace gate dead weight as furnace gate locking force design, furnace gate locking device's locking force utilizes the furnace gate dead weight, does not need equipment such as cylinder or pneumatic cylinder, and corresponding electrical control element also need not additionally to increase, has reduced the fund input during the construction, and the running cost reduces.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic structural view of the locking block of the present invention.
In the figure: 1. an electric hoist; 2. a furnace door; 3. a gantry steel structure; 4. a pulley; 5. a locking block; 6. locking the door slide; 7. a guide section; 8. a lower sliding section; 9. and (4) locking the section.
Detailed Description
The present invention will be further explained below.
Example 1: referring to fig. 1 and 2, a furnace door locking device for a preheating furnace, includes furnace door 2 and portal steel structure 3, be equipped with on portal steel structure 3 and lift by crane the electric block 1 of operation to furnace door 2, carry out lifting by crane of furnace door 2 through electric block 1 and realize opening and close of furnace door 2, the side of furnace door 2 is equipped with pulley 4, the portal is just structural to be equipped with latch segment 5, set up the locking door slide 6 that is convenient for pulley 4 gliding and locking on latch segment 5, pulley 4 and the locking door slide 6 sliding connection on the latch segment 5 utilize the cooperation of pulley 4 and locking door slide 6, when furnace door 2 was put down to electric block 1, utilize the dead weight of furnace door 2, realize the locking of furnace door 2.
The locking door slide 6 is divided into three sections from top to bottom, and the locking section 9 that is guide section 7, gliding section 8 and slope in proper order, guide section 7 is the opening form for in guide pulley 4 gets into locking door slide 6, avoid pulley 4 and 5 edges of latch segment to collide with and cause the damage, gliding section 8 is vertical to be set up, and gliding section 8 is used for the vertical lift of furnace gate 2 to the steady decline of furnace gate 2 is to locking section 9, 9 lower extremes of locking section incline towards the furnace inboard, and when pulley 4 got into locking section 9 back looks furnace side slope slip, it is steady near to furnace to drive furnace gate 2 in the process of descending, finally realizes closing and locking of furnace, and the gradient of locking section 9 specifically is decided according to the on-the-spot furnace gate 2 circumstances.
The pulley 4 has two middle upper portions and middle lower portions which are positioned on the side face of the furnace door 2, and the locking block 5 has two middle portions and two lower portions which are respectively positioned on the portal steel structure 3. The left side and the right side of the furnace door 2 are provided with four groups of pulleys 4, and the door frame steel structure is provided with a locking block 5 matched with the door frame steel structure. Two sets of pulleys 4 and the cooperation of latch segment 5 are adopted respectively to the furnace gate 2 left and right sides, and aim at makes furnace gate 2 promote or descend in-process even running, causes furnace gate 2 to rock in avoiding electric block 1 course of operation, and simultaneously behind furnace gate 2 auto-lock, both ends all hug closely in the furnace chamber mouth about enabling furnace gate 2.
The working principle is as follows: when the furnace door 2 is opened, the electric hoist 1 lifts the furnace door 2, and the pulley 4 loosens the furnace door 2 along the inclined plane of the locking door slideway 6; when the oven door 2 is closed, the pulley 4 closes and locks the oven door 2 along the inclined plane of the locking door slideway 6, and the locking force is provided by the self weight of the oven door 2.
During installation: four groups of pulleys 4 are additionally arranged on two sides of the furnace door 2, four groups of locking blocks 5 with locking door slide ways 6 are processed, the furnace door 2 is firstly hoisted to the closing position of the furnace door 2 by using an electric hoist 1, the furnace door 2 is tightly attached to the sealing surface of the preheating furnace by using bolts or other external force, and then the four groups of locking door slide ways 6 are welded on a door frame steel structure after being matched with the four groups of pulleys 4 on the furnace door 2.
The furnace door locking device for the preheating furnace provided by the utility model is introduced in detail, and the principle and the implementation mode of the utility model are explained by applying a specific example, and the explanation of the above embodiment is only used for helping to understand the method and the core idea of the utility model; while the invention has been described in terms of specific embodiments and applications, it will be apparent to those skilled in the art that numerous variations and modifications can be made without departing from the spirit and scope of the invention as defined in the appended claims.

Claims (5)

1. The utility model provides a furnace gate locking device for preheater, includes furnace gate and portal steel construction, its characterized in that: the door frame steel structure is provided with an electric hoist for lifting the furnace door, the side face of the furnace door is provided with a pulley, the door frame is structurally provided with a locking block, the locking block is provided with a locking door slide rail convenient for the pulley to slide downwards and lock, and the pulley is in sliding connection with the locking door slide rail on the locking block.
2. An oven door locking device for a preheating oven according to claim 1, characterized in that: the locking door slide is divided into three sections from top to bottom, the three sections are sequentially a guide section, a lower sliding section and an inclined locking section, the guide section is in an open shape, the lower sliding section is vertically arranged, and the lower end of the locking section inclines towards the inner side of the hearth.
3. An oven door locking device for a preheating oven according to claim 2, characterized in that: the pulley has two and is located the well upper portion and the well lower part of furnace gate side, the latch segment has two and is located the middle part and the lower part of portal steel construction respectively.
4. An oven door locking device for a preheating oven according to claim 3, characterized in that: the door frame is characterized in that the left side and the right side of the door are respectively provided with four groups of pulleys, and the door frame steel structure is provided with a locking block matched with the door frame steel structure.
5. An oven door locking device for a preheating oven according to claim 1, characterized in that: the locking block is welded on the portal rigid structure.
CN201921723276.7U 2019-10-15 2019-10-15 Furnace door locking device for preheating furnace Active CN209978621U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921723276.7U CN209978621U (en) 2019-10-15 2019-10-15 Furnace door locking device for preheating furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921723276.7U CN209978621U (en) 2019-10-15 2019-10-15 Furnace door locking device for preheating furnace

Publications (1)

Publication Number Publication Date
CN209978621U true CN209978621U (en) 2020-01-21

Family

ID=69251803

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921723276.7U Active CN209978621U (en) 2019-10-15 2019-10-15 Furnace door locking device for preheating furnace

Country Status (1)

Country Link
CN (1) CN209978621U (en)

Similar Documents

Publication Publication Date Title
CN100510535C (en) Fire door fitting of furnace for solidifying coat inside tubular product
CN209978621U (en) Furnace door locking device for preheating furnace
CN2798005Y (en) High temp bogie electric resistance furnace
CN111910059A (en) Vertical high vacuum heat treatment furnace
CN111349883A (en) Track accessory heating powder zinc impregnation production line
CN204043408U (en) With the straight column type elevating translational ferry bus of automatic push-pull car device
CN217627206U (en) Electromechanical equipment hoisting device for high-rise construction of building
CN107381342A (en) A kind of design method for realizing aluminium electroloysis slag grabbing bottom translation
CN206205692U (en) A kind of bilateral opposite opened shield door for self-shileding device
CN204198656U (en) A kind of rotary coke tank apparatus for examination and repair
CN212962819U (en) Trolley furnace
CN212241540U (en) 90-degree concrete precast slab overturning machine
CN211169761U (en) Working platform device for modifying crown block beam at top of blast furnace
CN210119112U (en) Tunnel furnace door with good sealing performance
CN205821389U (en) A kind of laterally opened glowing furnace of bell
CN102221295A (en) Thermal treatment line equipment composite structure
CN212741436U (en) Vertical high vacuum heat treatment furnace
CN215887151U (en) Independently driven trolley furnace for heat treatment
CN211112117U (en) Automatic sealing door of heat treatment multipurpose furnace
CN211903748U (en) Heating furnace door with enhanced sealing performance
CN107936991A (en) A kind of dry quenched coke tank bottom shutter opening and closing and transport tool car
CN212640563U (en) Vacuum quenching furnace for horizontally taking and placing workpieces
CN210420045U (en) Trolley type resistance furnace
CN211717180U (en) Heating furnace door lifting system
CN213866059U (en) Online sealing device of dry quenching coke tank

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant