CN209940415U - Lift for construction - Google Patents

Lift for construction Download PDF

Info

Publication number
CN209940415U
CN209940415U CN201920587228.3U CN201920587228U CN209940415U CN 209940415 U CN209940415 U CN 209940415U CN 201920587228 U CN201920587228 U CN 201920587228U CN 209940415 U CN209940415 U CN 209940415U
Authority
CN
China
Prior art keywords
connecting block
rotating shaft
construction
hydraulic rod
operation plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920587228.3U
Other languages
Chinese (zh)
Inventor
张忠林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920587228.3U priority Critical patent/CN209940415U/en
Application granted granted Critical
Publication of CN209940415U publication Critical patent/CN209940415U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Types And Forms Of Lifts (AREA)

Abstract

The utility model discloses an elevator for construction relates to construction machinery technical field, this elevator for construction, including the operation board, one side fixedly connected with sleeve of operation board, the operation board cup joints at the sleeve of its one side and bracing piece through fixed connection, one side fixedly connected with safety protection network of bracing piece, the bottom card of operation board is equipped with two spouts, the operation board is through seting up spout and the first connecting block sliding connection in its bottom. This lift for construction, simple structure, the equipment is simple and convenient, uses portably, has reached the purpose of convenient to use, through setting up safety protection network, for constructor's safety protection driving, also can use the device to transport the material, the bracing piece is pulled out, demolishs safety protection network, places the finishing material at the top of operation board, then through flexible hydraulic stem, transport the material to the eminence alright, make the device have the versatility.

Description

Lift for construction
Technical Field
The utility model relates to a construction machinery technical field specifically is a lift for construction.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a specified place. The method comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like. The construction site is called as a building construction site or a construction site, also called as a construction site, the construction safety technical measure is an important component in construction organization design, is a safety management and technical file for specifically arranging and guiding engineering safety construction, is an instruction file for safety production in engineering construction, has the function of safety production rules in the management of the construction site, is a site for producing products in the building industry, and has the attention of establishing the safety regulation, safety operation knowledge and safety measures of the construction site in order to ensure the safety and health of constructors in the construction process.
The job site can be divided into indoor and outdoor, and indoor construction such as our common interior decoration in the interior decoration, often needs the furred ceiling, and the furred ceiling just needs a higher platform, makes the workman stand on it and carries out the construction, but, the work platform that current building indoor construction used uses and needs interim equipment, and the back is accomplished in the equipment in addition, highly fixed, and it is inconvenient to use.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a lift for construction has solved the work platform of current building indoor construction usefulness and has used and need assemble temporarily, assembles moreover and accomplishes the back, highly fixed, awkward problem.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes:
a building construction elevator comprises an operation plate, wherein one side of the operation plate is fixedly connected with a sleeve, the operation plate is sleeved with a support rod through the sleeve fixedly connected to one side of the operation plate, one side of the support rod is fixedly connected with a safety protection net, the bottom of the operation plate is clamped with two sliding grooves, the operation plate is in sliding connection with a first connecting block through the sliding grooves formed in the bottom of the operation plate, a first rotating shaft is inserted into the first connecting block, a second connecting block is fixedly connected to one side of the bottom of the operation plate, a second rotating shaft is inserted into the second connecting block, a hydraulic rod is movably connected to the outer surface of the first rotating shaft, one end, away from the first rotating shaft, of the hydraulic rod is movably connected with the second rotating shaft, the first connecting block is movably connected with a first lifting rod through the first rotating shaft arranged in the first connecting block, and the second connecting block is movably connected with a second lifting rod through the second rotating shaft arranged in the second connecting block, and one end of the first lifting rod, which is far away from the first connecting block, and one end of the second lifting rod, which is far away from the second connecting block, are both provided with idler wheels.
Optionally, a through hole is formed in one side of the first connecting block, and the first connecting block is connected with the first rotating shaft in an inserting mode through the through hole formed in one side of the first connecting block.
Optionally, a through hole is formed in one side of the second connecting block, and the second connecting block is connected with the second rotating shaft in an inserting mode through the through hole formed in one side of the second connecting block.
Optionally, one end of the hydraulic rod is fixedly connected with a first circular ring, and the hydraulic rod is movably connected with the first rotating shaft through the first circular ring arranged at one end of the hydraulic rod.
Optionally, one end of the hydraulic rod, which is far away from the first ring, is fixedly connected with a second ring, and the hydraulic rod is movably connected with the second rotating shaft through the second ring arranged at one end of the hydraulic rod.
Optionally, the middle part of the first lifting rod is movably connected with the middle part of the second lifting rod through a pin shaft.
(III) advantageous effects
The utility model provides a lift for construction possesses following beneficial effect:
(1) this lift for construction, when using, constructor stands at the top of operation board, inserts the bracing piece in the sleeve of operation board one side, makes safety protection net surround the operation board, adjusts the length of hydraulic stem, risees the operation board to suitable height, constructor to the position of indoor eminence construct alright, the device height-adjustable, it is simple and convenient to use to reached the purpose of convenient to use.
(2) This lift for construction, through setting up safety protection network, constructor when high altitude construction, safety protection network can prevent that constructor from dropping from the high altitude, for constructor's safe protection drives the protection navigation, and during the interior decoration furred ceiling, also can use the device to transport the material, the bracing piece is pulled out, demolish safety protection network, place the top at the operation board with the finishing material, then through flexible hydraulic stem, transport the material to the eminence alright, make the device have the versatility, through setting up the gyro wheel, reach the purpose of being convenient for to remove.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the operation plate of the present invention;
fig. 3 is the structure diagram of the hydraulic rod of the present invention.
In the figure: 1-operation plate, 2-sleeve, 3-support rod, 4-safety protection net, 5-chute, 6-first connecting block, 7-first rotating shaft, 8-second connecting block, 9-second rotating shaft, 10-hydraulic rod, 11-first lifting rod, 12-second lifting column, 13-roller, 14-first ring and 15-second ring.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", and the like, indicate the orientation or positional relationship indicated based on the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
In the present invention, unless otherwise expressly stated or limited, the terms "disposed," "mounted," "connected," and "fixed" are to be construed broadly, e.g., as meaning either a fixed connection or a removable connection; may be a mechanical connection; may be directly connected or indirectly connected through an intermediate. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature.
Referring to fig. 1-3, the present invention provides a technical solution:
a building construction elevator comprises an operation plate 1, a constructor stands on the surface of the operation plate 1 to operate, one side of the operation plate 1 is fixedly connected with a sleeve 2, the operation plate 1 is sleeved with a support rod 3 through the sleeve 2 fixedly connected to one side of the operation plate, one side of the support rod 3 is fixedly connected with a safety protection net 4, through arranging the safety protection net 4, the safety protection net 4 can prevent the constructor from falling from the high altitude when the constructor works at high altitude, two sliding chutes 5 are clamped at the bottom of the operation plate 1, the operation plate 1 is in sliding connection with a first connecting block 6 through the sliding chutes 5 arranged at the bottom of the operation plate, a first rotating shaft 7 is inserted in the first connecting block 6, a second connecting block 8 is fixedly connected to one side of the bottom of the operation plate 1, a second rotating shaft 9 is inserted in the second connecting block 8, a hydraulic rod 10 is movably connected to the outer surface of the first rotating shaft 7, the purpose of pushing and pulling the first connecting block 6 is achieved through the telescopic hydraulic rod 10, one end, far away from the first rotating shaft 7, of the hydraulic rod 10 is movably connected with the second rotating shaft 9, the first connecting block 6 is movably connected with the first lifting rod 11 through the first rotating shaft 7 arranged in the first connecting block, the second connecting block 8 is movably connected with the second lifting rod 12 through the second rotating shaft 9 arranged in the second connecting block, the purpose of adjusting the included angle between the first lifting rod 11 and the second lifting rod 12 is achieved through the telescopic hydraulic rod 10 by pushing and pulling the first connecting block 6, the purpose of lifting the working plate 1 is achieved, a constructor stands on the top of the working plate 1, the purpose of lifting and descending the constructor is achieved through the telescopic hydraulic rod 10, the roller 13 is arranged at one end, far away from the first connecting block 6, of the first lifting rod 11 and the other end, far away from the second connecting block 8, of the second lifting rod 12, and the roller 13 is arranged, the device is convenient to move, when a constructor needs to transfer the position during high-altitude operation, a worker on the ground can transfer the lifter by pushing the lifting rod, and therefore the purpose of transferring the constructor is achieved.
As an optional technical solution of the utility model:
a through hole is formed in one side of the first connecting block 6, and the first connecting block 6 is connected with the first rotating shaft 7 in an inserting mode through the through hole formed in one side of the first connecting block.
As an optional technical solution of the utility model:
a through hole is formed in one side of the second connecting block 8, and the second connecting block 8 is connected with the second rotating shaft 9 in an inserting mode through the through hole formed in one side of the second connecting block.
As an optional technical solution of the utility model:
one end of the hydraulic rod 10 is fixedly connected with a first circular ring 14, and the hydraulic rod 10 is movably connected with the first rotating shaft 7 through the first circular ring 14 arranged at one end of the hydraulic rod.
As an optional technical solution of the utility model:
one end of the hydraulic rod 10 far away from the first circular ring 14 is fixedly connected with a second circular ring 15, and the hydraulic rod 10 is movably connected with the second rotating shaft 9 through the second circular ring 15 arranged at one end of the hydraulic rod.
As an optional technical solution of the utility model:
the middle part of the first lifting rod 11 is movably connected with the middle part of the second lifting rod 12 by using a pin shaft.
When using, during interior decoration, the constructor stands at the top of operation board 1, insert bracing piece 3 in the sleeve 2 of operation board 1 one side, make safety protection net 4 surround operation board 1, adjust hydraulic stem 10's length, rise operation board 1 to suitable height, constructor to the position of indoor eminence construct alright, during the interior decoration furred ceiling, also can use the device to transport the material, bracing piece 3 pulls out, demolish safety protection net 4, place finishing material at the top of operation board 1, then through flexible hydraulic stem 10, transport the material to the eminence alright.
To sum up, when the building construction elevator is used, a constructor stands on the top of an operation plate 1, inserts a support rod 3 into a sleeve 2 at one side of the operation plate 1, enables a safety protection net 4 to surround the operation plate 1, adjusts the length of a hydraulic rod 10, raises the operation plate 1 to a proper height, and can construct the position of an indoor high place by the constructor, the device is adjustable in height and convenient to use, so that the aim of convenient use is fulfilled, the constructor can be prevented from falling from the high altitude by the safety protection net 4 when working at high altitude by arranging the safety protection net 4, the constructor can be protected and navigated by the constructor, and materials can be conveyed by the device when the indoor ceiling is decorated, the support rod 3 is pulled out, the safety protection net 4 is dismantled, decoration materials are placed on the top of the operation plate 1, and then the hydraulic rod 10 is stretched, the material is transported to a high place, so that the device has multiple purposes, and the purpose of convenient movement is achieved by arranging the roller 13.
It is noted that in the present disclosure, unless otherwise explicitly specified or limited, a first feature "on" or "under" a second feature may be directly contacting the first and second features or indirectly contacting the first and second features through an intermediate. Also, a first feature "on," "over," and "above" a second feature may be directly or diagonally above the second feature, or may simply indicate that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature may be directly under or obliquely under the first feature, or may simply mean that the first feature is at a lesser elevation than the second feature.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a lift for construction, includes operation board (1), its characterized in that:
one side of the operation plate (1) is fixedly connected with a sleeve (2), the operation plate (1) is sleeved with a support rod (3) through the sleeve (2) fixedly connected to one side of the operation plate, one side of the support rod (3) is fixedly connected with a safety protection net (4), the bottom of the operation plate (1) is clamped with two sliding chutes (5), the operation plate (1) is slidably connected with a first connecting block (6) through the sliding chutes (5) arranged at the bottom of the operation plate, a first rotating shaft (7) is inserted into the first connecting block (6), a second connecting block (8) is fixedly connected to one side of the bottom of the operation plate (1), a second rotating shaft (9) is inserted into the second connecting block (8), the outer surface of the first rotating shaft (7) is movably connected with a hydraulic rod (10), one end, far away from the first rotating shaft (7), of the hydraulic rod (10) is movably connected with the second rotating shaft (9), first connecting block (6) are through setting up first pivot (7) and first lifter (11) swing joint inside it, second connecting block (8) are through setting up second pivot (9) and second lifter (12) swing joint inside it, the one end of keeping away from first connecting block (6) and the one end of keeping away from second connecting block (8) in second lifter (12) are all provided with gyro wheel (13) in first lifter (11).
2. The construction elevator according to claim 1,
a through hole is formed in one side of the first connecting block (6), and the first connecting block (6) is connected with the first rotating shaft (7) in an inserting mode through the through hole formed in one side of the first connecting block.
3. The construction elevator according to claim 1,
a through hole is formed in one side of the second connecting block (8), and the second connecting block (8) is connected with the second rotating shaft (9) in an inserting mode through the through hole formed in one side of the second connecting block.
4. The construction elevator according to claim 1,
one end of the hydraulic rod (10) is fixedly connected with a first circular ring (14), and the hydraulic rod (10) is movably connected with the first rotating shaft (7) through the first circular ring (14) arranged at one end of the hydraulic rod.
5. The construction elevator according to claim 1,
one end of the hydraulic rod (10) far away from the first circular ring (14) is fixedly connected with a second circular ring (15), and the hydraulic rod (10) is movably connected with the second rotating shaft (9) through the second circular ring (15) arranged at one end of the hydraulic rod.
6. The construction elevator according to claim 1,
the middle part of the first lifting rod (11) is movably connected with the middle part of the second lifting rod (12) through a pin shaft.
CN201920587228.3U 2019-04-26 2019-04-26 Lift for construction Expired - Fee Related CN209940415U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920587228.3U CN209940415U (en) 2019-04-26 2019-04-26 Lift for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920587228.3U CN209940415U (en) 2019-04-26 2019-04-26 Lift for construction

Publications (1)

Publication Number Publication Date
CN209940415U true CN209940415U (en) 2020-01-14

Family

ID=69130132

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920587228.3U Expired - Fee Related CN209940415U (en) 2019-04-26 2019-04-26 Lift for construction

Country Status (1)

Country Link
CN (1) CN209940415U (en)

Similar Documents

Publication Publication Date Title
CN205590250U (en) Movable support for construction
CN106829323B (en) A kind of architectural engineering material elevator
CN103521807A (en) Liftable laser positioning high-space suspender perforation mounting device and operation method
CN207674077U (en) A kind of adjustable architectural engineering surveying instrument supporting frame
CN203696028U (en) Liftable laser-positioning high-space suspender punching device
CN104110119A (en) Simple device and mounting method for positioning ceiling suspenders in building construction
CN209940415U (en) Lift for construction
CN110775909A (en) Elevator device for power equipment maintenance
CN205777435U (en) Exterior wall finishing hoistable platform
CN111074887A (en) Portable soil nail mounting plate
CN206328046U (en) The horizontal punching lifting beam device of Large Rotor
CN212300358U (en) Horizontal fixing device is used in native survey and drawing
CN206071584U (en) Heading equipment support meanss
CN203867147U (en) Construction ceiling lifting rod positioning installing method and simple device
CN211110950U (en) Elevator device for power equipment maintenance
CN208122240U (en) Constructing operation frame
CN209021527U (en) Tooling platform for pump case built-up welding
CN209568682U (en) A kind of adjustable scaffold
CN208532059U (en) Hanging device with high altitude operation function
CN207672956U (en) Floor leveling horizon equipment
CN206857843U (en) A kind of adjustable cable reel rest stand
US20010045079A1 (en) Wall panel lifting system used for forming multistory block and brick walls
CN206203763U (en) Self-driving floor hanging apparatus
CN111139888A (en) Soil nailing wall tapping device
CN216265825U (en) Retractable electric hammer drilling equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200114

Termination date: 20210426