CN209924417U - Connecting assembly of construction scaffold - Google Patents

Connecting assembly of construction scaffold Download PDF

Info

Publication number
CN209924417U
CN209924417U CN201920493947.9U CN201920493947U CN209924417U CN 209924417 U CN209924417 U CN 209924417U CN 201920493947 U CN201920493947 U CN 201920493947U CN 209924417 U CN209924417 U CN 209924417U
Authority
CN
China
Prior art keywords
scaffold
pin
adapter sleeve
backup pad
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920493947.9U
Other languages
Chinese (zh)
Inventor
许长建
刘菲菲
姜贤红
程涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Fangyuanda Construction Group Co Ltd
Original Assignee
Qingdao Fangyuanda Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Fangyuanda Construction Group Co Ltd filed Critical Qingdao Fangyuanda Construction Group Co Ltd
Priority to CN201920493947.9U priority Critical patent/CN209924417U/en
Application granted granted Critical
Publication of CN209924417U publication Critical patent/CN209924417U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model discloses a relate to construction frame technical field specifically is a coupling assembling of construction frame, including adapter sleeve and backup pad, the adapter sleeve is cylindrical structure, and the upper and lower both ends of adapter sleeve all are equipped with the draw-in groove, the utility model discloses well adapter sleeve and the integrative setting of backup pad have played and have connected scaffold pillar and scaffold extension board effect simultaneously, and the hitch structure is firm, have increased the security of equipment, the utility model discloses the direct block of scaffold pillar about well adapter sleeve can in corresponding draw-in groove, connect easy dismounting, have improved preparation and processing time around the construction, are fit for promoting.

Description

Connecting assembly of construction scaffold
Technical Field
The utility model relates to a construction frame technical field specifically is a coupling assembling of construction frame.
Background
The construction frame is a working platform which is set up to ensure that each construction process is smoothly carried out. The scaffold is divided into an outer scaffold and an inner scaffold according to the erected positions, and the connecting components are required to be used for connection when the building scaffold is erected.
Among the prior art, often connect the construction frame through adapter sleeve and screw, the structure is not very stable, and there is the drawback of inconvenient dismouting in junction, uses comparatively inconveniently, has increased the preparation time before the construction and the processing time after the construction.
To this end, we propose a connection assembly for construction scaffolding to better address the above drawbacks.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a coupling assembling of construction scaffold to solve the problem of proposing among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a coupling assembling of construction scaffold, includes adapter sleeve and backup pad, the adapter sleeve is cylindrical structure, and the upper and lower both ends of adapter sleeve all are equipped with the draw-in groove, and the block has the scaffold pillar in the draw-in groove, and the equal fixed welding of the left and right sides face of adapter sleeve has the backup pad, the backup pad is rectangle platelike structure, and the last surface mounting of backup pad has the scaffold extension board, it is fixed through the pin between adapter sleeve and the scaffold pillar, and the pin is spacing through the spacing ring.
Preferably, the inner wall of the clamping groove is fixedly provided with a rubber layer in a circle, and the rubber layer is movably attached to the outer ring of the scaffold pillar.
Preferably, the upper surface of backup pad is equipped with two sets of connecting holes and two sets of spacing posts No. one, and two sets of connecting holes and two sets of spacing posts are interval distribution, and spacing post is the fixed welding of cylindrical structure at the upper surface of backup pad, and the upper and lower surface setting of backup pad is run through respectively at the upper and lower both ends of a connecting hole.
Preferably, the tip of scaffold extension board is equipped with spacing hole and No. two connecting holes, spacing hole corresponds the setting with spacing post, and No. two connecting holes correspond the setting with a connecting hole.
Preferably, when the scaffold support plate is arranged on the upper surface of the support plate, the limiting column is movably clamped in the corresponding limiting hole, the second connecting hole and the corresponding first connecting hole are provided with screws together, and the second connecting hole, the limiting hole and the screws are connected in a threaded fit mode.
Preferably, the inner wall left side of draw-in groove is equipped with the pinhole, and the activity block has the pin in the pinhole, the pin is the flexible groove of character cut in bas-relief structure activity setting inside the scaffold pillar, through spring fixed connection between the right flank of pin and the right side inner wall in flexible groove.
Preferably, the one end activity that the pinhole was kept away from to the pin passes the outside scaffold pillar outer lane surface setting of adapter sleeve, and the pin passes the tip on scaffold pillar outer lane surface and the outer lane looks parallel and level of scaffold pillar, and the pin passes the tip activity laminating on scaffold pillar outer lane surface and has the spacing ring, the spacing ring passes through screw-thread fit and connects in the outer lane department of scaffold pillar.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model has the advantages that the connecting sleeve and the supporting plate are arranged integrally, which plays the role of connecting the scaffold pillar and the scaffold supporting plate simultaneously, and the connecting structure is stable, thereby increasing the safety of the equipment;
2. the utility model discloses the direct block of scaffold pillar about well adapter sleeve can in corresponding draw-in groove, connect easy dismounting, improved preparation and processing time around the construction, be fit for promoting.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is an enlarged schematic view of a structure shown in fig. 1 according to the present invention.
In the figure: the connecting sleeve comprises a connecting sleeve 1, a supporting plate 2, a scaffold strut 3, a scaffold supporting plate 4, a first connecting hole 5, a limiting column 6, a pin hole 7, a pin 8, a limiting ring 9, a rubber layer 10, a second connecting hole 11, a clamping groove 12, a telescopic groove 13, a spring 14 and a limiting hole 15.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 2, the present invention provides a technical solution: a connecting assembly of a construction frame comprises a connecting sleeve 1 and a supporting plate 2, wherein the connecting sleeve 1 is of a cylindrical structure, clamping grooves 12 are formed in the upper end and the lower end of the connecting sleeve 1, a rubber layer 10 is fixedly arranged on the inner wall of each clamping groove 12 in a circle, the rubber layer 10 is movably attached to the outer ring of a construction frame strut 3, the rubber layer 10 avoids hard abrasion generated when the end part of the construction frame strut 3 is connected with the connecting sleeve 1, and the service life of equipment is prolonged;
a scaffold pillar 3 is clamped in the clamping groove 12, a support plate 2 is fixedly welded on the left side surface and the right side surface of the connecting sleeve 1, the support plate 2 is of a rectangular plate-shaped structure, two groups of first connecting holes 5 and two groups of limiting columns 6 are arranged on the upper surface of the support plate 2, the two groups of first connecting holes 5 and the two groups of limiting columns 6 are distributed at intervals, the limiting columns 6 are fixedly welded on the upper surface of the support plate 2 in a cylindrical structure, the upper end and the lower end of each first connecting hole 5 are respectively arranged by penetrating through the upper surface and the lower surface of the support plate 2, the connecting stability of the support plate 2 and the scaffold support plate 4 is further improved when the limiting columns 6 are clamped in the limiting holes 15, the scaffold support plate 4 is arranged on the upper surface of the support plate 2, the limiting holes 15 and the second connecting holes 11 are arranged at the end parts of the scaffold support plate 4, when the scaffold support plate 4 is arranged on the upper surface of the support plate 2, the limiting column 6 is movably clamped in the corresponding limiting hole 15, the second connecting hole 11 and the corresponding first connecting hole 5 are provided with screws together, and the second connecting hole 11, the limiting hole 15 and the screws are connected in a thread fit manner;
fix through pin 8 between adapter sleeve 1 and the scaffold pillar 3, pin 8 is spacing through spacing ring 9, the inner wall left side of draw-in groove 12 is equipped with pinhole 7, activity block has pin 8 in the pinhole 7, pin 8 is the flexible groove 13 of character cut in bas-relief structure activity setting in scaffold pillar 3 inside, through spring 14 fixed connection between the right flank of pin 8 and the right side inner wall of flexible groove 13, the one end activity that pin 8 kept away from pinhole 7 passes adapter sleeve 1 outside scaffold pillar 3 outer lane surface setting, and pin 8 passes the tip on scaffold pillar 3 outer lane surface and scaffold pillar 3's outer lane looks parallel and level, pin 8 passes the tip activity laminating on scaffold pillar 3 outer lane surface and has spacing ring 9, spacing ring 9 is in the outer lane department of scaffold pillar 3 through screw-thread fit connection.
The working principle is as follows: firstly, the draw-in groove 12 block of adapter sleeve 1 lower extreme is on the scaffold pillar 3 of lower extreme, the scaffold pillar 3 block of upper end is in the draw-in groove 12 of adapter sleeve 1 upper end again, when the installation, press down the one end of 8 tip of pin and 3 outer lane parallel and level of scaffold pillar earlier, make when the scaffold pillar 3 is installed in adapter sleeve 1, the block that the pin 8 other end can be smooth is fixed in pinhole 7, realize fixing between the two, spacing ring 9 rotation spacing to 8 tip of pin on the scaffold pillar 3 again, avoid pin 8 to drop by the external influence, the security of connecting between the multiplicable structure, and scaffold extension board 4 passes through the fix with screw on backup pad 2, holistic steadiness is stronger.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a coupling assembling of construction frame, includes adapter sleeve (1) and backup pad (2), its characterized in that: adapter sleeve (1) is cylindrical structure, and the upper and lower both ends of adapter sleeve (1) all are equipped with draw-in groove (12), and the block has scaffold pillar (3) in draw-in groove (12), and the equal fixed welding of the left and right sides face of adapter sleeve (1) has backup pad (2), backup pad (2) are rectangle platelike structure, and the last surface mounting of backup pad (2) has scaffold extension board (4), it is fixed through pin (8) between adapter sleeve (1) and scaffold pillar (3), and pin (8) are spacing through spacing ring (9).
2. A connecting assembly for a construction scaffold as claimed in claim 1, wherein: the inner wall of the clamping groove (12) is fixedly provided with a rubber layer (10) in a circle, and the rubber layer (10) is movably attached to the outer ring of the scaffold strut (3).
3. A connecting assembly for a construction scaffold as claimed in claim 1, wherein: the upper surface of backup pad (2) is equipped with two sets of connecting holes (5) and two sets of spacing post (6) No. one, and two sets of connecting hole (5) and two sets of spacing post (6) are interval distribution, and spacing post (6) are the upper surface of cylindrical structure fixed welding in backup pad (2), and the upper and lower surface setting that backup pad (2) were run through respectively at the upper and lower both ends of a connecting hole (5).
4. A connecting assembly for a construction scaffold as claimed in claim 1, wherein: the tip of scaffold extension board (4) is equipped with spacing hole (15) and No. two connecting holes (11), spacing hole (15) correspond the setting with spacing post (6), and No. two connecting holes (11) correspond the setting with connecting hole (5).
5. A connection assembly for a construction scaffold according to claim 4 wherein: when installing in the upper surface of backup pad (2) scaffold frame extension board (4), spacing post (6) activity block is in corresponding spacing hole (15), and the screw is equipped with in No. two connecting holes (11) and the connecting hole (5) that correspond in the same installation, connect through screw-thread fit between No. two connecting holes (11), spacing hole (15) and the screw.
6. A connecting assembly for a construction scaffold as claimed in claim 1, wherein: the inner wall left side of draw-in groove (12) is equipped with pinhole (7), and the activity block has pin (8) in pinhole (7), pin (8) are the activity of character cut in bas-relief shape structure and set up in telescopic groove (13) of scaffold pillar (3) inside, through spring (14) fixed connection between the right flank of pin (8) and the right side inner wall of telescopic groove (13).
7. A connection assembly for a construction scaffold according to claim 6 wherein: one end activity that pinhole (7) were kept away from in pin (8) passes adapter sleeve (1) outside scaffold pillar (3) outer lane surface setting, and pin (8) pass the tip on scaffold pillar (3) outer lane surface and the outer lane looks parallel and level of scaffold pillar (3), and pin (8) pass the tip activity laminating on scaffold pillar (3) outer lane surface and have spacing ring (9), outer lane department at scaffold pillar (3) is connected through screw-thread fit in spacing ring (9).
CN201920493947.9U 2019-04-12 2019-04-12 Connecting assembly of construction scaffold Expired - Fee Related CN209924417U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920493947.9U CN209924417U (en) 2019-04-12 2019-04-12 Connecting assembly of construction scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920493947.9U CN209924417U (en) 2019-04-12 2019-04-12 Connecting assembly of construction scaffold

Publications (1)

Publication Number Publication Date
CN209924417U true CN209924417U (en) 2020-01-10

Family

ID=69073338

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920493947.9U Expired - Fee Related CN209924417U (en) 2019-04-12 2019-04-12 Connecting assembly of construction scaffold

Country Status (1)

Country Link
CN (1) CN209924417U (en)

Similar Documents

Publication Publication Date Title
CN209924417U (en) Connecting assembly of construction scaffold
CN215484493U (en) High-stability diagonal tension door type scaffold
CN211396932U (en) Reinforced safety vertical net
CN210713757U (en) Scaffold for building
CN211548280U (en) Light and stable mounting structure for curtain wall
CN211341161U (en) Prestressing force support frame convenient to equipment
CN210032540U (en) Steel column installation operation platform
CN217028372U (en) A safety protection structure for water conservancy construction
CN214886129U (en) Civil engineering is with enclosing fender device convenient to it makes an uproar to fall
CN214383990U (en) Mounting structure of building assembled wall body
CN214942222U (en) Climbing frame equipment convenient to install
CN110748012A (en) Steel structure crossbeam
CN211524324U (en) Fence for power equipment convenient to install
CN216973731U (en) Steel structure node component with good safety performance
CN215106040U (en) Steel construction assembly type structure
CN216276344U (en) Curtain wall with novel connecting structure
CN220599427U (en) Combined invisible guardrail assembly
CN211312221U (en) Bridge cylinder mound assembled operation platform device
CN213477215U (en) Combined spliced steel structure
CN213979829U (en) Scaffold frame capable of being rapidly disassembled and assembled and scaffold
CN214135893U (en) Assembling table for attaching frame fixed special-shaped aluminum plate
CN213626616U (en) Scaffold convenient to change connecting piece
CN217400478U (en) Combined anode auxiliary material platform with good stability
CN219622206U (en) Construction frame
CN216865888U (en) Novel building scaffold fastener structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200110

Termination date: 20210412