CN209797293U - Intelligent monitoring and alarming system for black box of tower crane - Google Patents

Intelligent monitoring and alarming system for black box of tower crane Download PDF

Info

Publication number
CN209797293U
CN209797293U CN201921243306.4U CN201921243306U CN209797293U CN 209797293 U CN209797293 U CN 209797293U CN 201921243306 U CN201921243306 U CN 201921243306U CN 209797293 U CN209797293 U CN 209797293U
Authority
CN
China
Prior art keywords
main control
control chip
module
circuit
tower crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921243306.4U
Other languages
Chinese (zh)
Inventor
王北一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Vocational and Technical College
Guangdong Institute of Textile Technology
Original Assignee
Guangdong Institute of Textile Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Institute of Textile Technology filed Critical Guangdong Institute of Textile Technology
Priority to CN201921243306.4U priority Critical patent/CN209797293U/en
Application granted granted Critical
Publication of CN209797293U publication Critical patent/CN209797293U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

the utility model relates to a black box intelligent monitoring alarm system of tower crane belongs to hoist technical field, include: bridge measuring module, the amplifying module, the filtering module, the overvoltage protection module, main control chip, the LCD screen, the button, memory and power module, bridge measuring module gathers hoist moment signal, moment signal passes through the amplifying module in proper order, the filtering module, overvoltage protection module finally carries to main control chip, main control chip passes through the circuit and links to each other with the LCD screen, button and power module all link to each other with main control chip through the circuit, the memory links to each other with main control chip through the circuit and carries out signal transmission, the computer passes through level conversion chip and links to each other with main control chip, main control chip passes through the circuit and links to each other with the ball switch that sets up on the hoist. The utility model discloses a ball switch monitoring tower crane rocks the degree, comes mobile crane moment signal through the resistance foil gage among the electric bridge measuring module simultaneously, and then monitors hoist moment.

Description

intelligent monitoring and alarming system for black box of tower crane
Technical Field
the utility model relates to a hoist technical field especially relates to a tower crane black box intelligent monitoring alarm system.
background
In recent years, with the enhancement of infrastructure construction in China, large-scale engineering machinery is developed towards large-scale and automation. The control system of the tower crane is more and more complex, and the moment of the tower crane cannot be monitored in the operation process of the tower crane, so that faults exist, property loss can be caused, and the life and property safety of people can be endangered.
SUMMERY OF THE UTILITY MODEL
the utility model discloses a solve tower crane operation in-process and can't monitor hoist moment, therefore there is the trouble, not only can cause loss of property, still can endanger people's the technical problem of the security of the lives and property, and then provide a tower crane black box intelligent monitoring alarm system.
The utility model adopts the technical scheme that:
An intelligent monitoring and alarming system for a black box of a tower crane comprises: a bridge measuring module, an amplifying module, a filtering module, an overvoltage protection module, a main control chip, a liquid crystal screen, a key, a memory and a power supply module,
the bridge measurement module collects a crane moment signal, the moment signal is sequentially transmitted to the main control chip through the amplification module, the filtering module and the overvoltage protection module, the main control chip is connected with the liquid crystal display through a circuit, the keys and the power supply module are connected with the main control chip through a circuit, and the memory is connected with the main control chip through a circuit to carry out signal transmission;
the computer is connected with the main control chip through the level conversion chip;
The main control chip is connected with a ball switch arranged on the crane through a circuit.
Further, the specific model of the main control chip is AD μ C812.
Further, the specific type of the memory is AT24C 256.
Further, the level shift chip is specifically MAX 232.
Further, the specific model of the ball switch is SW-520V.
the utility model discloses following beneficial effect has to prior art:
the utility model discloses a ball switch monitoring tower crane rocks the degree, comes mobile crane moment signal through the resistance foil gage among the electric bridge measuring module simultaneously, and then monitors hoist moment, effectively prevents the occurence of failure.
Drawings
Fig. 1 is a block diagram of the present invention;
FIG. 2 is a circuit diagram of a bridge measurement module according to the present invention;
Fig. 3 is a circuit diagram of the amplifying module of the present invention;
Fig. 4 is a circuit diagram of the filter module of the present invention;
fig. 5 is a circuit diagram of the overvoltage protection module of the present invention;
Fig. 6 is a serial port connection circuit diagram of the level shift chip of the present invention;
FIG. 7 is a circuit diagram of the key connection of the present invention;
Fig. 8 is a circuit diagram of the interface between the lcd panel and the main control chip;
fig. 9 is a circuit diagram of the interface between the memory and the main control chip of the present invention;
Fig. 10 is a circuit diagram of the power module of the present invention;
Fig. 11 is an interface circuit diagram of the ball switch and the main control chip of the present invention.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings.
an intelligent monitoring and alarming system for a black box of a tower crane comprises: a bridge measuring module 1, an amplifying module 2, a filtering module 3, an overvoltage protection module 4, a main control chip 5, a liquid crystal screen 6, a key 7, a memory 8 and a power module 9,
the bridge measurement module 1 collects crane moment signals, R1 and R2 in the bridge measurement module 1 are BF350 high-precision resistance strain gauges respectively, the strain of an arch bar is converted into the change of resistance values, the moment signals are sequentially transmitted to the main control chip 5 through the amplification module 2, the filter module 3 and the overvoltage protection module 4, the amplification module 2 amplifies the moment signals, the amplified signals are transmitted to an A/D acquisition end of the main control chip 5 through an overvoltage protection circuit, as shown in figure 5, R31 in the circuit is a current-limiting resistor, C32 plays a role in filtering, the signals are more stable, D9 and D10 form the overvoltage protection circuit to prevent the overvoltage protection circuit from being too high or too low and damaging the single chip microcomputer, the main control chip 5 is connected with the liquid crystal screen 6 through a circuit, the liquid crystal screen 6 can prompt monitoring personnel to play an alarm role, the key 7 and the power supply module 9 are both connected with the main control chip 5 through circuits, the power module 9 is to provide a digital direct current power supply and an analog direct current power supply for the system, the utility model adopts the LM7805 and the LM7905 to combine with a series of filtering and voltage stabilizing to design various power supplies required by the system, the memory 8 is connected with the main control chip 5 through a circuit to carry out signal transmission, and the memory 8 is used for storing monitoring information;
the computer 12 is connected with the main control chip 5 through the level conversion chip 10;
The main control chip 5 is connected with a ball switch 11 arranged on the crane through a circuit, the SW-520V is a low-current ball switch, and when the main control chip is shaken by external force or a set angle is 45 degrees higher than a conduction angle, two pins are conducted to be in a short-circuit state.
The specific model of the main control chip 5 is AD μ C812.
The specific model of the memory 8 is AT24C 256.
the level shift chip 10 is specifically MAX 232.
The specific model of the ball switch 11 is SW-520V.
The working process is as follows:
firstly, strain of an arch bar is obtained for BF350 high-precision resistance strain gauges through R1 and R2 in an electric bridge measuring module 1 respectively, so that a moment signal is obtained, the moment signal passes through an amplifying module 2 and then passes through a filtering module 3, the filtered signal enters an overvoltage protection module 4 and finally enters a main control chip 5, SW-520V is a small-current ball switch, when the arch bar is shaken by external force or a set angle is 45 degrees higher than the conduction angle, two pins are conducted to be in a short-circuit state, the signal is sent to the main control chip 5, and the main control chip 5 displays moment parameters and the state of the ball switch through a liquid crystal display 6 to give a prompt and alarm.

Claims (5)

1. An intelligent monitoring and alarming system for a black box of a tower crane comprises: the device comprises an electric bridge measuring module (1), an amplifying module (2), a filtering module (3), an overvoltage protection module (4), a main control chip (5), a liquid crystal screen (6), a key (7), a memory (8) and a power supply module (9),
The crane moment signal is collected by the electric bridge measuring module (1), the moment signal is sequentially transmitted to the main control chip (5) through the amplifying module (2), the filtering module (3) and the overvoltage protection module (4), the main control chip (5) is connected with the liquid crystal screen (6) through a circuit, the keys (7) and the power supply module (9) are connected with the main control chip (5) through a circuit, and the memory (8) is connected with the main control chip (5) through a circuit to transmit signals;
the computer (12) is connected with the main control chip (5) through the level conversion chip (10);
The main control chip (5) is connected with a ball switch (11) arranged on the crane through a circuit.
2. the intelligent monitoring and alarming system for the black box of the tower crane according to claim 1, wherein the specific model of the main control chip (5) is AD μ C812.
3. The intelligent monitoring and alarming system for the black box of the tower crane as claimed in claim 1, wherein the specific model of the memory (8) is AT24C 256.
4. The intelligent monitoring and alarming system for the black box of the tower crane according to claim 1, wherein the level conversion chip (10) is MAX 232.
5. the intelligent monitoring and alarming system for the black box of the tower crane as claimed in claim 1, wherein the specific model of the ball switch (11) is SW-520V.
CN201921243306.4U 2019-08-02 2019-08-02 Intelligent monitoring and alarming system for black box of tower crane Expired - Fee Related CN209797293U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921243306.4U CN209797293U (en) 2019-08-02 2019-08-02 Intelligent monitoring and alarming system for black box of tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921243306.4U CN209797293U (en) 2019-08-02 2019-08-02 Intelligent monitoring and alarming system for black box of tower crane

Publications (1)

Publication Number Publication Date
CN209797293U true CN209797293U (en) 2019-12-17

Family

ID=68818132

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921243306.4U Expired - Fee Related CN209797293U (en) 2019-08-02 2019-08-02 Intelligent monitoring and alarming system for black box of tower crane

Country Status (1)

Country Link
CN (1) CN209797293U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111498702A (en) * 2020-05-19 2020-08-07 广东职业技术学院 Tower crane safety recording device and recording method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111498702A (en) * 2020-05-19 2020-08-07 广东职业技术学院 Tower crane safety recording device and recording method

Similar Documents

Publication Publication Date Title
CN209797293U (en) Intelligent monitoring and alarming system for black box of tower crane
CN107884713A (en) A kind of generator failure detector
CN204886920U (en) Not hard up part of nuclear power station signal conditioning circuit for monitoring system
CN205209645U (en) Mining high tension cable terminal box temperature on -line monitoring and warning system
CN109488349B (en) Method and system for monitoring pressure of mining single hydraulic prop
CN202946196U (en) Tunnel gas monitoring system
CN202022663U (en) Torque limiting device with automatic sensor cable breakage detection function
CN202864766U (en) Overload warning control device of straight arm-type lorry-mounted crane
CN201738564U (en) Axial over-loading alarming system for scaffold
CN204101636U (en) A kind of accumulator on-line monitoring system
CN2831146Y (en) Antistatic wrist worn states central monitor
CN212450335U (en) Tower crane safety recording device
CN205023773U (en) Pole hoisting equipment's monitoring system is embraced in suspension of two rocking arms
CN207587143U (en) A kind of multipath gas warning device
CN202864765U (en) Straight-arm type lorry-mounted crane with moment-limited alarm device
CN217741301U (en) Mining electric shovel based on motor monitoring protection system
CN202110227U (en) Monitoring and diagnosing device of high-voltage electrical equipment
CN205981511U (en) Grinder traction force detects and alarm device
CN112701791A (en) Data online monitoring system of intelligent power distribution cabinet
CN204405225U (en) A kind of breaker temperature monitoring system
CN204224110U (en) Intelligent cucurbit operation recording instrument
CN204462761U (en) Based on the digitizing crane load limiter of CAN
CN219302621U (en) Online monitoring system for storage battery
CN204389035U (en) The intelligent thermometer of pinpoint accuracy
CN211577390U (en) Generator export PT early warning device that breaks wire

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191217