CN209780319U - Building engineering is with consolidating strutting arrangement - Google Patents

Building engineering is with consolidating strutting arrangement Download PDF

Info

Publication number
CN209780319U
CN209780319U CN201920342955.3U CN201920342955U CN209780319U CN 209780319 U CN209780319 U CN 209780319U CN 201920342955 U CN201920342955 U CN 201920342955U CN 209780319 U CN209780319 U CN 209780319U
Authority
CN
China
Prior art keywords
block
fixed block
sleeve
screw
stopper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920342955.3U
Other languages
Chinese (zh)
Inventor
黄记亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xu Peng
Zhejiang Maiwei Construction Co.,Ltd.
Original Assignee
Zhengzhou Zhongtian Building Energy Saving Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Zhongtian Building Energy Saving Co Ltd filed Critical Zhengzhou Zhongtian Building Energy Saving Co Ltd
Priority to CN201920342955.3U priority Critical patent/CN209780319U/en
Application granted granted Critical
Publication of CN209780319U publication Critical patent/CN209780319U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a building engineering is with consolidating strutting arrangement, including backup pad, turning block, movable pipe, stopper and sleeve, the symmetrical welding of surface has the fixed block in the backup pad, the fixed block upper end is provided with the turning block, the outer wall welding of fixed block one side has the stopper, the fixed block deviates from the outer wall welding of stopper one side and has first connecting block, the inside screw of having seted up of first connecting block, the symmetrical welding of turning block one side outer wall has the sleeve, the turning block deviates from the outer wall welding of sleeve one side and has the second connecting block, the inside second through-hole of having seted up of second connecting block, the inside screw that is provided with of second through-hole. The utility model discloses a set up supporting shoe, rivet, fixed block, turning block and movable tube, reached the change and thrown the effect that props inclination and fixed steel pipe body, improved the stability of scaffold frame, ensured staff's life safety.

Description

Building engineering is with consolidating strutting arrangement
Technical Field
The utility model relates to a construction machinery technical field specifically is a building engineering is with consolidating strutting arrangement.
Background
During the building engineering construction, the scaffold can be used usually, contain in the scaffold and throw the structure of propping, be used for the scaffold just begin to set up when, because even the wall body does not yet set up, for the stability of ensureing the scaffold, can use an oblique steel pipe body, one end is connected in the pole setting with rotatory fastener, the other end bracing is on ground, play the supporting role, but one end bracing is on ground, construction site earth's surface soil is soft, can not provide the sufficient stability of scaffold during the bracing, when the scaffold takes place to incline, throw the effect that can not play the support, life safety to site constructor causes the threat.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building engineering is with consolidating strutting arrangement possesses the fixed advantage of propping of throwing, has solved the throwing and has propped the problem that lacks fixed equipment.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a building engineering is with consolidating strutting arrangement, includes backup pad, turning block, activity pipe, stopper and sleeve, the symmetrical welding of surface has the fixed block in the backup pad, the fixed block upper end is provided with the turning block, the outer wall welding of fixed block one side has the stopper, the fixed block deviates from the outer wall welding of stopper one side and has first connecting block, the inside screw of having seted up of first connecting block, the symmetrical welding of turning block one side outer wall has the sleeve, the turning block deviates from the outer wall welding of sleeve one side and has the second connecting block, the inside second through-hole of having seted up of second connecting block, the inside screw that is provided with of second.
preferably, the upper surface of the supporting plate is provided with first through holes in a rectangular array, and the first through holes are movably provided with rivets.
Preferably, the inside movable tube that is provided with of fixed block and turning block, movable tube one side outer wall has been seted up and has been placed the mouth, and places the mouth inside and place the steel pipe body.
Preferably, the limiting block is rotatably arranged inside the sleeve.
Preferably, the screw penetrates through the second through hole and is rotatably installed inside the screw hole.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. The utility model discloses a set up the fixed block, turning block and movable tube, reached to change and thrown and prop inclination's effect, according to scaffold height change steel pipe body and ground angle during the use, one end is installed in the pole setting, the other end is placed inside placing the mouth, the manual movable tube of taking of staff is placed inside the turning block, the manual turning block of taking of staff, make the sleeve rotate around the stopper, first connecting block and second connecting block contact, the manual spanner of taking of staff rotates the screw, the screw rotates inside the screw, it wants the laminating to drive the turning block and fixed block, turning block and fixed block inner wall and the laminating of movable tube outer wall, produce frictional force, give the movable tube and provide stability, avoid the movable tube to take place to rotate, the stability of steel pipe body has been improved, site operation personnel's life safety has been protected.
2. The utility model discloses a set up backup pad, first through-hole and rivet, reached the effect of fixed steel pipe body, when having selected mounted position, the staff is manual places the backup pad, makes backup pad contact ground to the hammer hammering rivet of taking makes the rivet run through first through-hole fixed mounting in the underground, and the rivet provides stability for the backup pad, avoids the steel pipe body to take place to remove, has improved the security of steel pipe body.
Drawings
FIG. 1 is a schematic view of the supporting plate of the present invention;
FIG. 2 is a schematic top view of the supporting plate structure of the present invention;
Fig. 3 is an enlarged schematic view of the structure a in fig. 1 according to the present invention;
Fig. 4 is the utility model discloses a stopper structure looks sideways at the schematic diagram.
In the figure: 1. a support plate; 11. a first through hole; 12. riveting; 13. a fixed block; 14. a limiting block; 15. a first connection block; 16. a screw hole; 2. rotating the block; 21. a second connecting block; 22. a second through hole; 23. a screw; 24. a sleeve; 3. a movable tube; 31. a placement port; 32. a steel pipe body.
Detailed Description
the technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1 to 4, the present invention provides an embodiment: the utility model provides a building engineering is with consolidating strutting arrangement, includes backup pad 1, turning block 2, movable tube 3, stopper 14 and sleeve 24, and the upper surface of backup pad 1 is rectangular array and distributes and have first through-hole 11, and the inside movable mounting of first through-hole 11 has rivet 12. When the installation position is selected, the support plate 1 is placed manually by a worker, the support plate 1 is made to contact with the ground, the hammer hammering rivet 12 is taken, the rivet 12 penetrates through the first through hole 11 and is fixedly installed underground, the rivet 12 provides stability for the support plate 1, the steel pipe body 32 is prevented from moving, and the stability of the steel pipe body 32 is improved.
fixed block 13 is welded to the surface symmetry on backup pad 1, and fixed block 13 upper end is provided with turning block 2, and fixed block 13 one side outer wall welding has stopper 14, and fixed block 13 deviates from 14 one side outer wall welding of stopper has first connecting block 15, and screw 16 has been seted up inside first connecting block 15, and 2 one side outer wall symmetry welding of turning block has sleeve 24, and stopper 14 rotates and installs inside sleeve 24. When the turning block 2 rotates, the limiting block 14 rotates inside the sleeve 24, and controlled rotation of the turning block 2 is guaranteed. The outer wall of one side, departing from the sleeve 24, of the rotating block 2 is welded with a second connecting block 21, a second through hole 22 is formed in the second connecting block 21, a screw 23 is arranged in the second through hole 22, and the screw 23 penetrates through the second through hole 22 and is rotatably installed in the screw hole 16. Fixed block 13 and 2 inside movable tubes 3 that are provided with of turning block, 3 one side outer walls of movable tubes have been seted up and have been placed mouth 31, and place mouthful 31 inside and have been placed steel pipe body 32. One end of the steel pipe body 32 is fixed on the upright column, so that the angle and the distance between the steel pipe body 32 and the ground are determined, the steel pipe body 32 is prevented from inclining when being placed inside the placing opening 31, and the stability of the steel pipe body 32 is improved. According to scaffold height change steel pipe body 32 and ground angle during the use, one end is installed in the pole setting, the other end is placed inside placing mouth 31, the manual movable tube 3 of taking of staff is placed inside turning block 2, the manual turning block 2 of taking of staff, make sleeve 24 rotate around stopper 14, first connecting block 15 and the contact of second connecting block 21, the manual spanner that takes of staff rotates screw 23, screw 23 rotates in 16 insides of screw, it laminates with fixed block 13 to drive turning block 2, turning block 2 and 13 inner walls of fixed block laminate with 3 outer walls of movable tube, produce frictional force, give movable tube 3 and provide stability, avoid movable tube 3 to take place to rotate, the stability of steel pipe body 32 has been improved, site constructor's life safety has been protected.
The working principle is as follows: according to scaffold height change steel pipe body 32 and ground angle during the use, one end is installed in the pole setting, the other end is placed inside placing mouth 31, the manual movable tube 3 of taking of staff is placed inside turning block 2, the manual turning block 2 of taking of staff, make sleeve 24 rotate around stopper 14, first connecting block 15 and the contact of second connecting block 21, the manual spanner that takes of staff rotates screw 23, screw 23 rotates in 16 insides of screw, it laminates with fixed block 13 to drive turning block 2, turning block 2 and 13 inner walls of fixed block laminate with 3 outer walls of movable tube, produce frictional force, give movable tube 3 and provide stability, avoid movable tube 3 to take place to rotate, the stability of steel pipe body 32 has been improved, site constructor's life safety has been protected.
When the installation position is selected, the support plate 1 is placed manually by a worker, the support plate 1 is made to contact with the ground, the hammer hammering rivet 12 is taken, the rivet 12 penetrates through the first through hole 11 and is fixedly installed underground, the rivet 12 provides stability for the support plate 1, the steel pipe body 32 is prevented from moving, and the stability of the steel pipe body 32 is improved.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (5)

1. The utility model provides a building engineering is with consolidating strutting arrangement, includes backup pad (1), turning block (2), activity pipe (3), stopper (14) and sleeve (24), its characterized in that: the utility model discloses a screw bolt, including backup pad (1), surface symmetry welding has fixed block (13), fixed block (13) upper end is provided with turning block (2), fixed block (13) one side outer wall welding has stopper (14), fixed block (13) deviate from stopper (14) one side outer wall welding and have first connecting block (15), screw (16) have been seted up to first connecting block (15) inside, turning block (2) one side outer wall symmetry welding has sleeve (24), turning block (2) deviate from sleeve (24) one side outer wall welding and have second connecting block (21), second connecting block (21) inside has been seted up second through-hole (22), second through-hole (22) inside is provided with screw (23).
2. The reinforcing and supporting device for the building engineering as claimed in claim 1, wherein: the upper surface of the supporting plate (1) is provided with first through holes (11) in a rectangular array, and rivets (12) are movably mounted in the first through holes (11).
3. The reinforcing and supporting device for the building engineering as claimed in claim 1, wherein: fixed block (13) and turning block (2) inside are provided with movable pipe (3), movable pipe (3) one side outer wall has been seted up and has been placed mouth (31), and has been placed mouth (31) inside and has been placed steel pipe body (32).
4. The reinforcing and supporting device for the building engineering as claimed in claim 1, wherein: the limiting block (14) is rotatably arranged inside the sleeve (24).
5. The reinforcing and supporting device for the building engineering as claimed in claim 1, wherein: the screw (23) penetrates through the second through hole (22) and is rotatably installed inside the screw hole (16).
CN201920342955.3U 2019-03-16 2019-03-16 Building engineering is with consolidating strutting arrangement Active CN209780319U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920342955.3U CN209780319U (en) 2019-03-16 2019-03-16 Building engineering is with consolidating strutting arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920342955.3U CN209780319U (en) 2019-03-16 2019-03-16 Building engineering is with consolidating strutting arrangement

Publications (1)

Publication Number Publication Date
CN209780319U true CN209780319U (en) 2019-12-13

Family

ID=68798252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920342955.3U Active CN209780319U (en) 2019-03-16 2019-03-16 Building engineering is with consolidating strutting arrangement

Country Status (1)

Country Link
CN (1) CN209780319U (en)

Similar Documents

Publication Publication Date Title
CN211948458U (en) Device for enhancing stability of foundation pit support
CN209780319U (en) Building engineering is with consolidating strutting arrangement
KR20140015019A (en) Arch wall shoring structure
CN210223002U (en) Novel geological environment monitoring and early warning device
CN215562672U (en) Novel retaining wall supporting structure for foundation pit excavation
CN212742558U (en) Inner supporting structure for foundation pit
CN214460376U (en) Novel building engineering pile device
CN210459227U (en) Safety device in geotechnical engineering construction
CN212613690U (en) Flat iron type rigid wall connecting piece for building construction scaffold
CN213508487U (en) Steel bearing structure in foundation pit
CN210346725U (en) Geological disaster site with rust and corrosion prevention function
CN202430722U (en) Assembled-type manpower hole digging protection device
CN210288422U (en) Template for deep foundation pit support
CN207775898U (en) A kind of inclination pile pit supporting construction
CN217923616U (en) Foundation pit supporting device for building construction
CN213741108U (en) Quick detachable formula underground structure supporting device
CN216142047U (en) Protection device for building foundation ditch
CN215857891U (en) Foundation ditch support effect detection device
CN213120320U (en) Protective equipment is demolishd in blasting of binocular wall structure water tower under complex environment
CN215369722U (en) Anti-tipping device of rotary drilling rig
CN213233524U (en) Foundation unit for steel structure for building curtain wall engineering
CN217811114U (en) Anchoring device for preventing landslide geological disasters
CN215562709U (en) A side slope reinforcerment system for basic building engineering
CN214835088U (en) Foundation ditch construction support is used in high-speed railway construction
CN218778627U (en) Fixed gantry for manual hole digging pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240321

Address after: Room 1306-2, Nandu building, Jiaxing Economic and Technological Development Zone, Zhejiang 314000

Patentee after: Zhejiang Maiwei Construction Co.,Ltd.

Country or region after: Zhong Guo

Address before: 314000, Room 701, Building 15, Shengda Garden, Xiuzhou District, Jiaxing City, Zhejiang Province

Patentee before: Xu Peng

Country or region before: Zhong Guo

Effective date of registration: 20240319

Address after: 314000, Room 701, Building 15, Shengda Garden, Xiuzhou District, Jiaxing City, Zhejiang Province

Patentee after: Xu Peng

Country or region after: Zhong Guo

Address before: 450000 room 1510, unit 2, building 3, Guomao new territory, Jinshui District, Zhengzhou City, Henan Province

Patentee before: ZHENGZHOU ZHONGTIAN BUILDING ENERGY SAVING Co.,Ltd.

Country or region before: Zhong Guo