CN209698874U - A kind of simulation tooling prefabricated for exhaust pipe - Google Patents
A kind of simulation tooling prefabricated for exhaust pipe Download PDFInfo
- Publication number
- CN209698874U CN209698874U CN201822196765.3U CN201822196765U CN209698874U CN 209698874 U CN209698874 U CN 209698874U CN 201822196765 U CN201822196765 U CN 201822196765U CN 209698874 U CN209698874 U CN 209698874U
- Authority
- CN
- China
- Prior art keywords
- simulation
- column
- prefabricated
- exhaust pipe
- tooling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000004088 simulation Methods 0.000 title claims abstract description 107
- 230000003014 reinforcing effect Effects 0.000 claims description 13
- 239000007787 solid Substances 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims description 5
- 238000009417 prefabrication Methods 0.000 abstract description 4
- 238000010276 construction Methods 0.000 abstract 1
- 238000004519 manufacturing process Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 210000003205 muscle Anatomy 0.000 description 2
- 238000007792 addition Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The utility model belongs to simulation tooling technical field, more particularly to a kind of simulation tooling prefabricated for exhaust pipe, including the first simulation column and the second simulation column, second simulation column setting is fixed on above the first simulation column, first simulation column and the second simulation column lateral surface positioning are provided with several simulation flanges, the side of first simulation column and the second simulation column is provided with several support columns, several support frames are provided between support column.Flange is simulated in setting on the first simulation column and the second simulation column in the utility model, for simulating the flange-interface position in gas turbine main body, setting support column simulates the support construction of gas turbine on the outside of the first simulation column and the second simulation column, the locations of structures for simulating flange and support column is accurate, convenient for Prefabrication pipeline, so as to directly assemble finished product on the spot, pipeline precision is high, it avoids modifying, improves working efficiency.
Description
Technical field
The utility model belongs to simulation tooling technical field, and in particular to a kind of simulation work prefabricated for exhaust pipe
Dress.
Background technique
Gas turbine exhaust pipe belongs to high-precision, and the pipeline of operating condition harshness, dimensional tolerance and angle tolerance are very high, supplies
The small product size of oil pipe line is huge, weight is big, precision is high.Pipeline is produced according to actual demand in process of production, but is pacified
When being attached to production scene, due in installation process cutting, group to, welding after can generate subtle error, this error needs again
It corrects, make film and a series of operation, can be only achieved required precision, do over again and increased considerably cost, working efficiency is low.
Utility model content
The purpose of this utility model is the presence of the above problem in view of the prior art, proposes that a kind of structure is simple, simulation
Precisely, supporting & stablizing, the simulation tooling prefabricated for exhaust pipe.
The purpose of this utility model can be realized by the following technical scheme: a kind of simulation work prefabricated for exhaust pipe
Dress, including the first simulation column and the second simulation column, the second simulation column setting are fixed on above the first simulation column, and described first
It simulates column and the second simulation column lateral surface positioning is provided with several simulation flanges, the first simulation column and second simulate column
Side is provided with several support columns, several support frames are provided between the support column.
In a kind of above-mentioned simulation tooling prefabricated for exhaust pipe, the lower edge of the first simulation column lateral surface
It is provided with outwardly projecting first fixed edge, it is solid that the upper edge of the first simulation column lateral surface is provided with outwardly projecting second
Deckle, the lower edge of the second simulation column lateral surface are provided with outwardly projecting third fixed edge, the second simulation column lateral surface
Lower edge be provided with outwardly projecting third fixed edge.
In a kind of above-mentioned simulation tooling prefabricated for exhaust pipe, outside first fixed edge and the first simulation column
The first reinforcing rib is provided between side.
In a kind of above-mentioned simulation tooling prefabricated for exhaust pipe, outside second fixed edge and the first simulation column
The second reinforcing rib is provided between side.
In a kind of above-mentioned simulation tooling prefabricated for exhaust pipe, outside the third fixed edge and the second simulation column
Third reinforcing rib is provided between side.
Ground setting in a kind of above-mentioned simulation tooling prefabricated for exhaust pipe, below first fixed edge
There is the positioning plate for being fixed below ground 5CM, be uniformly equipped with several screws on first fixed edge, for consolidating first
Deckle is installed on positioning plate.
In a kind of above-mentioned simulation tooling prefabricated for exhaust pipe, if the ground of the positioning plate side is provided with
Dry latches, and is provided with lock hole on the lock.
In a kind of above-mentioned simulation tooling prefabricated for exhaust pipe, second fixed edge and third fixed edge it
Between be evenly arranged with two layers of screw for connect installation.
Flange is simulated in setting on the first simulation column and the second simulation column in the utility model, for simulating gas turbine master
Flange-interface position on body, setting support column simulates the support knot of gas turbine on the outside of the first simulation column and the second simulation column
Structure, the locations of structures for simulating flange and support column is accurate, is convenient for Prefabrication pipeline, so as to directly be assembled on the spot
Product, pipeline precision is high, avoids modifying, and improves working efficiency.
Detailed description of the invention
Fig. 1 is a kind of overlooking structure diagram of the simulation tooling prefabricated for exhaust pipe of the utility model;
Fig. 2 is A-A the schematic diagram of the section structure in Fig. 1;
Fig. 3 is the structural schematic diagram of the first simulation column and the second simulation column;
Fig. 4 is schematic enlarged-scale view at α in Fig. 3.
In figure, the first simulation column 1, the second simulation column 2, simulation flange 3, support column 4, support frame 5, the first fixed edge 6, the
Two fixed edges 7, third fixed edge 8, the first reinforcing rib 9, the second reinforcing rib 10, third reinforcing rib 11, positioning plate 12, screw 13,
Lock 14, lock hole 15.
Specific embodiment
It is specific embodiment of the utility model and in conjunction with attached drawing below, the technical solution of the utility model is made further
Description, but the utility model is not limited to these examples.
As shown in Figure 1, Figure 2 and Figure 3, a kind of simulation tooling prefabricated for exhaust pipe, including the first simulation column 1 and the
1 top of the first simulation column, the first simulation column 1 and the second simulation 2 lateral surface of column are fixed in two simulation columns 2, the second simulation setting of column 2
Positioning is provided with several simulation flanges 3, and the side that the first simulation column 1 and second simulate column 2 is provided with several support columns 4,
Several support frames 5 are provided between support column 4.
First simulation column 1 and second simulation column 2 be hollow cylinder, mitigate weight, save manufacture material, reduce tooling at
This, the first simulation column 1 and second simulates the shape that column 2 is used to simulate gas turbine central apparatus, the setting protrusion of flange 3 is simulated,
The flange-interface on gas turbine is simulated, integral device volume is big, and structure is complicated, and pump-line status requirement precision is high, seperated
For the first simulation column 1 and the second simulation column 2, convenient for the production and installation of tooling, first simulates the mould of column 1 and the setting of its lateral surface
Quasi- flange 3 is integrally formed, and the simulation flange 3 of the second simulation column 2 and the setting of its lateral surface is integrally formed, stable structure, and position is quasi-
Really, the piping support structure of the simulation of support column 4 on the spot, pump-line quantity is more, and caliber is big, and support frame is arranged on support column 4
5, carry out Prefabrication pipeline for positioning support, under the conditions of reaching high-precision, simplifies structure, it is easy to produce.
Preferably, the lower edge of the first simulation 1 lateral surface of column is provided with outwardly projecting first fixed edge 6, the first simulation
The upper edge of 1 lateral surface of column is provided with outwardly projecting second fixed edge 7, and the lower edge of the second simulation 2 lateral surface of column is provided with
Outwardly projecting third fixed edge 8.First simulation column 1 is fixed on the positioning on bottom surface with the first fixed edge 6, the second simulation column
2 third fixed edge 8 and the second fixed edge 7 are attached fixation, and assembling is simple accurate.
It is further preferred that being provided with the first reinforcing rib 9 between the first fixed edge 6 and the first simulation 1 lateral surface of column.First
Reinforcing rib 9 can increase the intensity of the first fixed edge 6.
Preferably, the second reinforcing rib 10 is provided between the second fixed edge 7 and the first simulation 1 lateral surface of column.Second reinforces
Muscle 10 can increase the intensity of the second fixed edge 7.
Preferably, third reinforcing rib 11 is provided between third fixed edge 8 and the second simulation 2 lateral surface of column.Third is reinforced
Muscle 11 can increase the intensity of the second fixed edge 7.
Preferably, as shown in figure 4, the ground of 6 lower section of the first fixed edge is provided with the positioning plate for being fixed below ground 5CM
12, several screws 13 are uniformly equipped on the first fixed edge 6, for the first fixed edge 6 to be installed on positioning plate 12.Due to whole
The simulation tooling volume of body is big and weight is big, and bottom surface positioning fixation below is more advantageous to stable installation.
Preferably, the ground of 12 side of positioning plate is provided with several locks 14, is provided with lock hole 15 on lock 14.Lock
Button 14 in wear lock shaft, 12 upper side of positioning plate is limited, positioning plate 12 by positioning with bottom surface on, stable structure.
Preferably, be evenly arranged between the second fixed edge 7 and third fixed edge 8 two layers of screw 13 for connect installation.
The screw 13 for two circles being arranged on the second fixed edge 7 and third fixed edge 8 helps to be stably connected with structure, the second simulation column 2
It can be stably fixed on the first simulation column 1, will not be relatively moved in pipe prefabrication production process, tool structure is steady
Fixed, precision is high.
The utility model uses the simulation flange 3 and supporting pillar being arranged on the first simulation column 1 and the second simulation column 2
Structure simulates the structure of gas turbine, and integrally formed first simulation column 1 and the second simulation column 2 are easy to assembly, and structure is accurate,
For producing high-precision exhaust pipe, Product Precision is high, and quality is stablized, and assembling use can be directly carried out on the spot, reduces
Do over again again after assembling on the spot refine the case where, reduce modification rate, effectively improve production efficiency.
The specific embodiments described herein are merely examples of the spirit of the present invention.The utility model institute
Belonging to those skilled in the art can make various modifications or additions to the described embodiments or using similar
Mode substitute, but without departing from the spirit of the present application or beyond the scope of the appended claims.
Claims (8)
1. a kind of simulation tooling prefabricated for exhaust pipe, which is characterized in that including the first simulation column and the second simulation column, institute
It states the setting of the second simulation column to be fixed on above the first simulation column, the first simulation column and the second simulation column lateral surface positioning setting
There are several to simulate flange, the side that the first simulation column and second simulate column is provided with several support columns, the support
Several support frames are provided between column.
2. a kind of simulation tooling prefabricated for exhaust pipe according to claim 1, which is characterized in that first mould
The lower edge of quasi- column lateral surface is provided with outwardly projecting first fixed edge, the upper edge setting of the first simulation column lateral surface
There is outwardly projecting second fixed edge, the lower edge of the second simulation column lateral surface is provided with outwardly projecting third and fixes
The lower edge on side, the second simulation column lateral surface is provided with outwardly projecting third fixed edge.
3. a kind of simulation tooling prefabricated for exhaust pipe according to claim 2, which is characterized in that described first is solid
The first reinforcing rib is provided between deckle and the first simulation column lateral surface.
4. a kind of simulation tooling prefabricated for exhaust pipe according to claim 2, which is characterized in that described second is solid
The second reinforcing rib is provided between deckle and the first simulation column lateral surface.
5. a kind of simulation tooling prefabricated for exhaust pipe according to claim 2, which is characterized in that the third is solid
Third reinforcing rib is provided between deckle and the second simulation column lateral surface.
6. a kind of simulation tooling prefabricated for exhaust pipe according to claim 2, which is characterized in that described first is solid
Ground below deckle is provided with the positioning plate for being fixed below ground 5CM, is uniformly equipped on first fixed edge several
A screw, for the first fixed edge to be installed on positioning plate.
7. a kind of simulation tooling prefabricated for exhaust pipe according to claim 6, which is characterized in that the positioning plate
The ground of side is provided with several locks, is provided with lock hole on the lock.
8. a kind of simulation tooling prefabricated for exhaust pipe according to claim 2, which is characterized in that described second is solid
Be evenly arranged between deckle and third fixed edge two layers of screw for connect installation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822196765.3U CN209698874U (en) | 2018-12-26 | 2018-12-26 | A kind of simulation tooling prefabricated for exhaust pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822196765.3U CN209698874U (en) | 2018-12-26 | 2018-12-26 | A kind of simulation tooling prefabricated for exhaust pipe |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209698874U true CN209698874U (en) | 2019-11-29 |
Family
ID=68638362
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822196765.3U Expired - Fee Related CN209698874U (en) | 2018-12-26 | 2018-12-26 | A kind of simulation tooling prefabricated for exhaust pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209698874U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111604845A (en) * | 2020-06-24 | 2020-09-01 | 浙江燃创透平机械股份有限公司 | Pipeline installation tool for gas turbine factory |
CN115070649A (en) * | 2022-07-22 | 2022-09-20 | 江南造船(集团)有限责任公司 | Simulation tool for marine main engine lubricating oil pump and installation method thereof |
-
2018
- 2018-12-26 CN CN201822196765.3U patent/CN209698874U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111604845A (en) * | 2020-06-24 | 2020-09-01 | 浙江燃创透平机械股份有限公司 | Pipeline installation tool for gas turbine factory |
CN111604845B (en) * | 2020-06-24 | 2022-02-25 | 浙江燃创透平机械股份有限公司 | Pipeline installation tool for gas turbine factory |
CN115070649A (en) * | 2022-07-22 | 2022-09-20 | 江南造船(集团)有限责任公司 | Simulation tool for marine main engine lubricating oil pump and installation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209698874U (en) | A kind of simulation tooling prefabricated for exhaust pipe | |
CN103521861B (en) | Based on blisk profile electrolytic machining device and the method for three-dimensional complex wake | |
CN105677978A (en) | Horizontal multi-pipe support and prefabricating construction method thereof based on BIM | |
CN102535642A (en) | Assembling type node of spatial freeform curved latticed shell steel structure and assembling method of assembling type node | |
CN202577600U (en) | Assembled joint of latticed shell steel structure with free space and curved surface | |
Bechert et al. | Integrative structural design and engineering methods for segmented timber shells-BUGA Wood Pavilion | |
CN208498757U (en) | A kind of big group of ship is found stage profile without code assembling structure | |
CN106437190B (en) | A kind of strengthening reconstruction method of industrial building legacy | |
CN206346355U (en) | A kind of support with adjustable system of all-wing aircraft curtain wall | |
CN206050007U (en) | The manual active frame of plain type | |
Tessmann et al. | Rotoform: realization of hollow construction elements through roto-forming with hyper-elastic membrane formwork | |
CN206123895U (en) | H -pile mould with adjustable | |
CN107414711B (en) | Novel assembly jig for cementing of rear machine body | |
CN207484265U (en) | Spelling fills implicit low-pylon cable-stayed bridge | |
CN108500836A (en) | A kind of slideway grinder basic component and preparation method using cast mineral and prepare mold | |
CN205967101U (en) | Car seat curb plate forming die | |
CN206958392U (en) | A kind of built-in type bearing of cable bearer | |
CN107202199A (en) | The built-in type bearing and its installation method of a kind of cable bearer | |
CN202152546U (en) | A preceding drilling method drilling steel member assembly die | |
CN206677459U (en) | A kind of assembling jig frame of high-rise building rhombus column | |
CN204449735U (en) | A kind of main platform carcasing in wind-driven generator unit equipment cabin frock | |
Hidding et al. | Structural adaptation through stiffness tuning | |
CN205134864U (en) | Adjustable hyperbolic veneer fossil fragments and skeleton base layer series interconnected system that constitutes by these fossil fragments | |
CN107052661B (en) | Electromobile frame assembly welding tooling | |
CN205445133U (en) | Assembled is combination formula anti -wind post structure for enclosure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191129 |
|
CF01 | Termination of patent right due to non-payment of annual fee |