CN209686976U - A kind of three towers - Google Patents

A kind of three towers Download PDF

Info

Publication number
CN209686976U
CN209686976U CN201920345699.3U CN201920345699U CN209686976U CN 209686976 U CN209686976 U CN 209686976U CN 201920345699 U CN201920345699 U CN 201920345699U CN 209686976 U CN209686976 U CN 209686976U
Authority
CN
China
Prior art keywords
king
post
platform
connecting rod
arc groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920345699.3U
Other languages
Chinese (zh)
Inventor
李瑞莲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FOSHAN NANHAI GUANHENG STEEL STRUCTURE Co Ltd
Original Assignee
FOSHAN NANHAI GUANHENG STEEL STRUCTURE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FOSHAN NANHAI GUANHENG STEEL STRUCTURE Co Ltd filed Critical FOSHAN NANHAI GUANHENG STEEL STRUCTURE Co Ltd
Priority to CN201920345699.3U priority Critical patent/CN209686976U/en
Application granted granted Critical
Publication of CN209686976U publication Critical patent/CN209686976U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Support Of Aerials (AREA)

Abstract

The utility model discloses a kind of three towers, king-post, several cross bars and antenna holder for being used to connect adjacent two king-posts of prism distribution including three corresponding triangular platforms, antenna holder includes the first connecting rod and the pole for being connected to the first connecting rod other end that columned platform, one end and platform side connect, platform offers round table-like through-hole, through-hole is coaxial with platform, the inner wall of through-hole set there are three with the corresponding matched arc groove in king-post side, the radian of arc groove is less than π;Each king-post is equipped with the barrier assembly moved upwards for limiting platform.As long as guaranteeing that the side of king-post is fitted into place in arc groove, high accuracy install can be realized;Platform is small to the active force of king-post in the utility model, and king-post is not easily damaged;Three king-posts are in firm triangular structure under the connection of cross bar, and structural strength is high.

Description

A kind of three towers
Technical field
The utility model relates to communicate ancillary equipment field, and in particular to a kind of three towers.
Background technique
The antenna holder of existing three tower is generally connected by screw bolts or is welded on king-post, using the connection of welding Mode, antenna holder can not be dismantled, and antenna holder just is completed to weld with king-post before installing, and the installation accuracy of antenna holder depends on The quality of welding, and the mode being connected by screw bolts, to make antenna holder and king-post be connected firmly, preventing antenna holder from deflecting, Tightened using bolt and be easy to cause king-post surface damage, since wind load is larger when king-post uses, be easy from king-post it is impaired from It bends.Therefore, need that a kind of installation accuracy is high, king-post surface is not easy due to installing three impaired towers.
Utility model content
For overcome the deficiencies in the prior art, the purpose of this utility model is to provide a kind of installation accuracy height, king-post table Face is not easy due to installing three impaired towers.
The purpose of this utility model is implemented with the following technical solutions:
A kind of three towers, the king-post of the prism distribution including three corresponding triangular platforms several are used to connect adjacent two towers The cross bar and antenna holder of column, antenna holder include columned platform, the first connecting rod of one end and platform side connection and company It is connected to the pole of the first connecting rod other end, platform offers round table-like through-hole, and through-hole is coaxial with platform, and the inner wall of through-hole is equipped with Three are less than π with the corresponding matched arc groove in king-post side, the radian of arc groove;Each king-post is equipped with upward for limiting platform The barrier assembly of movement.
Preferably, barrier assembly is clip.
Further, it is connected between adjacent clip by second connecting rod.
Preferably, each first connecting rod other end is equipped with U-bolt, and each pole passes through corresponding U-bolt and corresponding first Connecting rod connection.
Preferably, at least provided with two first connecting rods on the platform side of same perpendicular.
Preferably, the angle of each king-post and horizontal plane is 88 °~89 °.
Preferably, mounting plate is equipped at the top of king-post, mounting plate is equipped with lightning rod.
Compared with prior art, the utility model has the beneficial effects that:
It is entrenched in arc groove by the side of king-post, horizontal direction upper king-post strut can not be rotated relative to platform, as long as protecting The side for demonstrate,proving king-post is fitted into place in arc groove, and high accuracy install can be realized;It is limited on vertical direction by barrier assembly Platform moves upwards, and due to being obliquely installed for king-post, limits platform by the distance between each king-post and moves downward, relative to existing The gravity of bolt long-time bearing platform when having technology to adopt reinforcing, platform is small to the active force of king-post in the utility model, and king-post is not It is easily damaged;Three king-posts are in firm triangular structure under the connection of cross bar, and structural strength is high.
Detailed description of the invention
Fig. 1 is the three tower structural schematic diagrams of specific embodiment of the present utility model.
Fig. 2 is the antenna holder bottom view of specific embodiment of the present utility model.
Fig. 3 is the barrier assembly structural schematic diagram of specific embodiment of the present utility model.
Wherein: 10, king-post;20, cross bar;301, platform;3011, through-hole;3012, arc groove;302, first connecting rod;303, Pole;304, U-bolt;40, clip;50, second connecting rod;60, mounting plate;70, lightning rod;80, brace.
Specific embodiment
Specific embodiment of the present utility model is described below in detail, the example of specific embodiment is shown in the accompanying drawings, In which the same or similar labels are throughly indicated same or similar element or elements with the same or similar functions.Under Face is exemplary by reference to the embodiment that attached drawing describes, and is only used for explaining the utility model, and should not be understood as to this reality With novel limitation.
In the description of the present invention, it should be understood that term " center ", " longitudinal direction ", " transverse direction ", " length ", " width Degree ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside", " suitable The orientation or positional relationship of the instructions such as hour hands ", " counterclockwise ", " axial direction ", " radial direction ", " circumferential direction " is orientation based on the figure Or positional relationship, be merely for convenience of describing the present invention and simplifying the description, rather than the device of indication or suggestion meaning or Element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as the limit to the utility model System.In addition, defining " first ", the feature of " second " can explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise indicated, the meaning of " plurality " is two or more.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " is pacified Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally Connection;It can be mechanical connection, be also possible to be electrically connected;Can be directly connected, can also indirectly connected through an intermediary, It can be the connection inside two elements.For the ordinary skill in the art, above-mentioned art can be understood with concrete condition The concrete meaning of language in the present invention.
As shown in Figure 1-3, as three towers in one of specific embodiment of the utility model, including three King-post 10, several cross bars 20 and antenna holder for being used to connect adjacent two king-posts 10 of the prism distribution of corresponding triangular platform, day Line bracket includes the first connecting rod 302 and be connected to first connecting rod that columned platform 301, one end and 301 side of platform connect The pole 303 of 302 other ends, platform 301 offer round table-like through-hole 3011, and through-hole 3011 and platform 301 are coaxial, through-hole 3011 inner wall set there are three with the corresponding matched arc groove 3012 in 10 side of king-post, the radian of arc groove 3012 is less than π;Each tower Column 10 is equipped with the barrier assembly moved upwards for limiting platform 301.
Three prisms of the corresponding triangular platform of three king-posts 10 of three towers, the distance between three king-posts 10 from top to bottom by It is cumulative big, it is the routine techniques of those skilled in the art according to the size that through-hole 3011 is arranged in the actual installation height of platform 301 Means, details are not described herein, and after platform 301 is installed in place, lower end, can not be downward since the distance between three king-posts 10 increase Movement;King-post 10 is embedded in arc groove 3012, the rotation of limitation platform 301 in the horizontal direction;By the way that barrier assembly is arranged Limitation platform 301 moves upwards, so that platform 301 is fixed on king-post 10 from three-dimensional space;If it is solid to directly adopt bolt Fixed, bolt will bear the gravity of platform 301 for a long time, also provide enough pressing forces and platform 301 is avoided to send out relative to king-post 10 Raw movement, it is impaired that bolt is easy to cause king-post 10, and installation accuracy is lower;When the radian of arc groove 3012 is greater than π, 10 side of king-post Face can not be embedded in arc groove 3012, cannot achieve the installation of platform 301 Yu king-post 10.
Specifically, barrier assembly is clip 40.Clip 40 clamps king-post 10 by bolt, and the active force of bolt is not direct King-post 10 is acted on, in addition clip 40 need to provide the resistance for preventing 301 upward sliding of platform, and clip 40 is to king-post 10 Chucking power be much smaller than and directly adopt the pressing force of screw bolt reinforcing platform 301.
Lead to 301 upward sliding of platform for the loosening of clip 40, is connected between adjacent clip 40 by second connecting rod 50, it is real Existing three clips 40 link, when clip 40 loosens, due to three prisms distribution of the corresponding triangular platform of king-post 10, clip 40 It moves upwards, since second connecting rod 50 realizes the rigid connection of even clip 40, the distance between two clips 40 can not contract Short, clip 40 can not move upwards, and platform 301 can not move upwards.
When pole 303 installs out of plumb, the adjustment of the verticality, horizontal angle, inclination angle and orientation of each antenna is carried out, Workload when installation is considerably increased, construction period is extended.
Each 302 other end of first connecting rod be equipped with U-bolt 304, each pole 303 by corresponding U-bolt 304 with it is corresponding First connecting rod 302 connects, and 301 side of platform of same perpendicular is equipped with two first connecting rods 302.Guarantee that pole 303 hangs down Straight installation, convenient for the installation of later period antenna.
The angle of each king-post 10 and horizontal plane is 88 °~89 °.Avoid king-post 10 and the angle of horizontal plane too small, limitation three The manufacture height of turret, restricts the application of triangle tower.
Mounting plate 60 is equipped at the top of king-post 10, mounting plate 60 is equipped with lightning rod 70.
For the structural strength for improving three towers, connected by brace 80 between adjacent crossbars 20.
Above embodiment is only the certain preferred embodiments of the utility model, cannot limit the utility model with this The range of protection, the variation and replacement of any unsubstantiality that those skilled in the art is done on the basis of the utility model Belong to the utility model range claimed.

Claims (7)

1. a kind of three towers, the king-post of the prism distribution including three corresponding triangular platforms several is used to connect adjacent described two The cross bar and antenna holder of king-post, which is characterized in that the antenna holder includes columned platform, one end and the platform side The first connecting rod of face connection and the pole for being connected to the first connecting rod other end, the platform offer round table-like through-hole, The through-hole and the platform are coaxial, the inner wall of the through-hole set there are three with the corresponding matched arc groove in king-post side, The radian of the arc groove is less than π;Each king-post is equipped with the barrier assembly moved upwards for limiting the platform.
2. three tower according to claim 1, which is characterized in that the barrier assembly is clip.
3. three tower according to claim 2, which is characterized in that connected between the adjacent clip by second connecting rod It connects.
4. three tower according to claim 1, which is characterized in that each first connecting rod other end is equipped with U-bolt, respectively The pole is connected by the corresponding U-bolt with the corresponding first connecting rod.
5. three tower according to claim 4, which is characterized in that at least set on the platform side of same perpendicular There are two first connecting rods.
6. three tower according to claim 1, which is characterized in that the angle of each king-post and horizontal plane is 88 °~ 89°。
7. three tower according to claim 1, which is characterized in that be equipped with mounting plate, the mounting plate at the top of the king-post It is equipped with lightning rod.
CN201920345699.3U 2019-03-18 2019-03-18 A kind of three towers Active CN209686976U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920345699.3U CN209686976U (en) 2019-03-18 2019-03-18 A kind of three towers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920345699.3U CN209686976U (en) 2019-03-18 2019-03-18 A kind of three towers

Publications (1)

Publication Number Publication Date
CN209686976U true CN209686976U (en) 2019-11-26

Family

ID=68605417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920345699.3U Active CN209686976U (en) 2019-03-18 2019-03-18 A kind of three towers

Country Status (1)

Country Link
CN (1) CN209686976U (en)

Similar Documents

Publication Publication Date Title
CN211172029U (en) Temporary supporting device for steel purlin
CN206667730U (en) A kind of scalable suspension scaffold of socket joint type disk button
CN202577380U (en) Steel member perpendicularity correcting device for construction of upright column piles
CN209686976U (en) A kind of three towers
CN205119990U (en) Connection survey frame
CN206987423U (en) A kind of building jacking device
CN208981645U (en) A kind of building structure wind-brace column
CN214948055U (en) Fixed mounting formula total powerstation support
CN211395376U (en) Auxiliary positioning device for mounting arch rib of arch bridge with extra-large steel box girder
CN103248272A (en) Component bracket structure
CN208455656U (en) A kind of anchor ear support device
CN210801062U (en) Lamp pole mounting structure
CN201355631Y (en) Stand column base system for installing antenna
CN205173885U (en) Install in iron tower scissor holder's ptz support
CN110847011A (en) Steel trestle bailey sheet fixing device and fixing method thereof
CN206861058U (en) A kind of high-temperature-hot-water pipeline fixing bracket device
CN204531360U (en) The multistage Level tune bracing or strutting arrangement of soldering-free type
CN215572954U (en) Shield constructs total powerstation of guidance system and observes fixed platform
CN203821934U (en) Draught fan support applied to side surface of electric transmission line angle iron tower
CN219364359U (en) Construction bracket for cantilever bent cap of circular single-column high pier
CN218813841U (en) Landscape lamp foundation ground cage
CN220209303U (en) Lightning protection pole earthing device
CN210422895U (en) Power cable protection support in top section tower section of thick bamboo
CN218386505U (en) A crane span structure mounting system for tubular pile basis portable installation
CN203703562U (en) Observation platform for construction surveying

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant