Weather simulation laboratory with detachable Simulation house Download PDF

Info

Publication number
CN209674706U
CN209674706U CN201822213275.XU CN201822213275U CN209674706U CN 209674706 U CN209674706 U CN 209674706U CN 201822213275 U CN201822213275 U CN 201822213275U CN 209674706 U CN209674706 U CN 209674706U
Authority
CN
China
Prior art keywords
simulation
house
detachable
weather
natural environment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822213275.XU
Other languages
Chinese (zh)
Inventor
金渊
关宇
张倩
李同智
洪沅伸
陈熙
焦然
陆涛
孙舟
潘鸣宇
王伟贤
陈振
袁小溪
刘秀兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING ESHENGTAIHE CTRL TECH Co Ltd
State Grid Corp of China SGCC
State Grid Beijing Electric Power Co Ltd
Original Assignee
BEIJING ESHENGTAIHE CTRL TECH Co Ltd
State Grid Corp of China SGCC
State Grid Beijing Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING ESHENGTAIHE CTRL TECH Co Ltd, State Grid Corp of China SGCC, State Grid Beijing Electric Power Co Ltd filed Critical BEIJING ESHENGTAIHE CTRL TECH Co Ltd
Priority to CN201822213275.XU priority Critical patent/CN209674706U/en
Application granted granted Critical
Publication of CN209674706U publication Critical patent/CN209674706U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Instructional Devices (AREA)

Abstract

The utility model provides a kind of weather simulation laboratory with detachable Simulation house, comprising: natural environment simulation laboratory, natural environment simulation laboratory include ground, side wall and roof, and ground, side wall and roof surround accommodation space;Simulation house, Simulation house are arranged in accommodation space, and Simulation house is detachably connected with ground, and accommodation space is divided into interior environment lab space and external environment lab space by Simulation house;Natural environment simulator, natural environment simulator External Environment lab space simulating natural environment.The technical solution of the utility model effectively solves Simulation house in the prior art replacement when manpower and material resources waste the problem of.

Description

Weather simulation laboratory with detachable Simulation house
Technical field
The utility model relates to the technical fields of weather simulation laboratory, have removable form in particular to one kind The weather simulation laboratory in quasi- house.
Background technique
Weather simulation laboratory needs to simulate different natural environments, and the tangible natural environment simulation of the natural environment of simulation is real Indoor progress is tested, needs to meet this requires the structure of Simulation house, construction, material etc. under above-mentioned different natural environments Demand.The dismounting of Simulation house is usually destructive larger, such as needs crash simulation house and natural environment simulation laboratory Ground etc..The waste of manpower and material resources is caused in this way.
Utility model content
The main purpose of the utility model is to provide a kind of weather simulation laboratory with detachable Simulation house, with Solve the problems, such as the waste of Simulation house in the prior art manpower and material resources when replacement.
To achieve the goals above, the utility model provides a kind of weather emulation experiment with detachable Simulation house Room, comprising: natural environment simulation laboratory, natural environment simulation laboratory include ground, side wall and roof, ground, side wall and Roof surrounds accommodation space;Simulation house, Simulation house are arranged in accommodation space, and Simulation house removably connects with ground It connects, accommodation space is divided into interior environment lab space and external environment lab space by Simulation house;Natural environment simulator, from Right environment simulator External Environment lab space simulating natural environment.
Further, Simulation house includes wood frame, and wood frame is detachably connected with ground.
Further, ground has groove, and wood frame is located in groove.
Further, Simulation house further includes the first wooden cladding boards, the first cladding boards be arranged in wood frame with Form the side wall of Simulation house.
Further, Simulation house further includes plasterboard, and the inside of the first cladding boards is arranged in plasterboard.
Further, wood frame includes multiple vertical columns and multiple connecting cross beams, and column and connecting cross beam are removable It links together with unloading.
Further, roof includes wooden truss, and wooden truss and wood frame are detachably connected.
Further, wooden truss includes more wooden support rods, and adjacent support rod is detachable structure.
Further, Simulation house further includes the second cladding boards, and the second cladding boards are removably disposed on wooden truss.
Using the technical solution of the utility model, using removably between Simulation house and natural environment simulation laboratory Mode connects, and in this way when disassembly Simulation house or the material etc. of replacement Simulation house, directly carries out dismounting Simulation house, Crash simulation house and the ground of natural environment simulation laboratory etc. are not needed, above structure saves cost of labor.This is practical Novel technical solution efficiently solves the Simulation house in the prior art waste of manpower and material resources when replacement and asks Topic.
Detailed description of the invention
The accompanying drawings constituting a part of this application is used to provide a further understanding of the present invention, this is practical Novel illustrative embodiments and their description are not constituteed improper limits to the present invention for explaining the utility model. In the accompanying drawings:
Fig. 1 shows the structure of the embodiment of the weather simulation laboratory of detachable Simulation house according to the present utility model Schematic diagram.
Wherein, the above drawings include the following reference numerals:
10, natural environment simulation laboratory;11, ground;20, Simulation house.
Specific embodiment
It should be noted that in the absence of conflict, the features in the embodiments and the embodiments of the present application can phase Mutually combination.The utility model will be described in detail below with reference to the accompanying drawings and embodiments.
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.Unless another It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
For ease of description, spatially relative term can be used herein, as " ... on ", " ... top ", " ... upper surface ", " above " etc., for describing such as a device shown in the figure or feature and other devices or spy The spatial relation of sign.It should be understood that spatially relative term is intended to comprising the orientation in addition to device described in figure Except different direction in use or operation.For example, being described as if the device in attached drawing is squeezed " in other devices It will be positioned as " under other devices or construction after part or construction top " or the device of " on other devices or construction " Side " or " under other devices or construction ".Thus, exemplary term " ... top " may include " ... top " and " in ... lower section " two kinds of orientation.The device can also be positioned with other different modes and (is rotated by 90 ° or in other orientation), and And respective explanations are made to the opposite description in space used herein above.
Now, the illustrative embodiments according to the application are more fully described with reference to the accompanying drawings.However, these are exemplary Embodiment can be implemented by many different forms, and should not be construed to be limited solely to embodiment party set forth herein Formula.It should be understood that it is thoroughly and complete to these embodiments are provided so that disclosure herein, and these are shown The design of example property embodiment is fully conveyed to those of ordinary skill in the art, in the accompanying drawings, for the sake of clarity, expands layer With the thickness in region, and make that identical device is presented with like reference characters, thus description of them will be omitted.
As shown in Figure 1, the weather simulation laboratory with detachable Simulation house of the present embodiment includes: natural environment mould Draft experiment room 10, Simulation house 20 and natural environment simulator.Natural environment simulation laboratory 10 include ground 11, side wall and Roof, ground 11, side wall and roof surround accommodation space.Simulation house 20 is arranged in accommodation space, Simulation house 20 and ground Face 11 is detachably connected, and accommodation space is divided into interior environment lab space and external environment lab space by Simulation house 20.From Right environment simulator External Environment lab space simulating natural environment.
Using the technical solution of the present embodiment, using detachable place between Simulation house and natural environment simulation laboratory Formula connection directly carries out dismounting Simulation house, no in this way when disassembly Simulation house or the material etc. of replacement Simulation house Crash simulation house and the ground of natural environment simulation laboratory etc. are needed, above structure saves cost of labor.The present embodiment Technical solution efficiently solve the problems, such as Simulation house in the prior art replacement when manpower and material resources waste.
As shown in Figure 1, in the technical scheme of this embodiment, Simulation house 20 includes wood frame, wood frame and ground Face 11 is detachably connected.Wood frame materials are easy, easy to process.The connectors such as angle bar are set in wood frame, then Foot bolt is connected by connector with ground 11.Above structure processing cost is lower.
As shown in Figure 1, in the technical scheme of this embodiment, ground 11 has groove, wood frame is located in groove.On Stating structure makes Simulation house 20 relatively more firm.Specifically, the gap between groove and wood frame is provided with sealant, sealing Glue has the function of sealing waterproof, can prevent the liquid in natural environment simulated experiment room from entering groove in this way.The bottom of groove If there is drainage channel can be discharged by groove have the liquid such as water in groove in portion.
As shown in Figure 1, in the technical scheme of this embodiment, Simulation house 20 further includes the first wooden cladding boards, the The side wall that Simulation house 20 is formed in wood frame is arranged in one cladding boards.The Simulation house 20 of the present embodiment can be well Simulate the energy consumption in the house of wood materials.Specifically, electric energy is all made of in the weather simulation laboratory of the present embodiment to mention For energy, for example, heating, refrigeration, heating etc..
As shown in Figure 1, in the technical scheme of this embodiment, Simulation house 20 further includes plasterboard, plasterboard setting exists The inside of first cladding boards.Plasterboard is arranged two layers, and heating film is arranged between two layers of plasterboard, can prevent simulation room in this way Room 20 is on fire.
As shown in Figure 1, in the technical scheme of this embodiment, wood frame includes multiple vertical columns and multiple connections Crossbeam, column and connecting cross beam are removably joined together.Specifically, each corner is both provided with vertical stand Column is spaced 1 meter between the adjacent column of every face wall.Connecting cross beam is detachably connected between two adjacent columns, this Sample makes Simulation house firmer, and Simulation house 20 is prevented to be easily deformed.It is connected by screw bolts between column and connecting cross beam , such handling ease, cost of manufacture is lower.It is of course also possible to use the mosaic texture of male-female engagement is connected, then again It is fixed by the way of gluing.
As shown in Figure 1, in the technical scheme of this embodiment, roof includes wooden truss, wooden truss and wood frame It is detachably connected.Above structure makes the dismounting between wooden truss and wood frame more convenient, does not need crash simulation The structure in house 20.
(not shown) in the technical scheme of this embodiment, wooden truss includes more wooden support rods, adjacent Support rod is detachable structure.Above structure processing cost is lower.Similarly, above-mentioned detachable structure can be connected for screw, Or the mosaic texture of male-female.
As shown in Figure 1, in the technical scheme of this embodiment, Simulation house 20 further includes the second cladding boards, the second clad can Plate is removably disposed on wooden truss.Above structure processing cost is low, easy to connect.Room is provided in second cladding boards Watt, it is more nearly in this way with actual house, the numerical value of survey is more accurate.
It should be noted that at least 2 meters of inner wall of the outer wall of Simulation house apart from natural environment simulation laboratory, weather is imitative The energy resource supply of true experiment room is electric energy supply
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or their combination.
It should be noted that the description and claims of this application and term " first " in above-mentioned attached drawing, " Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way Data be interchangeable under appropriate circumstances, so that presently filed embodiment described herein for example can be in addition to herein Sequence other than those of diagram or description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that Be to cover it is non-exclusive include, for example, containing the process, method, system, product or equipment of a series of steps or units not Those of be necessarily limited to be clearly listed step or unit, but may include be not clearly listed or for these processes, side The intrinsic other step or units of method, product or equipment.
The above descriptions are merely preferred embodiments of the present invention, is not intended to limit the utility model, for this For the technical staff in field, various modifications and changes may be made to the present invention.It is all in the spirit and principles of the utility model Within, any modification, equivalent replacement, improvement and so on should be included within the scope of protection of this utility model.

Claims (9)

1. a kind of weather simulation laboratory with detachable Simulation house characterized by comprising
Natural environment simulation laboratory (10), the natural environment simulation laboratory (10) include ground (11), side wall and roof, The ground (11), side wall and roof surround accommodation space;
Simulation house (20), the Simulation house (20) are arranged in the accommodation space, the Simulation house (20) with it is described Ground (11) is detachably connected, and the accommodation space is divided into interior environment lab space and outer ring by the Simulation house (20) Border lab space;
Natural environment simulator, the natural environment simulator is to the external environment lab space simulating natural environment.
2. the weather simulation laboratory according to claim 1 with detachable Simulation house, which is characterized in that the mould Quasi- house (20) include wood frame, and the wood frame and the ground (11) are detachably connected.
3. the weather simulation laboratory according to claim 2 with detachable Simulation house, which is characterized in that describedly Face (11) has groove, and the wood frame is located in the groove.
4. the weather simulation laboratory according to claim 2 with detachable Simulation house, which is characterized in that the mould Quasi- house (20) further include the first wooden cladding boards, and first cladding boards are arranged in the wood frame described in formation The side wall of Simulation house (20).
5. the weather simulation laboratory according to claim 4 with detachable Simulation house, which is characterized in that the mould Quasi- house (20) further include plasterboard, and the inside of first cladding boards is arranged in the plasterboard.
6. the weather simulation laboratory according to claim 2 with detachable Simulation house, which is characterized in that the wood Matter frame includes multiple vertical columns and multiple connecting cross beams, and the column and the connecting cross beam are detachably connected to one It rises.
7. the weather simulation laboratory according to claim 2 with detachable Simulation house, which is characterized in that the room Top includes wooden truss, and the wooden truss and the wood frame are detachably connected.
8. the weather simulation laboratory according to claim 7 with detachable Simulation house, which is characterized in that the wood Matter truss includes more wooden support rods, and the adjacent support rod is detachable structure.
9. the weather simulation laboratory according to claim 7 with detachable Simulation house, which is characterized in that the mould Quasi- house (20) further include the second cladding boards, and second cladding boards are removably disposed on the wooden truss.
CN201822213275.XU 2018-12-26 2018-12-26 Weather simulation laboratory with detachable Simulation house Active CN209674706U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822213275.XU CN209674706U (en) 2018-12-26 2018-12-26 Weather simulation laboratory with detachable Simulation house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822213275.XU CN209674706U (en) 2018-12-26 2018-12-26 Weather simulation laboratory with detachable Simulation house

Publications (1)

Publication Number Publication Date
CN209674706U true CN209674706U (en) 2019-11-22

Family

ID=68563736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822213275.XU Active CN209674706U (en) 2018-12-26 2018-12-26 Weather simulation laboratory with detachable Simulation house

Country Status (1)

Country Link
CN (1) CN209674706U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118166910A (en) * 2024-05-14 2024-06-11 中国建筑设计研究院有限公司 Full-scale house frame and full-scale house construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118166910A (en) * 2024-05-14 2024-06-11 中国建筑设计研究院有限公司 Full-scale house frame and full-scale house construction method

Similar Documents

Publication Publication Date Title
Loss et al. Connections for steel–timber hybrid prefabricated buildings. Part II: Innovative modular structures
CN110512790B (en) High and large space multi-curvature suspended ceiling structure and construction method thereof
US20180298600A1 (en) Building Panel Assembly and Method of Manufacturing
CA2787508A1 (en) Module for the construction of buildings, and construction method
CN209674706U (en) Weather simulation laboratory with detachable Simulation house
Vogrinec et al. Simplified modelling of timber-framed walls under lateral loads
Pintarič et al. Mathematical modelling of timber-framed walls using fictive diagonal elements
CN209227776U (en) A kind of three-dimensional building module
Vallee et al. Design and dimensioning of a complex timber-glass hybrid structure: the IFAM pedestrian bridge
Polastri et al. Numerical analyses of high-and medium-rise CLT buildings braced with cores and additional shear walls
Vogrinec et al. Influence of the design approach on the behaviour of timber-frame panel buildings under horizontal forces
CN202767578U (en) Modular data center
Samarasinghe et al. Applications of design for excellence in prefabricated building services systems
WO2019007229A1 (en) Floor slab system
CN210295486U (en) Aviation maintenance teaching sealant coating simulation exercise rack
CN216053573U (en) Assembled steel structure solid model for teaching
CN206438642U (en) A kind of spliced panel structure and building
Rumlová et al. The timber tie beam: the analysis of spatial framework joint
CN203425534U (en) Building block combined type cable-stayed bridge model
CN208433152U (en) A kind of cable duct outdoor scene simulation training display systems
CN105544732A (en) Foldable portable house
CN209674689U (en) Interior environmental laboratory for weather simulation laboratory
Antonini et al. Towards nZEB: modular pre-assembled steel systems for residential buildings
CN108399874A (en) Non-maintaining modularization open air two sides billboard
CN110241948A (en) A kind of modularization wall displacement fixed form

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant