CN209673085U - A kind of blower settlement monitoring prior-warning device - Google Patents

A kind of blower settlement monitoring prior-warning device Download PDF

Info

Publication number
CN209673085U
CN209673085U CN201920693666.8U CN201920693666U CN209673085U CN 209673085 U CN209673085 U CN 209673085U CN 201920693666 U CN201920693666 U CN 201920693666U CN 209673085 U CN209673085 U CN 209673085U
Authority
CN
China
Prior art keywords
fixedly connected
blower
connecting rod
settlement monitoring
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920693666.8U
Other languages
Chinese (zh)
Inventor
雷平飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taiyuan Zhiyi Wind Energy Technology Co ltd
Shanxi Installation Group Co Ltd
Original Assignee
Shanxi Industrial Equipment Installation Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Industrial Equipment Installation Group Co Ltd filed Critical Shanxi Industrial Equipment Installation Group Co Ltd
Priority to CN201920693666.8U priority Critical patent/CN209673085U/en
Application granted granted Critical
Publication of CN209673085U publication Critical patent/CN209673085U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Control Of Positive-Displacement Air Blowers (AREA)

Abstract

The utility model discloses a kind of blower settlement monitoring prior-warning devices, including tunnel body and jet blower, wall is fixedly connected with fixed case in the tunnel body, slideway is offered in the middle part of the fixed case, being slidably connected in the slideway, there are two sliding blocks, the sliding block bottom end is fixedly connected to connection frame, mounting rack there are two being fixedly connected above the jet blower side wall, the mounting rack side is fixedly connected with attachment base, the attachment base side is socketed with first connecting rod, the first connecting rod other end sliding sleeve is connected to the second connecting rod, the second connecting rod other end is fixedly connected with rack gear, side is fixedly connected there are two fixed frame in the tunnel body, and two fixed frames are respectively fixedly connected in fixed case two sides, the utility model improves the source of early warning installation effectiveness that blower drop is heavy or falls down, it can be more accurate to wind Machine sedimentation is detected, and blower sedimentation information can also be carried out warning processing in time.

Description

A kind of blower settlement monitoring prior-warning device
Technical field
The utility model relates to detection technique field, specially a kind of blower settlement monitoring prior-warning device.
Background technique
Domestic built tunnel has much now, and to Zhongnanshan Mountain Tunnel, the tunnel Bao Jiashan, Liuyang river tunnel is all speciality Tunnel is mounted with many jet blowers, probably at 200 meters to 250 meters or so, just for the safety used at the top of tunnel There is one group of jet blower (every group 2 or 3 are differed), although built-in fitting has all done pull-out test before installing jet blower, National requirements is all met, but there may be the risks for settling or falling down after jet blower installation now, now The early warning installation that blower drop sinks or falls down is relatively complicated, cannot more accurately detect to blower sedimentation, thus cannot Blower sedimentation information is subjected to warning processing in time, and also more insecure to the installation of blower now, apoplexy is used for a long time Machine is easy to produce loosening.For this purpose, it is proposed that a kind of blower settlement monitoring prior-warning device.
Utility model content
The purpose of this utility model is to provide a kind of blower settlement monitoring prior-warning devices, to solve in above-mentioned background technique The problem of proposition.
To achieve the above object, the utility model provides the following technical solutions: a kind of blower settlement monitoring prior-warning device, packet Tunnel body and jet blower are included, wall is fixedly connected with fixed case in the tunnel body, offers slideway in the middle part of the fixed case, institute It states and is slidably connected in slideway there are two sliding block, the sliding block bottom end is fixedly connected to connection frame, on the jet blower side wall Side is fixedly connected there are two mounting rack, and the mounting rack side is fixedly connected with attachment base, and the attachment base side is socketed with the One connecting rod, the first connecting rod other end sliding sleeve are connected to the second connecting rod, and the second connecting rod other end is fixed to be connected It is connected to rack gear, side is fixedly connected there are two fixed frame in the tunnel body, and two fixed frames are respectively fixedly connected in fixed case Two sides, the fixed frame side are rotatably connected to fluted disc, and connection, the fixed peace in the fixed frame bottom end is engaged with rack in the fluted disc Equipped with torque sensor, and torque sensor output shaft is rotatablely connected by the rotation axis of belt and fluted disc, the fixed frame one Side is fixedly installed with warning lamp, and the torque sensor output end is electrically connected with controller, the controller output end and police Show that lamp is electrically connected.
Preferably, the mounting rack top is fixedly connected with gasket.
Preferably, the connecting pin of two connection frames is to place in the same direction.
Preferably, the installation foot of two mounting racks is opposite places.
Preferably, the fixed case middle part bottom end is fixedly installed with fastening screw by internal and external threads, and fastening screw is solid Dingan County is immediately below sliding block.
Preferably, the first connecting rod and the second connecting rod are rectangular shaft.
Compared with prior art, the utility model has the beneficial effects that
1, the utility model passes through first connecting rod first and is socketed in attachment base and then is fixed with screw, then will Second connecting rod is socketed in the other end of first connecting rod and then is fixed using screw, is matched rack gear with fluted disc and is nibbled It closes, then in long-term use, if jet blower, there is a situation where settling, then jet blower drives first connecting rod and second Connecting rod moves down, and then the second connecting rod band carry-over bar moves down, then rack drives fluted disc is rotated, thus fluted disc It drives torque sensor to be rotated by belt, warning lamp is then controlled by controller and is alarmed, improve blower drop Source of early warning installation effectiveness that is heavy or falling down more accurate can detect blower sedimentation, can also be in time by wind Machine sedimentation information carries out warning processing.
2, mounting rack is placed at the top of the connecting pin of connection frame, then passes through cunning by the utility model moving jet blower Block slides in slideway pushes connection frame, and connection frame is made to be stuck on mounting rack and then be fixed using bolt, then using tight Gu sliding block is fixed in screw, so that assembling is stronger, it is not easy to generate loosening in long-term use.
Detailed description of the invention
Fig. 1 is the utility model overall structure diagram;
Fig. 2 is the utility model fixed case sectional view;
Fig. 3 is the utility model jet blower side view;
Fig. 4 is enlarged drawing at A in the utility model Fig. 1;
Fig. 5 is that the utility model is electrically connected block diagram.
In figure: 1, tunnel body;2, fixed case;3, slideway;4, sliding block;5, connection frame;6, fastening screw;7, jet blower; 8, mounting rack;9, gasket;10, attachment base;11, first connecting rod;12, the second connecting rod;13, rack gear;14, fixed frame;15, tooth Disk;16, torque sensor;17, warning lamp.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-5 is please referred to, the utility model provides a kind of technical solution: a kind of blower settlement monitoring prior-warning device, including Tunnel body 1 and jet blower 7,1 inner wall of tunnel body are fixedly connected with fixed case 2, and slideway 3, slideway 3 are offered in the middle part of fixed case 2 It is inside slidably connected there are two sliding block 4,4 bottom end of sliding block is fixedly connected to connection frame 5, and wherein 7 model SDS of jet blower, is penetrated Mounting rack 8 there are two being fixedly connected above 7 side wall of flow fan, 8 side of mounting rack is fixedly connected with attachment base 10, attachment base 10 1 Side is socketed with first connecting rod 11, and 11 other end sliding sleeve of first connecting rod is connected to the second connecting rod 12, and the second connecting rod 12 is another One end is fixedly connected with rack gear 13, is fixedly connected on the inside of tunnel body 1 there are two fixed frame 14, and two fixed frames 14 are fixed respectively 2 two sides of fixed case are connected to, 14 side of fixed frame is rotatably connected to fluted disc 15, and fluted disc 15 engages connection, fixed frame with rack gear 13 14 bottom ends are fixedly installed with torque sensor 16, wherein 16 model WSNJ-101 of torque sensor, and torque sensor 16 is defeated Shaft is rotatablely connected by the rotation axis of belt and fluted disc 15, and 14 side of fixed frame is fixedly installed with warning lamp 17, wherein warning 17 model LTE-1101J of lamp, 16 output end of torque sensor are electrically connected with controller, controller output end and warning lamp 17 It is electrically connected, 8 top of mounting rack is fixedly connected with gasket 9, can be installed connection frame 5 and mounting rack 8 more by gasket 9 Securely, the connecting pin of two connection frames 5 is to place in the same direction, and the installation foot of two mounting racks 8 is to place in opposite directions, can be same by two To connection frame 5 and two opposite mounting racks 8 carry out clamping support, be then fixed using bolt, ensure that connection more Add securely, 2 middle part bottom end of fixed case is fixedly installed with fastening screw 6 by internal and external threads, and fastening screw 6 is fixedly mounted on cunning Immediately below block 4, sliding block 4 can be fixed by fastening screw 6, guarantee stabilization of the blower in fixation, first connecting rod 11 and second connecting rod 12 be rectangular shaft, after being socketed first connecting rod 11 and the second connecting rod 12, ensure that Rack gear 13 matches with fluted disc 15, will not deviate, and mounting rack 8 is placed on the connection of connection frame 5 by moving jet blower 7 It at the top of foot, is then slided in slideway 3 by sliding block 4 and pushes connection frame 5, be stuck in connection frame 5 on mounting rack 8 and then utilize spiral shell Bolt is fixed, and is then fixed using fastening screw 6 to sliding block 4, is socketed in attachment base 10 by first connecting rod 11 Then be fixed with screw, then by the second connecting rod 12 be socketed in first connecting rod 11 the other end then utilize screw into Row is fixed, and is matched rack gear 13 with fluted disc 15 and is engaged, then in long-term use, if the feelings that jet blower 7 settles Condition, then jet blower 7 drives first connecting rod 11 and the second connecting rod 12 to move down, and then the second connecting rod 12 is with movable tooth Item 13 moves down, then rack gear 13 is rotated with active toothed disk 15, thus fluted disc 15 by belt drive torque sensor 16 into Row rotation, then the signal of generation is transferred to controller by torque sensor 16, then by controller control warning lamp 17 into Row alarm.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. a kind of blower settlement monitoring prior-warning device, including tunnel body (1) and jet blower (7), it is characterised in that: the tunnel Body (1) inner wall is fixedly connected with fixed case (2), is offered slideway (3) in the middle part of the fixed case (2), sliding in the slideway (3) There are two sliding block (4) for connection, and sliding block (4) bottom end is fixedly connected to connection frame (5), on jet blower (7) side wall There are two being just fixedly connected mounting rack (8), mounting rack (8) side is fixedly connected with attachment base (10), the attachment base (10) side is socketed with first connecting rod (11), and first connecting rod (11) other end sliding sleeve is connected to the second connecting rod (12), the second connecting rod (12) other end is fixedly connected with rack gear (13), is fixedly connected with two on the inside of the tunnel body (1) A fixed frame (14), and two fixed frames (14) are respectively fixedly connected in fixed case (2) two sides, fixed frame (14) side turns Dynamic to be connected with fluted disc (15), the fluted disc (15) engages connection with rack gear (13), and fixed frame (14) bottom end is fixedly installed with Torque sensor (16), and torque sensor (16) output shaft is rotatablely connected by the rotation axis of belt and fluted disc (15), it is described Fixed frame (14) side is fixedly installed with warning lamp (17), and torque sensor (16) output end is electrically connected with controller, The controller output end and warning lamp (17) are electrically connected.
2. a kind of blower settlement monitoring prior-warning device according to claim 1, it is characterised in that: mounting rack (8) top End is fixedly connected with gasket (9).
3. a kind of blower settlement monitoring prior-warning device according to claim 1, it is characterised in that: two connection frames (5) connecting pin is to place in the same direction.
4. a kind of blower settlement monitoring prior-warning device according to claim 1, it is characterised in that: two mounting racks (8) installation foot is opposite places.
5. a kind of blower settlement monitoring prior-warning device according to claim 1, it is characterised in that: in the fixed case (2) Portion bottom end is fixedly installed with fastening screw (6) by internal and external threads, and fastening screw (6) is fixedly mounted on immediately below sliding block (4).
6. a kind of blower settlement monitoring prior-warning device according to claim 1, it is characterised in that: the first connecting rod (11) and the second connecting rod (12) is rectangular shaft.
CN201920693666.8U 2019-05-15 2019-05-15 A kind of blower settlement monitoring prior-warning device Active CN209673085U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920693666.8U CN209673085U (en) 2019-05-15 2019-05-15 A kind of blower settlement monitoring prior-warning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920693666.8U CN209673085U (en) 2019-05-15 2019-05-15 A kind of blower settlement monitoring prior-warning device

Publications (1)

Publication Number Publication Date
CN209673085U true CN209673085U (en) 2019-11-22

Family

ID=68575155

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920693666.8U Active CN209673085U (en) 2019-05-15 2019-05-15 A kind of blower settlement monitoring prior-warning device

Country Status (1)

Country Link
CN (1) CN209673085U (en)

Similar Documents

Publication Publication Date Title
CN208901003U (en) A kind of adjustable monitoring device bracket
CN209673085U (en) A kind of blower settlement monitoring prior-warning device
CN111928881A (en) Infrared sensor
CN204944387U (en) Plastic bearing clearance pick-up unit
CN208204423U (en) A kind of easy-to-dismount monitoring camera
CN207634923U (en) Can adjust automatically angle high-altitude monitoring device
CN112954924B (en) Thing networking management device of usefulness is administered to basic unit's society
CN214929383U (en) Anti-rotation anti-drop fixing structure of automobile sensor
CN209569484U (en) A kind of numerically-controlled machine tool electronic monitoring equipment support frame
CN108709582A (en) Monitoring system is fastened using the bolt of proximity sensor
CN208984327U (en) A kind of curtain head life detecting device
CN108278946A (en) A kind of round nut size qualification detection device
CN207848340U (en) A kind of light-duty binding beam fixing piece
CN215375327U (en) Explosion-proof type industrial gas detector
CN218384187U (en) Accident prevention reminding device for enterprise safety production
CN215726800U (en) Vibration testing device for speed reducer
CN210571306U (en) Portable optometry device for anti-light hard screen
CN218995342U (en) Water quality index detection device
CN216717686U (en) But short-term test's gas tightness detector
CN208705025U (en) A kind of bolt detection device for fastening parts of automobiles
CN217821772U (en) Heat radiation structure for multidimensional three-technology composite sensing detector
CN214278094U (en) Air quality monitoring device
CN220084205U (en) Real-time temperature detection device
CN221078783U (en) Energy consumption detection device for central air conditioning system
CN212008853U (en) Distributed motor quality detection system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210610

Address after: 030032 8 Xinhua Road, Taiyuan economic and Technological Development Zone, Xiaodian District, Taiyuan, Shanxi

Patentee after: SHANXI INDUSTRIAL EQUIPMENT INSTALLATION GROUP Co.,Ltd.

Patentee after: Taiyuan Zhiyi Wind Energy Technology Co.,Ltd.

Address before: 030032 No.8 Xinhua Road, Taiyuan Economic and Technological Development Zone, Shanxi Province

Patentee before: SHANXI INDUSTRIAL EQUIPMENT INSTALLATION GROUP Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 030032 No. 8, Xinhua Road, Tanghuai Industrial Park, Shanxi transformation and comprehensive reform demonstration zone, Taiyuan City, Shanxi Province

Patentee after: Shanxi Installation Group Co.,Ltd.

Patentee after: Taiyuan Zhiyi Wind Energy Technology Co.,Ltd.

Address before: 030032 8 Xinhua Road, Taiyuan economic and Technological Development Zone, Xiaodian District, Taiyuan, Shanxi

Patentee before: SHANXI INDUSTRIAL EQUIPMENT INSTALLATION GROUP Co.,Ltd.

Patentee before: Taiyuan Zhiyi Wind Energy Technology Co.,Ltd.