CN209653079U - A kind of hydraulic engineering Accrete clearing device - Google Patents
A kind of hydraulic engineering Accrete clearing device Download PDFInfo
- Publication number
- CN209653079U CN209653079U CN201920290515.8U CN201920290515U CN209653079U CN 209653079 U CN209653079 U CN 209653079U CN 201920290515 U CN201920290515 U CN 201920290515U CN 209653079 U CN209653079 U CN 209653079U
- Authority
- CN
- China
- Prior art keywords
- pipeline
- sleeve
- pulverization process
- rotation axis
- fixedly connected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Crushing And Grinding (AREA)
Abstract
The utility model discloses a kind of hydraulic engineering Accrete clearing devices; including drainage pipeline; pulverization process pipeline is equipped with inside drainage pipeline; several filter hole are uniformly provided on pulverization process pipe side wall; one end of pulverization process pipeline is fixedly connected with first sleeve, and the lateral wall circular array of first sleeve shows the first sliding block, and the first sliding block is slidably connected inside first sliding groove; the other end of pulverization process pipeline is fixedly connected with connector sleeve, is equipped with guard box outside connector sleeve;It is equipped with rotation axis inside pulverization process pipeline, is dredged in rotation axis and is connected to several Disintegrating knifes, the side wall that the other end of rotation axis passes through guard box reaches output end that is external and being fixedly connected with motor.Disintegrating knife in the utility model in rotation axis carries out pulverization to filter residue, until being crushed to can be discharged by filter hole, and then convenient for being concentrated by drainage hole, the filter residue small volume after crushing, a possibility that blocking drainage hole is extremely low, improves the efficiency of dredging work.
Description
Technical field
The utility model relates to hydrotechnics field more particularly to a kind of hydraulic engineering Accrete clearing devices.
Background technique
Hydraulic engineering be in order to control, the water resources and environment of utilization and protection earth's surface and underground and every engineering for building
The general name of construction.For controlling and deploying the surface water and groundwater of nature, reach the engineering removing the evil emerging sharp purpose and building.
Also referred to as Hydraulic Projects.Water is human being's production and essential precious resources of living, but the state of its naturally occurring is not fully
Meet the needs of the mankind.Only build hydraulic engineering, just can control water flow, prevent flood, and carry out water adjusting and
Distribution, to meet people's lives and production to the needs of water resource.
Traditional hydraulic engineering Accrete clearing device, most of is all very simple Accrete clearing device, can not be well to production
Raw product, which is become silted up, is cleared up, and cannot be guaranteed underwater cleaning, has also been brought not while reducing eco-environmental quality
Benefit can not stir product silt before dredging so that Accrete clearing device does not have good dredging function, cannot facilitate dredging
The desilting efficiency data of the device greatly reduces in the dredging of device, so that the device does not have agitation function well, greatly
Reduce the utilizing status of product silt;Simultaneously existing Accrete clearing device can not to the bacterial treatment in mud and dredging pipeline, into
One step reduces dredging effect.A kind of hydraulic engineering Accrete clearing device is proposed thus.
Utility model content
The utility model proposes a kind of hydraulic engineering Accrete clearing device, to solve the above problems.
To achieve the goals above, the utility model adopts the technical scheme that
A kind of hydraulic engineering Accrete clearing device, including drainage pipeline are designed, is equipped with pulverization process inside the drainage pipeline
Pipeline is uniformly provided with several filter hole on the pulverization process pipe side wall, and one end of the pulverization process pipeline is fixed to be connected
It is connected to first sleeve, the lateral wall circular array of the first sleeve shows several first sliding blocks, and first sliding block is slidably connected
Inside the first sliding groove opened up on the drainage pipeline inner sidewall, the other end of the pulverization process pipeline is fixedly connected with
Connector sleeve, the connector sleeve outside are equipped with guard box, and the guard box is fixedly connected on one end of the drainage pipeline;
It is equipped with rotation axis inside the pulverization process pipeline, is dredged in the rotation axis and is connected to several Disintegrating knifes, described turn
One end of moving axis is fixedly connected with multiple second sliding blocks, and multiple second sliding blocks are slidably connected at the first sleeve inner sidewall
On in the second sliding slot that is opened up, the side wall that the other end of the rotation axis passes through the guard box reaches external and fixed
It is connected with the output end of motor, the motor is fixedly connected on the lateral wall of the guard box by several fixed brackets.
Preferably, 2, the connector sleeve is fixedly connected with second sleeve far from one end of the pulverization process pipeline, described
Second sleeve is located inside the guard box, and circular array shows several teeth, the teeth engagement on the connector sleeve inner sidewall
Multiple driven gears are connected with, multiple driven gear engagements are connected with the same driving gear, and the driving gear is fixedly attached
In the rotation axis.
Preferably, fixing sleeve is connected to fixed link to multiple driven gears respectively, and the fixed link is rotatably connected on described
On the inner roof wall of guard box.
Preferably, the quantity of the driven gear is 3-8, and multiple driven gears are annular array distribution.
Preferably, the diameter of the driving gear is less than or equal to the diameter of the driven gear, and the driven gear
Diameter be the second sleeve diameter 1/10-1/3.
Preferably, auger, the auger edge and the draining are fixedly installed on the pulverization process pipeline lateral wall
Insides of pipes wall is inconsistent.
Preferably, several drainage holes are offered on the drainage pipeline, and on each described drainage hole respectively
It is equipped with sealing cover.
The utility model proposes a kind of hydraulic engineering Accrete clearing device, beneficial effect is:
1. water flow is flowed into the pulverization process pipeline being arranged inside drainage pipeline by first sleeve, water passes through pulverization process
Filter hole stream on pipeline flows out concentration outflow on drainage pipeline and through drainage hole, prevents water flow from flowing to simultaneously with waste residue
Drainage hole causes to block pipeline, can not carry out normal dredging work;
2. the filter residue in water flow stays in inside pulverization process pipeline, motor drives rotation axis rotation, the crushing in rotation axis
Blade carries out pulverization to filter residue, until being crushed to can be discharged by filter hole, and then convenient for being concentrated by drainage hole,
A possibility that filter residue small volume after crushing, blocking drainage hole, is extremely low, improves the efficiency of dredging work;
3. motor drives rotation axis rotation, and then drives driving gear rotation, driving gear engages driven gear and then band
Dynamic pulverization process pipeline rotation, the auger of pulverization process pipeline external are stirred the deposit inside drainage pipeline, are allowed to
It is moved to drainage hole and concentrates discharge, auger can be stirred the deposit inside drainage pipeline and be allowed to mobile, further
The movement for improving the efficiency and water flow of dredging work ensure that deposit is less inside drainage pipeline, further avoids stifled
A possibility that plug.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the Section A-A structural schematic diagram of the utility model.
Fig. 3 is the section B-B structural schematic diagram of the utility model.
Fig. 4 is the pulverization process pipeline schematic perspective view of the utility model.
In figure: drainage pipeline, pulverization process pipeline, first sleeve, the first sliding block, connector sleeve, guard box, motor, rotation
Axis, auger, teeth 10, driving gear 11, driven gear 12, fixed link 13, Disintegrating knife 14, the second sliding block 15, first sliding groove
16, second sliding slot 17, second sleeve 18.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.
Referring to Fig.1-4, a kind of hydraulic engineering Accrete clearing device, including drainage pipeline 1 are equipped with inside drainage pipeline 1 and crush
Pipeline 2 is handled, is uniformly provided with several filter hole on 2 side wall of pulverization process pipeline, one end of pulverization process pipeline 2 is fixedly connected
There is first sleeve 3, the lateral wall circular array of first sleeve 3 shows several first sliding blocks 4, and the first sliding block 4 is slidably connected at draining
Inside the first sliding groove 16 opened up on 1 inner sidewall of pipeline, the other end of pulverization process pipeline 2 is fixedly connected with connector sleeve 5, even
Guard box 6 is equipped with outside female connector 5, guard box 6 is fixedly connected on one end of drainage pipeline 1;
It is equipped with rotation axis 8 inside pulverization process pipeline 2, is dredged in rotation axis 8 and is connected to several Disintegrating knifes 14, rotation axis 8
One end is fixedly connected with multiple second sliding blocks 15, and multiple second sliding blocks 15 are slidably connected on 3 inner sidewall of first sleeve and are opened up
Second sliding slot 17 in, the side wall that the other end of rotation axis 8 passes through guard box 6 reaches external and is fixedly connected with motor 7
Output end, motor 7 is fixedly connected on the lateral wall of guard box 6 by several fixed brackets;
Several drainage holes are offered on drainage pipeline 1, and matching is equipped with sealing cover respectively on each drainage hole.
Water flow is flowed into the pulverization process pipeline 2 being arranged inside drainage pipeline 1 by first sleeve 3, and water passes through at crushing
The filter hole stream on pipeline 2 is managed on drainage pipeline 1 and is flowed out by drainage hole and concentrates outflow, prevents water flow and waste residue simultaneously
Flowing to drainage hole causes to block pipeline, can not carry out normal dredging work.
Filter residue in water flow stays in inside pulverization process pipeline 2, and motor 7 drives rotation axis 8 to rotate, the powder in rotation axis 8
Broken blade 14 carries out pulverization to filter residue, can be by filter hole until being crushed to, and then is convenient for passing through drainage hole concentration
A possibility that discharge, the filter residue small volume after crushing, blocking drainage hole, is extremely low, improves the efficiency of dredging work.
Connector sleeve 5 is fixedly connected with second sleeve 18 far from one end of pulverization process pipeline 2, and second sleeve 18 is located at protection
Inside case 6, circular array shows several teeth 10 on 5 inner sidewall of connector sleeve, and the engagement of teeth 10 is connected with 6 driven gears 12,6
Driven gear 12 is annular array distribution, and 6 engagements of driven gear 12 are connected with the same driving gear 11, and driving gear 11 is solid
Surely it is socketed in rotation axis 8, fixing sleeve is connected to fixed link 13 to multiple driven gears 12 respectively, and fixed link 13 is rotatably connected on protection
On the inner roof wall of case 6.
During carrying out dredging work, pulverization process pipeline 2 is also being rotated, and makes the filter inside pulverization process pipeline 2
Slag can be crushed in all directions, and crush efficiency is higher, crushing effect is more preferable.
The diameter of driving gear 11 is equal to the diameter of driven gear 12, and the diameter of driven gear 12 is second sleeve 18
The 1/10 of diameter.
Auger 9 is fixedly installed on 2 lateral wall of pulverization process pipeline, 9 edge of auger offsets with 1 inner sidewall of drainage pipeline
Touching.Auger 9 can be stirred the deposit inside drainage pipeline 1, be allowed to mobile, further increase the effect of dredging work
Rate.
To sum up water flow is flowed into the pulverization process pipeline 2 being arranged inside drainage pipeline 1 by first sleeve 3, and water passes through powder
Filter hole stream on broken processing pipeline 2 flows out concentration outflow on drainage pipeline 1 and through drainage hole;
Filter residue in water flow stays in inside pulverization process pipeline 2, and motor 7 connects external power supply, starts to work, and drives rotation
Axis 8 rotates, and the Disintegrating knife 14 in rotation axis 8 carries out pulverization to filter residue, until being crushed to can be by filter hole, in turn
It is discharged convenient for being concentrated by drainage hole;
Motor 7 drives rotation axis 8 to rotate, and then driving gear 11 is driven to rotate, and driving gear 11 engages driven gear 12
And then pulverization process pipeline 2 is driven to rotate, the auger 9 outside pulverization process pipeline 2 carries out the deposit inside drainage pipeline 1
Stirring is allowed to be moved to drainage hole concentration discharge.
In the description of the present invention, it should be understood that term " coaxial ", " bottom ", " one end ", " top ", " in
The orientation of the instructions such as portion ", " other end ", "upper", " side ", " top ", "inner", " front ", " center ", " both ends " or position are closed
System is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of describing the present invention and simplifying the description, rather than
The device or element of indication or suggestion meaning must have a particular orientation, be constructed and operated in a specific orientation, therefore cannot
It is construed as a limitation of the present invention.
In addition, term " first ", " second ", " third ", " the 4th " are used for description purposes only, and should not be understood as instruction or
It implies relative importance or implicitly indicates the quantity of indicated technical characteristic, define " first ", " second ", " the as a result,
Three ", the feature of " the 4th " can explicitly or implicitly include at least one of the features.
In the present invention unless specifically defined or limited otherwise, term " installation ", " setting ", " connection ", " Gu
Calmly ", the terms such as " being screwed on " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;
It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, can also indirectly connected through an intermediary, it can be with
It is the interaction relationship of the connection or two elements inside two elements, unless otherwise restricted clearly, for this field
For those of ordinary skill, the concrete meaning of above-mentioned term in the present invention can be understood as the case may be.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (7)
1. a kind of hydraulic engineering Accrete clearing device, it is characterised in that: including drainage pipeline (1), set inside the drainage pipeline (1)
Have pulverization process pipeline (2), is uniformly provided with several filter hole, the pulverization process on pulverization process pipeline (2) side wall
One end of pipeline (2) is fixedly connected with first sleeve (3), and the lateral wall circular array of the first sleeve (3) shows several first
Sliding block (4), first sliding block (4) are slidably connected at the first sliding groove (16) opened up on the drainage pipeline (1) inner sidewall
The other end of inside, the pulverization process pipeline (2) is fixedly connected with connector sleeve (5), and protection is equipped with outside the connector sleeve (5)
Case (6), the guard box (6) are fixedly connected on one end of the drainage pipeline (1);
Rotation axis (8) are equipped with inside the pulverization process pipeline (2), is dredged on the rotation axis (8) and is connected to several Disintegrating knifes
(14), one end of the rotation axis (8) is fixedly connected with multiple second sliding blocks (15), and multiple second sliding block (15) slidings connect
It connects in the second sliding slot (17) opened up on the first sleeve (3) inner sidewall, the other end of the rotation axis (8) passes through institute
The side wall for stating guard box (6) reaches output end that is external and being fixedly connected with motor (7), and the motor (7) passes through several
Fixed bracket is fixedly connected on the lateral wall of the guard box (6).
2. a kind of hydraulic engineering Accrete clearing device according to claim 1, it is characterised in that: the connector sleeve (5) is separate
One end of the pulverization process pipeline (2) is fixedly connected with second sleeve (18), and the second sleeve (18) is located at the protection
Case (6) is internal, and circular array is shown several teeth (10) on connector sleeve (5) inner sidewall, and teeth (10) engagement is connected with
Multiple driven gears (12), multiple driven gear (12) engagements are connected with the same driving gear (11), the driving gear
(11) it is fixedly attached on the rotation axis (8).
3. a kind of hydraulic engineering Accrete clearing device according to claim 2, it is characterised in that: multiple driven gears
(12) fixing sleeve is connected to fixed link (13) respectively, and the fixed link (13) is rotatably connected on the inner roof wall of the guard box (6).
4. a kind of hydraulic engineering Accrete clearing device according to claim 2, it is characterised in that: the driven gear (12)
Quantity is 3-8, and multiple driven gears (12) are annular array distribution.
5. a kind of hydraulic engineering Accrete clearing device according to claim 2, it is characterised in that: the driving gear (11)
Diameter is less than or equal to the diameter of the driven gear (12), and the diameter of the driven gear (12) is the second sleeve
(18) 1/10-1/3 of diameter.
6. a kind of hydraulic engineering Accrete clearing device according to claim 1, it is characterised in that: the pulverization process pipeline
(2) it is fixedly installed on lateral wall auger (9), auger (9) edge and the drainage pipeline (1) inner sidewall are inconsistent.
7. a kind of hydraulic engineering Accrete clearing device according to claim 1, it is characterised in that: on the drainage pipeline (1)
Several drainage holes are offered, and matching is equipped with sealing cover respectively on each described drainage hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920290515.8U CN209653079U (en) | 2019-03-08 | 2019-03-08 | A kind of hydraulic engineering Accrete clearing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920290515.8U CN209653079U (en) | 2019-03-08 | 2019-03-08 | A kind of hydraulic engineering Accrete clearing device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209653079U true CN209653079U (en) | 2019-11-19 |
Family
ID=68526235
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920290515.8U Expired - Fee Related CN209653079U (en) | 2019-03-08 | 2019-03-08 | A kind of hydraulic engineering Accrete clearing device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209653079U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113175049A (en) * | 2021-05-08 | 2021-07-27 | 湖南人文科技学院 | Drainage system design structure of landscape garden |
-
2019
- 2019-03-08 CN CN201920290515.8U patent/CN209653079U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113175049A (en) * | 2021-05-08 | 2021-07-27 | 湖南人文科技学院 | Drainage system design structure of landscape garden |
CN113175049B (en) * | 2021-05-08 | 2022-07-08 | 湖南人文科技学院 | Drainage system design structure of landscape garden |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111501986B (en) | Pipeline desilting equipment for sewage treatment | |
CN211057964U (en) | High-efficient sewage pipes that hydraulic engineering used | |
CN112554311B (en) | Sponge urban road drainage structures | |
CN213452362U (en) | Drainage pipeline for preventing and treating water in coal mine | |
CN209653079U (en) | A kind of hydraulic engineering Accrete clearing device | |
CN110104927A (en) | A kind of river sludge multistage recycling and processing device | |
CN110241910A (en) | A kind of well lid of the lower well of municipal administration | |
CN212103661U (en) | Bridge drainage system | |
CN209323675U (en) | One kind having the integrated prefabricated pumping plant of automatically cleaning | |
CN209603242U (en) | A kind of municipal drainage pipeline cleaning equipment | |
CN209636938U (en) | A kind of novel intelligent automatic control pollution cutting device | |
CN109518749A (en) | A kind of water conservancy may filter that muddy water removes mud equipment | |
CN213014428U (en) | A river course ecological remediation sediment removal device for hydraulic engineering | |
CN215053386U (en) | Dredging dredging device for hydraulic construction engineering | |
CN116159852A (en) | Heavy metal restoration and collection equipment | |
CN108842847A (en) | The quick desilting equipment of water conservancy construction | |
CN108911381A (en) | Rainwater purification apparatus | |
CN108031152A (en) | A kind of novel flocculation device | |
CN208965618U (en) | It is a kind of for removing the irrigating apparatus of riverway sludge | |
CN208633830U (en) | A kind of rock push-bench hopper dredger slag cleaning device | |
CN210066620U (en) | Hydraulic pipeline for hydraulic engineering | |
CN207405754U (en) | A kind of municipal pipeline Accrete clearing device | |
CN211688327U (en) | High efficiency sewage treatment stirring pond | |
CN216075425U (en) | Municipal works drainage pipe prevents blockking up structure | |
CN213141441U (en) | Crushing type grid with rotary drum clearance window |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191119 Termination date: 20210308 |
|