CN209627058U - A kind of data collection system for communication system of power grids scheduling - Google Patents

A kind of data collection system for communication system of power grids scheduling Download PDF

Info

Publication number
CN209627058U
CN209627058U CN201920308065.0U CN201920308065U CN209627058U CN 209627058 U CN209627058 U CN 209627058U CN 201920308065 U CN201920308065 U CN 201920308065U CN 209627058 U CN209627058 U CN 209627058U
Authority
CN
China
Prior art keywords
interchanger
router
data collection
module
acquisition server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920308065.0U
Other languages
Chinese (zh)
Inventor
陈永涛
衷宇清
崔兆阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangzhou Power Supply Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Power Supply Bureau Co Ltd filed Critical Guangzhou Power Supply Bureau Co Ltd
Priority to CN201920308065.0U priority Critical patent/CN209627058U/en
Application granted granted Critical
Publication of CN209627058U publication Critical patent/CN209627058U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of data collection systems for communication system of power grids scheduling, including dispatching terminal router, interchanger and acquisition server, interchanger is communicated to connect with dispatching terminal router, acquisition server respectively, acquisition server communicates to connect control centre, dispatching terminal router is used to the scheduling data of each substation being uploaded to acquisition server by interchanger, and dispatching terminal router includes redundant power;Interchanger is redundance type interchanger, and interchanger includes the first exchange snap-gauge and the second exchange snap-gauge, and the first exchange board and the second power board card are interconnected by stacking opening and constitute redundancy backup link.A kind of data collection system for communication system of power grids scheduling of the utility model, interchanger uses redundance type interchanger, redundancy backup link is constituted by the first exchange board therein and the second exchange board stacking opening interconnection, so that data transmission has more reliability, stability.

Description

A kind of data collection system for communication system of power grids scheduling
Technical field
The utility model relates to dispatching of power netwoks fields more particularly to a kind of data for communication system of power grids scheduling to acquire system System.
Background technique
Dispatching of power netwoks is to guarantee power network safety operation, external reliable power supply, guarantee all kinds of power generation work A kind of effective management means for orderly carrying out and using.The specific works content of power scheduling is set according to various information acquisition The information that the standby data information fed back or monitoring personnel provide, in conjunction with power grid actual operation parameters, such as voltage, circuit, frequency Rate, load etc. comprehensively consider every production work development condition, judge power grid security, economical operation state, pass through electricity Words or automatic system issue operational order, and commander site operation personnel or automatic control system are adjusted, and such as adjust generator Power output, Load adjustment distribution, switched capacitor, reactor etc., so that it is guaranteed that power grid continues safe and stable operation.
During operation of power networks, usually pass through alarm, configuration, performance data of the Data Acquisition and Communication System to each substation Received and be uploaded to grid dispatching center, grid dispatching center according to the data being collected into, coordinated, organized, being commanded, Power grid related work is instructed, to ensure the safe operation of power supply.In grid operation, traditional electric power dispatching exchange network network The network structure of only one switching node, this form is weak, does not form network routing detour protection, poor reliability.With The fast development of power grid construction, substation, concentrator station etc. dispatching of power netwoks is communicated and proposes requirements at the higher level, need more reliable, more Stable data transmission network, to ensure the stability of dispatching of power netwoks data acquisition.
Utility model content
For overcome the deficiencies in the prior art, the purpose of this utility model is to provide it is a kind of for the communication system of power grids scheduling Data collection system is capable of providing the data transmission link of redundancy, it is ensured that the stability of dispatching of power netwoks data acquisition.
The purpose of this utility model adopts the following technical scheme that realization:
A kind of data collection system for communication system of power grids scheduling, including dispatching terminal router, interchanger and acquisition service Device, the interchanger are communicated to connect with the dispatching terminal router, the acquisition server respectively, the acquisition server communication Control centre is connected, the dispatching terminal router is used to the scheduling data of each substation being uploaded to described adopt by the interchanger Collect server, the dispatching terminal router includes redundant power;The interchanger is redundance type interchanger, the interchanger packet It includes the first exchange snap-gauge and the second exchange snap-gauge, the first exchange board and the second power board card is interconnected by stacking opening Constitute redundancy backup link.
Further, the first exchange board, the second exchange board include redundancy processing module, PHY module With MAC Switching Module;The MAC Switching Module is equipped with the communication interface for access network based on ethernet;The PHY module with it is described The connection of MAC Switching Module;CPU and the stacking opening are integrated in the MAC Switching Module.
Further, the dispatching terminal router includes access-layer router, convergence layer router and core layer router, The access-layer router receives the scheduling data of each substation and is uploaded to the convergence layer router of corresponding subregion, each The convergence layer router of subregion will dispatch data and be uploaded to the core layer router, the core layer router with it is described Switch communication connection.
Further, the dispatching terminal router is also communicated to connect with the weather monitoring module for being installed on each substation.
Further, the weather monitoring module includes temperature sensor, humidity sensor and air velocity transducer.
Further, the acquisition server includes one of 2G, 3G, 4G module or a variety of.
Further, the acquisition server further includes network interface and USB interface.
Further, the acquisition server is additionally provided with sound and light alarm module, and the sound and light alarm module is used for even Failure is connect to alarm.
Compared with prior art, the utility model has the beneficial effects that:
A kind of data collection system for communication system of power grids scheduling of the utility model, is collected each by dispatching terminal router The scheduling data of each substation are uploaded to acquisition server by interchanger by the scheduling data of a substation, dispatching terminal router, into And realize the acquisition of scheduling data, convenient for being scheduled to operation of power networks;Interchanger uses redundance type interchanger, by therein First exchange board and second exchange board stacking opening interconnection constitute redundancy backup link so that data transmission have more reliability, Stability.
Detailed description of the invention
Fig. 1 is a kind of each module connection diagram of data collection system for communication system of power grids scheduling of embodiment;
Fig. 2 is each module connection diagram of Fig. 1 interchanger;
Fig. 3 is each module connection diagram of Fig. 1 acquisition server;
Fig. 4 is Fig. 1 acquisition server communication interface schematic diagram;
Fig. 5 is weather monitoring module diagram in embodiment.
Specific embodiment
In the following, being described further in conjunction with attached drawing and specific embodiment to the utility model, it should be noted that Under the premise of not colliding, it can be formed in any combination between various embodiments described below or between each technical characteristic new Embodiment.
A kind of data collection system for communication system of power grids scheduling is present embodiments provided, as shown in Figure 1, including dispatching terminal Router, interchanger and acquisition server, interchanger are communicated to connect with dispatching terminal router, acquisition server respectively, acquisition clothes Be engaged in device communication connection control centre, and dispatching terminal router is used to the scheduling data of each substation being uploaded to acquisition clothes by interchanger Business device, dispatching terminal router includes redundant power;As shown in Fig. 2, interchanger is redundance type interchanger, interchanger includes first Snap-gauge and the second exchange snap-gauge are exchanged, the first exchange board and the second power board card are interconnected by stacking opening and constitute redundancy backup chain Road.Dispatching terminal router is also communicated to connect with the weather monitoring module for being installed on each substation.
The data collection system of this implementation, it is intended to while realizing scheduling data acquisition, by redundance type interchanger, so that Data transmission has more reliability, stability.Wherein, redundance type interchanger, including cabinet, power supply and exchange board, power supply and friendship It changes board to be arranged in cabinet, power supply is redundant power, including the first power supply and second source;Exchanging board is 2 pieces, i.e., the One exchange board and the second exchange board;Referring to Fig. 2, any exchange board includes that redundancy processing module, PHY module and MAC are handed over Change the mold block;MAC Switching Module is equipped with the communication interface for access network based on ethernet;PHY module is connect with MAC Switching Module;MAC CPU and stacking opening are integrated in Switching Module;First exchange board and the second power board card pass through the stacking opening interconnection structure At redundancy backup link.First exchange board and the second power board card stack are placed in cabinet inside, after power supply is arranged in cabinet End.The hardware composition of single set exchange board by power supply redundancy processing module, the MAC Switching Module of integrated processor, physical layer with Too net phy interface module etc. forms.The MAC Switching Module of integrated processor is by being integrated with the MAC exchange chip group of processor At mainly realizing system configuration, system administration, resource tune wherein integrated processor is the Operation Centre of whole system software With functions such as, Operation and Maintenance;Integrated MAC mainly includes the exchange of ethernet mac layer and Ethernet physical interface part, is embedded with High-speed switching logic unit realizes the data exchange between Fast Ethernet or Gigabit Ethernet Fabric Interface, to realize line Fast forwarding capability, and communication bus is provided, realize intelligent control function.Physical layer ethernet PHY interface module mainly completes number According to coding/decoding, string-and convert, signal driving etc. work, support speed auto-negotiation function.Redundant power exports two groups of 12VDC Voltage, while being the first exchange board and the second exchange board power supply, when one group of power supply breaks down, can be by redundancy at Reason module rapidly changes to second group of power supply.Redundant power is made of two blocks of power supplys, makes the two mutually by redundancy processing module For backup;Redundancy exchange board is made of two pieces of exchange boards, and every piece exchanges board by the exchange chip and PHY of integrated processor Chip (PHY, that is, physical layer) is constituted, and two pieces of power board cards are connected by the stacking opening that exchange chip integrates, and constitutes redundancy backup chain Road;Redundancy Software system is built upon on Labcard driver, for controlling the agreement and application software of managing redundant power board.It is superfluous Remaining processing module is existing mature technology, is seldom repeated here.Two pieces of power board cards are spliced by the heap that MAC Switching Module provides Mouth is interconnected, and since stacking opening supports multilink, ought wherein a link be broken down, in addition link can still carry out Data transmission.After two pieces of power board cards are interconnected by stacking opening simultaneously, link redundancy algorithm can be realized by stacking opening, so that two Block power board is externally being run just as an interchanger, after connecting at this time with the terminal of double netcard, even if there is one piece of exchange board Failure, the terminal still can pass through another piece of exchange board and external progress data communication.MAC chip, 100,000,000/gigabit physics Layer chip all uses Broadcom company related chip;It is attached between MAC and PHY chip by relevant interface, and to this A little chips are configured.Two-way DC voltage is exported after the transformed processing of DC power supply into redundancy processing circuit, by redundancy The DC voltage that single channel is exported after control processing is sent to respectively on two pieces of exchange boards, to power to whole system.
In addition, in Fig. 1, dispatching terminal router includes access-layer router, convergence layer router and core layer router, Dispatch data net I phase network core routers, convergence layer router use cisco7609 router, configure with double engines, redundant electric Source has OC3, e1 port, Ethernet 1000M exchange mouth;Access layer node router uses cisco7604 router, configuration Redundant power, single engine had 2 with last e1 port, and 6 or more Ethernet 100M exchange mouth.Core layer node presses active/standby devices Configuration, convergence layer, access node layer are configured by single device, and service access node is configured with cisco35 series of switch simultaneously.It adjusts Data network II phase network core routers, convergence layer router are spent using SR8805 router, configure with double engines, redundant power, Have OC3, e1 port, Ethernet 1000M exchange mouth;Access-layer router node uses 5040 router of H3CMSR, configures superfluous Remaining power supply, single engine, have 2 or more e1 ports, and 6 or more Ethernet 100M exchange mouth.Core layer node is matched by active/standby devices It sets;Convergence layer, access node layer are configured by single device, are had the service access node of independent communication computer room while being configured with H3C S3600 interchanger.Acquisition server obtains alarm, configuration, the performance of upload etc. at the station 110KV and the station 220KV by interchanger These scheduling data received are uploaded to control centre, run for dispatching of power netwoks by data, acquisition server.Dispatching terminal road By the equal configuring redundancy power supply of device, redundant power realizes the high availability of router, when a power supply breaks down, another electricity Source can take over its work at once, after replacing power supply, and be that two power supplys cooperate.In addition, in order to which control centre is real-time Get the weather monitoring situation of each substation, convenient for power network dispatching system occur bad weather it is arduous when, make phase in time The power scheduling running answered, unnecessary loss caused by avoiding because of bad weather.For this purpose, being existed by dispatching terminal router and setting The weather monitoring module of each substation communicates to connect, and weather monitoring module obtains the weather monitoring number of corresponding power transformation station location According to being uploaded to acquisition server by dispatching terminal router, weather data is uploaded in scheduling by acquisition server in real time The heart realizes the acquisition of weather data with this, further realizes the monitoring and dispatching processing to inclement weather conditions.In addition, In Security system is provided between dispatching terminal router and interchanger, security system is for the security isolation inside power grid, to protect Intranet is protected from the intrusion of illegal user, ensures the safety that data upload.
Specifically, as shown in figure 4, weather monitoring module includes temperature sensor, humidity sensor, air velocity transducer, temperature Degree sensor, humidity sensor, air velocity transducer output end connect respectively with dispatching terminal router communication.Pass through temperature sensing Device, humidity sensor and air velocity transducer are able to detect the weather such as temperature, humidity and the wind speed of each substation's corresponding position letter Breath, to provide meteorological basic data information for power grid bad weather Risk Scheduling.By meteorological basic data information, convenient for adjusting Degree center carries out corresponding coping style for inclement weather conditions.
In addition, passing through 2G/3G/4G as shown in Fig. 2, acquisition server includes one of 2G, 3G, 4G module or a variety of Module is uploaded to control centre for net basic data is dispatched.In addition, for the ease of dispatching the reception of data, acquisition server is also wrapped Network interface and USB interface are included, by network interface or USB interface, can also receive scheduling data.As shown in figure 3, acquisition server passes through Multiple communication interfaces are set, convenient for transmitting collected scheduling data to multiple and different equipment.It on the other hand, as shown in Fig. 2, should Acquisition server further includes sound and light alarm module, and sound and light alarm module is connected with CPU.Sound and light alarm module specifically may include shape State indicator light and buzzer siren.When acquisition server is received or is uploaded, status indicator lamp is lighted;Or connect Connect the flashing of the failure states indicator lights such as failure, upper electric fault.Likewise, buzzer siren can terminate in data processing or Buzzing alarm is issued when failure.Sound and light alarm module carries out acousto-optic report using ULN2003 driving circuit buzzer and LED light It is alert.Connecting fault detection, data transmission are detected as the prior art, seldom repeat here.
A kind of data collection system for communication system of power grids scheduling of the present embodiment, is collected each by dispatching terminal router The scheduling data of each substation are uploaded to acquisition server by interchanger by the scheduling data of substation, dispatching terminal router, in turn The acquisition of scheduling data is realized, convenient for being scheduled to operation of power networks;Interchanger uses redundance type interchanger, passes through therein the One exchange board and the second exchange board stacking opening interconnection constitute redundancy backup link, so that data transmission has more reliability, steady It is qualitative.
Above embodiment is only preferred embodiments of the present invention, cannot be protected with this to limit the utility model Range, the variation of any unsubstantiality that those skilled in the art is done on the basis of the utility model and replacement belong to In the utility model range claimed.

Claims (8)

1. it is a kind of for the communication system of power grids scheduling data collection system, it is characterised in that: including dispatching terminal router, interchanger and Acquisition server, the interchanger are communicated to connect with the dispatching terminal router, the acquisition server respectively, the acquisition clothes Be engaged in device communication connection control centre, and the dispatching terminal router is for uploading the scheduling data of each substation by the interchanger To the acquisition server, the dispatching terminal router includes redundant power;The interchanger is redundance type interchanger, described Interchanger includes that the first exchange snap-gauge and the second exchange snap-gauge, the first exchange board and the second power board card pass through heap Folded mouth interconnection constitutes redundancy backup link.
2. data collection system as described in claim 1, it is characterised in that: the first exchange board, second exchange Board includes redundancy processing module, PHY module and MAC Switching Module;The MAC Switching Module is equipped with for accessing ether The communication interface of net;The PHY module is connect with the MAC Switching Module;CPU and institute are integrated in the MAC Switching Module State stacking opening.
3. data collection system as described in claim 1, it is characterised in that: the dispatching terminal router includes access layer routing Device, convergence layer router and core layer router, the access-layer router receive the scheduling data of each substation and are uploaded to The convergence layer router of corresponding subregion, the convergence layer router of each subregion are uploaded to the core for data are dispatched Layer router, the core layer router are connect with the switch communication.
4. data collection system as described in claim 1, it is characterised in that: the dispatching terminal router also be installed on it is each The weather monitoring module of substation communicates to connect.
5. data collection system as claimed in claim 4, it is characterised in that: the weather monitoring module includes temperature sensing Device, humidity sensor and air velocity transducer.
6. data collection system as described in claim 1, it is characterised in that: the acquisition server includes 2G, 3G, 4G module One of or it is a variety of.
7. data collection system as claimed in claim 6, it is characterised in that: the acquisition server further includes network interface and USB Interface.
8. data collection system as described in claim 1, it is characterised in that: the acquisition server is additionally provided with sound-light alarm Module, the sound and light alarm module is for alarming to connecting fault.
CN201920308065.0U 2019-03-12 2019-03-12 A kind of data collection system for communication system of power grids scheduling Active CN209627058U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920308065.0U CN209627058U (en) 2019-03-12 2019-03-12 A kind of data collection system for communication system of power grids scheduling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920308065.0U CN209627058U (en) 2019-03-12 2019-03-12 A kind of data collection system for communication system of power grids scheduling

Publications (1)

Publication Number Publication Date
CN209627058U true CN209627058U (en) 2019-11-12

Family

ID=68456447

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920308065.0U Active CN209627058U (en) 2019-03-12 2019-03-12 A kind of data collection system for communication system of power grids scheduling

Country Status (1)

Country Link
CN (1) CN209627058U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111740927A (en) * 2020-07-20 2020-10-02 湖南航天捷诚电子装备有限责任公司 Redundant switch

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111740927A (en) * 2020-07-20 2020-10-02 湖南航天捷诚电子装备有限责任公司 Redundant switch

Similar Documents

Publication Publication Date Title
CN104682214B (en) Intelligent power supply control box
CN211296946U (en) Railway electric power comprehensive operation and maintenance management system
CN204557187U (en) A kind of IP network environmental monitoring system
CN105790990A (en) Method and system for monitoring and managing power distribution and utilization communication business
CN209402534U (en) A kind of communication equipment and communication system
CN112073224A (en) Intelligent substation interval electrical equipment measurement and control system and method
CN209627058U (en) A kind of data collection system for communication system of power grids scheduling
CN201820111U (en) Environmental monitoring device of outdoor telecommunication equipment cabinet
CN204669086U (en) Communication power supply monitoring data collection device and system thereof
CN207652390U (en) Expressway photovoltaic power station intelligent management monitor supervision platform
CN207652463U (en) A kind of equipment centralized control system
CN206559397U (en) Communications equipment room power and environment centralized supervision system
CN107942963A (en) A kind of electric power operational system based on coordinated signals and cloud platform
CN209088970U (en) A kind of novel Optical Channel Protection system based on OASS
CN207612365U (en) Unattended field overhead line video monitoring apparatus
CN207676470U (en) Building safety defense monitoring system based on TCP/IP
CN110531145A (en) A kind of intelligent lightening stroke counter having ad hoc network function
CN206991535U (en) Novel intelligent meter reading collecting transmitter
CN202815559U (en) Intelligent power distribution room management system
CN201608563U (en) Electric arc light intelligent remote monitoring system
CN203350710U (en) Intelligent monitoring system of converter station auxiliary equipment
CN208754312U (en) A kind of terminal management apparatus
CN207305004U (en) POE Power over Ethernet illuminates intelligence system
CN206100014U (en) Communication manager device of belt wheel net function
CN217360242U (en) Network and power supply state detection and reporting device based on NB-IoT +5G

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210209

Address after: 510620, No. two, No. 2, Tianhe South Road, Guangzhou, Guangdong, Tianhe District

Patentee after: Guangzhou Power Supply Bureau of Guangdong Power Grid Co.,Ltd.

Address before: 510000 No. 2 Tianhe Second Road, Tianhe District, Guangzhou City, Guangdong Province

Patentee before: GUANGZHOU POWER SUPPLY Co.,Ltd.