CN209603463U - Array fast-assembling inspection platform - Google Patents
Array fast-assembling inspection platform Download PDFInfo
- Publication number
- CN209603463U CN209603463U CN201920035396.1U CN201920035396U CN209603463U CN 209603463 U CN209603463 U CN 209603463U CN 201920035396 U CN201920035396 U CN 201920035396U CN 209603463 U CN209603463 U CN 209603463U
- Authority
- CN
- China
- Prior art keywords
- column
- inspection platform
- springboard
- fence
- layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses array fast-assembling inspection platforms, it includes four columns, and the bottom of four columns is provided with inspection platform pedestal, multiple-layer horizontal cross bar and vertical cross bar are equipped between the column, and constitutes multilevel-cell layer;It is connected between different height elementary layer by ladder;The short transverse of column is provided with middle tier platform and top layer platform used for overhaul.For when equipment is overhauled, a safe and reliable inspection platform is provided for service personnel, guarantee that maintenance task smoothly completes, the inspection platform structure is simple, is self-possessed lighter, it takes and tears open rapidly, transhipment convenience can carry out effective elementary layer assembling according to on-site actual situations, can adapt to different height, different parts, surrounding maintenance requirement, it can also realize that single side is dismountable simultaneously, give way to the equipment movement overhauled.
Description
Technical field
The utility model relates to array fast-assembling inspection platforms, belong to power equipment auxiliary repair device field.
Background technique
In daily service work, a large amount of high-rise working can be touched, wherein for equipment different parts, different height
It is a kind of greatly test, traditional eminence for service personnel when degree and equipment surrounding require the service work carried out
The method that operation mainly uses is: one is setting up steel pipe scaffold, i.e., needed for maintenance is set up with steel pipe in overhaul of the equipments position
Workbench, the process need to expend a large amount of manpower, and the time required for setting up is also very long, and the platform was using
It is inflexible in journey, it is unable to single side and removes give way to the mobile lifting of equipment, it is former with the fast, efficient, safe maintenance pursued at present
It is then inconsistent;Another method is to set up quick-installation scaffold, and for quick-installation scaffold, work surface is too single, Bu Nengjian
The maintenance requirement of different parts is cared for, if the equipment surrounding requires to be overhauled, then quick-installation scaffold is not able to satisfy the operating condition
Construction.Above two platform cannot all take into account the fast, efficient, safe maintenance operating condition that modernization maintenance is pursued.
Utility model content
The utility model aim is to provide array fast-assembling inspection platform, is mainly used for when equipment is overhauled, for inspection
It repairs personnel and one safe and reliable inspection platform is provided, guarantee that maintenance task smoothly completes, the inspection platform structure is simple, from
Weight is lighter, takes and tears open rapidly, transhipment convenience, can carry out effective elementary layer assembling according to on-site actual situations, can adapt to difference
Highly, different parts, surrounding maintenance requirement, while can also realize that single side is dismountable, it gives way to the equipment movement overhauled.
In order to realize above-mentioned technical characteristic, purpose of the utility model is realized as follows: the maintenance of array fast-assembling is flat
Platform, it includes four columns, and the bottom of four columns is provided with inspection platform pedestal, is equipped with multilayer between the column
Horizontal cross bar and vertical cross bar, and constitute multilevel-cell layer;It is connected between different height elementary layer by ladder;Along column
Short transverse is provided with middle tier platform and top layer platform used for overhaul.
The column is process using the production of high-strength aluminum pipe, and the limit pin hole in the upright bar of the column is oriented parallel to
Column diagonal line;The major architectural for constituting inspection platform is placed in more root post superpositions.
It is provided with screw rod height adjustment mechanism on the inspection platform pedestal, and adjusts the height of entire column.
The column, horizontal cross bar and vertical cross bar use horizontal and vertical square shape stable support structure.
It is connected using the bridging being in tilted layout support is intersected between the elementary layer.
Throwing support is fixedly installed on the outside of the column, the throwing support is connect with the outside rod piece of column.
The middle tier platform includes intermediate springboard, telescopic gangway, jump board support frame, 90 ° of skirting board limiting slots and skirt
Plate;The intermediate springboard is mounted on the inside of elementary layer, and 90 ° of skirting board limiting slots are mounted on 90 ° turns of inspection platform fence
Angular position, the skirting board are supported on 90 ° of skirting board limiting slots.
The top layer platform includes intermediate springboard, avris springboard, rectangular springboard, gathers together springboard, gather together jump board support frame, enclose
Column, 90 ° of skirting board limiting slots, 180 ° of skirting board limiting slots and skirting board;The avris springboard is mounted on the outside of elementary layer, institute
It states intermediate springboard to be mounted on the inside of elementary layer, 180 ° of skirting board limiting slots are mounted on the straight line position of inspection platform fence, and will
The interrupted position of column effectively connects, and the rectangular springboard is mounted in column;The center of elementary layer is arranged in the passable springboard
Position is simultaneously supported by gathering together jump board support frame.
The fence includes upright fence post and fence middle standing pillar, is installed between the upright fence post and fence middle standing pillar
There is fence horizon bar.
The throwing support includes strut of drawing money on credit, and the intermediate position of the strut of drawing money on credit is hinged with a section support rod.
The utility model has the advantages that:
1, the inspection platform device structure it is simple, it is easy to operate, improve labor efficiency, it is low in cost;
2, it is overhauled for eminence, it is applied widely and versatile;
3, this patent is reusable, possesses broad application prospect.
Detailed description of the invention
The utility model is described in further detail with reference to the accompanying drawings and examples.
Fig. 1 is the utility model overall structure diagram.
Fig. 2 is the utility model inspection platform understructure figure.
Fig. 3 is the utility model pillar construction schematic diagram.
Fig. 4 is the utility model horizontal cross bar structural schematic diagram.
Fig. 5 is the vertical bar structure schematic diagram of the utility model.
Fig. 6 is the utility model ladder structural schematic diagram.
Fig. 7 is the utility model bridging structural schematic diagram.
Fig. 8 is springboard structural schematic diagram among the utility model.
Fig. 9 is the utility model avris springboard structural schematic diagram.
Figure 10 is that the utility model gathers together springboard structural schematic diagram.
Figure 11 is that the utility model gathers together jump board support frame structural schematic diagram.
Figure 12 is the rectangular springboard structural schematic diagram of the utility model.
Figure 13 is the utility model fence upright bar structural schematic diagram.
Figure 14 is the utility model fence horizontal bar structure schematic diagram.
Figure 15 is the utility model fence middle standing pillar structure schematic diagram.
Figure 16 is that 90 ° of skirting boards of the utility model limit slot structure schematic diagram.
Figure 17 is the utility model skirting structure schematic diagram.
Figure 18 is that 180 ° of skirting boards of the utility model limit slot structure schematic diagram.
Figure 19 is that the utility model throws support structure schematic diagram.
In figure: 1, inspection platform pedestal;2, column;3, horizontal cross bar;4, vertical cross bar;5, ladder;6, bridging;7, in
Between springboard;8, avris springboard;9, springboard is gathered together;10, jump board support frame is gathered together;11, rectangular springboard;12, upright fence post;13, it encloses
Column horizon bar;14, fence middle standing pillar;15,90 ° of skirting board limiting slots;16, skirting board;17,180 ° of skirting board limiting slots;18,
Throw support.
Specific embodiment
The embodiments of the present invention is described further with reference to the accompanying drawing.
Fig. 1-19 is please referred to, array fast-assembling inspection platform, it includes four columns 2, and the bottom of four columns 2 is set
It is equipped with inspection platform pedestal 1, multiple-layer horizontal cross bar 3 and vertical cross bar 4 are installed between the column 2, and constitute multilevel-cell
Layer;It is connected between different height elementary layer by ladder 5;The short transverse of column 2 is provided with middle layer used for overhaul
Platform and top layer platform.
Further, the column 2 is process using the production of high-strength aluminum pipe, the spacer pin in the upright bar of the column 2
Hole is oriented parallel to column diagonal line;The major architectural for constituting inspection platform is placed in more superpositions of root post 2.
Further, it is provided with screw rod height adjustment mechanism on the inspection platform pedestal 1, and adjusts entire column 2
Highly.
Further, the column 2, horizontal cross bar 3 and vertical cross bar 4 stablize support using horizontal and vertical square shape
Structure.
Further, connected using the bridging 6 being in tilted layout support is intersected between the elementary layer.
Further, the outside of the column 2 is fixedly installed with throwing support 18, the outside rod piece for throwing support 18 with column 2
Connection.
Further, the middle tier platform includes intermediate springboard 7, telescopic gangway, jump board support frame, 90 ° of skirting board limits
Position slot 15 and skirting board 16;The intermediate springboard 7 is mounted on the inside of elementary layer, and 90 ° of skirting board limiting slots 15 are mounted on inspection
90 ° of rotation angle positions of platform rail are repaired, the skirting board 16 is supported on 90 ° of skirting board limiting slots 15.
Further, the top layer platform includes intermediate springboard 7, avris springboard 8, rectangular springboard 11, gathers together springboard 9, gathers
Close jump board support frame 10, fence, 90 ° of skirting board limiting slots, 15,180 ° of skirting board limiting slots 17 and skirting board 16;The avris is jumped
Plate 8 is mounted on the outside of elementary layer, and the intermediate springboard 7 is mounted on the inside of elementary layer, and 180 ° of skirting board limiting slots 17 are mounted on
The straight line position of inspection platform fence, and the interrupted position of column is effectively connected, the rectangular springboard 11 is mounted in column;Institute
Passable springboard 9 is stated the centre of elementary layer is arranged in and is supported by gathering together jump board support frame 10.
Further, the fence includes upright fence post 12 and fence middle standing pillar 14, the upright fence post 12 and fence
Fence horizon bar 13 is installed between middle standing pillar 14.
Further, the throwing support 18 includes strut of drawing money on credit, and the intermediate position of the strut of drawing money on credit is hinged with a section support rod.
As shown in Fig. 2, inspection platform pedestal 1, is mainly used for finely tuning the height of inspection platform difference column, compensate because of ground
Injustice causes platform inclination, and for increasing the contact area of platform and ground.
As shown in figure 3, column 2 by high-strength aluminum pipe production be process, the limit pin hole direction in column upright bar should be put down
Row is in column diagonal line, and so as to its versatility, column is between the main bearing member and each unit layer of inspection platform
Main connecting elements;Column is overlapped mutually, and constitutes the major architectural of entire inspection platform.
As shown in figure 4, horizontal cross bar 3 uses " mouth " font connection type, column is connected into an entirety, can effectively be prevented
Stop element layer frame torsional deformation in the horizontal direction, to improve the stability of inspection platform.
As shown in figure 5, vertical cross bar 4, mainly has both sides to act on, first is that column is connected into one in vertical direction
It is whole, the torsional deformation in vertical direction of prevention unit layer frame;Second is that provide support for springboard, vertical cross bar and column
Upper and lower two cross bars are connected, and the load bearing stength of vertical cross bar can be improved.
As shown in fig. 6, ladder 5, provides the channel that walks up and down for service personnel, mainly have landing ladder and intermediate ladder it
Point, landing ladder bottom is provided with mechanical brakeman, and intermediate ladder both ends are connected with column, and the connection lock of ladder is all made of anti-
Trip gear.
As shown in fig. 7, bridging 6, rides upon between column, it is ensured that inspection platform vertical direction is not distorted change
Shape on the column that can ride upon different units layer, improves steady between different units layer in multiple elementary layer anabolic processes
It is fixed.
As shown in figure 8, intermediate springboard 7, is mounted on the inside of elementary layer, can be installed at various height according to maintenance requirement;
It is simultaneously also the current platform of turning back of personnel channel.
As shown in figure 9, avris springboard 8, is mounted on elementary layer column, outside maintenance requirement can be provided to service personnel,
Generally it is chiefly used in top layer upkeep operation platform, openable current hole, side is arranged in the current stair access sites above and below personnel
Person who happens to be on hand for an errand person is current.
As shown in Figure 10, springboard 9 is gathered together, is generally chiefly used in elementary layer centre and needs to provide the work of upkeep operation platform
Condition can reserve enough equipment avoiding spaces according to maintenance requirement, so that selection reasonably gathers together springboard length
As shown in figure 11, jump board support frame 10 is gathered together, provides support to gather together springboard.
As shown in figure 12, rectangular springboard 11 is generally chiefly used in top layer upkeep operation platform, is mounted in column, for maintenance
Personnel provide biggish service area.
As shown in figure 13, fence upright bar 12 is generally chiefly used in top layer upkeep operation platform, is mounted on the inside of column, for inspection
It repairs personnel and biggish service area is provided.
As shown in figure 14, fence horizon bar 13 is mounted in two fence upright bars, provides reliable and secure shield to service personnel
Column, it is ensured that the personal safety of service personnel.
As shown in figure 15, fence middle standing pillar 14 is mounted between fence horizon bar, supports fence horizon bar, consolidates shield
Column.
As shown in figure 16,90 ° of skirting board limiting slots 15 are mounted on 90 ° of rotation angle positions of inspection platform fence, are skirting board
Reliable connection is provided.
As shown in figure 17, skirting board 16 are mounted on inspection platform position, prevent small piece material and work device on inspection platform
Tool, which falls, hurts sb.'s feelings;
As shown in figure 18,180 ° of skirting board limiting slots 17 are mounted on the straight line position of inspection platform fence, column can break
Continuous position effectively connects, it is ensured that the integrality of skirting board;
As shown in figure 19, support 18 is thrown, is connect with rod piece on the outside of column, prevents inspection platform from toppling over, it is ensured that inspection platform
Stability.Above-mentioned connecting portion fastener is both needed to installation trip-proof device.
Above-described embodiment is used to illustrate the utility model, rather than limits the utility model, practical at this
In novel spirit and scope of protection of the claims, to any modifications and changes that the utility model is made, this reality is both fallen within
With novel protection scope.
Claims (10)
1. array fast-assembling inspection platform, it is characterised in that: it includes four columns (2), and the bottom of four columns (2) is set
It is equipped with inspection platform pedestal (1), multiple-layer horizontal cross bar (3) and vertical cross bar (4) is installed between the column (2), and constitute
Multilevel-cell layer;It is connected between different height elementary layer by ladder (5);It is provided with and is used for along the short transverse of column (2)
The middle tier platform and top layer platform of maintenance.
2. array fast-assembling inspection platform according to claim 1, it is characterised in that: the column (2) uses high-strength aluminium
Pipe production is process, and the limit pin hole in the upright bar of the column (2) is oriented parallel to column diagonal line;More root posts (2)
The major architectural for constituting inspection platform is placed in superposition.
3. array fast-assembling inspection platform according to claim 1, it is characterised in that: on the inspection platform pedestal (1)
It is provided with screw rod height adjustment mechanism, and adjusts the height of entire column (2).
4. array fast-assembling inspection platform according to claim 1, it is characterised in that: the column (2), horizontal cross bar
(3) and vertical cross bar (4) uses horizontal and vertical square shape stable support structure.
5. array fast-assembling inspection platform according to claim 1, it is characterised in that: using intersection between the elementary layer
Bridging (6) support of inclination arrangement is connected.
6. array fast-assembling inspection platform according to claim 1, it is characterised in that: the outside of the column (2) is fixed
Throwing support (18) is installed, the throwing support (18) connect with the outside rod piece of column (2).
7. array fast-assembling inspection platform according to claim 1, it is characterised in that: the middle tier platform includes centre
Springboard (7), telescopic gangway, jump board support frame, 90 ° of skirting board limiting slots (15) and skirting board (16);Intermediate springboard (7) peace
On the inside of elementary layer, 90 ° of skirting board limiting slots (15) are mounted on 90 ° of rotation angle positions of inspection platform fence, described to kick
Sole (16) is supported on 90 ° of skirting board limiting slots (15).
8. array fast-assembling inspection platform according to claim 1, it is characterised in that: the top layer platform includes intermediate jumps
Plate (7), rectangular springboard (11), gathers together springboard (9), gathers together jump board support frame (10), fence, 90 ° of skirting boards avris springboard (8)
Limiting slot (15), 180 ° of skirting board limiting slots (17) and skirting board (16);The avris springboard (8) is mounted on the outer of elementary layer
Side, the intermediate springboard (7) are mounted on the inside of elementary layer, and 180 ° of skirting board limiting slots (17) are mounted on the straight of inspection platform fence
Line position, and the interrupted position of column is effectively connected, the rectangular springboard (11) is mounted in column;The passable springboard (9)
The centre of elementary layer is set and is supported by gathering together jump board support frame (10).
9. array fast-assembling inspection platform according to claim 8, it is characterised in that: the fence includes upright fence post
(12) and fence middle standing pillar (14) fence horizon bar, is installed between the upright fence post (12) and fence middle standing pillar (14)
(13).
10. array fast-assembling inspection platform according to claim 6, it is characterised in that: the throwing support (18) includes drawing money on credit
The intermediate position of strut, the strut of drawing money on credit is hinged with a section support rod.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920035396.1U CN209603463U (en) | 2019-01-09 | 2019-01-09 | Array fast-assembling inspection platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920035396.1U CN209603463U (en) | 2019-01-09 | 2019-01-09 | Array fast-assembling inspection platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209603463U true CN209603463U (en) | 2019-11-08 |
Family
ID=68398809
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920035396.1U Active CN209603463U (en) | 2019-01-09 | 2019-01-09 | Array fast-assembling inspection platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209603463U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577630A (en) * | 2019-01-09 | 2019-04-05 | 中国长江电力股份有限公司 | Array fast-assembling inspection platform |
CN113622365A (en) * | 2021-08-20 | 2021-11-09 | 中国长江电力股份有限公司 | Quick-assembling operation platform capable of movably walking on radial gate support arm and support hinge |
CN114856143A (en) * | 2022-05-17 | 2022-08-05 | 中国长江电力股份有限公司 | Hydropower station flood discharge flow passage self-adaptive fast-assembling maintenance platform and installation method |
-
2019
- 2019-01-09 CN CN201920035396.1U patent/CN209603463U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577630A (en) * | 2019-01-09 | 2019-04-05 | 中国长江电力股份有限公司 | Array fast-assembling inspection platform |
CN113622365A (en) * | 2021-08-20 | 2021-11-09 | 中国长江电力股份有限公司 | Quick-assembling operation platform capable of movably walking on radial gate support arm and support hinge |
CN114856143A (en) * | 2022-05-17 | 2022-08-05 | 中国长江电力股份有限公司 | Hydropower station flood discharge flow passage self-adaptive fast-assembling maintenance platform and installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209603463U (en) | Array fast-assembling inspection platform | |
CN102383588A (en) | Lifting platform for protecting safety of high-level construction | |
CN106049709A (en) | Connecting system of hybrid coupled shear wall and construction method | |
CN109577630A (en) | Array fast-assembling inspection platform | |
CN108252534A (en) | For the capital constructing device of truss installa-tion | |
CN113719163A (en) | Modular maintenance platform structure | |
CN209412699U (en) | A kind of assembly type walking underslung trolley operation platform | |
CN102287045B (en) | Square steel tube lifting outside scaffold | |
CN111927071A (en) | Movable operating platform | |
CN202530730U (en) | Aluminum alloy maintenance platform in furnace | |
CN207047702U (en) | A kind of bridge construction scaoffold | |
CN210086058U (en) | Matching type operating platform | |
CN204754150U (en) | Dish -type node formula scaffold | |
CN212897815U (en) | Modular maintenance platform structure and maintenance platform for cement plant storage warehouse | |
CN212714563U (en) | Fast-assembling recyclable pier body template combined operation platform | |
CN108147311A (en) | A kind of material lifting platform and its method for improving | |
CN114165040A (en) | Safety device for construction site of steel structure building engineering | |
CN104310184B (en) | Awning integral type escalator | |
CN209261195U (en) | A kind of assembled architecture exempts from outrigger Multifunctional high-altitude operation platform | |
CN207526141U (en) | A kind of small bore tower steel structure assembling formula operating platform | |
CN107419889B (en) | Operation platform for indoor roof construction | |
CN206971284U (en) | Fire-proof and explosion-proof sump oil cesspool integrates cover plate | |
CN206844680U (en) | Steel vestibule installation on ground load transfer device | |
CN201245964Y (en) | Moving platform | |
CN217379718U (en) | Prefabricated stairwell operation protection platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |