CN209602890U - A kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation structure - Google Patents

A kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation structure Download PDF

Info

Publication number
CN209602890U
CN209602890U CN201920238539.9U CN201920238539U CN209602890U CN 209602890 U CN209602890 U CN 209602890U CN 201920238539 U CN201920238539 U CN 201920238539U CN 209602890 U CN209602890 U CN 209602890U
Authority
CN
China
Prior art keywords
cured
slope
situ
foundation
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920238539.9U
Other languages
Chinese (zh)
Inventor
周华东
陈作雷
张正刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huiyi (shanghai) Environmental Geotechnical Technology Co Ltd
Original Assignee
Huiyi (shanghai) Environmental Geotechnical Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huiyi (shanghai) Environmental Geotechnical Technology Co Ltd filed Critical Huiyi (shanghai) Environmental Geotechnical Technology Co Ltd
Priority to CN201920238539.9U priority Critical patent/CN209602890U/en
Application granted granted Critical
Publication of CN209602890U publication Critical patent/CN209602890U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The utility model relates to reinforced soft soil ground technical fields, specifically disclose a kind of topsoil and are cured in situ and grid joint reinforcement soft soil foundation structure, including road structure, slope foundation, cured plate structure and cell structure;The slope foundation is located at the two sides of road structure, and road structure, slope foundation are respectively positioned in cured plate structure;Draining groove is offered in corresponding cured plate structure on the outside of the slope foundation;The cell structure is provided with several and the downside of cured plate structure is arranged in.It is cured in situ in conjunction with grid, realize point type solidification, project cost is low, construction period is short, improves subjacent bed soil bearing capacity, has good effect to reinforcing soft ground, point type solidification and tunneling boring solidification overlapping are carried out, the interspersed of pilot process is not needed, the tunneling boring cured plate body of formation can disperse upper load, reduce the bearing capacity of lower part compound base.

Description

A kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation structure
Technical field
The utility model relates to reinforced soft soil ground technical field, specifically a kind of topsoil is cured in situ combines with grid Reinforcing soft ground structure.
Background technique
Be cured in situ: it is a kind of that solidification being carried out in situ to soil bodys such as weak soils using curing agent, make the soil body reach some strength or Other requirements, to carry out treatment in situ to the soil body.China is improved in the solidification of the soil bodys such as dredging silt, Polluted Soil at present Aspect has done a large amount of research, but remains in laboratory test, bench-scale testing so far, and it is real that large-scale engineering has not yet been reached With the stage, while the recycling rate of the spoirs such as mud is far below level of developed countries, rivers and lakes dredging, dredging, work Cheng Jianshe can generate the waste soils such as a large amount of mud, and the environmental problems such as transport, stacking, land occupation, fugitive dust are prominent.For asking above Topic at this moment in engineering, is formed in situ crust layer using the technology of being cured in situ or plate body carries out shallow layer foundation processing, instead of cushion Realize recycling for soil resource.
Grid, also known as steel grating, steel grating or flase floor are that band steel and torsion steel are welded, its main application of grid exists Half space, aisle, ditch lid and step plate etc..It is also used in environmental protection equipment and sewage treatment etc., it is superior because of him Property is more and more widely adopted.
Gap length between grid grizzly bar can be set according to the requirement of the mode and water pump of removing dirt, manually remove lattice Grid gap is generally 16-25mm.Grid before setting pot or sedimentation basin generally uses 15-30mm, is up to 40mm.Grid equipment It is generally used on the irrigation channel of sewage treatment or the entrance of Boosting pumping station collecting-tank, main function is larger in removal sewage Suspension or floating material, to mitigate the processing load of subsequent water treatment technology, and play protection water pump, pipeline, instrument the effects of. It is general using mechanical scarfing cinder mode when the grid quantity of slag of interception is greater than 0.2m3/d;When the grid quantity of slag is less than 0.2m3/d, people can be used Mechanical scarfing cinder mode can also be used in work scarfing cinder mode.Applying for grid is answered in construction, design decoration, sewage treatment, engineering Have been widely used with equal fields.
Soft soil foundation refers to the ground being made of mud, muck soil, rinse fill, miscellaneous fill or other high-compressibility soil layers Base.This ground natural moisture content is excessive, and low bearing capacity is also easy to produce sliding or consolidation settlement under load action.It is soft soil roadbed Processing intent be improve highway subgrade stability and bearing capacity, reduce sedimentation.At present frequently with cushion, pre- in engineering The project cost of the processing of platen press and various displacement methods progress soft soil foundation, cushion and various displacement methods is very high, and constructs Duration is longer, and the construction period of preloading method is longer, and the construction period is wanted on some provisional roadbeds and workbench basis Ask very high.The environmental problems such as transport, stacking, land occupation, fugitive dust are prominent.
Utility model content
The purpose of this utility model is to provide a kind of topsoil be cured in situ with grid joint reinforcement soft soil foundation structure, To solve the problems mentioned in the above background technology.
To achieve the above object, the utility model provides the following technical solutions:
A kind of topsoil be cured in situ with grid joint reinforcement soft soil foundation structure, including it is road structure, slope foundation, solid Change hardened structure and cell structure;The slope foundation is located at the two sides of road structure, and road structure, slope foundation are respectively positioned on solidification On hardened structure;Draining groove is offered in corresponding cured plate structure on the outside of the slope foundation;The cell structure setting There are several and the downside of cured plate structure is set.
Further: the road structure is set gradually from top to bottom to banket for first level blotter, the second level Layer, third level cure layer.
It is further: the slope foundation include the horizontal reinforcing layer being connect with road structure and be located at horizontal reinforcing layer The slope reinforcement layer of the incline structure in outside can plant green plant on slope reinforcement layer, improve the consolidation effect to ground;Institute State horizontal reinforcing layer, slope reinforcement layer setting have two layers, respectively the first slope reinforcement layer and the second slope reinforcement layer, first Slope reinforcement layer is connect with the first level blotter on the road structure, the second slope reinforcement layer and the road structure On the second horizontal fill stratum, third level cure layer connection, so that roadbed is more easily constructed.
It is further: between the first slope reinforcement layer and first level blotter, the second slope reinforcement layer and second Junction setting connection slope foot between horizontal fill stratum, third level cure layer, plays protective action.
Further: the cured plate structure is carried out in situ solidification to soil bodys such as weak soils using curing agent, reaches the soil body Some strength or other requirements, thus to the soil body carry out treatment in situ, cured plate structure with a thickness of 0.3-0.6m, pass through Cured plate structural support road structure, slope foundation.
It is further: the cell structure spaced set, with a thickness of 0.1-0.6m, width 0.3-0.5m, grid Structure have intensity is big, creep is small, can adapt to all kinds of soil, not only bearing capacity is strong, corrosion resistance is strong for it, anti-aging is strong, and And also have the advantages that the big geomembrane coefficient of friction of intensity is big, eyelet is uniform, easy for construction, long service life etc. is a series of.
Further: the depth of the groove is 0.2-0.3m, and the water that top is flowed down is discharged along groove in time, avoids rain Water collects on the downside of slope foundation makes soil soften and be lost, and extends the service life of roadbed.
Compared with prior art, the utility model has the beneficial effects that being cured in situ in conjunction with grid, realize that point type is solid Change, project cost is low, and the construction period is short, improves subjacent bed soil bearing capacity, has good effect to reinforcing soft ground, will Point type solidification and tunneling boring solidification overlapping carry out, and do not need the interspersed of pilot process, the tunneling boring cured plate body of formation can divide Upper load is dissipated, the bearing capacity of lower part compound base is reduced.Grid is with intensity is big, creep is small, can adapt to all kinds of soil Earth, not only bearing capacity is strong, corrosion resistance is strong for it, anti-aging is strong, but also has that the big geomembrane coefficient of friction of intensity is big, eyelet is equal The a series of advantage such as even, easy for construction, long service life.
Detailed description of the invention
Fig. 1 is that a kind of topsoil is cured in situ the structural schematic diagram with grid joint reinforcement soft soil foundation structure.
In figure: 1- road structure, 2- slope foundation, 3- groove, 4- cured plate structure, 5- cell structure, 6- horizontal reinforcing Layer, 7- slope reinforcement layer, 8- first level blotter, the horizontal fill stratum of 9- second, 10- third level cure layer, 11- first Slope reinforcement layer, 12- the second slope reinforcement layer, 13- connection slope foot.
Specific embodiment
Embodiment 1
Please refer to figure, in the utility model embodiment, a kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation Structure, including road structure 1, slope foundation 2, cured plate structure 4 and cell structure 5;Slope foundation 2 is located at road structure 1 Two sides, road structure 1, slope foundation 2 are respectively positioned in cured plate structure 4.
The road structure 1 is set gradually from top to bottom as first level blotter 8, the second horizontal fill stratum 9, third Level cure layer 10.
The slope foundation 2 includes the horizontal reinforcing layer 6 connecting with road structure 1 and is located on the outside of horizontal reinforcing layer 6 Incline structure slope reinforcement layer 7, can plant green plant on slope reinforcement layer 7, improve the consolidation effect to ground;It is described Horizontal reinforcing layer 6, the setting of slope reinforcement layer 7 have two layers, respectively the first slope reinforcement layer 11 and the second slope reinforcement layer 12, First slope reinforcement layer 11 is connect with the first level blotter 8 on the road structure 1, the second slope reinforcement layer 12 and institute State the second horizontal fill stratum 9 on road structure 1, third level cure layer 10 connects, so that roadbed is more easily constructed;First Between slope reinforcement layer 11 and first level blotter 8, the second slope reinforcement layer 12 and the second horizontal fill stratum 9, third water Junction setting connection slope foot 13 between flat cured layer 10, plays protective action.
The cured plate structure 4 is carried out in situ solidification to soil bodys such as weak soils using curing agent, and the soil body is made to reach some strength Or other requirements, thus to the soil body carry out treatment in situ, cured plate structure 4 with a thickness of 0.3-0.6m, pass through cured plate Structure 4 supports road structure 1, slope foundation 2.
The cell structure 5 is provided with several, is equidistantly positioned in the downside of cured plate structure 4, the thickness of cell structure 5 Degree be 0.1-0.6m, width 0.3-0.5m, cell structure 5 have intensity is big, creep is small, can adapt to all kinds of soil, it is not Only bearing capacity is strong, corrosion resistance is strong, anti-aging is strong, but also have the big geomembrane coefficient of friction of intensity is big, eyelet uniformly, construction The a series of advantage such as convenience, long service life.
Embodiment 2
On the basis of embodiment 1, draining ditch is offered in the corresponding cured plate structure 4 in 2 outside of slope foundation The depth of slot 3, groove 3 is 0.2-0.3m, and the water that top flows down is discharged along groove 3 in time, avoids rainwater in slope foundation 2 Downside, which is collected, makes soil soften and be lost, and extends the service life of roadbed.
It is cured in situ in conjunction with grid, realizes point type solidification, project cost is low, and the construction period is short, improves the subjacent bed soil body Bearing capacity has good effect to reinforcing soft ground, and point type solidification and tunneling boring solidification overlapping are carried out, centre is not needed Process is interted, and the tunneling boring cured plate body of formation can disperse upper load, reduces the bearing capacity of lower part compound base. Grid have intensity is big, creep is small, can adapt to all kinds of soil, not only bearing capacity is strong, corrosion resistance is strong for it, anti-aging is strong, and And also have the advantages that the big geomembrane coefficient of friction of intensity is big, eyelet is uniform, easy for construction, long service life etc. is a series of.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (7)

1. a kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation structure, including road structure (1), slope foundation (2), cured plate structure (4) and cell structure (5);It is characterized in that, the slope foundation (2) is located at the two of road structure (1) Side, road structure (1), slope foundation (2) are respectively positioned on cured plate structure (4);Corresponding solidification on the outside of the slope foundation (2) Draining groove (3) are offered on hardened structure (4);The cell structure (5) is provided with several and is arranged in cured plate structure (4) downside.
2. a kind of topsoil according to claim 1 is cured in situ and grid joint reinforcement soft soil foundation structure, feature Be: the road structure (1) set gradually from top to bottom for first level blotter (8), the second horizontal fill stratum (9), Third level cure layer (10).
3. a kind of topsoil according to claim 2 is cured in situ and grid joint reinforcement soft soil foundation structure, feature Be: the slope foundation (2) includes the horizontal reinforcing layer (6) connecting with road structure (1) and is located at horizontal reinforcing layer (6) The slope reinforcement layer (7) of the incline structure in outside, horizontal reinforcing layer (6), slope reinforcement layer (7) setting have two layers, respectively First slope reinforcement layer (11) and the second slope reinforcement layer (12), on the first slope reinforcement layer (11) and the road structure (1) First level blotter (8) connection, the second slope reinforcement layer (12) bankets with the second level on the road structure (1) Layer (9), third level cure layer (10) connection.
4. a kind of topsoil according to claim 3 is cured in situ and grid joint reinforcement soft soil foundation structure, feature It is: between the first slope reinforcement layer (11) and first level blotter (8), the second slope reinforcement layer (12) and the second water Junction setting connection slope foot (13) between flat fill stratum (9), third level cure layer (10).
5. a kind of topsoil according to claim 1 to 4 be cured in situ with grid joint reinforcement soft soil foundation structure, It is characterized by: the cured plate structure (4) with a thickness of 0.3-0.6m.
6. a kind of topsoil according to claim 5 is cured in situ and grid joint reinforcement soft soil foundation structure, feature It is: cell structure (5) spaced set, with a thickness of 0.1-0.6m, width 0.3-0.5m.
7. a kind of topsoil according to claim 6 is cured in situ and grid joint reinforcement soft soil foundation structure, feature Be: the depth of the groove (3) is 0.2-0.3m.
CN201920238539.9U 2019-02-26 2019-02-26 A kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation structure Active CN209602890U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920238539.9U CN209602890U (en) 2019-02-26 2019-02-26 A kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920238539.9U CN209602890U (en) 2019-02-26 2019-02-26 A kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation structure

Publications (1)

Publication Number Publication Date
CN209602890U true CN209602890U (en) 2019-11-08

Family

ID=68403016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920238539.9U Active CN209602890U (en) 2019-02-26 2019-02-26 A kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation structure

Country Status (1)

Country Link
CN (1) CN209602890U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997030A (en) * 2020-08-11 2020-11-27 广东劲拓建设工程有限公司 Soft soil reinforcing and curing method
CN113216133A (en) * 2021-05-06 2021-08-06 岳阳市交通公路工程建设总公司 Soft foundation shallow section curing structure and construction method thereof
CN113897830A (en) * 2021-08-25 2022-01-07 浙江交工金筑交通建设有限公司 Construction method of soft foundation embankment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997030A (en) * 2020-08-11 2020-11-27 广东劲拓建设工程有限公司 Soft soil reinforcing and curing method
CN113216133A (en) * 2021-05-06 2021-08-06 岳阳市交通公路工程建设总公司 Soft foundation shallow section curing structure and construction method thereof
CN113897830A (en) * 2021-08-25 2022-01-07 浙江交工金筑交通建设有限公司 Construction method of soft foundation embankment

Similar Documents

Publication Publication Date Title
CN209602890U (en) A kind of topsoil is cured in situ and grid joint reinforcement soft soil foundation structure
CN101368383B (en) Method for treating soft soil roadbed by artificial composite crust layer
CN210766223U (en) Roadbed structure capable of preventing settlement during drainage
Chu et al. Methods for improvement of clay slurry or sewage sludge
CN101831904A (en) Permeable concrete pile
CN109137872B (en) Reinforced structure bag and method for processing soft foundation by using reinforced structure bag
Jones et al. Electrokinetic geosynthetics: from research to hype to practice
CN106836435A (en) The hard pavement construction method of underground water nature recharge
CN1179144C (en) Method for filling protective layer of embedded tube
CN104060601A (en) Construction method utilizing pile foundations of precast construction piles for ground treatment
CN212001226U (en) Backfill miscellaneous soil composite foundation structure
CN211922135U (en) Prevent subsiding highway subgrade
CN105862535A (en) Dredger fill solidification pile roadbed and construction method thereof
CN210529400U (en) Solidified building residue soil road structure
CN110080160B (en) Ecological seepage-proofing structure based on gravel-doped clay and herbaceous layer and construction method thereof
CN111576384A (en) Construction method of high-energy-level dynamic compaction
Pashazadeh et al. Estimating an appropriate plastic concrete mixing design for cutoff walls to control leakage under the earth dam
CN215758302U (en) High liquid limit soil roadbed structure
CN212865481U (en) Anti-cracking grain noodle for rural areas
CN212335677U (en) Farmland operation way with drainage function
CN114541362A (en) Foundation treatment method and artificial foundation
CN205368919U (en) Highway soft soil foundation treatment pile extension structure
CN106759284A (en) Gradual change type permeable concrete-broken stone pile, ground, building and method
CN208486146U (en) A kind of novel filter infiltration garden road step and sunk type square laying structure
CN208121494U (en) A kind of novel road roadbed

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant