CN209585630U CN201920238070.9U CN201920238070U CN209585630U CN 209585630 U CN209585630 U CN 209585630U CN 201920238070 U CN201920238070 U CN 201920238070U CN 209585630 U CN209585630 U CN 209585630U
Authority
CN
China
Prior art keywords
intubation
screwed pipe
outer tube
steel sleeve
sleeve outer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920238070.9U
Other languages
Chinese (zh)
Inventor
徐慧莹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tangshan University
Original Assignee
Tangshan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tangshan University filed Critical Tangshan University
Priority to CN201920238070.9U priority Critical patent/CN209585630U/en
Application granted granted Critical
Publication of CN209585630U publication Critical patent/CN209585630U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of building construction formwork adjustable support frames.Including the first steel sleeve outer tube, the first intubation screwed pipe, the first adjusting nut, the diagonal brace being arranged symmetrically, hinged-support, adjustable jacking, positioning pin and sliding sleeve;The lower end of first intubation screwed pipe is plugged in the first steel sleeve outer tube and is positioned by the first adjusting nut, hinged-support is arranged on steel sleeve outer tube, the upper end of first intubation screwed pipe is sleeved on adjustable jacking, diagonal brace includes the second steel sleeve outer tube, the second intubation screwed pipe and the second adjusting nut, and the lower end of the second intubation screwed pipe is plugged in the second steel sleeve outer tube and is positioned by the second adjusting nut.The utility model can carry out telescopic adjustment according to the width that installs for installing absolute altitude and slab form of cast-in-place concrete structure slab form, simple structure installs and easy to adjust, firm supporting, realizes recycling, and can accelerate to install speed, improve construction efficiency.

Description

Building construction formwork adjustable support frame
Technical field
The utility model relates to technical field of building construction, specifically a kind of building construction formwork adjustable support frame.
Background technique
With the fast development of the continuous development of China's building industrialization, especially skyscraper, cast-in-place concrete structure Engineering has become the dominant type of current concrete works, and form work engineering is as the main subdivisional work of structure of reinforced concrete One of, in Cast-in-situ Concrete Structural Engineering construction, the erection method of template and support frame will directly influence engineering construction Construction speed, construction quality and construction cost are also directly related to the safety of construction personnel and the economic benefit of construction enterprises, seek The rationalization to seek template with support frame reduces form work engineering expense, saves labour, is to reduce concrete structure engineering expense Important channel.
Formwork-support is an important component of form work engineering, is mutually deserved with form work engineering technological progress Development is arrived, the support system of current many countries has evolved into construction tool with their own characteristics, various series of products are formed, I State promotes and applies steel tubular support with couplers since the twentieth century sixties, and this support frame simple processing, assembling are flexible, but It is the quality of connection of the fastener node of steel tubular support with couplers and to install speed vulnerable to fastener quality itself and worker operation Influence, this result in template install quality and the construction period is difficult to obtain guarantee.
How effectively to improve the production of template and support frame, the efficiency of installation and removal and ensure engineering construction quality, It is current urgent problem to be solved.
Utility model content
The utility model aims to solve the problem that the above problem, so that a kind of building construction formwork adjustable support frame is provided, it can Telescopic adjustment, construction letter are carried out according to the width that installs for installing absolute altitude and slab form of cast-in-place concrete structure slab form It is single, install and easy to adjust, firm supporting, realize recyclings, and can accelerate to install speed, raising construction efficiency.
The utility model solves described problem, the technical solution adopted is that:
A kind of building construction formwork adjustable support frame, including pillar and fixation kit, pillar include outside the first steel sleeve Pipe, the first intubation screwed pipe and the first adjusting nut;The lower end of first intubation screwed pipe is plugged in the first steel sleeve outer tube simultaneously And it is positioned by the first adjusting nut;Fixation kit include the diagonal brace being arranged symmetrically, hinged-support, adjustable jacking, positioning pin and Sliding sleeve;Hinged-support is arranged on steel sleeve outer tube, and the upper end of the first intubation screwed pipe is sleeved on adjustable jacking, diagonal brace Including the second steel sleeve outer tube, the second intubation screwed pipe and the second adjusting nut, the lower end of the second intubation screwed pipe is plugged on the It being positioned in two steel sleeve outer tubes and by the second adjusting nut, the lower end of the second steel sleeve outer tube is hinged on hinged-support, the The upper end of two intubation screwed pipes is hinged on sliding sleeve, is provided with multiple and detent fit positioning on adjustable jacking Hole, sliding sleeve are sleeved on adjustable jacking and by positioning finger settings.
The utility model by adopting the above technical scheme, compared with prior art, the feature protruded is:
It can be stretched according to the width that installs for installing absolute altitude and slab form of cast-in-place concrete structure slab form It adjusts, simple structure installs and easy to adjust, firm supporting, realizes recyclings, and can accelerate to install speed, raising Construction efficiency.
Preferably, the further technical solution of the utility model is:
The card slot being used to support with position level wooden flute is provided on sliding sleeve.
The upper end of first intubation screwed pipe is provided with the supporting plate for holding slab form, increases the stress surface of pillar upper end Product enhances support frame overall structure stability.
The lower end of first steel sleeve outer tube is provided with pedestal, increases the forced area of lower rod end, and enhancing support frame is whole Structural stability.
The upper end of first intubation screwed pipe is fixedly mounted on the center of adjustable jacking.
Detailed description of the invention
Fig. 1 is the utility model embodiment structural schematic diagram;
In figure: horizontal wooden flute 1;First intubation screwed pipe 2;Slab form 3;Location hole 4;Sliding sleeve 5;Second intubation spiral shell Line pipe 6;Second adjusting nut 7;Second steel sleeve outer tube 8;Hinged-support 9;First steel sleeve outer tube 10;Pedestal 11;Adjustable top Support 12;Supporting plate 13;First adjusting nut 14;Positioning pin 15;Card slot 16.
Specific embodiment:
Below with reference to embodiment, the utility model is described in further detail, and purpose, which is only that, more fully understands the utility model Content, therefore, the cited case are not intended to limit the protection scope of the utility model.
Referring to Fig. 1, a kind of building construction formwork adjustable support frame, including pillar and fixation kit, pillar include first Steel sleeve outer tube 10, first is intubated screwed pipe 2 and the first adjusting nut 14;The lower end of first intubation screwed pipe 2 is plugged on first It is positioned in steel sleeve outer tube 10 and by the first adjusting nut 14;Fixation kit include the diagonal brace being arranged symmetrically, hinged-support 9, Adjustable jacking 12, positioning pin 15 and sliding sleeve 5;Hinged-support 9 is arranged on steel sleeve outer tube 10, the first intubation screwed pipe 2 Upper end be sleeved on adjustable jacking 12, diagonal brace include the second steel sleeve outer tube 8, second intubation screwed pipe 6 and second adjust Nut 7, the lower end of the second intubation screwed pipe 6 are plugged in the second steel sleeve outer tube 8 and are positioned by the second adjusting nut 7, The lower end of second steel sleeve outer tube 8 is hinged on hinged-support 9, and the upper end of the second intubation screwed pipe 6 is hinged on sliding sleeve 5, Multiple location holes 4 cooperated with positioning pin 15 are provided on adjustable jacking 12, sliding sleeve 5 is sleeved on adjustable jacking 12 And it is positioned by positioning pin 15.
The card slot 16 being used to support with position level wooden flute 1 is provided on sliding sleeve 5.
The upper end of first intubation screwed pipe 2 is welded with the supporting plate 13 for holding slab form 3, the first steel sleeve outer tube 10 Lower end be welded with pedestal 11, the top and bottom of pillar are respectively welded supporting plate 13 and pedestal 11, to increase end stress surface Product enhances support frame overall structure stability.
The upper end of first intubation screwed pipe 2 is fixedly mounted on the center of adjustable jacking 12.
By the horizontally-supported load of floor transmitted, construction loads and self weight etc. when pillar is primarily subjected to concreting, Upper and lower side is welded with supporting plate 13 and pedestal 11 respectively, to increase end forced area, by adjusting the top first of pillar when use Intubation screwed pipe 2 rotates the first adjusting nut 14 to change strut height, is become with adapting to the horizontally-supported height of different cross section Change, it is horizontally-supported that when installation should ensure that pillar upper and lower side is held out against, main diagonal brace, the adjustable jacking by being arranged symmetrically of fixation kit 12, sliding sleeve 5 etc. forms, and mainly by adjusting the requirement for adapting to different templates and installing height, and is used to fixed and firm branch Support system.
When production, the outer diameter 60mm of the first steel sleeve outer tube 10, wall thickness 3.2mm;Pedestal 11 is 200mm × 200mm, thickness The steel plate of 10mm;The outer diameter 48mm, wall thickness 2.5mm of first intubation screwed pipe 2;Supporting plate 13 is 150mm × 150mm, thickness 10mm Steel plate;The outer diameter 38mm of second steel sleeve outer tube 8, wall thickness 2.0mm;The outer diameter 30mm of second intubation screwed pipe 6, wall thickness 2.0mm;Sliding sleeve 5 is the square steel tube of length 100mm, 48 × 48 × 2.5mm of;Adjustable jacking 12 is square steel tube, 42 × 42 × 2.5mm, in 5 travel range of sliding sleeve, every 50mm is equipped with location hole 4;Horizontal wooden flute 1 is 100mm × 100mm's The lumps of wood.
Application method: (1) support frame install: supporting frame set up before according to design drawing surveying setting-out, since span centre First row pillar is installed, is fixed temporarily and pacifies second row pillar to both sides again, successively install by row, it is desirable that pillar is vertical, it is ensured that on In same vertical centerline, pillar upper end is adjusted above jacking 12 using adjustable jacking 12 and is installed floor lower layer's column The stupefied beam of the primary and secondary of template 3, positioned beneath is on the concrete floor that next floor has poured;(2) the stupefied beam of primary and secondary is installed simultaneously Pass through adjustable jacking 12 and carry out Pass line adjustment: supporting frame after the installation is completed, since across side master is successively installed by row Secondary stupefied beam, main stupefied beam adjust spiral shell after the installation is completed, by adjusting the sliding sleeve 5 on adjustable jacking 12, and rotation second Mother 7 and the first adjustment nut 2, adjust absolute altitude and the arch camber of the adjustable jacking 12 of floor, so that support frame overally supports Horizontal wooden flute 1 and slab form 3 are laid with time stupefied beam after adjustment;(3) template is installed: after secondary stupefied beam is laid with, being carried out Template installs, and the piece of all templates is arranged on time stupefied beam, and secondary stupefied beam splice is arranged on main stupefied beam;(4) template Install inspection of quality: template is installed post-tensioning and leads to line measurement module absolute altitude and position, qualified according to related specifications close inspection After can carry out reinforcing bar binding.
The utility model can install installing for absolute altitude and slab form 3 according to cast-in-place concrete structure slab form 3 Width carries out telescopic adjustment, and simple structure installs and easy to adjust, firm supporting, realizes recycling, and can accelerate to prop up If speed, construction efficiency is improved.
The above is only the preferred feasible embodiment of the utility model, not thereby limits to the power of the utility model Sharp range, it is all with equivalence changes made by the utility model specification and its accompanying drawing content, it is both contained in the utility model Within interest field.

Claims (5)

1. a kind of building construction formwork adjustable support frame, including pillar and fixation kit, it is characterised in that: pillar includes first Steel sleeve outer tube, the first intubation screwed pipe and the first adjusting nut;The lower end of first intubation screwed pipe is plugged on the first steel sleeve It is positioned in outer tube and by the first adjusting nut;Fixation kit include the diagonal brace being arranged symmetrically, hinged-support, adjustable jacking, Positioning pin and sliding sleeve;Hinged-support is arranged on steel sleeve outer tube, and the upper end of the first intubation screwed pipe is sleeved on adjustable top In support, diagonal brace includes the second steel sleeve outer tube, the second intubation screwed pipe and the second adjusting nut, the lower end of the second intubation screwed pipe It is plugged in the second steel sleeve outer tube and is positioned by the second adjusting nut, the lower end of the second steel sleeve outer tube is hinged on hinged On seat, the upper end of the second intubation screwed pipe is hinged on sliding sleeve, is provided with multiple and detent fit on adjustable jacking Location hole, sliding sleeve be sleeved on adjustable jacking and by positioning finger setting.
2. building construction formwork adjustable support frame according to claim 1, it is characterised in that: be provided on sliding sleeve It is used to support the card slot with position level wooden flute.
3. building construction formwork adjustable support frame according to claim 1, it is characterised in that: the first intubation screwed pipe Upper end is provided with the supporting plate for holding slab form.
4. building construction formwork adjustable support frame according to claim 1, it is characterised in that: the first steel sleeve outer tube Lower end is provided with pedestal.
5. building construction formwork adjustable support frame according to claim 1, it is characterised in that: the first intubation screwed pipe Upper end is fixedly mounted on the center of adjustable jacking.
CN201920238070.9U 2019-02-26 2019-02-26 Building construction formwork adjustable support frame Expired - Fee Related CN209585630U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920238070.9U CN209585630U (en) 2019-02-26 2019-02-26 Building construction formwork adjustable support frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920238070.9U CN209585630U (en) 2019-02-26 2019-02-26 Building construction formwork adjustable support frame

Publications (1)

Publication Number Publication Date
CN209585630U true CN209585630U (en) 2019-11-05

Family

ID=68356084

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920238070.9U Expired - Fee Related CN209585630U (en) 2019-02-26 2019-02-26 Building construction formwork adjustable support frame

Country Status (1)

Country Link
CN (1) CN209585630U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112502446A (en) * 2020-11-03 2021-03-16 中国一冶集团有限公司 Socket type center barrel temporary support and using method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112502446A (en) * 2020-11-03 2021-03-16 中国一冶集团有限公司 Socket type center barrel temporary support and using method thereof

Similar Documents

Publication Publication Date Title
CN204059955U (en) In-situ reinforced concrete slab template integral type braced structures
CN102828469A (en) Positioning mounting construction method for triangular steel constructed pillar of inclined-leg steel box
CN105648923B (en) Stay cable saddle positioning method
CN203066476U (en) Adjustable triangular support for plywood wall template with steel frame
CN209585630U (en) Building construction formwork adjustable support frame
CN210887278U (en) Fixing device for cup mouth type concrete foundation pit stand column
CN102926554A (en) Steel hanging seat template supports and construction method thereof
CN212129960U (en) Overhead installation device for frame beam reinforcing steel bars
CN111305597A (en) Building template supporting system and installation method thereof
CN203834370U (en) Arch ring steel formwork trolley for circular arch culvert
CN215907403U (en) Fine adjustment tool for supporting large steel formwork
CN212927107U (en) Diagonal brace for prefabricated wall panel construction
CN209741674U (en) Civil engineering cement pouring device
CN113309256A (en) Construction device and construction method for prefabricated shear wall with post-pouring section
CN209891347U (en) Pipe ditch inner formwork support device
CN205224579U (en) Steel framework template and self -supporting truss board combination concrete quick detach system
CN105064703A (en) Scale device for masonry wall building
CN216516860U (en) Independent supporting base for laminated slab
CN220789460U (en) Small box girder adjusting jacking frame
CN204899939U (en) Bent wall wherein partition wall formworking jumbo
CN210342437U (en) Adjustable stirrup cage welding frame
CN215368631U (en) Super high-rise core section of thick bamboo construction multifunctional measuring tool carries on platform
CN214994000U (en) Supporting and positioning structure for installing large-scale foundation steel bars
CN210086062U (en) Convenient cast-in-place case roof beam of adjusting pours support frame
CN214658843U (en) Building is template link for engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191105

Termination date: 20210226

CF01 Termination of patent right due to non-payment of annual fee