CN209568123U - A kind of copper-steel integrated tuyere case - Google Patents
A kind of copper-steel integrated tuyere case Download PDFInfo
- Publication number
- CN209568123U CN209568123U CN201920103417.9U CN201920103417U CN209568123U CN 209568123 U CN209568123 U CN 209568123U CN 201920103417 U CN201920103417 U CN 201920103417U CN 209568123 U CN209568123 U CN 209568123U
- Authority
- CN
- China
- Prior art keywords
- water
- muzzle
- chamber
- steel
- flange
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Blast Furnaces (AREA)
Abstract
A kind of copper-steel integrated tuyere case, steel muzzle and copper muzzle including passing through first flange Joint, the first closed water chamber is arranged in the copper muzzle, intake chamber is arranged in the inside of first water chamber, the first cooling chamber is arranged in the outside of first water chamber, inlet channel is arranged in the front side of first water chamber, the inlet channel connection intake chamber and the first cooling chamber, water conservancy diversion gusset is arranged in the first cooling chamber inside spin, second flange is arranged in the tail portion of the steel muzzle, the second water inlet and the second water outlet is arranged in the second flange, the second closed cooling chamber is arranged in the steel muzzle, the water conservancy diversion gusset and the second cooling chamber form spiral helicine water channel, water inlet pipe is set in the steel muzzle, first water inlet of the water inlet pipe by the second water inlet through first flange is connected with intake chamber.The tuyere case of the utility model is integrated, and avoids deforming, and extends the service life of equipment, using a set of water inlet system, so that structure is more simple.
Description
Technical field
The utility model relates to a kind of tuyere cover of blast furnace more particularly to a kind of copper-steel integrated tuyere cases.
Background technique
Blast furnace is a closed high temperature and pressure smelting vessel, air supply device by the tuyere equipment that is mounted on furnace shell to
Hot wind is blasted in furnace.Existing tuyere case is divided into tuyere small sleeve, tuyere medium sleeve and tuyere big sleeve, and wherein one end of tuyere medium sleeve is logical
It crosses tapered surface and tuyere small sleeve is tightly connected, the other end is tightly connected by tapered surface and tuyere big sleeve, tuyere small sleeve and air port
Middle set be copper metal constitute, tuyere big sleeve be iron quality metal material constitute, the higher cost of copper so that tuyere case at
This is higher, and respective inflow and outflow system is respectively set in tuyere small sleeve, tuyere medium sleeve, tuyere big sleeve, for tuyere case is cold
But, due in tuyere case tuyere small sleeve and tuyere medium sleeve be set in furnace, so wherein be heated most serious face be that air port is small
Wind taper pipe portion and the barrel-shaped face of outer face cone are crossed among set and front end portion, the damage at these positions are to cause blast furnace staying
The main reason for maintenance, and as tuyere case uses the extension of time, it be easy to cause in tuyere small sleeve and tuyere medium sleeve, air port
Set at the mating surface of tuyere big sleeve because mating surface deform caused by leak out, the gas leak in furnace is also easy to cause personal injury thing
Therefore tuyere medium sleeve uses long, because copper material intensity is low, long-term work at higher temperatures, be easy to cause deformation, causes air port small
Easily assembling, mating face seal be not tight for set.
Utility model content
The technical problem to be solved by the present invention is to provide a kind of copper-steel integrated tuyere cases for being able to solve the above problem.
The technical solution adopted in the utility model is in order to solve the above problem:
A kind of copper-steel integrated tuyere case, steel muzzle and copper muzzle including passing through first flange Joint, the copper muzzle
Shape with steel muzzle is hollow taper, and contact surface is formed closed under the inner wall of the copper muzzle, shell and first flange
First water chamber, the inside of first water chamber are arranged intake chamber, and the outside of first water chamber is arranged the first cooling chamber, and described the
Inlet channel, the inlet channel connection intake chamber and the first cooling chamber, the first cooling chamber inside spin is arranged in the front side of one water chamber
Water conservancy diversion gusset is set, the water conservancy diversion gusset and the first cooling chamber form spiral helicine water channel, the first flange be arranged first into
The mouth of a river and the first water outlet, the tail portion of the steel muzzle are arranged second flange, and the second water inlet and the is arranged in the second flange
Two water outlets, the inner wall of the steel muzzle, shell, contact surface forms closed under contact surface and second flange in first flange
Water conservancy diversion gusset is arranged in two cooling chambers, the second cooling chamber inside spin shape, and the water conservancy diversion gusset and the second cooling chamber form spiral
The water channel of shape, the first water outlet of the first flange connect the first cooling chamber and the second cooling chamber, setting in the steel muzzle
Water inlet pipe, first water inlet of the water inlet pipe by the second water inlet through first flange are connected with intake chamber.
Preferably, the steel muzzle is constituted using steel metal material.
Preferably, the copper muzzle is constituted using copper metal material.
Preferably, hollow spherical structure is set in the first flange.
The utility model has the advantages that
1, the utility model uses a set of water inlet system, and structure is simple, improves work efficiency.
2, tuyere case ontology uses integrated structure, deformation is avoided, so that the service life of tuyere case enhances.
3, the position that tuyere medium sleeve is arranged in existing equipment is replaced with into steel, reduces production cost.
Detailed description of the invention
Fig. 1 is the utility model top view;
Fig. 2 is the utility model A-A sectional view;
Fig. 3 is the utility model scheme of installation;
In figure: 1, copper muzzle, 2, steel muzzle, the 11, first water inlet, 12, first flange, 13, intake chamber, 14, first is cold
But room, the 15, first water chamber, 16, inlet channel, 17, hollow sphere, the 18, first water outlet, the 21, second water inlet, the 22, second method
Orchid, 23, water inlet pipe, 24, water conservancy diversion gusset, the 25, second cooling chamber, the 26, second water outlet.
Specific embodiment
In the following, being further described in conjunction with substantive distinguishing features and advantage of the example to the utility model, but this is practical new
Type is not limited to listed embodiment.
It please refers to shown in Fig. 1-3, the figure shows a kind of copper-steel integrated air port nooses described in the utility model embodiment
Structure illustrates only the related part of the utility model embodiment for ease of description.
A kind of copper-steel integrated tuyere case, it is described including the steel muzzle 2 and copper muzzle 1 being fixedly connected by first flange 12
Second flange 22, the lower contact surface of the inner wall of the steel muzzle 2, shell, second flange 22 and the first method is arranged in the tail portion of steel muzzle 2
Contact surface forms the second closed cooling chamber 25 on orchid 12, and water conservancy diversion gusset 24 is arranged in 25 inside spin of the second cooling chamber, described
Water conservancy diversion gusset 24 and the second cooling chamber 25 form spiral helicine water channel, and the second water inlet 21 and are arranged in the second flange 22
Two water outlets 26, are arranged the first water inlet 11 and the first water outlet 18 in the first flange 12, in first cooling chamber 25
Water inlet pipe 23 is set, and the water inlet pipe 23 is connected through the first water inlet 11 with intake chamber 13 by the second water inlet 21, institute
It is closed through water conservancy diversion gusset 24 to state water inlet pipe 23, the lower contact surface of inner wall, shell and the first flange 12 of the copper muzzle 1 forms close
Intake chamber 13, the outside setting first of first water chamber 15 is arranged in the first water chamber 15 closed, the inside of first water chamber 15
Inlet channel 16 is arranged in cooling chamber 14, the front side of first water chamber 15, and the inlet channel 16 connects intake chamber 13 and the first cooling
Water conservancy diversion gusset 24 is arranged in room 14,14 inside spin of the first cooling chamber, and the water conservancy diversion gusset 24 and the first cooling chamber 14 form spiral shell
The water channel for revolving shape, effectively can help tuyere case to cool down, the copper muzzle 1 and steel muzzle 2 are hollow taper, described
Copper muzzle 1 is made of copper metal material, and the steel muzzle 2 is made of steel material, and the first flange setting is hollow
17 structure of spherical surface, can preferably fit with belly pipe, and what is be arranged in second cooling chamber 25 and the first cooling chamber 14 leads
Stream gusset 24 can may be S shape for helical form, and water enters water inlet by water inlet pipe 23 by the water inlet 21 of second flange 22
Room 13 enters the first cooling chamber 14 by inlet channel 16, and water is entered in 14 inside spin shape of the first cooling chamber by the first water outlet 18
Second cooling chamber 25, water is discharged in 25 inside spin shape of the second cooling chamber by the second water outlet 26 of second flange 22, thus complete
Cheng Yici water cooling but, effectively can help tuyere case to cool down.
Tuyere case integration is avoided and is deformed in blast furnace by prolonged high temperature and corrosion by the utility model
Cause to generate gap between the front-end and back-end of tuyere case, so as to cause the generation of accident, while extending the use of tuyere case
Service life, tuyere case set gradually copper muzzle and steel muzzle, replace copper using steel, reduce production cost, and the utility model uses
A set of water inlet system, structure is simple, and first flange is provided with hollow sphere structure, fits, increases with the front end of belly pipe
Working efficiency.
The above is only the preferred embodiment of the utility model, it is noted that for the common skill of the art
For art personnel, without departing from the principle of this utility model, several improvements and modifications can also be made, these improve and
Retouching also should be regarded as the protection scope of the utility model.
Claims (4)
1. a kind of copper-steel integrated tuyere case, which is characterized in that steel muzzle and copper muzzle including passing through first flange Joint, institute
The shape for stating copper muzzle and steel muzzle is hollow taper, contact surface shape under the inner wall of the copper muzzle, shell and first flange
At the first closed water chamber, intake chamber is arranged in the inside of first water chamber, and the outside setting first of first water chamber is cooling
Inlet channel, the inlet channel connection intake chamber and the first cooling chamber is arranged in room, the front side of first water chamber, and described first is cooling
Water conservancy diversion gusset is arranged in indoor spiral, and the water conservancy diversion gusset and the first cooling chamber form spiral helicine water channel, and the first flange is set
Set the first water inlet and the first water outlet, the tail portion of the steel muzzle is arranged second flange, the second flange setting second into
The mouth of a river and the second water outlet, the inner wall of the steel muzzle, shell, contact surface is formed under contact surface and second flange in first flange
Water conservancy diversion gusset, the water conservancy diversion gusset and the second cooling chamber is arranged in the second closed cooling chamber, the second cooling chamber inside spin shape
Spiral helicine water channel is formed, the first water outlet of the first flange connects the first cooling chamber and the second cooling chamber, the steel mouth
Water inlet pipe is set in set, and first water inlet of the water inlet pipe by the second water inlet through first flange is connected with intake chamber
It connects.
2. a kind of copper-steel integrated tuyere case according to claim 1, which is characterized in that the steel muzzle uses steel metal
Material is constituted.
3. a kind of copper-steel integrated tuyere case according to claim 1, which is characterized in that the copper muzzle uses copper metal
Material is constituted.
4. a kind of copper-steel integrated tuyere case according to claim 1, which is characterized in that be arranged in the first flange hollow
Spherical structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920103417.9U CN209568123U (en) | 2019-01-22 | 2019-01-22 | A kind of copper-steel integrated tuyere case |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920103417.9U CN209568123U (en) | 2019-01-22 | 2019-01-22 | A kind of copper-steel integrated tuyere case |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209568123U true CN209568123U (en) | 2019-11-01 |
Family
ID=68332601
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920103417.9U Expired - Fee Related CN209568123U (en) | 2019-01-22 | 2019-01-22 | A kind of copper-steel integrated tuyere case |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209568123U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110823502B (en) * | 2019-11-20 | 2020-06-02 | 中国空气动力研究与发展中心超高速空气动力研究所 | Whole water-cooling bent in high temperature flow field |
CN112662829A (en) * | 2021-01-21 | 2021-04-16 | 南京玛格耐特智能科技有限公司 | Blast furnace tuyere small sleeve and manufacturing method thereof |
-
2019
- 2019-01-22 CN CN201920103417.9U patent/CN209568123U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110823502B (en) * | 2019-11-20 | 2020-06-02 | 中国空气动力研究与发展中心超高速空气动力研究所 | Whole water-cooling bent in high temperature flow field |
CN112662829A (en) * | 2021-01-21 | 2021-04-16 | 南京玛格耐特智能科技有限公司 | Blast furnace tuyere small sleeve and manufacturing method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209568123U (en) | A kind of copper-steel integrated tuyere case | |
CN204495075U (en) | There is the shaft cooler of diversion function | |
CN205368409U (en) | Overlap in wind gap that can prevent to upwarp | |
CN204421694U (en) | Can the titanium tube heat exchanger of effective improving heat exchanging efficiency | |
CN208720872U (en) | Efficient molten salt cooler | |
CN201495245U (en) | Stream guidance type blast furnace tuyere small sleeve | |
CN206531411U (en) | A kind of novel coil cooler | |
CN109576436A (en) | Compulsory circulative cooling flue | |
CN205260322U (en) | Quiet set of water -chilling plant of scroll compressor | |
CN202814165U (en) | Gasified black water heat exchanger and heat exchanger unit | |
CN102003825B (en) | Retractable archimedes type line vortex tube nozzle | |
CN214735871U (en) | Safe and energy-saving blowpipe of blast furnace air supply device | |
CN102191346B (en) | Combined tuyere small sleeve | |
CN204514069U (en) | A kind of afterheat heat exchanger based on cement kiln head waste gas | |
CN202519277U (en) | Intermediate sleeve of blast-furnace tuyere | |
CN209386847U (en) | Negative pressure heat exchangers for district heating | |
CN203202285U (en) | Valve element | |
CN201058876Y (en) | Modified blast furnace tuyere cover | |
CN210683826U (en) | Novel through-flow tuyere small sleeve | |
CN210367749U (en) | Blast furnace tuyere device for blast furnace ironmaking | |
CN202133287U (en) | Combined tuyere small sleeve | |
CN205352148U (en) | Abrasionproof decreases low -level (stack -gas) economizer | |
CN210620857U (en) | Novel inner core of through-flow tuyere small sleeve | |
CN203906390U (en) | Novel energy-saving jet device for hot-and-cold water circulating system | |
CN220132255U (en) | Energy-saving blast furnace tuyere small sleeve |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191101 Termination date: 20210122 |
|
CF01 | Termination of patent right due to non-payment of annual fee |