CN209567737U - Limited headroom descending reinforcing cage lifts by crane mounting device - Google Patents
Limited headroom descending reinforcing cage lifts by crane mounting device Download PDFInfo
- Publication number
- CN209567737U CN209567737U CN201920136498.2U CN201920136498U CN209567737U CN 209567737 U CN209567737 U CN 209567737U CN 201920136498 U CN201920136498 U CN 201920136498U CN 209567737 U CN209567737 U CN 209567737U
- Authority
- CN
- China
- Prior art keywords
- fixed pulley
- upper frame
- crane
- bracket
- mounting device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model belongs to construction site apparatus field, mounting device is lifted by crane more particularly to a kind of limited headroom descending reinforcing cage, solve the problems, such as that pile foundation steel bar cage can not be unable to complete normal lifts using crane under the conditions of limited headroom, boom hoisting main body including being in truncated rectangular pyramids structure setting, boom hoisting main body successively includes upper frame from top to bottom, bracket and chassis, bracket is symmetrically arranged inclination frame body, the first fixed pulley and the second fixed pulley being generally aligned in the same plane are provided on upper frame, the middle part of upper frame is arranged in first fixed pulley, the end of upper frame is arranged in second fixed pulley, bracket, which is located in a side frame body of the second fixed pulley, is provided with hoist engine, the wirerope of hoist engine is connected with suspender after passing sequentially through the second fixed pulley and the first fixed pulley, suspender is for connecting steel reinforcement cage.The utility model has prevented the high-order resistance phenomenon that may occur during lifting by crane steel reinforcement cage using crane.
Description
Technical field
The utility model belongs to construction site apparatus field, and in particular to a kind of limited headroom descending reinforcing cage lifting peace
Assembling device.
Background technique
Cast-in-place concrete pile is widely used because it has many advantages, such as, especially with the filling concrete of steel reinforcement cage
Stake.The construction process of pile foundation perfusion includes pore-forming, descending reinforcing cage, casts, pile extension.Due to designing pile length generally compared with
Greatly, while in view of the processing length and hoist length of steel reinforcement cage, may be related to steel reinforcement cage connects cage step, to meet
The long needs of stake.During the processing of steel reinforcement cage and lower section installation process, requires to use hanging device and cooperated.Currently
The construction equipment generally used in construction is mainly packaged type crane, crane for general construction landforms operability compared with
By force, but crane due to large arm it is longer, need sufficiently high operating space during lifting.And the setting point of installed steel reinforcement cage
When under the conditions of limited headroom, crane operation is since there are steric restrictions can not play its effect.
Summary of the invention
The utility model can not be unable to complete normally to solve pile foundation steel bar cage under the conditions of limited headroom using crane
The problem of lifting operation, provides a kind of limited headroom descending reinforcing cage lifting mounting device.
The utility model is achieved by the following technical solution: a kind of limited headroom descending reinforcing cage lifting mounting device,
Boom hoisting main body including being in truncated rectangular pyramids structure setting, boom hoisting main body successively include upper frame, bracket and bottom from top to bottom
Frame, bracket are symmetrically arranged inclination frame body, are provided with the first fixed pulley and the second fixed pulley being generally aligned in the same plane on upper frame,
The middle part of upper frame is arranged in first fixed pulley, and the end of upper frame is arranged in the second fixed pulley, and bracket is located at the one of the second fixed pulley
It is provided with hoist engine in side frame body, the wirerope of hoist engine is passed sequentially through to be connected with after the second fixed pulley and the first fixed pulley and be hung
Tool, suspender is for connecting steel reinforcement cage.
Upper frame includes the first square rack, and the first square rack upper middle position is fixed with two horizontal section steels, and two
It is fixed with connecting shaft in the middle part of horizontal section steel, the first fixed pulley is provided in connecting shaft.
Chassis includes the second square rack, is provided with two support rods in the plane where the second square rack.
It is fixed with horizontally disposed cross-brace between two adjacent brackets, cross-brace totally three, positioned at the two of lower part
Root cross-brace is for installing hoist engine.
The utility model needs to consign steel reinforcement cage to steel reinforcement cage setting point using hook machine before use, for subsequent steel
It is the lifting of muscle cage, easy for installation, the utility model need to be moved to stake holes top and make axle center and the stake holes of the first fixed pulley
Center is located at same vertical line.It need to guarantee that suspender can form effective connection with stirrup at the top of steel reinforcement cage simultaneously.
The utility model has the beneficial effect that compared with prior art
The utility model structure is simple, cost performance is high, and whole frame body height can be carried out according to the head room of corresponding position
Setting has prevented the high-order resistance phenomenon that may occur during lifting by crane steel reinforcement cage using crane.Meanwhile the utility model is grasped
Make it is easy, after suspender is transferred by hoist engine and is fixedly connected with steel reinforcement cage top by operator, then pass through hoist engine by its
Slowly lifting, whole operation only need 1~2 operator can be completed, greatly reduce construction cost.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the structural representation top view of upper frame in Fig. 1;
Fig. 3 is the structural representation top view of chassis in Fig. 1;
Fig. 4 is the utility model operating procedure schematic diagram one;
Fig. 5 is the utility model operating procedure schematic diagram two;
Fig. 6 is the utility model operating procedure schematic diagram three.
Figure label: 1- upper frame, the first square rack of 1.1-, 1.2- horizontal section steel, 1.3- connecting shaft, 2- chassis, 2.1-
Second square rack, 2.2- support rod, 3- hoist engine, the first fixed pulley of 4-, the second fixed pulley of 5-, 6- wirerope, 7- steel reinforcement cage,
8- suspender, 9- cross-brace, 10- bracket.
Specific embodiment
The utility model is specifically addressed in referring to Fig.1~Fig. 6, a kind of limited headroom descending reinforcing cage lifting installation dress
It sets, the boom hoisting main body including being in truncated rectangular pyramids structure setting, boom hoisting main body successively includes upper frame 1, bracket from top to bottom
10 and chassis 2, bracket 10 is symmetrically arranged inclination frame body, is provided with 4 He of the first fixed pulley being generally aligned in the same plane on upper frame 1
The middle part of upper frame 1 is arranged in second fixed pulley 5, the first fixed pulley 4, and the end of upper frame 1, bracket 10 is arranged in the second fixed pulley 5
Hoist engine 3 is provided in a side frame body of the second fixed pulley 5, the wirerope 6 of hoist engine 3 passes sequentially through the second fixed pulley 5
Be connected with suspender 8 after the first fixed pulley 4, suspender 8 is for connecting steel reinforcement cage 7.Upper frame 1 include the first square rack 1.1, first
The middle position on 1.1 top of square rack is fixed with two horizontal section steels 1.2, is fixed with connection in the middle part of two horizontal section steels 1.2
Axis 1.3 is provided with the first fixed pulley 4 in connecting shaft 1.3.Chassis 2 includes the second square rack 2.1,2.1 institute of the second square rack
Plane in be provided with two support rods 2.2.Horizontally disposed cross-brace 9 is fixed between two adjacent brackets 10, it is horizontal
To support 9 totally three, two cross-braces 9 positioned at lower part are for installing hoist engine 3.
Suspender 8 is door type structure, is process using channel steel, and the middle part of suspender 8 and wirerope 6 are fixed, the two of suspender
Circular through hole, the connection type of suspender 8 and steel reinforcement cage 6 are symmetrically provided on end slot steel are as follows: one end by suspender 8 with through-hole is mobile
To the second stirrup lower part of steel reinforcement cage 6, run through through-hole with externally threaded reinforcing bar using the both ends of processing, so that reinforcing bar is stuck in
The second stirrup lower part of steel reinforcement cage 6, and nut will be screwed on respectively with externally threaded reinforcing bar both ends.
The step of carrying out reinforcement cage hoisting and installation exercise using the utility model is:
The utility model is moved to stake holes position first, so that the center of suspender 8 and stake holes center are located at same vertical line;
Further, make the elongation of wirerope 6 complete the decentralization of suspender 8 by hoist engine 3, suspender 8 is connect with steel reinforcement cage 7;Into one
Step, by the slow lifting steel reinforcement cage 7 of hoist engine 3 until steel reinforcement cage 7 and ground are detached from, the so far lifting of completion steel reinforcement cage 7.
After the completion of lifting, the center to steel reinforcement cage 7 relative to stake holes is checked, and confirms error in controlled range
Afterwards, the decentralization of steel reinforcement cage 7 is completed by operation hoist engine 3.
Claims (4)
1. a kind of limited headroom descending reinforcing cage lifts by crane mounting device, the boom hoisting main body including being in truncated rectangular pyramids structure setting,
Be characterized in that: boom hoisting main body includes successively from top to bottom upper frame (1), bracket (10) and chassis (2), and bracket (10) is symmetrical
The inclination frame body of setting, is provided with the first fixed pulley (4) and the second fixed pulley (5) being generally aligned in the same plane on upper frame (1), and first
Fixed pulley (4) setting is at the middle part of upper frame (1), and in the end of upper frame (1), bracket (10) is located at for the second fixed pulley (5) setting
It is provided in one side frame body of two fixed pulleys (5) hoist engine (3), the wirerope (6) of hoist engine (3) passes sequentially through the second fixed pulley
(5) and after the first fixed pulley (4) it is connected with suspender (8), suspender (8) is for connecting steel reinforcement cage (7).
2. limited headroom descending reinforcing cage according to claim 1 lifts by crane mounting device, it is characterised in that: upper frame (1) includes
First square rack (1.1), the middle position on the first square rack (1.1) top are fixed with two horizontal section steels (1.2), and two
It is fixed with connecting shaft (1.3) in the middle part of horizontal section steel (1.2), the first fixed pulley (4) is provided in connecting shaft (1.3).
3. limited headroom descending reinforcing cage according to claim 2 lifts by crane mounting device, it is characterised in that: chassis (2) includes
Second square rack (2.1) is provided with two support rods (2.2) in the plane where the second square rack (2.1).
4. limited headroom descending reinforcing cage according to claim 3 lifts by crane mounting device, it is characterised in that: two adjacent branch
It is fixed between frame (10) horizontally disposed cross-brace (9), cross-brace (9) totally three, two cross-braces positioned at lower part
(9) for installing hoist engine (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920136498.2U CN209567737U (en) | 2019-01-27 | 2019-01-27 | Limited headroom descending reinforcing cage lifts by crane mounting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920136498.2U CN209567737U (en) | 2019-01-27 | 2019-01-27 | Limited headroom descending reinforcing cage lifts by crane mounting device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209567737U true CN209567737U (en) | 2019-11-01 |
Family
ID=68333126
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920136498.2U Active CN209567737U (en) | 2019-01-27 | 2019-01-27 | Limited headroom descending reinforcing cage lifts by crane mounting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209567737U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111847264A (en) * | 2020-08-11 | 2020-10-30 | 中铁第一勘察设计院集团有限公司 | Low-clearance steel reinforcement cage hoisting device and construction method thereof |
-
2019
- 2019-01-27 CN CN201920136498.2U patent/CN209567737U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111847264A (en) * | 2020-08-11 | 2020-10-30 | 中铁第一勘察设计院集团有限公司 | Low-clearance steel reinforcement cage hoisting device and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109231023B (en) | Method for installing jib system of portal crane | |
CN207361651U (en) | Aircushion vehicle jack up unit | |
CN209567737U (en) | Limited headroom descending reinforcing cage lifts by crane mounting device | |
CN206161433U (en) | Assembly pulley formula pneumatic cylinder loading test device | |
CN110387831A (en) | T beam reeving steel strands method | |
CN202296907U (en) | Suspension arm balanced movable arm tower crane capable of luffing based on steel rope traction | |
CN201793330U (en) | Gantry hanger frame device | |
CN206015665U (en) | Movable reinforcement cage installs equipment | |
CN107720569A (en) | One kind is removed inner climbing crane tower and hung with masts type roofing | |
CN105819352B (en) | Lifting device for detachable door type mast building and construction method thereof | |
CN209702166U (en) | A kind of sound barrier plate simply installs equipment | |
CN208024056U (en) | A kind of double flat arm ground type pole | |
CN108545629B (en) | Utilize the construction method of tower crane lifting girder truss | |
CN214653190U (en) | Adjustable portable lifting device | |
CN102745564B (en) | Lift strength tester | |
CN206232340U (en) | Energy-saving lowering or hoisting gear | |
CN105060124B (en) | Intra-frame portal crane system and hoisting use method thereof | |
CN113387279A (en) | Circular rail crane and assembling method thereof | |
CN208361796U (en) | For cooperating the device of tower crane lifting girder truss | |
CN205546570U (en) | Novel tuber pipe go up and down device | |
CN202322137U (en) | Telescopic hanger | |
CN216638734U (en) | Lifting appliance for bridge anti-net-throwing construction | |
CN205555924U (en) | A system's device for high altitude dismantlement tower crane | |
CN220100711U (en) | Beam reinforcement lifting supporting device | |
CN220926075U (en) | Portal crane for PC assembly type building |