CN209538742U - A kind of swimming pool brick layer infiltration repairing construction device - Google Patents

A kind of swimming pool brick layer infiltration repairing construction device Download PDF

Info

Publication number
CN209538742U
CN209538742U CN201822039328.0U CN201822039328U CN209538742U CN 209538742 U CN209538742 U CN 209538742U CN 201822039328 U CN201822039328 U CN 201822039328U CN 209538742 U CN209538742 U CN 209538742U
Authority
CN
China
Prior art keywords
swimming pool
tool
breakthrough
jointing agent
adhesive layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822039328.0U
Other languages
Chinese (zh)
Inventor
陈文俊
潘慧卫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201822039328.0U priority Critical patent/CN209538742U/en
Application granted granted Critical
Publication of CN209538742U publication Critical patent/CN209538742U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model provides a kind of swimming pool brick layer infiltration repairing construction device, belongs to building decoration technology field, is to provide a kind of short time limit, the swimming pool brick layer infiltration method for maintaining that expense is low, pollution is few.The device includes cutting tool, leakage detection tool and fix tool;Swimming pool is filled to by this method first to be flooded at pond bank 2/3, and the breakthrough of waste canal is looked for and record;Then leakage detection is carried out according to the breakthrough of record, cuts the jointing agent at each breakthrough until exposing adhesive layer, and continue to blow into adhesive layer, until bubble occurs in swimming pool inner wall, each point for bubble occur is recorded as permeation site;It is finally discharged water according to the most deep permeation site at record position, water level is put to bottom of pond bottom of pond, and construction personnel enters in swimming pool, cuts the jointing agent of permeation site surrounding, and fill up plugging mortar, closely knit with jointing agent;Net swimming pool fills water after jointing agent solidification, if repairing without infiltration phenomenon to the breakthrough at waste canal.

Description

A kind of swimming pool brick layer infiltration repairing construction device
Technical field
The utility model relates to building decoration technology fields, and in particular to a kind of swimming pool brick layer infiltration repairing construction device.
Background technique
Swimming pool is injected water into pond after the completion of patch block conserves by professional unit, at this moment often at the furrow bank of waste canal The phenomenon that seeping water causes water circulating apparatus constantly to operate, and causes energy waste.
In general, the processing mode for leakage includes: first is that injecting glue method reparation, this recovery technique are often used in building In structure.Advantage is to facilitate, and the repairing construction time is short, but disadvantage has after reparation it is also obvious that as effect is held time shorter Yellow liquid exudation causes facing pollution etc..Structure sheaf is gone to second is that the decorative brick face of bulk portion is all removed, is then being tied Again the repairing construction that waterproof carries out decorative cover again is smeared on structure layer, though can thoroughly solve the problems, such as leakage in this way, is done past It is longer toward the repairing construction period, it brings inconvenience to the use of owner.
For this phenomenon, need that a kind of short time limit, expense is low and reduces the swimming pool brick layer of water pollution infiltration maintenance side Case.
The information disclosed in the background technology section is intended only to increase the understanding to the general background of the utility model, and It is not to be construed as recognizing or implying in any form that the information is the prior art well known to persons skilled in the art.
Utility model content
The purpose of the utility model is to provide a kind of swimming pool brick layer infiltration repairing construction devices, find breakthrough by observation Afterwards, without removing architectural surface, it is only necessary to be cut to the jointing agent of stitching portion between adjacent architectural surface, then pass through smearing Leak stopping proprietary material is blocked, and is finally repaired to the jointing agent of defect, can both be saved the time in this way, while using Proprietary material is non-toxic material, use will not can generate pollution to water body in water, will not damage to human body.
To achieve the goals above, the technical solution of the utility model is:
A kind of swimming pool brick layer infiltration prosthetic device, it includes:
Tool is cut, the tool that cuts includes " a word tool " and hammer, can cut swimming by the tool that cuts The jointing agent at jointing agent and swimming pool inner wall permeation site at the waste canal breakthrough of pond exposes adhesive layer;
Leakage detection tool, in use, need at water submerged pond bank 2/3, the leakage detection tool includes air pump and gas injection needle, described Gas injection needle is connect by rubber tube with the air pump, and the adhesive layer at the gas injection needle and swimming pool waste canal breakthrough, which is inserted into, to be connected It connects, open air pump and increases pressure, the permeation site of swimming pool inner wall is enabled to bubble occur;And
Fix tool, the fix tool include plugging mortar and jointing agent, the plugging mortar be set to breakthrough and The outside of adhesive layer forms plugging mortar layer at permeation site, and the jointing agent is used for closely knit plugging mortar layer.
Compared with prior art, the utility model is beneficial has the technical effect that
Device is repaired in swimming pool brick layer infiltration provided by the utility model, including cuts tool, leakage detection tool and fix tool, is grasped Make simplicity, construction personnel only needs common hand-operated tools, and when carrying out repairing construction, swimming pool is filled to by it first to be flooded At pond bank 2/3, the waste canal of swimming pool surrounding is observed, breakthrough is found and records;Then according to the breakthrough marked at waste canal Leakage detection is carried out, the jointing agent at each breakthrough is cut until exposing adhesive layer, and continue to blow into adhesive layer, until swimming pool There is bubble in inner wall, and each point for bubble occur is recorded as permeation site;Finally put according to the most deep permeation site at record position Water, water level are put to bottom of pond, and construction personnel enters in swimming pool, the jointing agent of permeation site surrounding are cut, and fill up plugging mortar, with hook It is closely knit to stitch agent;Net swimming pool fills water after jointing agent solidification, if repairing without infiltration phenomenon to the breakthrough at waste canal It mends.The construction method is energy-saving without cutting finish coat, shortens repair time, reduces construction manpower consumption, same to time The about generation of building waste, used jointing agent and plugging mortar are non-toxic material, will not pollute water body in swimming pool, are had There is preferably promotional value.
Further, the filling thickness of the plugging mortar is 8mm~10mm.Certainly, it is contemplated that swimming pool is in use process In to fill water be normality, hydraulic pressure is bigger, and in order to guarantee to repair plugging effect, the thickness of plugging mortar will meet design requirement.
Further, the swimming pool pool wall successively includes structure sheaf, waterproof protective layer, adhesive layer and finish coat, wherein Jointing agent is filled between adjacent finish coat at brickwork joint.That is, there is no waterproof measure at adhesive layer, finish coat and adhesive layer it Between also without waterproof measure, the brickwork joint between finish coat passes through jointing agent and fills.
Further, the finish coat on swimming pool pool wall top is made by anti-skid brick.In order to guarantee swimming pool in use, The walking safety of user of service, the finish coat on swimming pool pool wall top need to be made of anti-skid brick.
Detailed description of the invention
Fig. 1 is the use signal of leakage detection tool in the prosthetic device of swimming pool brick layer infiltration in an embodiment of the present invention Figure;
Fig. 2 is the structural representation of swimming pool inner wall in swimming pool brick layer infiltration method for repairing and constructing in an embodiment of the present invention Figure.
In figure:
11- structure sheaf;12- waterproof protective layer;13- adhesive layer;14- finish coat;21- plugging mortar layer;22- dense layer; 31- air pump;32- gas injection needle;33- rubber tube;40- waste canal.
Specific embodiment
Below in conjunction with the drawings and specific embodiments to the utility model proposes swimming pool brick layer infiltration repairing construction device make It is further described.According to following explanation and claims, will be become apparent from feature the advantages of the utility model.It needs to illustrate , attached drawing is all made of very simplified form and using non-accurate ratio, only conveniently, lucidly to aid in illustrating originally The purpose of utility model embodiment.For sake of convenience, "upper" described below, "lower" are consistent with the upper and lower direction of attached drawing, But this can't be the limitation of technical solutions of the utility model.
Embodiment one
Below with reference to Fig. 1 and Fig. 2, the structure composition of the swimming pool brick layer infiltration prosthetic device of the utility model is described in detail.
Fig. 1 and Fig. 2 are please referred to, swimming pool brick layer infiltration prosthetic device, it includes the tool that cuts, leakage detection tool and reparation work Tool, the tool that cuts include " a word tool " and hammer, can cut hook at 40 breakthrough of swimming pool waste canal by cutting tool The jointing agent at agent and swimming pool inner wall permeation site is stitched, adhesive layer 13 is exposed;Leakage detection tool is in use, need water to flood pond bank 2/ At 3, leakage detection tool includes air pump 31 and gas injection needle 32, and gas injection needle 32 is connect by rubber tube 33 with air pump 31, gas injection needle 32 and Adhesive layer 13 at 40 breakthrough of swimming pool waste canal is inserted into connection, opens air pump 31 and increases pressure, enables to swimming pool inner wall Permeation site there is bubble;Fix tool includes plugging mortar and jointing agent, and plugging mortar is set at breakthrough and permeation site The outside of adhesive layer forms plugging mortar layer 21, and jointing agent is used for closely knit plugging mortar layer 21, to form dense layer 22.Pass through Being used cooperatively for tool, leakage detection tool and fix tool is cut, without cutting the finish coat 14 of breakthrough at swimming pool waste canal 40, It, can be after finding permeation site and marking, to permeation site four without the finish coat 14 cut at swimming pool inner wall permeation site The brickwork joint in week cuts part jointing agent to adhesive layer 13, and smears plugging mortar, closely knit with jointing agent, can be completed to swimming pool brick The reparation of layer infiltration.
In the present embodiment, it is highly preferred that swimming pool pool wall successively includes structure sheaf 11, waterproof protective layer 12, adhesive layer 13 And finish coat 14, wherein fill jointing agent between adjacent finish coat 14 at brickwork joint.That is, not preventing at adhesive layer 13 Water measure, also without waterproof measure between finish coat 14 and adhesive layer 13, the brickwork joint between finish coat 14 passes through jointing agent and fills.
In the present embodiment, it is highly preferred that the finish coat 14 on swimming pool pool wall top is made by anti-skid brick.In order to guarantee In use, the walking of user of service is safe, the finish coat 14 on swimming pool pool wall top needs to be made of anti-skid brick swimming pool.
Embodiment two
Please continue to refer to Fig. 1 and Fig. 2, the present embodiment additionally provides a kind of swimming pool brick layer infiltration method for repairing and constructing, the party Method includes the following steps:
Step 1: searching breakthrough
Swimming pool construct complete and by checking and accepting after, filled the water into pond, at the water submerged pond bank 2/3 until, at this time Quiet it need to put for 1 week, whether the waste canal 40 for during which appointing special messenger irregularly to observe swimming pool surrounding has the phenomenon that infiltration, if gone out The phenomenon that now seeping water marks in brick face, records each breakthrough;
Step 2: finding permeation site in swimming pool
It is marked according to breakthrough ready-made in waste canal 40 and carries out leakage detection, cut the jointing agent at each breakthrough until dew Adhesive layer 13 out, and continue to blow into adhesive layer 13, until there is bubble in swimming pool inner wall, each point note for bubble occur Record is permeation site;
Step 3: repairing construction
It is discharged water according to the most deep permeation site at record position, water level is put to bottom of pond, and is carried by construction personnel and repaired dress Set and enter in swimming pool, brickwork joint agent is carried out according to the permeation site of precedence record and is cut, the jointing agent of each permeation site surrounding into Row is cut, and plugging mortar is filled up into brickwork joint, filling up for jointing agent is carried out again after plugging mortar is dry, until closely knit;
It is examined Step 4: repairing
Water, then all breakthroughs of observational record are filled into swimming pool after jointing agent solidifies completely whether there are also leaking, such as Without infiltration phenomenon, then the jointing agent cut in waste canal 40 is repaired.
In conclusion swimming pool brick layer infiltration prosthetic device through this embodiment carries out infiltration construction, with traditional reparation side Formula is compared, and at least has following advantage:
First is that shortening repair time from repairing efficiency and at originally, having saved repair materials and construction material, reduce The generation of building waste needs at least seven working day with tradition reparation, worker is about 4~6 people by taking 50 meters of swimming pool as an example It compares, 2 workers is only needed using the method for the present embodiment, material only needs jointing agent and plugging mortar, without mortar, decoration Many repair materials such as face brick waterproof material;
Second is that from the point of view of labor intensity, traditional repair mode needs to prepare the electric hand tools such as electric hammer, electronic box, and this reality Only need " a word tool " and hammer as common hand-operated tools in the prosthetic device applied.
In the present embodiment, it is highly preferred that the method blown in step 2 includes the insertion gas injection needle 32 into adhesive layer 13, Gas injection needle 32 is connect by rubber tube 33 with air pump 31, is opened air pump 31 and is stepped up pressure.By being blown into adhesive layer 13 Enter gas, if having permeation site at swimming pool inner wall, during air blowing, the inner wall at permeation site will appear bubble.Gradually increase Plus-pressure is persistently blown to adhesive layer 13, and observation swimming pool inner wall constantly continues the position of bubbling, and records the position to penetrate into Point.
In the present embodiment, it is highly preferred that the method for recording permeation site in step 2 includes: that record swimming pool inner wall gas occurs Coordinate where bubble point, coordinate unit length are the side length of swimming pool finish coat 14.That is, it is contemplated that swimming pool inboard wall outer surface Finish coat 14 is posted, usually tapestry brick, the size of finish coat 14 is fixed, therefore can and vertical decorative cover lateral by number The quantity of brick determines the bubble point i.e. coordinate of permeation site.
In the present embodiment, it is highly preferred that cutting length along the jointing agent of permeation site surrounding in step 3 is 5cm, chisel Except depth is 2cm.In order to ensure repairing sufficiently, guarantee that repairing quality, the jointing agent in the brickwork joint of the surrounding of each permeation site are equal It need to cut, until exposing adhesive layer 13, moreover, the length that four direction is cut vertically and horizontally is very deep centered on permeation site Degree is both needed to meet reparation requirement, is subject to and slightly destroys adhesive layer 13, to break reducing as far as possible to original swimming pool inner wall In the case where bad, utmostly guarantee subsequent construction convenience and repairing quality.
In the present embodiment, pool inner water need to be emptied when it is highly preferred that being repaired in step 3.Due to checking swimming pool waste canal When 40 breakthrough, the built-in water of swimming pool and water floods at pond bank 2/3, thus repair the permeation site of swimming pool inner wall when It waits, needs to empty pool inner water, to stop the construction for cutting operating space and repair materials and maintenance space.
In the present embodiment, it is highly preferred that the filling thickness of plugging mortar is 8mm~10mm in plugging mortar layer 21.When So, it is contemplated that it is normality that swimming pool fills water in use, and hydraulic pressure is bigger, in order to guarantee to repair plugging effect, leak stopping sand The thickness of pulp layer 21 will meet design requirement.
Foregoing description is only the description to the utility model preferred embodiment, not to any limit of the scope of the utility model It is fixed.Any change, the modification that those skilled in the art does according to the disclosure above content belong to the protection model of claim It encloses.

Claims (4)

  1. The repairing construction device 1. a kind of swimming pool brick layer seeps water, which is characterized in that it includes:
    Cut tool, the tool that cuts includes " a word tool " and hammer, by it is described cut tool and can cut swimming pool overflow The jointing agent at jointing agent and swimming pool inner wall permeation site at the breakthrough of ditch exposes adhesive layer;
    Leakage detection tool, in use, needing at water submerged pond bank 2/3, the leakage detection tool includes air pump and gas injection needle, the gas injection Needle is connect by rubber tube with the air pump, and the adhesive layer at the gas injection needle and swimming pool waste canal breakthrough, which is inserted into, to be connected, and is beaten It opens air pump and increases pressure, the permeation site of swimming pool inner wall is enabled to bubble occur;And
    Fix tool, the fix tool include plugging mortar and jointing agent, and the plugging mortar is set to breakthrough and infiltration The outside of adhesive layer forms plugging mortar layer at point, and the jointing agent is used for closely knit plugging mortar layer.
  2. 2. the apparatus according to claim 1, which is characterized in that the filling thickness of the plugging mortar is 8mm~10mm.
  3. 3. the apparatus according to claim 1, which is characterized in that the swimming pool pool wall successively includes structure sheaf, waterproofing protection Layer, adhesive layer and finish coat, wherein fill jointing agent between adjacent finish coat at brickwork joint.
  4. 4. the apparatus according to claim 1, which is characterized in that the finish coat on swimming pool pool wall top is made by anti-skid brick It forms.
CN201822039328.0U 2018-12-06 2018-12-06 A kind of swimming pool brick layer infiltration repairing construction device Active CN209538742U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822039328.0U CN209538742U (en) 2018-12-06 2018-12-06 A kind of swimming pool brick layer infiltration repairing construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822039328.0U CN209538742U (en) 2018-12-06 2018-12-06 A kind of swimming pool brick layer infiltration repairing construction device

Publications (1)

Publication Number Publication Date
CN209538742U true CN209538742U (en) 2019-10-25

Family

ID=68263524

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822039328.0U Active CN209538742U (en) 2018-12-06 2018-12-06 A kind of swimming pool brick layer infiltration repairing construction device

Country Status (1)

Country Link
CN (1) CN209538742U (en)

Similar Documents

Publication Publication Date Title
CN107620312A (en) High hydraulic pressure precipitation well construction and hydrostatic slip casting method for blocking in a kind of Metro station excavation
CN109457735A (en) A kind of concrete wall and the restorative procedure in bottom plate infiltration crack
CN106381840B (en) Fracture plugging grouting method under a kind of high pressure moving water state
CN206143827U (en) Underground works crack repairing structure
CN105464194B (en) Less than the sewage network water-proof repairing construction method of level of ground water
CN110486023A (en) Tunnel defect administering method
CN107326868A (en) A kind of large reservoir concrete dam body fracture plugging method
CN108166517B (en) Well sealing method and well sealing device for super high-rise high-water pressure deep well dewatering well
CN109281491A (en) Full seam face grout construction method
CN212130547U (en) Temporary water retaining device for rapidly processing water and mud gushing problem in tunnel
CN110952644B (en) Leakage detection and leakage stoppage integrated device and process method thereof
CN107165434B (en) A kind of high-pressure slip-casting blocking method for toilet floor
CN109707176A (en) A kind of swimming pool brick layer infiltration method for repairing and constructing and device
CN209538742U (en) A kind of swimming pool brick layer infiltration repairing construction device
CN110185277A (en) The restorative procedure of existing building external wall seepage point
CN106121640A (en) The rock sample processing method of tilted stratum true triaxial pressure break physical simulation experiment and device
CN110284908B (en) Circumferential grouting plugging method in shield receiving well
CN111472568A (en) Concrete crack repairing device and method
CN109779287A (en) Microdilatancy water-proof emulsion construction technology
CN106337449A (en) Crack repairing structure for underground engineering and construction method of crack repairing structure
CN104988981B (en) A kind of well construction method of riding on present situation operation shield method drainage pipeline
CN105220695A (en) Close sand ovum layer moves water slip casting solidification construction
CN204112334U (en) Reserved shield crossing combined type foundation pit exterior-protected device
CN204715502U (en) To ride well system
CN112682073A (en) Water retaining wall structure for blocking tunnel portal in shield well and construction method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant