CN209508970U - Static pile driver for building construction - Google Patents

Static pile driver for building construction Download PDF

Info

Publication number
CN209508970U
CN209508970U CN201821654459.3U CN201821654459U CN209508970U CN 209508970 U CN209508970 U CN 209508970U CN 201821654459 U CN201821654459 U CN 201821654459U CN 209508970 U CN209508970 U CN 209508970U
Authority
CN
China
Prior art keywords
pile
rotating
fixed
pile driver
movably
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821654459.3U
Other languages
Chinese (zh)
Inventor
王乐政
马项武
毛树强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821654459.3U priority Critical patent/CN209508970U/en
Application granted granted Critical
Publication of CN209508970U publication Critical patent/CN209508970U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本实用新型涉及压桩设备技术领域,且公开了一种建筑施工静力压桩机,包括压桩机,所述压桩机的顶面固定安装有工作面,所述工作面顶面的右端固定安装有固定轴,所述固定轴的数量为四个且两个一组分为上下两组,每组所述固定轴的外表面均活动套接有转杆,两组所述转杆的左端均通过活动轴活动连接有左移动块。该建筑施工静力压桩机,通过螺纹杆、固定桩、固定轴、转杆和限位顶板之间的相互配合,转动螺纹杆可以使得固定桩沿着螺纹杆相互远离,同时使得转杆沿着固定轴旋转,从而调节两个限位顶板相互靠近,进而对两限位顶板之间的水泥桩进行限位,防止水泥桩底部上下摆动,造成压桩倾斜,提高了该压桩机的实用性。

The utility model relates to the technical field of pile-pressing equipment, and discloses a static pile-pressing machine for building construction, comprising a pile-pressing machine, a working surface is fixedly installed on the top surface of the pile-pressing machine, and the right end of the top surface There are fixed shafts fixedly installed, the number of the fixed shafts is four and two groups are divided into upper and lower groups, and the outer surface of each group of the fixed shafts is movably socketed with rotating rods, and the rotating rods of the two groups are The left ends are all movably connected with a left moving block through the movable shaft. The static pile driver for building construction, through the mutual cooperation between the threaded rod, the fixed pile, the fixed shaft, the rotating rod and the limit top plate, the rotating threaded rod can make the fixed piles move away from each other along the threaded rod, and at the same time make the rotating rod move along the threaded rod. Rotate with the fixed shaft, so as to adjust the two limit top plates close to each other, and then limit the cement pile between the two limit top plates, prevent the bottom of the cement pile from swinging up and down, causing the pile to tilt, and improve the practicality of the pile driver sex.

Description

一种建筑施工静力压桩机Static pile driver for building construction

技术领域technical field

本实用新型涉及压桩设备技术领域,具体为一种建筑施工静力压桩机。The utility model relates to the technical field of pile-pressing equipment, in particular to a static pile-pressing machine for building construction.

背景技术Background technique

利用静力压桩机自重及配重将预制桩逐节压入土中的压桩方法称为静力压桩,这种方法节约钢筋和混凝土,降低工程造价,而且施工时无噪音、无振动,无污染,对周围环境的干扰小,适用于软土地区、城市中心或建筑物密集处的桩基础工程,以及精密工厂的扩建工程,静力压桩机是建筑施工工程中必不可少的重型辅助器械。The method of pressing prefabricated piles into the soil one by one by using the self-weight and counterweight of the static pile driver is called static pile pressing. This method saves steel bars and concrete, reduces the cost of the project, and has no noise and vibration during construction. No pollution, little interference to the surrounding environment, suitable for pile foundation projects in soft soil areas, urban centers or dense buildings, and expansion projects of precision factories, static pile drivers are indispensable heavy-duty in construction projects assistive devices.

静力压桩机压桩时,先将水泥桩起吊,对准桩位,将水泥桩顶置于梁下,然后开动卷扬机牵引钢丝绳,逐渐将钢丝绳收紧,使活动压梁向下,将整个桩机的自重和配重荷载通过压梁压在水泥桩顶达到压桩目的,压桩时必须保证水泥桩整体方向垂直下压,现有的压桩机只有对桩施加压力的压梁,而水泥桩底部没有任何限位装置,为使得水泥桩能够竖直进入桩位需要人工进行辅助,由于水泥桩质量过大,人工辅助极为不便并且容易造成误差,不能保证桩垂直进入桩位,此外压桩过程中水泥桩的位置也可能发生轻微的倾斜,当水泥桩的倾斜度大于百分之一时就必须停止压桩寻找解决办法,现有压桩机内部并没有测量水泥桩倾斜角度的测量机构,人工采用仪器测量时极为不便且误差较大,不能真实反应水泥桩的倾斜度,提高施工工程的误差,降低了压桩机的实用性。When the static pile driver presses the pile, first lift the cement pile, align the pile position, place the top of the cement pile under the beam, then start the hoist to pull the wire rope, gradually tighten the wire rope, make the movable pressure beam downward, and put the whole The self-weight and counterweight load of the pile machine is pressed on the top of the cement pile by the pressure beam to achieve the purpose of pile compression. When the pile is pressed, it must be ensured that the overall direction of the cement pile is pressed down vertically. The existing pile driver only has a pressure beam that applies pressure to the pile, and There is no limit device at the bottom of the cement pile. Manual assistance is required to allow the cement pile to enter the pile vertically. Due to the excessive mass of the cement pile, manual assistance is extremely inconvenient and easily causes errors. It cannot ensure that the pile enters the pile vertically. The position of the cement pile may also be slightly inclined during the pile process. When the inclination of the cement pile is greater than 1%, the pile must be stopped to find a solution. There is no measurement of the inclination angle of the cement pile inside the existing pile driver Mechanism, it is extremely inconvenient and has large errors when manually using instruments to measure, which cannot truly reflect the inclination of the cement pile, increases the error of construction engineering, and reduces the practicability of the pile driver.

实用新型内容Utility model content

针对现有技术的不足,本实用新型提供了一种建筑施工静力压桩机,具备辅助竖直压桩减小施工误差和精确测量水泥桩倾斜度的优点,解决了现有的压桩机只有对桩施加压力的压梁,而水泥桩底部没有任何限位装置,为使得水泥桩能够竖直进入桩位需要人工进行辅助,由于水泥桩质量过大,人工辅助极为不便并且容易造成误差,不能保证桩垂直进入桩位,此外压桩过程中水泥桩的位置也可能发生轻微的倾斜,当水泥桩的倾斜度大于百分之一时就必须停止压桩寻找解决办法,现有压桩机内部并没有测量水泥桩倾斜角度的测量机构,人工采用仪器测量时极为不便且误差较大,不能真实反应水泥桩的倾斜度,提高施工工程的误差,降低了压桩机实用性的问题。Aiming at the deficiencies of the prior art, the utility model provides a static pile driver for building construction, which has the advantages of assisting vertical piles to reduce construction errors and accurately measuring the inclination of cement piles, and solves the problem of existing pile drivers. There is only a pressure beam that exerts pressure on the pile, and there is no limit device at the bottom of the cement pile. In order to make the cement pile enter the pile vertically, manual assistance is required. Due to the excessive mass of the cement pile, manual assistance is extremely inconvenient and easily causes errors. It cannot guarantee that the piles will enter the pile position vertically. In addition, the position of the cement piles may also be slightly inclined during the pile pressing process. When the inclination of the cement piles is greater than 1%, the piles must be stopped to find a solution. Existing pile presses There is no internal measuring mechanism for measuring the inclination angle of cement piles. It is extremely inconvenient to use instruments to measure manually and the error is large. It cannot truly reflect the inclination of cement piles, which increases the error of construction engineering and reduces the practicality of the pile driver.

本实用新型提供如下技术方案:一种建筑施工静力压桩机,包括压桩机,所述压桩机的顶面固定安装有工作面,所述工作面顶面的右端固定安装有固定轴,所述固定轴的数量为四个且两个一组分为上下两组,每组所述固定轴的外表面均活动套接有转杆,两组所述转杆的左端均通过活动轴活动连接有左移动块,两个所述左移动块的左侧均固定连接有固定桩,两个所述固定桩的内部均螺纹套接有螺纹杆,两个所述螺纹杆相靠近的一端固定连接有连接块,所述螺纹杆的外表面活动套接有位于连接块顶端和固定桩之间的固定帽,两组所述转杆的右端均通过活动轴活动连接有右移动块,两个所述右移动块的右侧均固定安装有限位块,两个所述限位块相靠近的一侧均固定安装有限位顶板,两个所述限位顶板相靠近的一侧通过轮轴活动安装有限位轮,所述限位顶板的正面开设有滑槽,所述滑槽位于工作面右侧底端的外部,所述滑槽内腔的左右两端固定套接有滑杆,所述滑杆的外表面活动套接有位于滑槽内部的滑块,所述滑杆的外表面活动套接有位于滑槽内部和滑块之间的弹力弹簧,所述弹力弹簧的左右两端分别与滑槽内腔的左端和滑块的左端固定连接,所述滑块的顶部固定安装有支架,所述支架的数量为两个,两个所述支架的顶端之间活动套接有转轴,所述支架左侧的顶端固定安装有观察盒,所述转轴的左端贯穿支架并延伸至观察盒的内部,所述转轴的外表面固定套接有位于两个支架之间的转板,所述转板右侧的上下两端均固定安装有测量壁,所述测量臂的右端通过轮轴活动安装有测轮。The utility model provides the following technical scheme: a static pile driver for construction, including a pile driver, a working surface is fixedly installed on the top surface of the pile driver, and a fixed shaft is fixedly installed on the right end of the top surface of the working surface , the number of the fixed shafts is four and two groups are divided into upper and lower groups, the outer surface of each group of the fixed shafts is movably socketed with rotating rods, and the left ends of the two groups of rotating rods pass through the movable shaft A left moving block is movably connected, and the left sides of the two left moving blocks are fixedly connected with fixed piles, and the insides of the two fixed piles are threaded with threaded rods, and one end of the two said threaded rods is close to each other. A connection block is fixedly connected, and the outer surface of the threaded rod is movably socketed with a fixed cap between the top of the connection block and the fixed pile. The right ends of the two sets of rotating rods are movably connected with a right moving block through a movable shaft. The right sides of the two right moving blocks are all fixedly equipped with a limit block, and the sides of the two limit blocks are fixedly installed with a limit top plate, and the sides of the two limit top plates are movable through the wheel shaft Limiting wheels are installed, the front of the limiting top plate is provided with a chute, the chute is located outside the bottom end on the right side of the working surface, the left and right ends of the inner cavity of the chute are fixedly sleeved with slide bars, the chute The outer surface of the rod is movably socketed with a slider located inside the chute, and the outer surface of the slider is movably socketed with an elastic spring located between the inside of the chute and the slider. The left and right ends of the elastic spring are respectively connected to the The left end of the inner cavity of the chute is fixedly connected with the left end of the slider, and a bracket is fixedly installed on the top of the slider. An observation box is fixedly installed on the top left side of the bracket, the left end of the rotating shaft runs through the bracket and extends to the inside of the observation box, and the outer surface of the rotating shaft is fixedly sleeved with a rotating plate located between the two brackets. Measuring walls are fixedly installed at the upper and lower ends of the right side of the plate, and a measuring wheel is movably installed at the right end of the measuring arm through a wheel shaft.

优选的,所述压桩机的右侧固定安装有滑梁,所述滑梁的右侧放置有水泥桩。Preferably, a sliding beam is fixedly installed on the right side of the pile driver, and cement piles are placed on the right side of the sliding beam.

优选的,所述测轮共有两个,且两个测轮均与水泥桩的外表面相接触。Preferably, there are two measuring wheels, and both measuring wheels are in contact with the outer surface of the cement pile.

优选的,所述转轴的左端固定安装有位于观察盒内部的固针杆,所述固针杆的外表面活动套接有指针。Preferably, the left end of the rotating shaft is fixedly equipped with a needle-fixing rod located inside the observation box, and the outer surface of the needle-fixing rod is movably fitted with a pointer.

优选的,所述观察盒的内部固定安装有观察镜,且观察镜正面的外边缘设有刻度线。Preferably, an observation mirror is fixedly installed inside the observation box, and a scale line is provided on the outer edge of the front of the observation mirror.

优选的,所述连接块的左右两侧均固定安装有旋转扭杆,两个所述旋转扭杆相远离的一端均固定安装有手柄。Preferably, rotating torsion bars are fixedly installed on both left and right sides of the connecting block, and handles are fixedly installed on the ends of the two rotating torsion bars that are far away from each other.

与现有技术对比,本实用新型具备以下有益效果:Compared with the prior art, the utility model has the following beneficial effects:

1、该建筑施工静力压桩机,通过螺纹杆、固定桩、固定轴、转杆和限位顶板之间的相互配合,转动螺纹杆可以使得固定桩沿着螺纹杆相互远离,同时使得转杆沿着固定轴旋转,从而调节两个限位顶板相互靠近,进而对两限位顶板之间的水泥桩进行限位,防止水泥桩底部上下摆动,造成压桩倾斜,提高了该压桩机的实用性。1. The static pile driver for building construction, through the mutual cooperation between the threaded rod, the fixed pile, the fixed shaft, the rotating rod and the limit top plate, the rotating threaded rod can make the fixed piles move away from each other along the threaded rod, and at the same time make the rotating The rod rotates along the fixed axis, so as to adjust the two limiting roofs to approach each other, and then limit the cement pile between the two limiting roofs, preventing the bottom of the cement pile from swinging up and down, causing the pile to tilt, and improving the pile driver. practicality.

2、该建筑施工静力压桩机,通过测量臂、转板、转轴以及支架之间的相互配合,转轴和转板可以在两个支架之间转动,当两个测轮同时接触到水泥桩时,会使得转板与水泥桩的左侧保持平行,若水泥桩倾斜时转板、转轴及转轴左端固定安装的指针也会发倾斜,工人通过观察镜上的刻度即可知道该水泥桩的倾斜程度,解决了现有压桩机内部并没有测量水泥桩倾斜角度的测量机构,人工采用仪器测量时极为不便且误差较大,不能真实反应水泥桩的倾斜度,提高施工工程的误差的问题,提高了该压桩机的实用性。2. The static pile driver for building construction, through the mutual cooperation between the measuring arm, the rotating plate, the rotating shaft and the bracket, the rotating shaft and the rotating plate can rotate between the two brackets. When the two measuring wheels touch the cement pile at the same time If the cement pile is inclined, the rotating plate, the rotating shaft and the pointer fixedly installed on the left end of the rotating shaft will also be tilted, and the worker can know the position of the cement pile through the scale on the observation mirror. The degree of inclination solves the problem that there is no measuring mechanism for measuring the inclination angle of cement piles inside the existing pile driver. It is extremely inconvenient to use instruments to measure manually and has large errors, which cannot truly reflect the inclination of cement piles and increase the error of construction projects. , improve the practicability of the pile driver.

附图说明Description of drawings

图1为本实用新型结构示意图;Fig. 1 is the structural representation of the utility model;

图2为本实用新型图1的局部俯视图;Fig. 2 is a partial top view of Fig. 1 of the utility model;

图3为本实用新型A处的结构放大示意图;Fig. 3 is the enlarged schematic diagram of the structure of A place of the utility model;

图4为本实用新型图1的局部右视图;Fig. 4 is a partial right view of Fig. 1 of the utility model;

图5为本实用新型转板的结构示意图。Fig. 5 is a structural schematic diagram of the rotating plate of the present invention.

图中:1、压桩机;2、工作面;3、固定轴;4、滑梁;5、水泥桩;6、转杆;7、活动轴;8、左移动块;9、固定桩;10、螺纹杆;11、连接块;12、旋转扭杆;13、手柄;14、固定帽;15、限位块;16、限位顶板;17、限位轮;18、滑槽;19、滑杆;20、滑块;21、弹力弹簧;22、支架;23、转轴;24、转板;25、测量臂;26、测轮;27、观察盒;28、固针杆;29、指针;30、右移动块。In the figure: 1, pile driver; 2, working face; 3, fixed shaft; 4, sliding beam; 5, cement pile; 6, rotating rod; 7, movable shaft; 8, left moving block; 9, fixed pile; 10, threaded rod; 11, connecting block; 12, rotating torsion bar; 13, handle; 14, fixed cap; 15, limiting block; 16, limiting top plate; 17, limiting wheel; 18, chute; 19, Slide bar; 20, slide block; 21, elastic spring; 22, support; 23, rotating shaft; 24, rotating plate; 25, measuring arm; 26, measuring wheel; 27, observation box; 28, fixed needle rod; 29, pointer ; 30. Move the block to the right.

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

请参阅图1-5,一种建筑施工静力压桩机,包括压桩机1,压桩机1的顶面固定安装有工作面2,压桩机1的右侧固定安装有滑梁4,滑梁4的右侧放置有水泥桩5,水泥桩5的顶端通过压梁固定,压梁既是对水泥桩施压的装置,又起到限制作用,防止水泥桩5倾倒,工作面2顶面的右端固定安装有固定轴3,固定轴3的数量为四个且两个一组分为上下两组,每组固定轴3的外表面均活动套接有转杆6,两组转杆6的左端均通过活动轴7活动连接有左移动块8,两个左移动块8的左侧均固定连接有固定桩9,两个固定桩9的内部均螺纹套接有螺纹杆10,两个螺纹杆10相靠近的一端固定连接有连接块11,连接块11的左右两侧均固定安装有旋转扭杆12,两个旋转扭杆12相远离的一端均固定安装有手柄13,螺纹杆10的外表面活动套接有位于连接块11顶端和固定桩9之间的固定帽14,两组转杆6的右端均通过活动轴7活动连接有右移动块30,两个右移动块30的右侧均固定安装有限位块15,两个限位块15相靠近的一侧均固定安装有限位顶板16,两个限位顶板16相靠近的一侧通过轮轴活动安装有限位轮17,在压桩施工过程中,水泥桩5始终向下移动,限位轮17不仅可以提供对水泥桩5水平的压力同时还有效的减少了水泥桩5对限位顶板16向下的摩擦力,有利于减少限位顶板16与水泥桩之间的摩擦,限位顶板16的正面开设有滑槽18,滑槽18位于工作面2右侧底端的外部,滑槽18内腔的左右两端固定套接有滑杆19,滑杆19的外表面活动套接有位于滑槽18内部的滑块20,滑杆19的外表面活动套接有位于滑槽18内部和滑块20之间的弹力弹簧21,弹力弹簧21始终对滑块20施加向右的压力,保证两个测轮26始终与水泥桩5的表面相接触,进而保证指针29与观察盒27相配合实时反映处水泥桩5的倾斜程度,弹力弹簧21的左右两端分别与滑槽18内腔的左端和滑块20的左端固定连接,滑块20的顶部固定安装有支架22,支架22的数量为两个,两个支架22的顶端之间活动套接有转轴23,转轴23的左端固定安装有位于观察盒27内部的固针杆28,固针杆28的外表面活动套接有指针29,支架22左侧的顶端固定安装有观察盒27,观察盒27的内部固定安装有观察镜,且观察镜正面的外边缘设有刻度线,转轴23的左端贯穿支架22并延伸至观察盒27的内部,转轴23的外表面固定套接有位于两个支架22之间的转板24,转板24右侧的上下两端均固定安装有测量壁,测量臂25的右端通过轮轴活动安装有测轮26测轮26共有两个,且两个测轮26均与水泥桩5的外表面相接触。Please refer to Figure 1-5, a static pile driver for building construction, including a pile driver 1, a working surface 2 is fixedly installed on the top surface of the pile driver 1, and a sliding beam 4 is fixedly installed on the right side of the pile driver 1 , a cement pile 5 is placed on the right side of the sliding beam 4, and the top of the cement pile 5 is fixed by a pressure beam. The right end of the surface is fixedly equipped with fixed shaft 3, the number of fixed shaft 3 is four and two groups are divided into upper and lower groups, and the outer surface of each group of fixed shaft 3 is movably socketed with rotating rod 6, and the two groups of rotating rods The left end of 6 all is connected with left moving piece 8 by movable shaft 7 movably, and the left side of two left moving pieces 8 is all fixedly connected with fixed stake 9, and the inside of two fixed stakes 9 is threadedly socketed with threaded rod 10, two One end close to each threaded rod 10 is fixedly connected with a connecting block 11, the left and right sides of the connecting block 11 are fixedly equipped with a rotating torsion bar 12, and the ends of the two rotating torsion bars 12 are fixedly equipped with a handle 13, and the threaded rod The outer surface of 10 is movably socketed with a fixed cap 14 positioned between the top of the connection block 11 and the fixed pile 9, and the right ends of two groups of rotating rods 6 are movably connected with a right moving block 30 through a movable shaft 7, two right moving blocks 30 The right side of each side is fixedly installed with a limit block 15, and the side where the two limit blocks 15 are close to each other is fixedly installed with a limit top plate 16, and the side where the two limit top plates 16 are close to is movably installed with a limit wheel 17 through the axle. During the construction process of pile pressing, the cement pile 5 moves downward all the time, and the limit wheel 17 can not only provide the horizontal pressure to the cement pile 5, but also effectively reduce the downward friction force of the cement pile 5 to the limit top plate 16, thereby effectively Help to reduce the friction between the limit top plate 16 and the cement pile, the front of the limit top plate 16 is provided with a chute 18, the chute 18 is located at the outside of the bottom end on the right side of the working surface 2, and the left and right ends of the chute 18 inner cavity are fixed sleeves A slide bar 19 is connected, the outer surface of the slide bar 19 is movably socketed with a slider 20 located inside the chute 18 , and the outer surface of the slide bar 19 is movably socketed with an elastic spring located between the inside of the chute 18 and the slide block 20 21. The elastic spring 21 always exerts rightward pressure on the slider 20 to ensure that the two measuring wheels 26 are always in contact with the surface of the cement pile 5, thereby ensuring that the pointer 29 cooperates with the observation box 27 to reflect the inclination of the cement pile 5 in real time The left and right ends of the elastic spring 21 are respectively fixedly connected with the left end of the inner chamber of the chute 18 and the left end of the slider 20. The top of the slider 20 is fixedly equipped with a bracket 22. The number of brackets 22 is two, and the two brackets 22 A rotating shaft 23 is movably socketed between the top ends of the rotating shaft 23, and a needle-fixing rod 28 located inside the viewing box 27 is fixedly installed on the left end of the rotating shaft 23. The outer surface of the needle-fixing rod 28 is movably socketed with a pointer 29, and the top of the left side of the bracket 22 is fixed. Observation box 27 is installed, and the inside of observation box 27 is fixedly equipped with observation mirror, and the outer edge of observation mirror front is provided with scale line, and the left end of rotating shaft 23 runs through support 22 and extends to the inside of observation box 27, and the outer surface of rotating shaft 23 The fixed socket is provided with a rotating plate 24 between the two supports 22, and the upper and lower ends of the right side of the rotating plate 24 are fixed and installed. Measuring wall is housed, and the right end of measuring arm 25 is equipped with surveying wheel 26 surveying wheel 26 and has two altogether by wheel shaft activity, and two surveying wheels 26 all contact with the outer surface of cement pile 5.

使用时,首先通过压桩机1内部的吊揽将水泥桩吊起并放置在滑梁4的右侧,之后旋转手柄13转动螺纹杆10,螺纹杆10可以使得固定桩9沿着螺纹杆10相互靠近或远离,并使得转杆6沿着固定轴3旋转,调节两个限位顶板16相互靠近并与水泥桩相互接触,然后旋转固定帽14限制螺纹杆10旋转,实现两限位顶板16对水泥桩底部的固定,保证水泥桩底部和顶部保持竖直,最后启动机器将水泥桩下压,下压过程中,两个测轮26同时接触到水泥桩,使得转板24与水泥桩的左侧保持平行,若水泥桩倾斜时转板24、转轴23及转轴23左端固定安装的指针29也会发倾斜,工人通过观察镜上的刻度即可知道该水泥桩的倾斜程度。During use, first the cement pile is hoisted and placed on the right side of the slide beam 4 by the suspension inside the pile driver 1, and then the rotating handle 13 turns the threaded rod 10, and the threaded rod 10 can make the fixed pile 9 move along the threaded rod 10. Close to or far away from each other, and make the rotating rod 6 rotate along the fixed shaft 3, adjust the two limit top plates 16 to approach each other and contact with the cement pile, and then rotate the fixed cap 14 to limit the rotation of the threaded rod 10 to realize the two limit top plates 16 To fix the bottom of the cement pile, ensure that the bottom and top of the cement pile remain vertical, and finally start the machine to press down the cement pile. During the downward pressure, the two measuring wheels 26 contact the cement pile at the same time, so that the rotation plate 24 and the cement pile The left side remains parallel, if the pointer 29 that rotating plate 24, rotating shaft 23 and rotating shaft 23 left ends are fixedly installed also can send tilting when cement pile tilts, the worker can know the degree of inclination of this cement pile by the scale on the observation mirror.

需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。It should be noted that in this article, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that there is a relationship between these entities or operations. There is no such actual relationship or order between them. Furthermore, the term "comprises", "comprises" or any other variation thereof is intended to cover a non-exclusive inclusion such that a process, method, article, or apparatus comprising a set of elements includes not only those elements, but also includes elements not expressly listed. other elements of or also include elements inherent in such a process, method, article, or device.

尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those skilled in the art can understand that various changes and modifications can be made to these embodiments without departing from the principle and spirit of the present invention , replacements and modifications, the scope of the present utility model is defined by the appended claims and their equivalents.

Claims (6)

1.一种建筑施工静力压桩机,包括压桩机(1),其特征在于:所述压桩机(1)的顶面固定安装有工作面(2),所述工作面(2)顶面的右端固定安装有固定轴(3),所述固定轴(3)的数量为四个且两个一组分为上下两组,每组所述固定轴(3)的外表面均活动套接有转杆(6),两组所述转杆(6)的左端均通过活动轴(7)活动连接有左移动块(8),两个所述左移动块(8)的左侧均固定连接有固定桩(9),两个所述固定桩(9)的内部均螺纹套接有螺纹杆(10),两个所述螺纹杆(10)相靠近的一端固定连接有连接块(11),所述螺纹杆(10)的外表面活动套接有位于连接块(11)顶端和固定桩(9)之间的固定帽(14),两组所述转杆(6)的右端均通过活动轴(7)活动连接有右移动块(30),两个所述右移动块(30)的右侧均固定安装有限位块(15),两个所述限位块(15)相靠近的一侧均固定安装有限位顶板(16),两个所述限位顶板(16)相靠近的一侧通过轮轴活动安装有限位轮(17),所述限位顶板(16)的正面开设有滑槽(18),所述滑槽(18)位于工作面(2)右侧底端的外部,所述滑槽(18)内腔的左右两端固定套接有滑杆(19),所述滑杆(19)的外表面活动套接有位于滑槽(18)内部的滑块(20),所述滑杆(19)的外表面活动套接有位于滑槽(18)内部和滑块(20)之间的弹力弹簧(21),所述弹力弹簧(21)的左右两端分别与滑槽(18)内腔的左端和滑块(20)的左端固定连接,所述滑块(20)的顶部固定安装有支架(22),所述支架(22)的数量为两个,两个所述支架(22)的顶端之间活动套接有转轴(23),所述支架(22)左侧的顶端固定安装有观察盒(27),所述转轴(23)的左端贯穿支架(22)并延伸至观察盒(27)的内部,所述转轴(23)的外表面固定套接有位于两个支架(22)之间的转板(24),所述转板(24)右侧的上下两端均固定安装有测量壁,所述测量臂(25)的右端通过轮轴活动安装有测轮(26)。1. a static pile driver for building construction, comprising pile driver (1), is characterized in that: the top surface of described pile driver (1) is fixedly installed with working surface (2), and described working surface (2) ) The right end of the top surface is fixedly equipped with a fixed shaft (3), the number of the fixed shaft (3) is four and two groups are divided into two groups, the outer surface of each group of the fixed shaft (3) is Rotating rod (6) is movably socketed, and the left ends of two groups of said rotating rods (6) are movably connected with left moving block (8) through movable shaft (7), and the left ends of two described left moving blocks (8) The sides are fixedly connected with fixed piles (9), and the insides of the two fixed piles (9) are threaded with threaded rods (10), and one end of the two said threaded rods (10) is fixedly connected with a connecting rod (10). Block (11), the outer surface of the threaded rod (10) is movably socketed with a fixed cap (14) between the top of the connecting block (11) and the fixed pile (9), and the two sets of rotating rods (6) The right end of each is movably connected with a right moving block (30) by a movable shaft (7), and the right sides of the two right moving blocks (30) are fixedly equipped with a limit block (15), and the two limit blocks ( 15) Limiting top plates (16) are fixedly installed on the adjacent side, and limited wheels (17) are installed on the adjacent side of the two limiting top plates (16) through the wheel shaft, and the limiting top plates (16) ) is provided with a chute (18) on the front, and the chute (18) is located outside the bottom end on the right side of the working surface (2), and the left and right ends of the inner chamber of the chute (18) are fixedly sleeved with slide bars ( 19), the outer surface of the slide bar (19) is movably socketed with a slider (20) located inside the chute (18), and the outer surface of the slide bar (19) is movably socketed with a slide block (20) located in the chute (18). ) inside and the elastic spring (21) between the slide block (20), the left and right ends of the elastic spring (21) are respectively fixedly connected with the left end of the inner cavity of the chute (18) and the left end of the slide block (20), A bracket (22) is fixedly installed on the top of the slider (20), the number of the brackets (22) is two, and a rotating shaft (23) is movably sleeved between the tops of the two brackets (22), The top on the left side of the support (22) is fixedly equipped with an observation box (27), and the left end of the rotating shaft (23) runs through the support (22) and extends to the inside of the observation box (27). The outer surface is fixedly sleeved with a rotating plate (24) between the two brackets (22), the upper and lower ends of the right side of the rotating plate (24) are fixedly equipped with measuring walls, and the measuring arm (25) The right end is movably equipped with measuring wheel (26) by the axle. 2.根据权利要求1所述的一种建筑施工静力压桩机,其特征在于:所述压桩机(1)的右侧固定安装有滑梁(4),所述滑梁(4)的右侧放置有水泥桩(5)。2. A kind of building construction static pile driver according to claim 1, is characterized in that: the right side of described pile driver (1) is fixedly installed with sliding beam (4), and described sliding beam (4) The right side of is placed with cement stake (5). 3.根据权利要求1所述的一种建筑施工静力压桩机,其特征在于:所述测轮(26)共有两个,且两个测轮(26)均与水泥桩(5)的外表面相接触。3. A kind of building construction static pile driver according to claim 1, is characterized in that: described surveying wheel (26) has two, and two surveying wheels (26) are all connected with cement pile (5) external surfaces in contact. 4.根据权利要求1所述的一种建筑施工静力压桩机,其特征在于:所述转轴(23)的左端固定安装有位于观察盒(27)内部的固针杆(28),所述固针杆(28)的外表面活动套接有指针(29)。4. A kind of building construction static pile driver according to claim 1, is characterized in that: the left end of described rotating shaft (23) is fixedly installed with the fixed needle rod (28) that is positioned at viewing box (27) inside, and A pointer (29) is movably socketed on the outer surface of the needle-fixing bar (28). 5.根据权利要求1所述的一种建筑施工静力压桩机,其特征在于:所述观察盒(27)的内部固定安装有观察镜,且观察镜正面的外边缘设有刻度线。5. A static pile driver for building construction according to claim 1, characterized in that: an observation mirror is fixedly installed inside the observation box (27), and a scale line is provided on the outer edge of the front of the observation mirror. 6.根据权利要求1所述的一种建筑施工静力压桩机,其特征在于:所述连接块(11)的左右两侧均固定安装有旋转扭杆(12),两个所述旋转扭杆(12)相远离的一端均固定安装有手柄(13)。6. A kind of static pile driver for building construction according to claim 1, characterized in that: the left and right sides of the connecting block (11) are fixedly equipped with rotating torsion bars (12), and the two rotating One end of the torsion bar (12) that is far away from each other is fixedly equipped with a handle (13).
CN201821654459.3U 2018-10-11 2018-10-11 Static pile driver for building construction Expired - Fee Related CN209508970U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821654459.3U CN209508970U (en) 2018-10-11 2018-10-11 Static pile driver for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821654459.3U CN209508970U (en) 2018-10-11 2018-10-11 Static pile driver for building construction

Publications (1)

Publication Number Publication Date
CN209508970U true CN209508970U (en) 2019-10-18

Family

ID=68192109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821654459.3U Expired - Fee Related CN209508970U (en) 2018-10-11 2018-10-11 Static pile driver for building construction

Country Status (1)

Country Link
CN (1) CN209508970U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111472338A (en) * 2020-04-17 2020-07-31 孙景辉 Device for detecting bearing capacity of pile-soil composite foundation
CN115288134A (en) * 2022-09-02 2022-11-04 青建总承包建设有限公司 Hydraulic static pile pressing device for building construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111472338A (en) * 2020-04-17 2020-07-31 孙景辉 Device for detecting bearing capacity of pile-soil composite foundation
CN115288134A (en) * 2022-09-02 2022-11-04 青建总承包建设有限公司 Hydraulic static pile pressing device for building construction

Similar Documents

Publication Publication Date Title
CN205301303U (en) Adjustable angle's middle -size and small -size two -dimentional simulation test test bench
CN107328689B (en) A mobile leveling high-precision testing device for concrete slump expansion testing and its testing method
CN209508970U (en) Static pile driver for building construction
CN111678772A (en) An experimental device for building bearing capacity in civil engineering
CN216668551U (en) Vertical detection equipment for building engineering construction
CN107101872A (en) Reinforced Concrete Beam Torsion Test Device
CN211477154U (en) A kind of building secondary structure foam concrete wall verticality detection device
CN209198220U (en) A retaining wall pressure test chamber
CN206696076U (en) Reinforced Concrete Beam Torsion Test Device
CN205940872U (en) Centrobaric calculating device of counter weight
CN210440913U (en) Surveying and mapping device for constructional engineering
CN209911138U (en) Stacked ring type direct shear apparatus
CN219776708U (en) A level measurement appearance for building engineering measures
CN218212455U (en) Steel structure detection device for building engineering
CN218382807U (en) Measuring device for architectural design
CN219100785U (en) Steel column positioning device
CN107815946A (en) A kind of intelligent road construction device and its method of work
CN110068304A (en) Vertical-horizontal detector
CN211651629U (en) Road and bridge construction measuring device
CN213778991U (en) Special elevation measurement device of building engineering design
CN210005049U (en) formwork supporting safety monitoring device
CN220270435U (en) A tool for measuring verticality of building construction
CN216283474U (en) A wall levelness measuring mechanism for project management project acceptance
CN219223727U (en) A special inclination measuring device for construction engineering
CN223707018U (en) Cement mortar trowelling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191018