CN209482481U - A kind of prefabricated board lifting built-in fitting - Google Patents
A kind of prefabricated board lifting built-in fitting Download PDFInfo
- Publication number
- CN209482481U CN209482481U CN201821416852.9U CN201821416852U CN209482481U CN 209482481 U CN209482481 U CN 209482481U CN 201821416852 U CN201821416852 U CN 201821416852U CN 209482481 U CN209482481 U CN 209482481U
- Authority
- CN
- China
- Prior art keywords
- sleeve barrel
- embedded sleeve
- fitting
- prefabricated board
- clamp
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model relates to a kind of prefabricated boards to lift built-in fitting, have embedded sleeve barrel;The embedded sleeve barrel is equipped with the clamp for being installed on framework of steel reinforcement;The clamp is connect by intermediate connector with embedded sleeve barrel;The intermediate connector includes flange body;The flange body is connect with embedded sleeve barrel;The clamp is fixedly connected on flange body.The utility model will conveniently and efficiently lift installation of embedded parts in place according to the needs of pre-buried position, eliminate welding sequence, and the position for carrying out lifting built-in fitting without corresponding positioning tool is fixed.
Description
Technical field
The utility model relates to prefabricated board manufacturing field, in particular to a kind of prefabricated board lifts built-in fitting.
Background technique
With the continuous development of building field, more efficient more environmentally friendly construction method is always the target that people pursue.It passes
The mode of construction that construction in a systematic way is built is generally used cast in situs, but cast in situs often brings many problems, such as construction dirt
It contaminates (solid refuse, dust, noise etc.).
Therefore, with the appearance of concrete prefabricated board, brought good characteristic is more and more built institute, team
Receive.Concrete prefabricated board not only can solve the problems such as construction pollution brought by above-mentioned cast in situs, but also be able to solve
Part mass problem (such as heat insulating ability is poor, infiltration etc.).
Concrete prefabricated board is i.e. previously prepared by way of pouring in factory, is subsequently used for in-site installation.Therefore, coagulation
Native prefabricated board only need to can be transported to different building sites by way of transport and construct.The transport of concrete prefabricated board is general
It is carried by lifting equipment.But existing haulage equipment is when lifting concrete prefabricated board, it is necessary to by multiple
Concrete prefabricated board is fixed in miscellaneous fixing tool, not only cumbersome, but also easily causes to damage to concrete prefabricated board
Wound results in the need for construction in later period repairing.
Utility model content
The purpose of the utility model is to provide a kind of quick and easy for installation, it is pre-buried that position adjusts multifarious prefabricated board lifting
Part.
Realizing the technical solution of the utility model aim is: the utility model has embedded sleeve barrel;It is characterized by: described
Embedded sleeve barrel is equipped with the clamp for being installed on framework of steel reinforcement.
Above-mentioned clamp is connect by intermediate connector with embedded sleeve barrel;The intermediate connector includes flange body;It is described to turn over
The connection of Bian Tiyu embedded sleeve barrel;The clamp is fixedly connected on flange body.
Above-mentioned intermediate connector further includes casing;Described sleeve pipe is set in the outside of embedded sleeve barrel;Edge on the inner wall of casing
Casing axis circle distribution has multiple sliding panels;One end of sliding panel is fixedly connected on internal surface of sleeve pipe, the other end and pre-buried set
The outer wall of cylinder is slidably connected;The sliding panel is radially extended along casing axis;The flange body is fixedly connected on the outer wall of casing
On.
One end that above-mentioned sliding panel and embedded sleeve barrel are slidably connected is equipped with rubber sliding block;It is set on the outer wall of the embedded sleeve barrel
The sliding slot for thering is corresponding with sliding panel and axis along embedded sleeve barrel to extend;The rubber sliding block is slidably arranged in sliding slot, and rubber
Glue sliding block and sliding slot are formed by friction to be damped.
Above-mentioned clamp includes rubber body;The open slot that can be installed on framework of steel reinforcement is offered in the rubber body.
Along casing axis circle distribution, there are four flange bodies on the outer wall of above-mentioned casing;The clamp is fixedly connected on flange
The lower surface of body.
Stopper is equipped in the hole of embedded sleeve barrel;Stopper plug is in the hole of embedded sleeve barrel.
The utility model has the effect of positive: (1) the utility model can be fixed directly with framework of steel reinforcement by clamp,
The position for fast implementing prefabricated board lifting built-in fitting is fixed, and traditional welding sequence is eliminated;And it is convenient for error correction;
(2) the utility model passes through the flange body of intermediate connecting body, and the connection that can reinforce embedded sleeve barrel and prefabricated board is strong
Degree is conducive to the safety and effectiveness of lifting;
(3) the utility model passes through the sliding of casing and embedded sleeve barrel, and lifting built-in fitting can be allowed for different-thickness
Prefabricated board, it is versatile;
(4) the utility model can be better ensured that the relative position of casing and embedded sleeve barrel, be poured by rubber sliding block
When concrete, it is ensured that the position of embedded sleeve barrel is constant, to guarantee pre-buried size constancy;
(5) the utility model can guarantee the internal screw thread of embedded sleeve barrel not by Concrete contamination by stopper.
Detailed description of the invention
In order to make the content of the utility model be easier to be clearly understood, below according to specific embodiment and combine attached
Figure, is described in further detail the utility model, wherein
Fig. 1 is the structural schematic diagram of the utility model embodiment one;
Fig. 2 is the cross-sectional view of the utility model embodiment one;
Fig. 3 is the structural schematic diagram of the utility model embodiment two;
Fig. 4 is the structural schematic diagram that stopper is arranged in the utility model embodiment one.
Specific embodiment
(embodiment one)
See that Fig. 1, Fig. 2 and Fig. 4, the utility model have embedded sleeve barrel 1;The embedded sleeve barrel 1 is equipped with intermediate connecting body
3;The intermediate connector 3 includes flange body 31 and casing 32;
Described sleeve pipe 32 is set in the outside of embedded sleeve barrel 1;It is distributed on the inner wall of casing 32 along casing axis even circumferential
There are four sliding panels 321;One end of sliding panel 321 is fixedly connected on 32 inner wall of casing, and the other end is equipped with rubber sliding block;It is described
Sliding panel 321 is radially extended along casing axis;The flange body 31 is fixedly connected on the outer wall of casing 32.
The outer wall of the embedded sleeve barrel 1 is equipped with sliding slot that is corresponding with sliding panel 321 and extending along the axis of embedded sleeve barrel 1
11;The rubber sliding block is slidably arranged in sliding slot 11, and rubber sliding block and sliding slot 11 form damping by friction.
Along casing axis circle distribution, there are four flange bodies 31 on the outer wall of described sleeve pipe 32;The lower surface of flange body 31 is set
There is the clamp 2 for being installed on framework of steel reinforcement.
The clamp 2 includes rubber body;The open slot that can be installed on framework of steel reinforcement is offered in the rubber body.
Stopper 4 is equipped in the hole of embedded sleeve barrel 1;The plug of stopper 4 is in the hole of embedded sleeve barrel 1.
(implementing two)
See that Fig. 3, the utility model have embedded sleeve barrel 1;On the outer wall of embedded sleeve barrel 1 along its circumference distribution there are four
Flange body;The lower surface of flange body 31 is equipped with the clamp 2 for being installed on framework of steel reinforcement.
The clamp 2 includes rubber body;The open slot that can be installed on framework of steel reinforcement is offered in the rubber body.
Stopper 4 is equipped in the hole of embedded sleeve barrel 1;The plug of stopper 4 is in the hole of embedded sleeve barrel 1.
Particular embodiments described above has carried out into one the purpose of this utility model, technical scheme and beneficial effects
Step is described in detail, it should be understood that being not limited to this foregoing is merely specific embodiment of the utility model
Utility model, within the spirit and principle of the utility model, any modification, equivalent substitution, improvement and etc. done should all wrap
Containing being within the protection scope of the utility model.
Claims (6)
1. a kind of prefabricated board lifts built-in fitting, have embedded sleeve barrel (1);It is used it is characterized by: the embedded sleeve barrel (1) is equipped with
In the clamp (2) being installed on framework of steel reinforcement;
The clamp (2) is connect by intermediate connector (3) with embedded sleeve barrel (1);The intermediate connector (3) includes flange body
(31);The flange body (31) connect with embedded sleeve barrel (1);The clamp (2) is fixedly connected on flange body (31).
2. a kind of prefabricated board according to claim 1 lifts built-in fitting, it is characterised in that: the intermediate connector (3) is also
Including casing (32);Described sleeve pipe (32) is set in the outside of embedded sleeve barrel (1);Along casing axis circle on the inner wall of casing (32)
Multiple sliding panels (321) are distributed with week;One end of sliding panel (321) is fixedly connected on casing (32) inner wall, the other end and pre-
The outer wall for burying sleeve (1) is slidably connected;The sliding panel (321) radially extends along casing axis;The flange body (31) is fixed
It is connected on the outer wall of casing (32).
3. a kind of prefabricated board according to claim 2 lifts built-in fitting, it is characterised in that: the sliding panel (321) and pre-
It buries one end that sleeve (1) is slidably connected and is equipped with rubber sliding block;The outer wall of the embedded sleeve barrel (1) is equipped with and sliding panel (321)
Sliding slot (11) that is corresponding and extending along the axis of embedded sleeve barrel (1);The rubber sliding block is slidably arranged in sliding slot (11), and rubber
Glue sliding block and sliding slot (11) are formed by friction to be damped.
4. to 3, a kind of one of them described prefabricated board lifts built-in fitting according to claim 1, it is characterised in that: the clamp
It (2) include rubber body;The open slot that can be installed on framework of steel reinforcement is offered in the rubber body.
5. a kind of prefabricated board according to claim 1 or 2 or 3 lifts built-in fitting, it is characterised in that: the outer wall of casing (32)
On along casing axis circle distribution there are four flange body (31);The clamp (2) is fixedly connected on the lower surface of flange body (31).
6. a kind of prefabricated board according to claim 1 or 2 lifts built-in fitting, it is characterised in that: in the hole of embedded sleeve barrel (1)
It is equipped with stopper (4);Stopper (4) plug is in the hole of embedded sleeve barrel (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821416852.9U CN209482481U (en) | 2018-08-30 | 2018-08-30 | A kind of prefabricated board lifting built-in fitting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821416852.9U CN209482481U (en) | 2018-08-30 | 2018-08-30 | A kind of prefabricated board lifting built-in fitting |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209482481U true CN209482481U (en) | 2019-10-11 |
Family
ID=68111222
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821416852.9U Expired - Fee Related CN209482481U (en) | 2018-08-30 | 2018-08-30 | A kind of prefabricated board lifting built-in fitting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209482481U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111037739A (en) * | 2019-12-25 | 2020-04-21 | 合肥中民筑友智造科技有限公司 | Prefabricated wall body bolt hole plays membrane frock |
-
2018
- 2018-08-30 CN CN201821416852.9U patent/CN209482481U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111037739A (en) * | 2019-12-25 | 2020-04-21 | 合肥中民筑友智造科技有限公司 | Prefabricated wall body bolt hole plays membrane frock |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103510640B (en) | A kind of fabricated shear wall and assembly method thereof | |
CN203639005U (en) | Reinforcing device of tower crane | |
CN106120861A (en) | A kind of assembled inspection well and installation method thereof | |
CN209482481U (en) | A kind of prefabricated board lifting built-in fitting | |
CN206784606U (en) | Adjustable built-in fitting | |
CN205346632U (en) | Pipe truss lifting device | |
CN208996210U (en) | A kind of prefabricated board | |
CN103883104B (en) | Quick-fried dry hanging article and mounting method thereof are drawn in a kind of location | |
CN104652611A (en) | Technology for embedding and fixing bolt sleeve | |
CN106436746A (en) | Prefabricated box-type substation cement foundation | |
CN204690961U (en) | Building positioning support | |
CN206428848U (en) | A kind of steel house assembling type outer wall plate installs node | |
CN206582081U (en) | A kind of refrigerating plant room is combined the unit with water circulating pump | |
CN203878756U (en) | Embedded connecting device | |
CN205226021U (en) | Circuit breaker basis rag bolt protective cap | |
CN204592635U (en) | A kind of flange with pile body mounting hole mould | |
CN203767898U (en) | Support beam of wall attaching device for tower crane | |
CN110005871B (en) | Welding structure and welding method for pipe jacking rib plate and flange | |
CN206015903U (en) | Groove built-in fitting | |
US10662640B2 (en) | Cement board | |
CN103938728B (en) | Pre-embedded connecting device | |
CN204475186U (en) | A kind of novel semicolumn template | |
US20130241199A1 (en) | Device and method for centering tubular members | |
CN203783116U (en) | Novel scaffold lacing device | |
CN205348394U (en) | Steel construction unit -installment wall body and girder steel cladding node thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191011 |