CN209440541U CN201821162881.7U CN201821162881U CN209440541U CN 209440541 U CN209440541 U CN 209440541U CN 201821162881 U CN201821162881 U CN 201821162881U CN 209440541 U CN209440541 U CN 209440541U
Authority
CN
China
Prior art keywords
fixed plate
interim
drilling platform
mounting hole
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821162881.7U
Other languages
Chinese (zh)
Inventor
何永冬
何沿志
杨祥福
唐平
黄艳红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nuclear Industry 23 Construction Co Ltd
Original Assignee
China Nuclear Industry 23 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nuclear Industry 23 Construction Co Ltd filed Critical China Nuclear Industry 23 Construction Co Ltd
Priority to CN201821162881.7U priority Critical patent/CN209440541U/en
Application granted granted Critical
Publication of CN209440541U publication Critical patent/CN209440541U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Drilling And Boring (AREA)

Abstract

The utility model belongs to drilling technical field of auxiliary equipment, and in particular to a kind of interim drilling platform.When in order to solve to carry out the punch operation of equipment mounting hole using existing method, there is a problem of that construction efficiency is low, construction operation amount is big, the utility model discloses a kind of interim drilling platforms for auxiliary bore hole operation.The interim drilling platform, including fixed plate, pressing plate and connector;The two sides up and down of plane where the fixed plate and the pressing plate are located at equipment mounting hole, and gripped by the connection of the connector and plane where equipment mounting hole;The fixed plate is equipped with drilling, and corresponding with equipment mounting hole.When carrying out auxiliary bore hole operation using the interim drilling platform of the utility model, the construction efficiency of punch operation can be improved, reduce construction operation amount.

Description

A kind of interim drilling platform
Technical field
The utility model belongs to drilling technical field of auxiliary equipment, and in particular to a kind of interim drilling platform.
Background technique
It punches and is seen everywhere in building peace industry, usually there are two types of sides when carrying out equipment fastening expansion bolt punching at present Case: one is the methods according to the punching of drawing unwrapping wire, are put in perforated surfaces according to the theoretical position of expansion bolt in drawing first Then punch position out carries out punch operation before equipment is in place;Be for second equipment in place after positional punch method, first Equipment is placed in position, carry out expanding screw is marked according to the physical location of equipment upper bolt hole after adjusting to device location Then equipment is removed carry out punch operation again by the practical punch position of bolt.
However, above two method has some problems in the actual operation process: the first drilling method is to scene Unwrapping wire precision and device fabrication precision have higher requirement, if there are deviation or device fabrications there are deviation for punching unwrapping wire, that Will lead to equipment mounting hole and can not be matched with bolt hole and is aligned, so as to cause expansion bolt can not normal mounting, then need at this time The operation such as plug-hole, unwrapping wire, punching is re-started, construction volume is greatly increased, not can guarantee punched position in this way and set Standby installation hole location exact matching alignment, so that not can guarantee expansion bolt disposably can smoothly install, leads to construction efficiency It reduces.Although the accurate positioning of bolt hole position can be improved in second of drilling method, avoid device fabrication deviation and unwrapping wire is inclined Influence of the difference to bolt hole position, but need to carry out Secondary Transport to equipment, not only increase the use of manpower and work equipment Investment increases workload, and repeatedly has bad luck and will increase the security risk of high altitude operation for the installation of altitude plant.
Utility model content
When in order to solve to carry out the punch operation of equipment mounting hole using existing method, there are construction efficiency, and low, construction is made The big problem of industry amount, the utility model proposes a kind of interim drilling platforms for auxiliary bore hole operation.The interim drilling is flat Platform, including fixed plate, pressing plate and connector;Plane is upper where the fixed plate and the pressing plate are located at equipment mounting hole Lower two sides, and gripped by the connection of the connector and plane where equipment mounting hole;The fixed plate is equipped with Drilling, and it is corresponding with equipment mounting hole.
Preferably, the connector uses bolt arrangement, and is equipped with and corresponds between the fixed plate and the pressing plate Bolt hole.
It preferably, further include filling member;The filling member is between the fixed plate and the pressing plate, for described Fixed plate carries out Auxiliary support.
It is further preferred that the filling member uses cushion block structure, and flat where the thickness of cushion block and equipment mounting hole The thickness in face is equal.
It is further preferred that the filling member is composed of the cushion block of multiple and different thickness.
Preferably, the filling member uses bolt arrangement, and with the fixed plate using being threadedly coupled, end is extended to It is contacted with the surface of the pressing plate.
Preferably, the filling member uses bolt arrangement, and with the pressing plate using being threadedly coupled, end extend to and The surface of the fixed plate contacts.
When carrying out auxiliary bore hole operation using the interim drilling platform of the utility model, have the advantages that
1, in the interim drilling platform of the utility model, by distinguishing in the two sides up and down of plane where equipment mounting hole Fixed plate and pressing plate are set, and are clamped plane where fixed plate and pressing plate and equipment mounting hole admittedly by connector It is fixed, the fixed temporary platform of installation is carried out to drilling device to be formed using fixed plate.In this way, when carrying out punch operation, The equipment for being equipped with interim drilling platform can directly be lifted in place, it then can be into using the temporary platform that fixed plate is formed The installation of row drilling device is fixed, so that saving unwrapping wire directly carries out punch operation.In this way, not only avoiding according to theoretical position When unwrapping wire punches, in fact it could happen that the problem of being actually unable to complete successfully installation, so that the efficiency and quality of construction are improved, and Back and forth having bad luck to equipment in positional punch operation, to reduce construction operation amount, improves after eliminating conventional equipment in place The safety of operation.
2, in the present invention, by setting filling member to which the spare area between fixed plate and pressing plate generates one A effective supporting point makes plane where filling member and equipment mounting hole that the support to fixed plate be collectively formed, thus increase pair The stability maintenance of fixed plate, and then guarantee the stabilization fixed to drilling device installation, improve drilling quality.
3, the interim drilling platform of the utility model, the processing is simple, easily manufactured, can be rapidly completed using live material Processing, while the connection with plane where equipment mounting hole can be rapidly completed, it is easy to operate, it is easy to use.
Detailed description of the invention
Fig. 1 is schematic cross-section when interim drilling platform is connect with equipment installation base in the present embodiment one;
Fig. 2 is the schematic diagram that interim drilling platform is connect with equipment mounting plane in the present embodiment two.
Specific embodiment
The technical solution of the utility model is described further with reference to the accompanying drawings and examples.
Embodiment one is beaten using the mounting hole on the interim drilling platform ancillary equipment installation base of the utility model Hole
As shown in connection with fig. 1, the interim drilling platform in the present embodiment, including 1, two pressing plate 2 of fixed plate and connector 3. Fixed plate 1 and pressing plate 2 are all made of plate armature, wherein fixed plate 1 is located at the top of equipment installation base 4, two pressing plates 2 Positioned at equipment installation base 4 lower section and be symmetrically distributed in the two sides of equipment mounting hole 41, while by 3 pairs of fixations of connector Plate 1 and pressing plate 2 carry out up and down through connection.At this point, using connector 3 to 4 two sides fixed plate 1 of equipment installation base and pressing plate 2 While tensioning function power, fixed plate 1 and pressing plate 2 are clamped on equipment installation base 4.At the same time, in fixed plate 1 On be additionally provided with drilling 11, and drill 11 size and location it is corresponding with equipment mounting hole 41.
The mistake of punch operation is carried out using the mounting hole on the interim drilling platform ancillary equipment installation base of the present embodiment Journey are as follows: firstly, fixed plate 1 and pressing plate 2 are gripped with equipment installation base 4, and by the drilling 11 in fixed plate 1 It is aligned with equipment mounting hole 41;Then, whole equipment is lifted to installation site, and completes to adjust the position of equipment;So Afterwards, by drilling device, such as vacuum chuck bores or magnetic drill, is fixed in fixed plate 1, drill bit is sequentially passed through drilling 11 It drills with mounting hole 41, to complete the punch operation for being directed to equipment installation base upper installing hole 41.
Preferably, in the present embodiment, connector 3 uses bolt arrangement, while setting respectively in fixed plate 1 and pressing plate 2 There is corresponding bolt hole, for connector 3 through connection.At this point, can be rapidly completed pair by the connections of bolts and nuts Fixed plate 1 is connected with the dismounting of pressing plate 2, to improve the dismounting speed between the temporary platform and equipment installation base, is improved Operating efficiency.Equally, in other embodiments, plate 1 and pressing plate 2 can also be fixed using other structures form in connector 3 Between connection, such as G-shaped clamp.
As shown in connection with fig. 1, the interim drilling platform of the present embodiment further includes two filling members 5, is located at equipment installation Between the fixed plate 1 and pressing plate 2 of 4 two sides of boss, while the thickness of filling member 5 is equal with the thickness of equipment installation base 4, and Form the symmetric relation about connector 3 in position with the equipment installation base 4 of respective side.In this way, by filling member 5 to solid The filling of rest between fixed board 1 and pressing plate 2, the i.e. filling to 3 outside rest of connector, may be implemented to fixed plate 1 Auxiliary support further increases the fastness that fixed plate 1 is fixedly clamped with equipment installation base 4, to guarantee to set drilling The fixed stability of standby installation, guarantees final borehole accuracy.
Preferably, filling member 5 uses cushion block structure in the present embodiment, by being inserted in the horizontal direction to 1 He of fixed plate Between pressing plate 2, so that the Auxiliary support to fixed plate 1 be rapidly completed.In addition, filling member 5 can also adopt a split structure, by The layer-by-layer heap of the cushion block of multiple and different thickness falls composition, so as to adjust filling member according to the gap between fixed plate 1 and pressing plate 2 5 thickness, to guarantee the stability to 1 Auxiliary support of fixed plate.
Embodiment two is punched using the mounting hole in the interim drilling platform ancillary equipment plane of the utility model
As shown in connection with fig. 2, the difference of the interim drilling platform in the present embodiment and the interim drilling platform in embodiment one It is: since mounting hole 61 is in equipment plane 6 at this time, so two pressing plates 2 in the present embodiment are respectively positioned on installation The same side in hole 61, and fixed plate 1 is located at the top of equipment plane 6, and pressing plate 2 is located at the lower section of equipment plane 6, while will consolidate Fixed board 1 is fixed on along the extending direction of equipment planar radial, to form the temporary platform for installing drilling device.
In addition, in the present embodiment, filling member 5a uses bolt arrangement, directly it is threadedly coupled with fixed plate 1, and End is extended to be contacted with 2 surface of pressing plate.In this way, during whole operation, can adjustment bolt at any time screw-in length, So as to adjust the distance between fixed plate 1 and pressing plate 2 size, guarantee what fixed plate 1 and pressing plate 2 and equipment plane 6 gripped Stablize, and then guarantees final borehole accuracy.Equally, filling member 5a can also be directly threadedly coupled with pressing plate 2, then End is extended to and is contacted with the surface of fixed plate 1, by adjusting the screw-in length of bolt, so as to adjust fixed plate 1 and pressing plate 2 The distance between size.

Claims (7)

1. a kind of interim drilling platform, which is characterized in that including fixed plate, pressing plate and connector;The fixed plate and the pressure The two sides up and down of plane where plate is located at equipment mounting hole, and pass through the connection of the connector and equipment mounting hole institute It is gripped in plane;The fixed plate is equipped with drilling, and corresponding with equipment mounting hole.
2. interim drilling platform according to claim 1, which is characterized in that the connector uses bolt arrangement, and Corresponding bolt hole is equipped between the fixed plate and the pressing plate.
3. interim drilling platform according to claim 1, which is characterized in that further include filling member;The filling member is located at Between the fixed plate and the pressing plate, for carrying out Auxiliary support to the fixed plate.
4. interim drilling platform according to claim 3, which is characterized in that the filling member uses cushion block structure, and The thickness of cushion block is equal with the thickness of plane where equipment mounting hole.
5. interim drilling platform according to claim 4, which is characterized in that the filling member by multiple and different thickness pad Block is composed.
6. interim drilling platform according to claim 3, which is characterized in that the filling member uses bolt arrangement, and With the fixed plate using being threadedly coupled, end is extended to be contacted with the surface of the pressing plate.
7. interim drilling platform according to claim 3, which is characterized in that the filling member uses bolt arrangement, and With the pressing plate using being threadedly coupled, end is extended to be contacted with the surface of the fixed plate.
CN201821162881.7U 2018-07-23 2018-07-23 A kind of interim drilling platform Active CN209440541U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821162881.7U CN209440541U (en) 2018-07-23 2018-07-23 A kind of interim drilling platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821162881.7U CN209440541U (en) 2018-07-23 2018-07-23 A kind of interim drilling platform

Publications (1)

Publication Number Publication Date
CN209440541U true CN209440541U (en) 2019-09-27

Family

ID=68008430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821162881.7U Active CN209440541U (en) 2018-07-23 2018-07-23 A kind of interim drilling platform

Country Status (1)

Country Link
CN (1) CN209440541U (en)

Similar Documents

Publication Publication Date Title
CN102632273B (en) Adjustable multi-point positioning hole making device and hole making method
CN102126145A (en) Power takeoff shift fork fixture
CN102765001A (en) Special clamp for support leg boring of development machine
CN205437901U (en) Green wood board drilling clamping device
CN209440541U (en) A kind of interim drilling platform
CN211818031U (en) Locking structure for integral aluminum alloy building template
CN208644696U (en) A kind of inclined hole perforating locator
CN102941377A (en) Reaming fixture and method of marine low speed diesel engine
CN202344294U (en) Drilling and clamping device for railway turnout flat backing plate
CN205571130U (en) Special punch press of otic placode connecting hole processing
CN213597500U (en) Wall template connection structure for building construction
CN206643619U (en) A kind of angle bar boring grab
CN103128576B (en) Railway turnout plane base plate hole-drilling chucking device and manufacturing method thereof
CN211736491U (en) Connecting device for building structure steel beam and existing concrete column
CN205977923U (en) T type frid connection structure
CN208778420U (en) A kind of simple connecting device of thin-wall construction
CN203621959U (en) Auxiliary device for precision machining of joints
CN110158672B (en) Method for mounting foundation pile high-strain stress sensor
CN207255303U (en) The quick puncher of babinet corner
CN214263586U (en) Fixing structure of stamping die
CN211142818U (en) Angle positioning device for assembling steel structure bridge web
CN218799356U (en) Flange plate jig tool used on tower crane attachment frame
CN206104960U (en) Pneumatic cylinder bottom plate drilling special fixture
CN218667889U (en) Beam column structure of steel structure factory building
CN215315850U (en) Drilling device of wallboard for steel wire rope electric block

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant