CN209412902U CN201920012923.7U CN201920012923U CN209412902U CN 209412902 U CN209412902 U CN 209412902U CN 201920012923 U CN201920012923 U CN 201920012923U CN 209412902 U CN209412902 U CN 209412902U
Authority
CN
China
Prior art keywords
cylinder
stack shell
pumping plant
integrated prefabricated
ladder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920012923.7U
Other languages
Chinese (zh)
Inventor
胡华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang Environmental Protection Technology Co Ltd
Original Assignee
Nanchang Environmental Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanchang Environmental Protection Technology Co Ltd filed Critical Nanchang Environmental Protection Technology Co Ltd
Priority to CN201920012923.7U priority Critical patent/CN209412902U/en
Application granted granted Critical
Publication of CN209412902U publication Critical patent/CN209412902U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of integrated prefabricated pumping plants, cylinder includes the first stack shell and the second stack shell, first stack shell is set to three side of upper, middle and lower of cylinder, first stack shell of the second stack shell connection three side of upper, middle and lower, the diameter of first stack shell is greater than the second stack shell, ventilation duct is set at the top of cylinder, ventilation duct one end is connected to cylinder, the other end is connect with exhaust fan, gas pressure sensor is set in cylinder, gas pressure sensor and exhausting mechatronics, ladder is fixedly installed in cylinder, sliding slot is arranged in ladder both ends, sliding block is set in sliding slot, cutting ferrule is equipped on the outside of sliding block, ladder outer upper end corresponds to the hinged bar of sliding block, torsional spring is socketed in the rotation axis of bar, pumping plant access hole is set at the top of cylinder, inspection platform plate is fixedly installed in cylinder, the utility model reduces the manufacturing process difficulty of pumping plant cylinder, and it can be to inner barrel gas Body is timely discharged.

Description

A kind of integrated prefabricated pumping plant
Technical field
The utility model relates to slaughtering animal equipment technical fields, and in particular to a kind of integrated prefabricated pumping plant.
Background technique
Pumping plant is to be provided with the hydraulic power of certain pressure and flow and the device of Pneumatic pressure power and engineering claims to pump and pump It stands engineering.The general name of the buildings such as water inlet, water outlet, the pump house of irrigation and drainage pumping station.
Current prefabricated pump station structure is various informative, and the sewage of processing is also various.But existing prefabricated pumping plant is more, and structure is complicated, Sewage is also easy to produce various gases in the siltation easy to form of the bottom of pumping plant and pumping plant, and the gas of generation is as discharge can not in time Normal service and use can be will affect.
Utility model content
(1) technical problems to be solved
In order to overcome the shortage of prior art, it is proposed that a kind of integrated prefabricated pumping plant reduces the manufacture work of pumping plant cylinder Skill difficulty, and inner barrel gas can timely be discharged.
(2) technical solution
The utility model is achieved through the following technical solutions: the utility model proposes a kind of integrated prefabricated pumping plant, Including cylinder, the cylinder includes the first stack shell and the second stack shell, and first stack shell is set to three side of upper, middle and lower of cylinder, institute The first stack shell of the second stack shell connection three side of upper, middle and lower is stated, the diameter of first stack shell is greater than the second stack shell, the cylinder top Ventilation duct is arranged in portion, and described ventilation duct one end is connected to cylinder, and the other end is connect with exhaust fan, and gas pressure is arranged in the cylinder Force snesor, the gas pressure sensor and exhausting mechatronics, the cylinder is interior to be fixedly installed ladder, the ladder both ends Sliding slot is set, sliding block is set in the sliding slot, is equipped with cutting ferrule on the outside of the sliding block, it is hinged that the ladder outer upper end corresponds to sliding block Bar, the rotation axis outside of the bar are socketed with torsional spring, and pumping plant access hole is arranged at the top of the cylinder, fixes in the cylinder Inspection platform plate is set.
Furthermore, first stack shell, the second stack shell are welded and fixed.
Furthermore, first stack shell, the second stack shell segmented welding, first stack shell and the welding of the second stack shell connect Meeting place, there are ventholes.
Furthermore, first stack shell, the second stack shell outside are equipped with lifting lug.
Furthermore, the model TOKIMEC INC-PX605 of the gas pressure sensor.
Furthermore, handrail is arranged in corresponding pumping plant access hole side at the top of the cylinder.
Furthermore, headlamp is arranged in the cylinder inner top.
(3) beneficial effect
The utility model compared with the existing technology, has the advantages that
1, cylinder is made of the first stack shell welded connecting alternate with the second stack shell, reduces the manufacturing process difficulty of cylinder.
2, the first stack shell and the second stack shell weld segmented welding, there are ventholes, just blocking can occur now by venthole As.
3, it is equipped with gas pressure sensor in cylinder, can detect the gas pressure of inner barrel, and controls exhaust fan for cylinder The pernicious gas in internal portion is extracted out in time.
4, ladder both ends are equipped with sliding block, be equipped with cutting ferrule on the outside of sliding block, and it is carry-on that cutting ferrule can be used for wearing fixed maintenance personal Protective bandage improves safety when maintenance personal enters in cylinder.
Detailed description of the invention
Fig. 1 is the utility model structure diagram.
Fig. 2 is the position A partial enlarged view in Fig. 1.
Fig. 3 is the first stack shell of the utility model and the second stack shell attachment structure schematic diagram.
1- cylinder;The first stack shell of 11-;The second stack shell of 12-;13- lifting lug;2- ventilation duct;21- exhaust fan;22- gas pressure Sensor;3- ladder;31- sliding slot;32- sliding block;33- cutting ferrule;34- bar;35- torsional spring;4- pumping plant access hole;41- maintenance is flat Platen;42- handrail;43- headlamp.
Specific embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation Example, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein is only used to explain The utility model is not used to limit the utility model.
A kind of integrated prefabricated pumping plant as shown in FIG. 1 to FIG. 3, including cylinder 1, the cylinder 1 include the first stack shell 11 with Second stack shell 12, first stack shell 11 are set to three side of upper, middle and lower of cylinder 1, and second stack shell 12 connects three side of upper, middle and lower The first stack shell 11, the diameter of first stack shell 11 is greater than the second stack shell 12, ventilation duct 2 is arranged at the top of the cylinder 1, described 2 one end of ventilation duct is connected to cylinder 1, and the other end is connect with exhaust fan 21, and gas pressure sensor 22 is arranged in the cylinder 1, The gas pressure sensor 22 is electrically connected with exhaust fan 21, ladder 3 is fixedly installed in the cylinder 1,3 both ends of ladder are set Sliding slot 31 is set, sliding block 32 is set in the sliding slot 31, is equipped with cutting ferrule 33,3 outer upper end pair of ladder on the outside of the sliding block 32 The hinged bar 34 of sliding block 32 is answered, torsional spring 35 is socketed on the outside of the rotation axis of the bar 34, pump is set at the top of the cylinder 1 It stands access hole 4, inspection platform plate 41 is fixedly installed in the cylinder 1.
Furthermore, first stack shell 11, the second stack shell 12 are welded and fixed.
Furthermore, first stack shell 11,12 segmented welding of the second stack shell, first stack shell 11 and the second stack shell There are ventholes at 12 welded connectings, and venthole is located on the stack shell of cylinder 1, to be not easy to plug.
Furthermore, first stack shell 11, be equipped with lifting lug 13 on the outside of the second stack shell 12, lifting lug 13 can be used for first The lifting of stack shell 11 and the second stack shell 12 is installed.
Furthermore, the model TOKIMEC INC-PX605 of the gas pressure sensor 22.
Furthermore, corresponded at the top of the cylinder 14 side of pumping plant access hole setting handrail 42, for service personnel from Helping when entering 1 inside of cylinder at pumping plant access hole 4.
Furthermore, headlamp 43 is arranged in 1 inner top of cylinder, can be to illuminating inside cylinder 1, easy access The progress of personnel's service work.
Working principle: the cylinder 1 of the pumping plant meets guarantor by being welded to form after the grafting alternate with the second stack shell 12 of the first stack shell 11 Intensity when cylinder 1 itself uses has been demonstrate,proved, and cylinder 1 is manufactured without whole, has greatly reduced 1 manufacturing process of cylinder Difficulty.Segmented welding when the first stack shell 11 and the second stack shell 12 weld simultaneously, weld are installed with venthole, so that logical Stomata is set on stack shell, is capable of the generation of just clogging, is influenced the ventilatory effect of cylinder 1.
In addition, 1 top closing plate of cylinder is equipped with exhaust fan 21, exhaust fan 21 is electrically connected with gas pressure sensor 22, can The air pressure inside cylinder 1 is monitored by gas pressure sensor 22, and control exhaust fan 21 passes through ventilation duct 2 for staving 1 in time Outside internal pernicious gas extraction cylinder 1.
It is additionally provided with pumping plant access hole 4 on the sealing plate at the top of cylinder 1, maintenance personal can be from it from into inside cylinder 1, to setting It is standby to be overhauled.Into when, entrance can be helped by handrail 42, and drop on inspection platform plate 41 by the climbing of ladder 3, into Row maintenance.
Maintenance personal can tie up resilient protection band in loins when climbing on ladder 3, and its both ends is passed through corresponding card It is fixed after set 33, it is fallen so as to avoid maintenance personal that unexpected layback occurs, guarantees the safety of maintenance personal.3 upper end of ladder Equipped with corresponding bar 34, bar 34 can carry out limited support to sliding block 32 under the action of torsional spring 35.
Embodiment described above is only that preferred embodiments of the present invention are described, not practical to this Novel conception and scope is defined.Without departing from the design concept of the present utility model, ordinary people in the field couple The all variations and modifications that the technical solution of the utility model is made, should fall within the protection scope of the present utility model, this reality With novel claimed technology contents, it is all described in the claims.

Claims (7)

1. a kind of integrated prefabricated pumping plant, including cylinder (1), it is characterised in that: the cylinder (1) include the first stack shell (11) with Second stack shell (12), first stack shell (11) are set to three side of upper, middle and lower of cylinder (1), in the second stack shell (12) connection In lower three sides the first stack shell (11), the diameter of first stack shell (11) is greater than the second stack shell (12), at the top of the cylinder (1) It is arranged ventilation duct (2), described ventilation duct (2) one end is connected to cylinder (1), and the other end is connect with exhaust fan (21), the cylinder (1) gas pressure sensor (22) are set in, the gas pressure sensor (22) is electrically connected with exhaust fan (21), the cylinder (1) ladder (3) are fixedly installed in, sliding slot (31) are arranged in ladder (3) both ends, sliding block (32) are set in the sliding slot (31), Cutting ferrule (33) are equipped on the outside of the sliding block (32), ladder (3) outer upper end corresponds to the hinged bar (34) of sliding block (32), described It is socketed with torsional spring (35) on the outside of the rotation axis of bar (34), pumping plant access hole (4) is set at the top of the cylinder (1), the cylinder (1) inspection platform plate (41) are fixedly installed in.
2. a kind of integrated prefabricated pumping plant according to claim 1, it is characterised in that: first stack shell (11), second Stack shell (12) is welded and fixed.
3. a kind of integrated prefabricated pumping plant according to claim 2, it is characterised in that: first stack shell (11), second There are ventholes at stack shell (12) segmented welding, first stack shell (11) and the second stack shell (12) welded connecting.
4. a kind of integrated prefabricated pumping plant according to claim 1, it is characterised in that: first stack shell (11), second Lifting lug (13) are equipped on the outside of stack shell (12).
5. a kind of integrated prefabricated pumping plant according to claim 1, it is characterised in that: the gas pressure sensor (22) Model TOKIMEC INC-PX605.
6. a kind of integrated prefabricated pumping plant according to claim 1, it is characterised in that: respective pump at the top of the cylinder (1) Stand access hole (4) side setting handrail (42).
7. a kind of integrated prefabricated pumping plant according to claim 1, it is characterised in that: cylinder (1) the inner top setting Headlamp (43).
CN201920012923.7U 2019-01-04 2019-01-04 A kind of integrated prefabricated pumping plant Active CN209412902U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920012923.7U CN209412902U (en) 2019-01-04 2019-01-04 A kind of integrated prefabricated pumping plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920012923.7U CN209412902U (en) 2019-01-04 2019-01-04 A kind of integrated prefabricated pumping plant

Publications (1)

Publication Number Publication Date
CN209412902U true CN209412902U (en) 2019-09-20

Family

ID=67942655

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920012923.7U Active CN209412902U (en) 2019-01-04 2019-01-04 A kind of integrated prefabricated pumping plant

Country Status (1)

Country Link
CN (1) CN209412902U (en)

Similar Documents

Publication Publication Date Title
CN206054220U (en) A kind of high-pressure inflating pump
CN209412902U (en) A kind of integrated prefabricated pumping plant
CN207739174U (en) A kind of deceleration and apparatus for energy recovery
CN210699529U (en) Friedel-crafts reaction hydrogen chloride tail gas absorbing device
CN206917964U (en) Without rod-type compression cylinder
CN2928139Y (en) Double body horizontal life saving escape cab
CN215445163U (en) Lifting valve for gas switching air channel
CN205191052U (en) Safety guard for pipeline
CN212383451U (en) Control system for temperature of ammonia water in ammonia water absorption tower
CN202115782U (en) Safe water seal for hydrogen peroxide working solution storage tank
CN200946094Y (en) Pneumatic oil pumping device
CN202788938U (en) Inflatable temporary alternative apparatus for mine explosion-proof door
CN207750725U (en) Skid-mounted type babinet for integrated hydrogenation system
CN207716085U (en) Gas drive pumps skid hydrogenation plant
CN215506219U (en) Waste gas emergency discharge buffer system
CN207333849U (en) A kind of safety valve
CN213018870U (en) Associated gas recovery unit for well group
CN207307045U (en) A kind of ductwork type environmental protection heptafluoro-propane automatic fire extinguishing system
CN214216932U (en) Integrated efficient air exchange system in tank car
CN110230716A (en) A kind of direct-firing low speed coal mill mixes furnace cigarette explosion-protection equipment and its working method
CN211255966U (en) Direct-discharging hot stuffy pool exhaust system
CN206722939U (en) A kind of light bus blower air inlet assembly
CN215654737U (en) Gas proportioning controller
CN217518630U (en) Low-concentration gas backheating oxidation bathing water heater
CN220632854U (en) Lifting fire monitor mechanism

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant