CN209412834U - A kind of assembled crown beam structure of foundation pit enclosure wall - Google Patents

A kind of assembled crown beam structure of foundation pit enclosure wall Download PDF

Info

Publication number
CN209412834U
CN209412834U CN201821936936.5U CN201821936936U CN209412834U CN 209412834 U CN209412834 U CN 209412834U CN 201821936936 U CN201821936936 U CN 201821936936U CN 209412834 U CN209412834 U CN 209412834U
Authority
CN
China
Prior art keywords
foundation pit
enclosure wall
pit enclosure
girder steel
beam structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821936936.5U
Other languages
Chinese (zh)
Inventor
胡琦
胡焕
朱海娣
黄星迪
丁继民
黄天明
李健平
娄泽峰
王涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dongtong Geotechnical Technology Co Ltd
Original Assignee
Dongtong Geotechnical Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongtong Geotechnical Technology Co Ltd filed Critical Dongtong Geotechnical Technology Co Ltd
Priority to CN201821936936.5U priority Critical patent/CN209412834U/en
Application granted granted Critical
Publication of CN209412834U publication Critical patent/CN209412834U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a kind of assembled crown beam structures of foundation pit enclosure wall, it is intended to provide a kind of integral strength that foundation pit enclosure wall not only can be improved, but also short construction period, it is easy for construction, and it removes conveniently, can repeatedly dismount the assembled crown beam structure of the foundation pit enclosure wall used.It includes the girder steel monomer that several length directions along foundation pit enclosure wall are sequentially distributed, girder steel monomer is equipped with the downward opening assembly through slot matched with foundation pit enclosure wall, the upper end of foundation pit enclosure wall is protruded into assembly through slot, and girder steel monomer is supported on the upper end of foundation pit enclosure wall by the inner top surface of assembly through slot, is bolted between two neighboring girder steel monomer.

Description

A kind of assembled crown beam structure of foundation pit enclosure wall
Technical field
The utility model relates to a kind of foundation pit enclosure walls, and in particular to a kind of assembled crown beam structure of foundation pit enclosure wall.
Background technique
The basement foundation ditch of building or structures, often needs to carry out construction foundation pit enclosure wall, with closing on the outside of foundation pit Underground water, while also have both supporting and retaining system hole outside active earth pressure.Current foundation pit enclosure wall generallys use TRD engineering method, SMW work Method construction etc., foundation pit enclosure wall includes underground cement soil wall and several is successively plugged in underground along underground cement soil wall length direction Cement soil wall inner wall fashioned iron, then, earth's surface along foundation pit enclosure wall length direction construction reinforced bar concrete capping beam (or For armored concrete crown beam), to improve the integral strength of foundation pit enclosure wall.Currently, this beared down on one by construction reinforced bar concrete Beam, the mode that the wall fashioned iron being located above earth's surface is linked together, although the integral strength of foundation pit enclosure wall can be improved;But There are long construction periods for it, the deficiencies of removing difficulty, and can not recycle.
Utility model content
The purpose of this utility model is to provide for a kind of integral strength that foundation pit enclosure wall not only can be improved, Er Qieshi The work period is short, easy for construction, and removes conveniently, can repeatedly dismount the assembled crown beam structure of the foundation pit enclosure wall used.
The technical solution of the utility model is:
A kind of assembled crown beam structure of foundation pit enclosure wall, is sequentially distributed including several length directions along foundation pit enclosure wall Girder steel monomer, girder steel monomer is equipped with the downward opening assembly through slot that matches with foundation pit enclosure wall, foundation pit enclosure wall Upper end is protruded into assembly through slot, and the upper end that girder steel monomer is supported on foundation pit enclosure wall by assembling the inner top surface of through slot, adjacent It is bolted between two girder steel monomers.
This programme replaces traditional armored concrete capping beam using the assembled crown beam structure of foundation pit enclosure wall, not only The integral strength of foundation pit enclosure wall, and short construction period can be improved, it is easy for construction, and remove conveniently, it can repeat to tear open Dress uses.
Preferably, being interference fit between the assembly through slot and foundation pit enclosure wall of girder steel monomer.In this way, steel can be improved Connective stability between beam monomer and foundation pit enclosure wall is conducive to the integral strength for improving foundation pit enclosure wall.
Preferably, the groove depth of assembly through slot is greater than 0.4 meter.The groove depth of assembly through slot, which is greater than 0.4 meter, can make girder steel list Connective stability between body and foundation pit enclosure wall is conducive to the integral strength for improving foundation pit enclosure wall.
Preferably, being equipped with several bolt connecting holes towards the side of the girder steel monomer on the inside of foundation pit.In this way, being conducive to Girder steel monomer is connected with the type steel support beam in foundation pit, is conducive to install type steel support beam.
Preferably, bolt connecting hole is uniformly distributed in two rows.So, it is ensured that type steel support beam and girder steel list The bonding strength of body.
Preferably, girder steel monomer is rectangular parallelepiped structure, the length direction of through slot and the length direction of girder steel monomer are assembled It is parallel.
Preferably, the length of girder steel monomer is greater than 1 meter.Girder steel monomer length is too small to be unfavorable for improving construction efficiency.
Preferably, the both ends of girder steel monomer are equipped with connection board.
Preferably, the top of girder steel monomer is equipped with several vertical stiffening plates being parallel to each other and several pieces of connections are each vertical The connection top plate of stiffening plate, the vertical stiffening plate is parallel with the length direction of girder steel monomer, and connection top plate is located at vertical add The top of strong plate.On the one hand vertical stiffening plate is conducive to the intensity of raising girder steel monomer, on the other hand, Ke Yifang with top plate is connect Just it is bolted between the connection board of two neighboring girder steel monomer.
Preferably, girder steel monomer is made of steel plate.
The beneficial effects of the utility model are: replacing traditional reinforcing bar using the assembled crown beam structure of foundation pit enclosure wall The integral strength of foundation pit enclosure wall, but also short construction period not only can be improved in concrete capping beam, easy for construction, and tears open It is used except dismounting conveniently, can be repeated.
Detailed description of the invention
Fig. 1 is a kind of top view of the girder steel monomer of the assembled crown beam structure of foundation pit enclosure wall of the utility model.
Fig. 2 is a kind of the schematic diagram of the section structure in Fig. 1 at A-A.
Fig. 3 is a kind of vertical view in practice of construction of the assembled crown beam structure of foundation pit enclosure wall of the utility model Figure.
Fig. 4 is a kind of side view in practice of construction of the assembled crown beam structure of foundation pit enclosure wall of the utility model Figure.
In figure:
Girder steel monomer 1, connection board 1.1, vertical stiffening plate 1.2 connect top plate 1.3, assemble through slot 1.4;
Foundation pit enclosure wall 2;
Type steel support beam 3.
Specific embodiment
To keep technical solutions of the utility model embodiment purposes, technical schemes and advantages clearer, with reference to the accompanying drawing Clearly explanation and illustration is carried out to the technical solution of the utility model embodiment, but following embodiments are only the utility model Preferred embodiment, rather than whole embodiments.Based on the implementation example in the implementation mode, those skilled in the art are not making wound Obtained other embodiments under the premise of the property made is worked, belong to the protection scope of the utility model.
The embodiments of the present invention are described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning Same or similar element or element with the same or similar functions are indicated to same or similar label eventually.Below by ginseng The embodiment for examining attached drawing description is exemplary, and is only used for explaining this programme, and cannot be construed to the utility model Limitation.
Referring to following description and drawings, it will be clear that these and other aspects of the embodiments of the present invention.At these In description and attached drawing, it is originally practical to indicate to implement to specifically disclose some particular implementations in the embodiments of the present invention Some modes of the principle of novel embodiment, but it is to be understood that the range of the embodiments of the present invention is not limited. On the contrary, the embodiments of the present invention include the spirit for falling into attached claims and all changes within the scope of intension, Modification and equivalent.
In the description of the present invention, it should be understood that term " thickness ", "upper", "lower", "horizontal", "top", The orientation or positional relationship of the instructions such as "bottom", "inner", "outside", " circumferential direction " is to be based on the orientation or positional relationship shown in the drawings, only It is the utility model and simplified description for ease of description, rather than the device or element of indication or suggestion meaning must have spy Fixed orientation is constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.In the utility model Description in, the meaning of " plurality " is at least two, such as two, three etc., unless otherwise specifically defined, " several " Being meant that indicates one or more.
In the present invention unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " Gu It is fixed " etc. terms shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral: can be Mechanical connection is also possible to be electrically connected or can communicate each other;It can be directly connected, the indirect phase of intermediary can also be passed through Even, the connection inside two elements or the interaction relationship of two elements be can be, unless otherwise restricted clearly.For this For the those of ordinary skill in field, the concrete meaning of above-mentioned term in the present invention can be understood as the case may be.
Specific embodiment one: as shown in Fig. 1, Fig. 2, Fig. 3, a kind of assembled crown beam structure of foundation pit enclosure wall, including The girder steel monomer 1 that several length directions along foundation pit enclosure wall 2 are sequentially distributed.
In the present embodiment, foundation pit enclosure wall 2 is underground cement soil continuous wall, and TRD engineering method and SMW engineering method is used to construct, First construction underground water soil wall, is then sequentially inserted into wall fashioned iron according to the design pitch requirements of fashioned iron within the walls in underground soil cement (the usual H profile steel of wall fashioned iron), and the upper end of the underground cement soil wall of foundation pit enclosure wall reaches above earth's surface.
Girder steel monomer 1 is rectangular parallelepiped structure.Girder steel monomer is welded to form by steel plate.The length of girder steel monomer is greater than 1 meter, this In embodiment, the length of girder steel monomer is 2 meters, and girder steel monomer length is too small to be unfavorable for improving construction efficiency, girder steel monomer length It is too long, it is unfavorable for actual production and transport.
Girder steel monomer is equipped with the downward opening assembly through slot 1.4 matched with foundation pit enclosure wall, assembles the length of through slot It is parallel with the length direction of girder steel monomer to spend direction.Assembly through slot is rectangular channel.The groove depth for assembling through slot is greater than 0.4 meter, this The groove depth that through slot is assembled in embodiment is 0.5 meter.The groove depth for assembling through slot is too shallow, then is unfavorable for girder steel monomer and foundation pit enclosure wall Connective stability.
As shown in Fig. 1, Fig. 2, Fig. 3, Fig. 4, the upper end of foundation pit enclosure wall 1 is protruded into assembly through slot 1.4, foundation pit enclosure wall Upper end be against assembly through slot inner top surface on.It is interference fit between the assembly through slot and foundation pit enclosure wall of girder steel monomer.Steel The upper end that beam monomer is supported on foundation pit enclosure wall by assembling the inner top surface of through slot.
The both ends of girder steel monomer are equipped with connection board 1.1.The top of girder steel monomer be equipped with several be parallel to each other vertical plus The connection top plate 1.3 of strong plate 1.2 and several pieces of each vertical stiffening plates of connection.The length direction phase of vertical stiffening plate and girder steel monomer In parallel, connection top plate is located at the top of vertical stiffening plate.Connection top plate is weldingly connected with vertical stiffening plate.The top of connection board Edge is flushed with the upper surface for connecting top plate.Gap is equipped between connection board and neighbouring connection top plate.
Be bolted between two neighboring girder steel monomer, specifically, the connection board of two neighboring girder steel monomer it Between be bolted, so that each girder steel monomer is linked together.
Several bolt connecting holes are equipped with towards the side of the girder steel monomer on the inside of foundation pit.Bolt connecting hole is in two rows It is uniformly distributed.
The present embodiment replaces traditional armored concrete capping beam, nothing using the assembled crown beam structure of foundation pit enclosure wall Site operation armored concrete capping beam is needed, the integral strength of foundation pit enclosure wall so not only can be improved, but also assembled is preced with The beam structure construction period is short, easy for construction, and removes conveniently, can repeat dismounting and use.
On the other hand, as shown in Figure 3, Figure 4, several be bolted is equipped with towards the side of the girder steel monomer on the inside of foundation pit Hole, and bolt connecting hole is uniformly distributed in two rows, in this way, being conducive to install the type steel support beam 3(in foundation pit to guarantee Foundation pit support can reliably bear the active earth pressure on the outside of foundation pit, be typically employed in the horizontal cloth of installation in foundation pit at present The type steel support beam set, the both ends of type steel support beam are against on the foundation pit enclosure wall on the inside of foundation pit), make the both ends of type steel support beam It can be against on the side of girder steel monomer, and the end of girder steel monomer Yu type steel support beam is bolted.

Claims (10)

1. a kind of assembled crown beam structure of foundation pit enclosure wall, characterized in that including several length directions along foundation pit enclosure wall The girder steel monomer being sequentially distributed, the bottom surface of girder steel monomer are equipped with the assembly through slot matched with foundation pit enclosure wall, foundation pit enclosure wall Upper end protrude into assembly through slot, and girder steel monomer is supported on the upper end of foundation pit enclosure wall, phase by the inner top surface of assembly through slot It is bolted between adjacent two girder steel monomers.
2. a kind of assembled crown beam structure of foundation pit enclosure wall according to claim 1, characterized in that the girder steel monomer Assembly through slot and foundation pit enclosure wall between for interference fit.
3. a kind of assembled crown beam structure of foundation pit enclosure wall according to claim 1, characterized in that the assembly through slot Groove depth be greater than 0.4 meter.
4. a kind of assembled crown beam structure of foundation pit enclosure wall according to claim 1 or 2 or 3, characterized in that towards base The side for cheating the girder steel monomer of inside is equipped with several bolt connecting holes.
5. a kind of assembled crown beam structure of foundation pit enclosure wall according to claim 4, characterized in that described to be bolted Hole is uniformly distributed in two rows.
6. a kind of assembled crown beam structure of foundation pit enclosure wall according to claim 1 or 2 or 3, characterized in that the steel Beam monomer is rectangular parallelepiped structure, and the length direction for assembling through slot is parallel with the length direction of girder steel monomer.
7. a kind of assembled crown beam structure of foundation pit enclosure wall according to claim 6, characterized in that the girder steel monomer Length be greater than 1 meter.
8. a kind of assembled crown beam structure of foundation pit enclosure wall according to claim 6, characterized in that the girder steel monomer Both ends be equipped with connection board.
9. a kind of assembled crown beam structure of foundation pit enclosure wall according to claim 8, characterized in that the girder steel monomer Top be equipped with the connection top plates of several vertical stiffening plates being parallel to each other and several pieces of each vertical stiffening plates of connection, it is described vertical Stiffening plate is parallel with the length direction of girder steel monomer, and connection top plate is located at the top of vertical stiffening plate.
10. a kind of assembled crown beam structure of foundation pit enclosure wall according to claim 1 or 2 or 3, characterized in that described Girder steel monomer is made of steel plate.
CN201821936936.5U 2018-11-22 2018-11-22 A kind of assembled crown beam structure of foundation pit enclosure wall Active CN209412834U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821936936.5U CN209412834U (en) 2018-11-22 2018-11-22 A kind of assembled crown beam structure of foundation pit enclosure wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821936936.5U CN209412834U (en) 2018-11-22 2018-11-22 A kind of assembled crown beam structure of foundation pit enclosure wall

Publications (1)

Publication Number Publication Date
CN209412834U true CN209412834U (en) 2019-09-20

Family

ID=67934860

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821936936.5U Active CN209412834U (en) 2018-11-22 2018-11-22 A kind of assembled crown beam structure of foundation pit enclosure wall

Country Status (1)

Country Link
CN (1) CN209412834U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112554207A (en) * 2020-12-28 2021-03-26 京兴国际工程管理有限公司 Foundation pit supporting pile top crown beam structure and construction method thereof
CN113404054A (en) * 2020-03-16 2021-09-17 江苏华岩建设有限公司 Cement mixing pile type, cast-in-place pile type crown beam construction method and crown beam system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113404054A (en) * 2020-03-16 2021-09-17 江苏华岩建设有限公司 Cement mixing pile type, cast-in-place pile type crown beam construction method and crown beam system
CN112554207A (en) * 2020-12-28 2021-03-26 京兴国际工程管理有限公司 Foundation pit supporting pile top crown beam structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN209412834U (en) A kind of assembled crown beam structure of foundation pit enclosure wall
CN210315571U (en) Deep foundation pit supporting structure
CN109083203A (en) A kind of vertical laying method of HDPE film
CN111218941A (en) Combined type section steel supporting rod piece
CN109537600A (en) Foundation pit enclosure wall assembled all steel crown beam
CN208415293U (en) Integral prefabricated assembled main transformer foundation for indoor substation
CN209412833U (en) A kind of assembly type crown beam structure of foundation pit enclosure wall
CN107012872B (en) Construction method of sludge deep foundation pit
CN113684833A (en) Assembled braced system based on arched beam structure
CN209277185U (en) A kind of foundation pit enclosure wall assembled all steel crown beam
CN110499752A (en) Assembled underground continuous wall
CN205530345U (en) Modular many storehouses utility tunnel structure
CN212561535U (en) Combined type section steel supporting rod piece
CN1097227A (en) Flat lattice type ring-beam supporting method
CN209723794U (en) A kind of silo roof of assembled silo
CN218813749U (en) Assembled shaped steel sheet pile combination supporting device
CN216041355U (en) Prefabricated retaining component for basement and mold thereof
CN216342312U (en) Novel underground water retaining wall for filling
CN215801829U (en) Basement side wall anti-seepage system based on fixed stagnant water steel sheet
CN213062022U (en) Assembled braced system based on arched beam structure
CN214063000U (en) In-tunnel reinforcing structure for deformation of shield tunnel
CN217204182U (en) Device for sealing position of downcomer well of foundation pit
CN113236266B (en) Construction method for constructing standard segment water collection pit of shield pipe gallery by utilizing steel pipe sheet
CN220580215U (en) Steel construction and dry wall connection structure
CN109235614A (en) A kind of assembly type can have enough to meet the need temporary drain and its construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A fabricated crown beam structure of foundation pit retaining wall

Effective date of registration: 20211229

Granted publication date: 20190920

Pledgee: Hangzhou branch of Zhejiang Tailong Commercial Bank Co.,Ltd.

Pledgor: Dongtong Geotechnical Science and Technology Inc.

Registration number: Y2021330002743

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220608

Granted publication date: 20190920

Pledgee: Hangzhou branch of Zhejiang Tailong Commercial Bank Co.,Ltd.

Pledgor: Dongtong Geotechnical Science and Technology Inc.

Registration number: Y2021330002743